Prevention and control reinforcing device for floating of large-diameter shield segment

The shield segment reinforcement device addresses tunnel instability by redirecting buoyancy forces using a scissor-shaped structure with grouting pipes and inclined rods, enhancing stability and enabling rapid grouting to prevent further damage.

CN119083504AActive Publication Date: 2024-12-06GUANGZHOU RAILWAY (GROUP) CORPORATION +4
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411392732.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-08
Publication Date
2024-12-06
Estimated Expiration
2044-10-08

AI Technical Summary

Technical Problem

Existing tunnel structures face instability and damage due to floating caused by adjacent excavation and groundwater rise, leading to cracks, misalignment, and potential structural damage, with current grouting methods providing limited support.

Method used

A large-diameter shield segment floating prevention and control reinforcement device using a scissor-shaped structure with grouting reinforcement pipes, hinge joints, and inclined rods to transfer buoyancy forces, incorporating a displacement sensor and breakable hinge joints for controlled grouting.

Benefits of technology

Enhances foundation reinforcement by redirecting buoyancy forces, preventing floating and stabilizing the tunnel structure, while allowing rapid grouting to address instability without re-drilling, thus improving safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083504A_ABST
    Figure CN119083504A_ABST
Patent Text Reader

Abstract

The invention discloses a large-diameter shield segment floating prevention and control reinforcing device which comprises at least two grouting reinforcing pipes, a penetrating inclined hole is formed in a soil body between the two grouting reinforcing pipes, a hinge joint is arranged at the intersection of the lower end of the penetrating inclined hole, and two hinge shafts of the hinge joint are fixedly connected with inclined rods respectively; a limiting round rod is arranged outside the upper end of the grouting reinforcing pipe, the upper end of the inclined rod is fixedly connected with a supporting rod, the supporting rod is fixedly connected with a side rod, and the side rod is located at the bottom of the limiting round rod. The shear fork structure is matched with the grouting reinforcement pipe to reinforce the foundation, and when the duct piece floats upwards, the inclined rod of the shear fork structure is arranged above the duct piece, so that insufficient supporting force of soil covering above the duct piece is transferred to the grouting reinforcement pipe, and the floating control structure is stronger.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of tunnel anti-floating structures, and in particular to a prevention and control reinforcement device for floating large-diameter shield segments. Background Art

[0002] The tunnel will float to a certain extent due to the influence of the adjacent building foundation pit, pipeline gallery foundation pit and underground passage excavation, other lines crossing and the rise of groundwater level. When the floating amount of the shield tunnel exceeds the limit, it will cause cracks or misalignment between the segments, affecting the stability of driving. In serious cases, it will cause the shield tunnel bolts to break, joints to be damaged, segments to be partially broken, cracks to expand and seep water, and even cause the main structure of the tunnel to be damaged, posing a threat to the operational safety of trains or vehicles in the shield tunnel.

[0003] At present, grouting is commonly used to control the buoyancy of tunnel segments, forming hard agglomerates above the tunnel segments. The dispersion of the hard agglomerates results in limited supporting capacity. Therefore, a control device for soft soil reinforcement and anti-floating is needed to improve the reinforcement effect. Summary of the invention

[0004] The purpose of the present invention is to solve the shortcomings existing in the prior art and to propose a large-diameter shield segment floating prevention and control reinforcement device, thereby solving the problems existing in the prior art.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions:

[0006] A large-diameter shield segment floating prevention and control reinforcement device comprises at least two grouting reinforcement pipes, an oblique hole is arranged in the soil between the two grouting reinforcement pipes, a hinge joint is arranged at the intersection of the lower ends of the oblique holes, and two hinge shafts of the hinge joint are respectively fixedly connected to the oblique rod;

[0007] A limiting round rod is arranged outside the upper end of the grouting reinforcement pipe, the upper end of the inclined rod is fixedly connected to the support rod, the support rod is fixedly connected to the side rod, and the side rod is located at the bottom of the limiting round rod.

[0008] Preferably, the hinged joint is provided with a torsion spring, and the hinged shaft of the hinged joint is threadedly connected to the inclined rod.

[0009] Preferably, a transverse hole is provided at the upper end of the grouting reinforcement pipe, the upper end of the grouting reinforcement pipe is slidably connected to an end cap, the inner wall of the end cap is fixedly connected to a circular rod, the circular rod slides through the transverse hole, and the limiting circular rod is fixedly connected to the outer side of the end cap.

[0010] Preferably, a displacement sensor is fixedly connected between the end cap and the upper end of the grouting reinforcement pipe.

