Shield receiving system and method

Through the sliding sealing technology of embedded steel rings and piston members, the problem of excessive sleeve length and complex drive devices in shield receiving is solved, and efficient and safe shield receiving is achieved, which is suitable for different formation environments.

CN119084015APending Publication Date: 2024-12-06BEIJING JINGHESHUNTONG TUNNEL ENG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411257417.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing shield receiving system requires longer sleeves and drive devices, resulting in high construction costs, long construction periods and low efficiency. Especially in the face of underground environments with high soil and water pressure, it is difficult to achieve effective sealing and simplify construction.

Method used

The embedded steel ring and piston member are combined to achieve the reception of the shield through the sliding seal between the first and second elastic sealing components and the sleeve, avoiding the excessive length of the sleeve and the use of the drive device, and simplifying the construction process.

Benefits of technology

It realizes the sealing effect during the shield receiving process, reduces construction costs and construction periods, is suitable for waterless and water-free formations, simplifies the shield receiving structure, and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119084015A_ABST
    Figure CN119084015A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of shield receiving, and discloses a shield receiving system and a shield receiving method.The shield receiving system comprises an embedded steel ring, a piston component and first elastic sealing assemblies, and the embedded steel ring is provided with the first elastic sealing assemblies distributed in the circumferential direction of the inner wall; the piston component is arranged in a receiving channel at least formed by an embedded steel ring, and the periphery of the piston component and the receiving channel form sliding sealing through a first elastic sealing assembly; one end of the piston component in the axial direction is open, the other end of the piston component is closed, and the open end of the piston component forms a containing cavity used for being filled with a tunneling protection medium so that a shield part can enter the containing cavity. The length of the sleeve can be shortened, an existing shield receiving structure or mode can be simplified, the construction cost is reduced, and the construction period is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of shield receiving technology, and in particular relates to a shield receiving system and a shield receiving method. Background Art

[0002] With the construction of a large number of subway lines, shield construction is being used more and more frequently. Every time the shield is started and accepted, it faces the problem of groundwater. On the one hand, the burial depth of subway stations is getting deeper and deeper, and the water and soil pressure during the start and acceptance period is getting higher and higher. On the other hand, as the country's requirements for environmental protection become more and more stringent, more and more stringent systems are adopted for groundwater extraction. Therefore, precipitation construction is generally not allowed during the start and acceptance of the shield, which makes the control of groundwater during the start and acceptance of the shield increasingly difficult.

[0003] At present, there are several main ways to receive the shield. One is to use the end reinforcement method, inject cement slurry into the stratum in the shield receiving area, and reinforce the receiving end stratum to a certain strength before receiving the shield; the second is to use the freezing consolidation method for the receiving end stratum, freeze the groundwater in the shield receiving area into a non-flowing state, and then receive the shield; the third is to use the full steel sleeve reception method, buckle a closed steel sleeve on the embedded steel ring at the receiving end, the length of the steel sleeve is longer than the length of the shield, and then backfill the soil in the closed steel sleeve. After the soil in the steel sleeve is backfilled and compacted, the shield completes the tunnel excavation and completely drills into the sealed steel sleeve, thereby completing the reception of the shield. The existing mainstream methods can achieve safe reception of shields, each with its own advantages and disadvantages, but the cost is relatively high, the construction period is relatively long, and the engineering volume is relatively large.

[0004] Among them, when a steel sleeve is used for receiving, the required sleeve length is often longer. In an existing shield receiving system, a plate similar to a piston is used to move in the sleeve, and a hydraulic cylinder is used as a driving device to provide support force to cope with the water pressure generated during the shield receiving process. Although this can better cope with the water pressure, the length of the sleeve is still maintained at a longer length, and the increase in the driving device also leads to increased costs, and the complexity of sleeve disassembly and assembly is also increased accordingly, and the construction is cumbersome and inefficient. Summary of the invention

[0005] In view of this, the object of the present invention is to provide a shield receiving system and a shield receiving method to solve the problem that the existing shield receiving system needs to be matched with a longer sleeve for receiving.

[0006] In order to achieve the above object, the present invention adopts the following technical solutions:

[0007] On the one hand, a shield receiving system is provided, comprising a pre-embedded steel ring, a piston component and a first elastic sealing assembly, wherein the pre-embedded steel ring is provided with a plurality of first elastic sealing assemblies distributed along the circumference of the inner wall, the piston component is arranged in a receiving channel formed by at least the pre-embedded steel ring, and the outer periphery of the piston component forms a sliding seal with the receiving channel through the first elastic sealing assembly;

[0008] The piston component is open at one end in the axial direction and closed at the other end. The open end of the piston component forms an accommodating chamber for filling a tunneling protection medium for the shield part to enter.

