Construction method of small-spacing unsymmetrical pressure tunnel portal protection structure

By setting up anchor piles and backfill concrete layers at the tunnel entrance and adopting slope protection structure, the problem of tunnel structure instability caused by steep slope terrain and unstable geology is solved, the stability of the tunnel and mountain slope is improved, and the tunnel damage is avoided and rupture.

CN119084011APending Publication Date: 2024-12-06CCCC THIRD HARBOR ENGINEERING CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411469145.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-21
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

When laying high-speed railways in mountainous areas, steep slope terrain and unstable geology lead to unstable tunnel structure, forming biased tunnels, which may lead to rupture and collapse, especially when small-pitch tunnels pass through areas with asymmetric terrain, the structure is under stress. Complex and poor stability.

Method used

The construction method of the protective structure of the tunnel entrance of the small pitch biased tunnel includes setting up anchor piles, backfill concrete layers and slope protection structures on both sides of the tunnel, and improving the water cut gutters, retaining walls, frame anchors and skeleton slope protection measures such as water cutoff gutters, retaining walls, frame anchors and skeleton slope protection. Tunnel structure and stability of mountain slopes.

Benefits of technology

The stability of the tunnel structure is improved by anchoring piles and backfilling concrete layers, and the slope protection structure enhances the stability of the mountain slope, avoids tunnel damage, and ensures tunnel safety and structural integrity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119084011A_ABST
    Figure CN119084011A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of tunnel portal protection, and discloses a construction method of a small-spacing unsymmetrical pressure tunnel portal protection structure, a first tunnel and a second tunnel penetrate through a mountain, a first secondary lining is arranged in the first tunnel, and a second secondary lining is arranged in the second tunnel; a retaining wall is arranged on the side, close to the mountain body, of the first tunnel, a plurality of anchoring piles are arranged on the two sides of the first tunnel, and a backfill concrete layer is arranged on the base of the portal section of the second tunnel. According to the construction method of the small-spacing unsymmetrical pressure tunnel portal protection structure, the anchoring piles, the backfill concrete layer and the slope protection structure are arranged, and the anchoring piles and the backfill concrete layer improve the stability of the structure between the first tunnel and the second tunnel and the stability of the structures of the first tunnel and the second tunnel correspondingly; and meanwhile, the stability of the mountain slope is improved through the slope protection structure, and tunnel damage is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel opening protection, and in particular to a construction method of a small-spacing bias-pressure tunnel opening protection structure. Background Art

[0002] When high-speed railways are laid in mountainous areas, the tunnel entrances need to be set in steep slope terrain sections. However, the steep slope sections have complex topography and landforms, poor geological conditions, and unstable soil, which will lead to insufficient local burial depth of the tunnel entrance, unstable structure, and the formation of a biased tunnel. At the same time, when small-spacing tunnels pass through this section at the same time, the structural stress will become more complicated and the stability will be worse.

[0003] The biased tunnel is formed due to asymmetric terrain or geological rock factors, which causes asymmetric loads on both sides of the tunnel structure. When the tunnel entrance is located on an unstable hillside with poor terrain conditions and the soil thickness on both sides of the tunnel top is seriously inconsistent, it is a biased phenomenon. If not handled properly, the tunnel may rupture and collapse in severe cases.

[0004] When the pressure on one side of the tunnel is too high, the stress on the tunnel structure is uneven, and local stress concentration and excessive deformation may lead to shear failure of the tunnel structure. Summary of the invention

[0005] In view of the deficiencies in the prior art, the present invention provides a construction method for a small-spacing bias-pressure tunnel entrance protection structure, which solves the problems mentioned in the above background.

[0006] The present invention provides the following technical solutions: a construction method of a small-pitch biased tunnel entrance protection structure, the small-pitch biased tunnel entrance protection structure comprising: a first tunnel and a second tunnel passing through a mountain, a first secondary lining being arranged in the first tunnel, and a second secondary lining being arranged in the second tunnel;

[0007] A retaining wall is provided on one side of the first tunnel close to the mountain, a plurality of anchor piles are provided on both sides of the first tunnel, a backfill concrete layer is provided at the base of the entrance section of the second tunnel, and slope protection structures are provided at the entrances of the first tunnel and the second tunnel on the mountain;

[0008] The slope protection structure includes a water intercepting ditch set on the mountain, a frame anchor rod buried in the mountain slope, and a skeleton slope protection set on the mountain slope;

[0009] Construction methods, including:

[0010] Step S1, construction of water intercepting ditch (8);

[0011] Step S2, construction of the opening retaining wall (5);

[0012] Step S3, construction of anchor piles (6);

[0013] Step S4, construction of the first tunnel (1);

[0014] Step S5, backfilling the second tunnel (2) with a concrete layer (7);

[0015] Step S6, construction of the entrance of the second tunnel (2);

[0016] Step S7, cave roof protection construction.