[0011] Preferably, the inclined rod is a hollow rod, and a slurry discharge hole is provided in the middle of the inclined rod;

[0012] A hard lump is arranged at the bottom of the inclined rod.

[0013] Preferably, the hinged joint is a breakable structure.

[0014] The advantages of the present invention are: a large-diameter shield segment floating prevention and control reinforcement device provided by the present invention uses a scissor structure and a grouting reinforcement pipe to reinforce the foundation. When the segment is at risk of floating, an inclined rod of the scissor structure is arranged above the segment, thereby transferring the insufficient supporting force of the soil covering above the segment to the grouting reinforcement pipe, so that the floating control structure is stronger.

[0015] The pipe segment of the present invention floats up beyond the designed bearing capacity, that is, the hinge joint bulges and breaks upward. On the one hand, due to the angle setting of the inclined rod, when the hinge joint floats up, the grouting reinforcement pipe remains motionless due to the large reinforcement depth. Therefore, the hardened block moves in the H direction as shown in the figure. On the one hand, it moves directly above the tunnel to prevent floating. On the other hand, cracks and cavities are formed at the original position of the hardened block. At this time, the inclined rod can be used for rapid grouting to alleviate the further deterioration of foundation instability. Compared with re-drilling, on the one hand, it saves rescue time. On the other hand, it forms an adjacent enlargement with the hardened block, and there is no need to drill to the position of the hardened block, so that the reinforcement effect is stronger. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a basic structural schematic diagram of the present invention;

[0017] Figure 2 yes Figure 1 A local enlarged view of point E in FIG.

[0018] Figure 3 It is a front view of the present invention;

[0019] Figure 4 It is a schematic diagram of the connection structure between the end cap and the grouting reinforcement pipe of the present invention. DETAILED DESCRIPTION

[0020] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0021] Example 1

[0022] like Figures 1 to 4As shown, the present invention provides a large-diameter shield segment floating prevention and control reinforcement device, including at least two grouting reinforcement pipes 1. According to the geological conditions, the structure of the present invention is arranged at intervals on the direction of the tunnel. The present invention is explained by one of the unit structures. An inclined hole 2 is arranged in the soil between the two grouting reinforcement pipes 1. A hinge head 3 is arranged at the intersection of the lower end of the inclined hole 2. The two hinge shafts of the hinge head 3 are respectively fixedly connected to the inclined rod 4. The hinge head 3 is provided with a torsion spring. The hinge shaft of the hinge head 3 is threadedly connected with the inclined rod 4. The hinge head 3 is first threadedly fixed with one of the inclined rods 4 and inserted into the lower part of the inclined hole 2. The other inclined rod 4 is inserted into the inclined hole 2 and threadedly connected with the hinge head 3 located underground through a guide. If necessary, the inclined rod 4 is reinforced by grouting in the inclined hole 2.

[0023] A limiting round rod 5 is arranged on the outer side of the upper end of the grouting reinforcement pipe 1, and the upper end of the inclined rod 4 is fixedly connected to the support rod 6. A sliding hole is arranged on the upper end of the inclined rod 4. The support rod 6 can slide and telescope relative to the inclined rod 4 for easy installation. After assembly, it is fixed by welding. The support rod 6 is fixedly connected to the side rod 7, and the side rod 7 is located at the bottom of the limiting round rod 5.

[0024] In Example 1, Figure 1 and Figure 3 As shown, the conventional measure to prevent the pipe segment 10 from floating up is to set grouting hardened blocks 42 on the pipe segment. In view of the poor integrity of the soil in the tunnel crossing area (insufficient bearing capacity of soft soil, etc.), the grouting reinforcement pipe 1 is used to reinforce the foundation. When the pipe segment 10 is at risk of floating up, the scattered hardened blocks 42 have insufficient supporting force. The present invention sets a scissor-shaped inclined rod 4 above the pipe segment 10. The buoyancy F1 of the pipe segment 10 is divided into force F2 through the inclined rod 4 and acts on F3 of the grouting reinforcement pipe 1, thereby transferring the insufficient supporting force of the covering soil above the pipe segment 10 to the grouting reinforcement pipe 1, so that the floating control structure is stronger.

[0025] Example 2

[0026] like Figures 1 to 4 As shown, a transverse hole 11 is provided at the upper end of the grouting reinforcement pipe 1, and the upper end of the grouting reinforcement pipe 1 is slidably connected to an end cap 12, and a circular rod 13 is fixedly connected to the inner wall of the end cap 12. The circular rod 13 slides through the transverse hole 11, so that the end cap 12 can slide and rise within a certain range without falling off, and the limiting circular rod 5 is fixedly connected to the outer side of the end cap 12, and a displacement sensor 14 is fixedly connected between the end cap 12 and the upper end of the grouting reinforcement pipe 1, and soft soil is filled and covered in the installation pit 111 at the upper end of the grouting reinforcement pipe 1.