[0009] In a possible implementation, the piston member includes an end closure member and a cylindrical member, wherein the end closure member is connected to the inner side of the cylindrical member and closes one end of the cylindrical member, and the outer periphery of the cylindrical member forms a sliding seal with the receiving channel through a first elastic sealing assembly. An extension portion extending in the axial direction is provided at the closed end of the cylindrical member, and a reinforcement portion is provided between the extension portion and the end closure member.

[0010] In a possible implementation, the end closure is provided with a filling portion which is communicated with the accommodating cavity so as to fill the accommodating cavity with a tunneling protection medium.

[0011] In a possible implementation, the piston component includes a plurality of splicing parts distributed along the circumferential direction, and two adjacent splicing parts are connected by flange connection or welding.

[0012] In a possible implementation, it also includes a sleeve coaxially connected to the embedded steel ring, the sleeve and the embedded steel ring together form the receiving channel, and the sleeve is provided with a plurality of groups of second elastic sealing components distributed along the circumferential direction to form a sliding seal with the piston member.

[0013] In a possible implementation, the axial length of the piston member is greater than or equal to the distance between the second elastic sealing component and the first elastic sealing component so as to form a sliding seal with the embedded steel ring and the sleeve at the same time.

[0014] In a possible implementation, it further includes a transition ring connected between the sleeve and the embedded steel ring, and the inner diameter of the transition ring, the inner diameter of the embedded steel ring and the inner diameter of the movable piston are consistent.

[0015] In a possible implementation, a tail brush is provided at the outer end of the embedded steel ring, and the tail brush is provided with a first adjustment component for adjusting the pressing force.

[0016] In a possible implementation, a tail brush is provided at one end of the sleeve facing away from the embedded steel ring, and the tail brush is provided with a second adjustment component for adjusting the pressing force.

[0017] In a possible implementation, both the first elastic sealing component and the second elastic sealing component are provided with a third adjustment component for adjusting the pressing force.

[0018] In a possible implementation, the embedded steel ring is not provided with the first elastic sealing component.

[0019] In a possible implementation, it also includes a reaction force support device and a shield receiving base, wherein the reaction force support device is used to support the piston member before the piston member moves with the shield, and the shield receiving base is used to support the piston member and / or the shield.

[0020] On the other hand, a shield receiving method is also provided, comprising the following steps:

[0021] Before the shield enters the shield receiving area, a plurality of first elastic sealing components distributed along the circumferential direction are installed on the inner wall of the embedded steel ring of the tunnel door at the shield receiving end, and a piston component is installed on the inner side of the embedded steel ring, the first elastic sealing component is pressed against the outer circumference of the piston component, and the piston component forms a sliding seal with the embedded steel ring through the first elastic sealing component, wherein one end of the piston component in the axial direction is open and the other end is closed, and the open end of the piston component forms a receiving cavity for filling the excavation protection medium for the shield part to enter;

[0022] When shield receiving the waterless stratum, the following steps are also included:

[0023] A tail brush is installed at one end of the embedded steel ring close to the station, and the tail brush is pressed against the outer wall of the piston component;

[0024] A reaction force support device is installed on the rear side of the piston component, and the accommodating cavity in the piston component is filled with soil and the soil is compacted;

[0025] The shield receives the shield. The shield cuts into the soil in the piston component accommodating cavity from the station end wall. When the shield cutterhead approaches the closed end of the piston component, the shield stops excavating, and the reaction force support device is removed and the shield receiving base is installed in front of the piston component.

[0026] The shield advances, and the shield and the piston member pushed by the shield move together on the shield receiving base. When the piston member leaves the first elastic sealing component installed in the embedded steel ring, the first elastic sealing component is pressed against the outer shell of the shield;

[0027] The shield pushes the piston member to continue sliding on the shield receiving base until the shield tail leaves the inner area of ​​the embedded steel ring, and the tail brush is pressed against the outer shell of the shield;

[0028] The piston components, shield and shield receiving base are dismantled, and the shield receiving work is completed.

[0029] In a possible implementation, when receiving a water-bearing formation, the following steps are also included:

[0030] A sleeve is installed on the outer side of the piston component, the sleeve is coaxially connected to the embedded steel ring, and a second elastic sealing component installed in the sleeve is pressed against the outer periphery of the piston component, and the piston component forms a sliding seal with the piston component through the second elastic sealing component;

[0031] A tail brush is installed at the end of the sleeve away from the embedded steel ring, and the tail brush is pressed against the outer wall of the piston component;

[0032] A reaction force support device is installed on the rear side of the piston component, and the accommodating cavity in the piston component is filled with soil and the soil is compacted;

[0033] The shield receives the shield. The shield cuts into the soil in the piston component accommodating cavity from the station end wall. When the shield cutterhead approaches the closed end of the piston component, the shield stops excavating, and the reaction force support device is removed and the shield receiving base is installed in front of the piston component.