[0017] Preferably, the retaining wall is 10m high, 1.75m wide, 6m long, and has a slope of 1:0.25. There are two anchor piles on the side of the first tunnel away from the second tunnel, and five anchor piles between the first tunnel and the second tunnel. The plurality of anchor piles are made of C35 reinforced concrete, and the cross-sectional dimensions of the anchor piles are 2.5m×2.25m, the length of the anchor piles is 22m, and the length of the anchor piles exposed outside the foundation is 11m. The first ear wall and the second ear wall are respectively provided on the back side of the first tunnel and the second tunnel, and the first ear wall is connected to the first secondary lining, so the second ear wall is connected to the second secondary lining, the inner side of the first ear wall facing the first tunnel and the inner side of the second ear wall facing the second tunnel are both arc-shaped, the retaining wall, the first ear wall and the second ear wall are all made of C35 reinforced concrete, and the backfill concrete layer is made of C20 plain concrete.

[0018] Preferably, the center line of the cut-off ditch is greater than 5m from the edge of the excavation line of the side slope, the wall thickness of the cut-off ditch is 30cm, the frame anchor rods are set on the primary slope of the mountain, the length of the frame anchor rods is 10m, the spacing between adjacent frame anchor rods is 3m, the horizontal angle of the frame anchor rods is 15°, the skeleton slope protection is set on the secondary slope and above of the mountain, the cut-off ditch and the skeleton slope protection are both made of C25 concrete, and the thickness of the skeleton slope protection is 80cm.

[0019] Preferably, in step S1:

[0020] Before the construction of the water intercepting ditch, safety hazards such as collapse and falling rocks are eliminated one by one, and isolated rocks on the top of the slope of the tunnel entrance and those that affect the construction and operation of the line are removed one by one.

[0021] Preferably, the step S2 includes:

[0022] Step S21, drainage system setting, the retaining wall is staggered with PVC pipe drainage holes with a diameter of 0.1m at every 2m up, down, left and right on the roadbed surface and above, and the drainage slope is not less than 4%. In order to prevent the drainage holes from being blocked, an anti-filter layer should be set at the inlet of the drainage holes, and the anti-filter layer material is bagged sand mixed with gravel or geosynthetics;

[0023] Step S22, pouring concrete for the retaining wall, and building the wall toe step and the wall body at the same time to ensure the strength and integrity of the part.

[0024] Preferably, in step S3:

[0025] Step S31, manual excavation of piles and wall protection construction, adopting the method of excavating one section and supporting one section, wherein the excavation depth is less than 2m, and each section is constructed as a construction cycle. The wall protection is C20 reinforced concrete with a thickness of 20cm. Vertical steel bars are inserted between sections, and the vertical steel bars are inserted into the lower section 25cm to improve the integrity of the wall protection. The templates are connected and fixed with clamps and fasteners to ensure rigidity. The wall protection concrete can be removed after pouring for 8 hours;

[0026] Step S32, the steel cage is made and installed. A special person is assigned to direct the crane operation. Two lifting points are set. During the lifting process, the steel cage should be lifted and lowered gently. After the steel cage is fully lifted, it is slowly moved to the corresponding pile hole. When the steel cage is lifted into the hole, the center of the steel skeleton should be aligned with the pile hole and then inserted into the hole. During the lowering process, the steel cage should be kept vertical and not allowed to touch the inner wall of the pile hole;

[0027] Step S33, pouring concrete for the pile body. During the concrete pouring process, a string tube is used to ensure that the end of the string tube is no more than 2 meters away from the pouring surface of the concrete to prevent the coarse aggregate and cement mortar from being separated and segregated. The pile core concrete is vibrated once every 0.3 meters or so to ensure the density of the pile core concrete. Each pile core must be poured continuously without leaving any construction joints.