[0027] In Example 2, the inclined rod 4 in Example 1 is displaced to act on the limiting round rod 5, so that the end cap 12 moves, and the displacement sensor 14 identifies the displacement, and then performs risk analysis and subsequent management and reinforcement.

[0028] Example 3

[0029] like Figures 1 to 4 As shown, the inclined rod 4 is a hollow rod, and a slurry discharge hole 41 is arranged in the middle of the inclined rod 4; a hardened block 42 is arranged at the bottom of the inclined rod 4, and a hardened block 42 is formed at the bottom of the inclined rod 4 by drilling a hole 43 on the ground surface. The hardened block 42 is in the form of a conventional anti-floating means, and the hardened block 42 does not cover the slurry discharge hole 41.

[0030] Specifically, the hinged joint 3 is an easily breakable structure.

[0031] In Example 3, conventional means are used to form hardened blocks 42 on both sides above the pipe segment 10. The hardened blocks 42 prevent the pipe segment 10 below from floating up. When the pipe segment 10 floats up beyond the designed bearing capacity, that is, the hinge joint 3 bulges upward and breaks, on the one hand, due to the angle setting of the inclined rod 4, when the hinge joint 3 floats up, the grouting reinforcement pipe 1 remains motionless due to the large reinforcement depth, so the hardened blocks 42 are as follows. Figure 1 The H-direction movement shown, on the one hand, moves toward the top of the tunnel to prevent floating, and on the other hand, cracks and cavities are formed at the original position of the hardened block 42. At this time, the inclined rod 4 can be used for rapid grouting to alleviate the further deterioration of foundation instability. Compared with re-drilling, on the one hand, it saves rescue time, and on the other hand, it forms an adjacent enlargement with the hardened block 42, without the need to drill to the position of the hardened block 42, thereby strengthening the effect.

[0032] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A large-diameter shield segment floating prevention and control reinforcement device, comprising at least two grouting reinforcement pipes (1), characterized in that: An inclined hole (2) is provided in the soil between the two grouting reinforcement pipes (1), a hinge joint (3) is provided at the intersection of the lower ends of the inclined holes (2), and two hinge shafts of the hinge joint (3) are respectively fixedly connected to the inclined rods (4); A limiting round rod (5) is arranged outside the upper end of the grouting reinforcement pipe (1); the upper end of the inclined rod (4) is fixedly connected to a support rod (6); the support rod (6) is fixedly connected to a side rod (7); and the side rod (7) is located at the bottom of the limiting round rod (5).

2. According to claim 1, a large-diameter shield segment floating prevention and control reinforcement device is characterized by: The hinged joint (3) is provided with a torsion spring, and the hinged shaft of the hinged joint (3) is threadedly connected to the inclined rod (4).

3. According to claim 1, a large-diameter shield segment floating prevention and control reinforcement device is characterized by: A transverse hole (11) is provided at the upper end of the grouting reinforcement pipe (1), the upper end of the grouting reinforcement pipe (1) is slidably connected to an end cap (12), the inner wall of the end cap (12) is fixedly connected to a circular rod (13), the circular rod (13) slides through the transverse hole (11), and the limiting circular rod (5) is fixedly connected to the outer side of the end cap (12).

4. A large-diameter shield segment floating prevention and control reinforcement device according to claim 3, characterized in that: A displacement sensor (14) is fixedly connected between the end cap (12) and the upper end of the grouting reinforcement pipe (1).

5. According to claim 1, a large-diameter shield segment floating prevention and control reinforcement device is characterized by: The inclined rod (4) is a hollow rod, and a slurry discharge hole (41) is arranged in the middle of the inclined rod (4); A hard block (42) is arranged at the bottom of the inclined rod (4).

6. A large-diameter shield segment floating prevention and control reinforcement device according to claim 5, characterized in that: The hinged joint (3) is an easily breakable structure.

Citation Information

Patent Citations

  • Pipeline anti-displacement anti-floating mechanism and pipeline anti-floating construction method

    CN110566722A

  • Shield tunnel concrete segment micro reinforcing pile

    CN114922661A

  • Flexible pipeline concrete encapsulation anti-floating and anti-sidesway construction method

    CN118462910A

  • Reinforcing structure of shield shallow earthing underneath pass riverway

    CN211692490U

  • Bottom plate anti-floating fixing structure of tunnel foundation pit

    CN220908485U