[0028] Step S34, spray anchor mesh protection construction, dig out a dense and stable fresh slope surface, drill holes, grout, install anchor rods, then hang the steel mesh, and finally high-pressure spray concrete.

[0029] Preferably, in step S4:

[0030] First, the first ear wall and the first and second linings are constructed, and then the waterproof layer, soil and rock layer and waterproof layer are constructed in sequence outside the first ear wall and the first and second linings;

[0031] In step S4:

[0032] The second ear wall and the second secondary lining are constructed first, and then the waterproof layer, earth and stone layer and water-proof layer are constructed in sequence outside the second ear wall and the second secondary lining.

[0033] Preferably, in step S5:

[0034] First, the silty clay layer at the base of the first and second tunnels was excavated, and the foundation pit near the center of the tunnel was excavated into a stepped shape with a height of 1m and a width of 1m. Concrete was then poured and the surface was roughened.

[0035] Preferably, in step S7:

[0036] The cave roof protection construction is carried out according to graded protection, with excavation level one and protection level one. The frame anchor construction includes:

[0037] Step S71, slope excavation: excavation in stages, and slope protection is performed in stages from bottom to top;

[0038] Step S72, drilling and cleaning: the hole position is located by surveying and setting out, assisted by the hanging line method; the anchor hole is drilled by a drilling machine, the hole diameter is 110mm, and the effective hole depth is not less than 10m; the anchor hole is tilted downward, with an angle of 15° with the horizontal plane, and the hole is drilled by dry drilling, and water drilling is strictly prohibited to prevent collapse and shrinkage of the hole; before grouting the anchor hole, a high-pressure air gun should be used to clean the hole to remove debris in the hole;

[0039] Step S73, frame anchor installation: frame anchors are set at frame beam nodes, the anchoring section is 10m long, 3 annular brackets are set every 1.5m of the frame anchor, the brackets are welded to the frame anchor, and the frame anchor is connected with a straight threaded sleeve;

[0040] Step S74, grouting: M35 cement mortar is used as the grouting material for the anchor hole, and the grouting pressure is not less than 0.4MPa; during grouting, the grouting pipe is inserted 30-50cm away from the bottom of the hole, and the slurry is continuously poured from bottom to top. As the slurry is poured, the grouting pipe is slowly pulled out, and the grouting shall not be stopped in the middle. When intermittent grouting is required under special circumstances, grouting shall be performed before initial setting. The grouting shall be uniform and dense, and there shall be no voids. Two groutings are required before initial setting; after the anchor hole is grouted, it shall be cured for at least 7 days. During the curing period, it is strictly forbidden to knock, shake the anchor or hang heavy objects on the rod body. After the mortar strength in the anchor hole reaches 70% of the design strength, the frame beam and the head are constructed;

[0041] Step S75, slotting: the frame beam is manually slotted; the longitudinal and transverse beam slots are 28 cm deep and 35 cm wide; the edging slots are 40 cm deep (and fully embedded in the slope) and 50 cm wide; the bottom of the frame slots must be compacted and the periphery of the frame beams must be backfilled;

[0042] Step S76, tying steel bars: steel bars are arranged inside the longitudinal and transverse beams of the frame, and the extension is made by lap welding. When constructing in sections, the main bars must be reserved for the extension hook steel bars; the main bars are welded to the frame anchor bars at the anchor bars, and the steel bar joints are avoided at the nodes;

[0043] Step S77, concrete pouring: The frame beam is integrally poured with C25 concrete, the water retaining edge and the frame beam concrete are cast in one piece, and the concrete around the anchor holes and other places where the steel bars are densely packed should be poured carefully to ensure the quality.

[0044] Compared with the prior art, the present invention has the following beneficial effects:

[0045] 1. The present invention, by setting anchor piles, backfill concrete layers and slope protection structures, the anchor piles and backfill concrete layers respectively improve the stability of the structure between the first tunnel and the second tunnel and the stability of the first tunnel and the second tunnel themselves, and at the same time the slope protection structure improves the stability of the mountain slope to avoid tunnel damage.

[0046] 2. The present invention improves the stability of the soil by providing a backfill concrete layer.

[0047] 3. The present invention is constructed in the order of water cutoff ditch construction, tunnel retaining wall construction, anchor pile construction, first tunnel portal construction, second tunnel portal backfill concrete layer construction, second tunnel portal construction, and tunnel roof protection construction, which is convenient to construct. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] Figure 1 This is a plan layout diagram of the present invention;

[0049] Figure 2 This is a schematic diagram of the structure at the retaining wall position of the AA section of the present invention;

[0050] Figure 3 It is a schematic diagram of the structure at the first and second lining positions of the BB section of the present invention;

[0051] Figure 4 It is a schematic diagram of the structure at the positions of the first tunnel and the second tunnel of the CC section of the present invention;

[0052] Figure 5 For the present invention Figure 5 Schematic diagram of the side section structure at the middle DD position;

[0053] Figure 6 This is a schematic diagram of the distribution structure of the anchor piles of the present invention;

[0054] Figure 7 It is a flow chart of the construction method of the small-spacing bias-pressure tunnel entrance protection structure of the present invention;

[0055] Figure 8 This is a flow chart of anchor pile construction of the present invention;

[0056] Fig. 9 This is a flow chart of the frame anchor construction of the present invention.

[0057] In the figure: 1. First tunnel; 2. Second tunnel; 3. First and second linings; 4. Second and second linings; 5. Retaining wall; 6. Anchor piles; 7. Backfill concrete layer; 8. Water intercepting ditch; 9. Framework anchor rods; 10. Skeleton slope protection; 11. First ear wall; 12. Second ear wall; 13. Mountain. DETAILED DESCRIPTION

[0058] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0059] See also Figure 1-9 , a construction method of a small-spacing biased tunnel entrance protection structure, the small-spacing biased tunnel entrance protection structure comprising: a first tunnel 1 and a second tunnel 2 passing through a mountain 13, a first secondary lining 3 being arranged in the first tunnel 1, and a second secondary lining 4 being arranged in the second tunnel 2;

[0060] A retaining wall 5 is provided on one side of the first tunnel 1 close to the mountain 13, a plurality of anchor piles 6 are provided on both sides of the first tunnel 1, a backfill concrete layer 7 is provided at the base of the entrance section of the second tunnel 2, and slope protection structures are provided at the entrances of the first tunnel 1 and the second tunnel 2 on the mountain 13;

[0061] The slope protection structure includes a water intercepting ditch 8 arranged on the mountain 13, a frame anchor rod 9 buried in the slope of the mountain 13, and a skeleton slope protection 10 arranged on the slope of the mountain 13;

[0062] Construction methods, including:

[0063] Step S1, construction of water intercepting gutter 8;

[0064] Step S2, construction of the opening retaining wall 5;

[0065] Step S3, construction of anchor piles 6;

[0066] Step S4, construction of the first tunnel entrance 1;

[0067] Step S5, backfilling the second tunnel 2 with a concrete layer 7;

[0068] Step S6, construction of the second tunnel 2 entrance;

[0069] Step S7, cave roof protection construction.

[0070] The height of the retaining wall 5 is 10m, the top width is 1.75m, the length is 6m, and the slope of the retaining wall 5 is 1:0.25. There are two anchor piles 6 on the side of the first tunnel 1 away from the second tunnel 2, and there are five anchor piles 6 between the first tunnel 1 and the second tunnel 2. The multiple anchor piles 6 are all made of C35 reinforced concrete, and the cross-sectional dimensions of the anchor piles 6 are 2.5m×2.25m, the length of the anchor piles 6 is 22m, and the length of the anchor piles 6 exposed outside the foundation is 11m. The first ear wall 11 and the second ear wall 12 are respectively arranged on the back side of the mountain of the first tunnel 1 and the second tunnel 2, and the first ear wall 11 is connected to the first secondary lining 3, so the second ear wall 12 is connected to the second secondary lining 4, the first ear wall 11 facing the inner side of the first tunnel 1 and the second ear wall 12 facing the inner side of the second tunnel 2 are both arc-shaped, the retaining wall 5, the first ear wall 11 and the second ear wall 12 are all made of C35 reinforced concrete, and the backfill concrete layer 7 is made of C20 plain concrete.

[0071] The center line of the water-cutting ditch 8 is greater than 5m away from the edge of the excavation line of the side slope. The wall thickness of the water-cutting ditch 8 is 30cm. The frame anchor rods 9 are set on the primary slope of the mountain 13. The length of the frame anchor rods 9 is 10m. The spacing between adjacent frame anchor rods 9 is 3m. The horizontal angle of the frame anchor rods 9 is 15°. The skeleton slope protection 10 is set on the secondary slope and above of the mountain 13. The water-cutting ditch 8 and the skeleton slope protection 10 are both made of C25 concrete, and the thickness of the skeleton slope protection 10 is 80cm.

[0072] In step S1: before the construction of the intercepting ditch 8, the potential safety hazards such as collapse and falling rocks are eliminated one by one, and the isolated rocks on the top of the back slope of the tunnel entrance and those that affect the construction and operation of the line are removed one by one.

[0073] Step S2 includes:

[0074] Step S21, drainage system setting, the wall of the retaining wall 5 is staggered with PVC pipe drainage holes with a diameter of 0.1m at every 2m up, down, left and right at the roadbed surface and above, and the drainage slope is not less than 4%. In order to prevent the drainage holes from being blocked, an anti-filter layer should be set at the inlet of the drainage holes, and the anti-filter layer material is bagged sand mixed with gravel or geosynthetics;

[0075] Step S22, pouring concrete for retaining wall 5, the wall toe step is built at the same time as the wall body to ensure the strength and integrity of the wall body. There should be no horizontal joints in the wall body concrete. The wall toe step is the weak point of the wall cross section and should be built at the same time as the wall body. If the back of the retaining wall 5 is backfilled due to over-excavation, its surface should be smoothed with cement mortar to form a flat seam.

[0076] In step S3:

[0077] Step S31, manual excavation of piles and wall protection construction, adopting the method of excavating one section and supporting one section, wherein the excavation depth is less than 2m, and each section is constructed as a construction cycle. The wall protection is C20 reinforced concrete with a thickness of 20cm. Vertical steel bars are inserted between sections, and the vertical steel bars are inserted into the lower section 25cm to improve the integrity of the wall protection. The templates are connected and fixed with clamps and fasteners to ensure rigidity. The wall protection concrete can be removed after pouring for 8 hours;

[0078] Step S32, the steel cage is made and installed. A special person is assigned to direct the crane operation. Two lifting points are set. During the lifting process, the steel cage should be lifted and lowered gently. After the steel cage is fully lifted, it is slowly moved to the corresponding pile hole. When the steel cage is lifted into the hole, the center of the steel skeleton should be aligned with the pile hole and then inserted into the hole. During the lowering process, the steel cage should be kept vertical and not allowed to touch the inner wall of the pile hole;

[0079] Step S33, pouring concrete for the pile body. During the concrete pouring process, a string tube is used to ensure that the end of the string tube is no more than 2 meters away from the pouring surface of the concrete to prevent the coarse aggregate and cement mortar from being separated and segregated. The pile core concrete is vibrated once every 0.3 meters or so to ensure the density of the pile core concrete. Each pile core must be poured continuously without leaving any construction joints.

[0080] Step S34, spray anchor mesh protection construction, dig out a dense and stable fresh slope surface, drill holes, grout, install anchor rods, then hang the steel mesh, and finally high-pressure spray concrete.

[0081] In step S4:

[0082] First, the first ear wall 11 and the first and second linings 3 are constructed, and then the waterproof layer, the soil and rock layer and the waterproof layer are constructed in sequence outside the first ear wall 11 and the first and second linings 3;

[0083] In step S4: firstly, the second ear wall 12 and the second secondary lining 4 are constructed, and then, the waterproof layer, the soil and stone layer and the waterproof layer are constructed in sequence outside the second ear wall 12 and the second secondary lining 4.

[0084] In step S5: first, the silty clay layer at the base of the first tunnel 1 and the second tunnel 2 is excavated, and the foundation pit near the center of the tunnel is excavated into a step shape with a height of 1m and a width of 1m, and then concrete is poured and the surface is roughened.

[0085] In step S7:

[0086] The cave roof protection construction is carried out according to graded protection, excavation level one, protection level one, among which the frame anchor 9 construction includes:

[0087] Step S71, slope excavation: excavation in stages, and slope protection is performed in stages from bottom to top;

[0088] Step S72, drilling and cleaning: the hole position is located by surveying and setting out, assisted by the hanging line method; the anchor hole is drilled by a drilling machine, the hole diameter is 110mm, and the effective hole depth is not less than 10m; the anchor hole is tilted downward, with an angle of 15° with the horizontal plane, and the hole is drilled by dry drilling, and water drilling is strictly prohibited to prevent collapse and shrinkage of the hole; before grouting the anchor hole, a high-pressure air gun should be used to clean the hole to remove debris in the hole;

[0089] Step S73, installation of frame anchor rods 9: frame anchor rods 9 are set at all frame beam nodes. The frame anchor rods are made of a single Φ32HRB400 threaded steel bar. The anchoring section is 10m long. Three annular brackets are set every 1.5m of the frame anchor rod 9. The brackets are welded to the frame anchor rods 9. The frame anchor rods 9 are connected with straight threaded sleeves.

[0090] Step S74, grouting: M35 cement mortar is used as the grouting material for the anchor hole, and the grouting pressure is not less than 0.4MPa; during grouting, the grouting pipe is inserted 30-50cm away from the bottom of the hole, and the slurry is continuously poured from bottom to top. As the slurry is poured, the grouting pipe is slowly pulled out, and the grouting shall not be stopped in the middle. When intermittent grouting is required under special circumstances, grouting shall be performed before initial setting. The grouting shall be uniform and dense, and there shall be no voids. Two groutings are required before initial setting; after the anchor hole is grouted, it shall be cured for at least 7 days. During the curing period, it is strictly forbidden to knock, shake the anchor or hang heavy objects on the rod body. After the mortar strength in the anchor hole reaches 70% of the design strength, the frame beam and the head are constructed;

[0091] Step S75, slotting: the frame beam is manually slotted; the longitudinal and transverse beam slots are 28 cm deep and 35 cm wide; the edging slots are 40 cm deep and fully embedded in the slope, with a slot width of 50 cm; the bottom of the frame slots must be compacted and the periphery of the frame beams must be backfilled;

[0092] Step S76, tying steel bars: steel bars are arranged inside the longitudinal and transverse beams of the frame, and the extension is made by lap welding. When constructing in sections, the main bars must be reserved for the extension hook steel bars; the main bars are welded to the frame anchor rods 9 at the anchor rods, and the steel bar joints are avoided at the nodes;

[0093] Step S77, concrete pouring: The frame beam is integrally poured with C25 concrete, the water retaining edge and the frame beam concrete are cast in one piece, and the concrete around the anchor holes and other places where the steel bars are densely packed should be poured carefully to ensure the quality.

[0094] Multiple anchor piles 6 can improve the stability of the surrounding structures of the first tunnel 1 and the second tunnel 2. The retaining wall 5 provides support for the unstable soil of the mountain 13 where the entrance is located in poor terrain conditions. Multiple frame anchor rods 9 are used to anchor the mountain 13. The slope surface is fixed by the skeleton slope protection 10 to prevent the slope from sliding. The silty clay layer at the base of the first tunnel 1 and the second tunnel 2 is excavated, and the foundation pit near the center of the tunnel is excavated into a stepped shape and concrete is poured to form a backfill concrete layer 7 to improve the stability of the soil.

[0095] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A construction method for a small-spacing bias-pressure tunnel entrance protection structure, characterized in that: A small-spacing bias-pressure tunnel entrance protection structure comprises: a first tunnel (1) and a second tunnel (2) passing through a mountain (13); a first secondary lining (3) is arranged in the first tunnel (1); and a second secondary lining (4) is arranged in the second tunnel (2); A retaining wall (5) is arranged on one side of the first tunnel (1) close to the mountain (13), a plurality of anchor piles (6) are arranged on both sides of the first tunnel (1), a backfill concrete layer (7) is arranged at the base of the opening section of the second tunnel (2), and slope protection structures are arranged at the openings of the first tunnel (1) and the second tunnel (2) on the mountain (13); The slope protection structure comprises a water intercepting ditch (8) arranged on a mountain (13), a frame anchor rod (9) buried in the slope of the mountain (13), and a skeleton slope protection (10) arranged on the slope of the mountain (13); Construction methods, including: Step S1, construction of water intercepting ditch (8); Step S2, construction of the opening retaining wall (5); Step S3, construction of anchor piles (6); Step S4, construction of the first tunnel (1); Step S5, backfilling the second tunnel (2) with a concrete layer (7); Step S6, construction of the entrance of the second tunnel (2); Step S7, cave roof protection construction.

2. The construction method of a small-spacing bias-pressure tunnel entrance protection structure according to claim 1 is characterized in that: The retaining wall (5) is 10 m high, 1.75 m wide at the top, and 6 m long. The retaining wall (5) has a slope of 1:0.

25. The number of anchor piles (6) on the side of the first tunnel (1) away from the second tunnel (2) is two. The number of anchor piles (6) located between the first tunnel (1) and the second tunnel (2) is five. The plurality of anchor piles (6) are made of C35 reinforced concrete. The cross-sectional dimensions of the anchor piles (6) are 2.5 m×2.25 m. The length of the anchor piles (6) is 22 m. The length of the anchor piles (6) exposed outside the foundation is 11 m. A first ear wall (11) and a second ear wall (12) are respectively arranged on the back side of the first tunnel (1) and the second tunnel (2), and the first ear wall (11) is connected to the first secondary lining (3), so that the second ear wall (12) is connected to the second secondary lining (4), the first ear wall (11) facing the inner side of the first tunnel (1) and the second ear wall (12) facing the inner side of the second tunnel (2) are both arc-shaped, the retaining wall (5), the first ear wall (11) and the second ear wall (12) are all made of C35 reinforced concrete, and the backfill concrete layer (7) is made of C20 plain concrete.

3. The construction method of a small-spacing bias-pressure tunnel entrance protection structure according to claim 2 is characterized in that: The center line of the cut-off ditch (8) is greater than 5 m from the edge of the excavation line of the side slope, the wall thickness of the cut-off ditch (8) is 30 cm, the frame anchor rods (9) are arranged on the primary slope of the mountain (13), the length of the frame anchor rods (9) is 10 m, the spacing between adjacent frame anchor rods (9) is 3 m, the horizontal angle of the frame anchor rods (9) is 15°, the skeleton slope protection (10) is arranged on the secondary slope and above of the mountain (13), the cut-off ditch (8) and the skeleton slope protection (10) are both made of C25 concrete, and the thickness of the skeleton slope protection (10) is 80 cm.

4. The construction method of a small-spacing bias-pressure tunnel entrance protection structure according to claim 1 is characterized in that: In step S1: Before the construction of the intercepting ditch (8), safety hazards such as collapse and falling rocks are eliminated one by one, and isolated rocks on the top of the back slope of the tunnel entrance and those that affect the construction and operation of the line are removed one by one.

5. The construction method of a small-spacing bias-pressure tunnel entrance protection structure according to claim 1 is characterized in that: The step S2 includes: Step S21, drainage system setting, the retaining wall (5) is provided with PVC pipe drainage holes with a diameter of 0.1m staggered every 2m up, down, left and right at the roadbed surface and above, and the drainage slope is not less than 4%. In order to prevent the drainage holes from being blocked, an anti-filter layer should be provided at the inlet of the drainage holes, and the anti-filter layer material is bagged sand mixed with gravel or geosynthetics; Step S22, concrete pouring of the retaining wall (5), the wall toe step and the wall body are built simultaneously to ensure the strength and integrity of the part.

6. The construction method of a small-spacing bias-pressure tunnel entrance protection structure according to claim 1 is characterized in that: In step S3: Step S31, manual excavation of piles and wall protection construction, adopting the method of excavating one section and supporting one section, wherein the excavation depth is less than 2m, and each section is constructed as a construction cycle. The wall protection is C20 reinforced concrete with a thickness of 20cm. Vertical steel bars are inserted between sections, and the vertical steel bars are inserted into the lower section 25cm to improve the integrity of the wall protection. The templates are connected and fixed with clamps and fasteners to ensure rigidity. The wall protection concrete can be removed after pouring for 8 hours; Step S32, the steel cage is made and installed. A special person is assigned to direct the crane operation. Two lifting points are set. During the lifting process, the steel cage should be lifted and lowered gently. After the steel cage is fully lifted, it is slowly moved to the corresponding pile hole. When the steel cage is lifted into the hole, the center of the steel skeleton should be aligned with the pile hole and then inserted into the hole. During the lowering process, the steel cage should be kept vertical and not allowed to touch the inner wall of the pile hole; Step S33, pouring concrete for the pile body. During the concrete pouring process, a string tube is used to ensure that the end of the string tube is no more than 2 meters away from the pouring surface of the concrete to prevent the coarse aggregate and cement mortar from being separated and segregated. The pile core concrete is vibrated once every 0.3 meters or so to ensure the density of the pile core concrete. Each pile core must be poured continuously without leaving any construction joints. Step S34, spray anchor mesh protection construction, dig out a dense and stable fresh slope surface, drill holes, grout, install anchor rods, then hang the steel mesh, and finally high-pressure spray concrete.

7. The construction method of a small-spacing bias-pressure tunnel entrance protection structure according to claim 1 is characterized in that: In step S4: Firstly, the first ear wall (11) and the first and second linings (3) are constructed, and then the waterproof layer, the soil and rock layer and the waterproof layer are constructed in sequence outside the first ear wall (11) and the first and second linings (3); In step S4: The second ear wall (12) and the second secondary lining (4) are constructed first, and then the waterproof layer, the soil and stone layer and the waterproof layer are constructed in sequence outside the second ear wall (12) and the second secondary lining (4).

8. The construction method of a small-spacing bias-pressure tunnel entrance protection structure according to claim 1 is characterized in that: In step S5: First, the silty clay layer at the base of the first tunnel (1) and the second tunnel (2) is excavated, and the foundation pit near the center of the tunnel is excavated into a step shape with a height of 1m and a width of 1m. Concrete is then poured and the surface is roughened.

9. The construction method of a small-spacing bias-pressure tunnel entrance protection structure according to claim 1, characterized in that: In step S7: The cave roof protection construction is carried out according to the graded protection, with excavation level one and protection level one. The construction of frame anchor rods (9) includes: Step S71, slope excavation: excavation in stages, and slope protection is performed in stages from bottom to top; Step S72, drilling and cleaning: the hole position is located by surveying and setting out, assisted by the hanging line method; the anchor hole is drilled by a drilling machine, the hole diameter is 110mm, and the effective hole depth is not less than 10m; the anchor hole is tilted downward, with an angle of 15° with the horizontal plane, and the hole is drilled by dry drilling, and water drilling is strictly prohibited to prevent collapse and shrinkage of the hole; before grouting the anchor hole, a high-pressure air gun should be used to clean the hole to remove debris in the hole; Step S73, installation of frame anchor rods (9): frame anchor rods (9) are installed at all frame beam nodes, the anchoring section is 10 m long, 3 annular brackets are installed every 1.5 m of the frame anchor rods (9), the brackets are welded to the frame anchor rods (9), and the frame anchor rods (9) are connected with straight threaded sleeves; Step S74, grouting: M35 cement mortar is used as the grouting material for the anchor hole, and the grouting pressure is not less than 0.4MPa; during grouting, the grouting pipe is inserted 30-50cm away from the bottom of the hole, and the slurry is continuously poured from bottom to top. As the slurry is poured, the grouting pipe is slowly pulled out, and the grouting shall not be stopped in the middle. When intermittent grouting is required under special circumstances, grouting shall be performed before initial setting. The grouting shall be uniform and dense, and there shall be no voids. Two groutings are required before initial setting; after the anchor hole is grouted, it shall be cured for at least 7 days. During the curing period, it is strictly forbidden to knock, shake the anchor or hang heavy objects on the rod body. After the mortar strength in the anchor hole reaches 70% of the design strength, the frame beam and the head are constructed; Step S75, slotting: the frame beam is slotted manually; the longitudinal and transverse beam slots are 28 cm deep and 35 cm wide; The edge groove is 40cm deep (and fully embedded in the slope), and 50cm wide; the bottom of the frame groove must be compacted, and the surrounding area of ​​the frame beam must be backfilled; Step S76, tying steel bars: steel bars are arranged inside the longitudinal and transverse beams of the frame, and the extension is made by lap welding. When constructing in sections, the main bars must be reserved for the extension hook steel bars; the main bars are welded to the frame anchor bars (9) at the anchor bars, and the steel bar joints are avoided at the nodes; Step S77, concrete pouring: The frame beam is integrally poured with C25 concrete, the water retaining edge and the frame beam concrete are cast in one piece, and the concrete around the anchor holes and other places where the steel bars are densely packed should be poured carefully to ensure the quality.

Citation Information

Patent Citations

  • Method for constructing tunnel located at mountain slope toe

    CN103089272A

  • Combined structure of soft foundation zone of unsymmetrical multi-arch tunnel portal and construction method

    CN113931169A

  • Tunnel structure located at mountain slope toe

    CN203161243U

  • High steep bias voltage foundation plate pilework in tunnel

    CN208220781U

  • Shallow-buried unsymmetrical-pressure ultra-small-clear-distance tunnel portal section structure

    CN218970039U