[0034] The shield advances, and the shield and the piston member pushed by the shield move together on the shield receiving base. When the piston member leaves the first elastic sealing component installed in the embedded steel ring, the first elastic sealing component is pressed against the outer shell of the shield;

[0035] The shield pushes the piston member to continue sliding on the shield receiving base. When the piston member leaves the inner area of ​​the sleeve, the second elastic sealing component in the sleeve is pressed against the outer shell of the shield.

[0036] The shield pushes the piston member to continue sliding on the shield receiving base until the shield tail leaves the inner area of ​​the embedded steel ring. At this time, the first elastic sealing component in the embedded steel ring is pressed against the outer surface of the tunnel segment;

[0037] Grouting is carried out to reinforce the soil outside the tunnel through the grouting holes on the shield-built tunnel segments. After the grouting solidifies, it forms a solid seal to prevent mud and water from entering the station.

[0038] The piston component, sleeve, shield and shield receiving base are removed, and the shield receiving work is completed.

[0039] Compared with the prior art, the present invention has the following beneficial effects:

[0040] The shield receiving system of the present invention has an accommodating cavity which is open at one end and closed at the other end and is formed at the open end. The accommodating cavity can be filled with an excavation protection medium for shield excavation. The filled excavation protection medium can not only make the piston component have a larger weight, which is beneficial to maintaining the water and soil pressure balance and protecting the piston component during the shield excavation process, but also enable the piston component to move relatively stably with the advancement of the shield after the shield part enters the accommodating cavity. At the same time, the piston component maintains a sliding seal with the embedded steel ring and / or sleeve, thereby realizing the reception of the shield, and avoiding the situation where the sleeve needs a longer length and a driving device is set. In addition, in combination with the embedded steel ring and the first elastic sealing component, sealing can be achieved during the shield receiving process, and the receiving construction is more convenient and simple.

[0041] The shield receiving system of the present invention is applicable to shield construction in waterless strata and water strata, can simplify the existing shield receiving structure or method, reduce construction costs, and shorten the construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] Figure 1 A cross-sectional view of a piston component of a shield receiving system;

[0043] Figure 2 A front view of a piston component of a shield receiving system;

[0044] Figure 3 It is a partial bottom schematic diagram of a piston component of a shield receiving system;

[0045] Figure 4 A cross-sectional view of a shield receiving assembly of a shield receiving system;

[0046] Figure 5 It is a cross-sectional view of a pre-buried steel ring of a shield receiving system;

[0047] Figure 6 A cross-sectional view of a sleeve of a shield receiving system;

[0048] Figure 7 It is a structural schematic diagram of a shield receiving system in the installation state when receiving shield in water strata;

[0049] Figure 8 It is a schematic diagram of a shield receiving system after the shield receiving system is installed before the shield receiving system is completed when receiving shield in water strata;

[0050] Fig. 9 It is a schematic diagram of a shield receiving system in a state of preparing to receive shields when receiving shields in water strata;

[0051] Fig.10It is a schematic diagram of the state of a shield receiving system after the shield excavation enters the accommodating cavity of the piston component when receiving the shield in a water stratum;

[0052] Fig.11 It is a schematic diagram of the state of a shield receiving system when receiving a shield in a water stratum, after the shield excavation enters the accommodating cavity of the piston component, the reaction force support device is removed and the shield receiving base is installed;

[0053] Fig.12 It is a schematic diagram of a shield receiving system in which the shield pushes the piston component to partially exit the sleeve when receiving the shield in a water stratum;

[0054] Fig.13 It is a schematic diagram of a shield receiving system in a state where the shield pushes the piston component to completely exit the sleeve when receiving the shield in a water stratum;

[0055] Fig.14 It is a schematic diagram of a shield receiving system in a shield receiving state when receiving a shield in a water stratum;

[0056] Fig.15 It is a schematic diagram of the preparation state of a shield receiving system when receiving shield in waterless strata;

[0057] Fig.16 It is a schematic diagram of the state of a shield receiving system when the shield changes from excavation to propulsion when receiving shield in waterless strata;

[0058] Fig.17 It is a schematic diagram of a shield receiving system when the shield pushes the piston component to partially exit the embedded steel ring during shield receiving in waterless strata;

[0059] Fig.18 It is a structural schematic diagram of a shield receiving system when the first elastic sealing component is not arranged in the embedded steel ring;

[0060] Fig.19 The schematic diagram is a structural diagram of a shield receiving system when a transition ring is added to achieve equal inner diameter receiving.

[0061] In the figure: 1-piston member; 11-cylindrical member; 12-end closure member; 121-addition port; 122-inlet and outlet; 123-flange plate; 13-accommodating chamber; 14-extension portion; 15-reinforcement plate; 16-flange opening; 2-embedded steel ring; 21-first elastic sealing assembly; 22-end flange; 23-first air path; 24-first air bag; 25-transition ring; 3-sleeve; 31-second elastic sealing assembly; 32-flange connection; 33-second air bag; 34-inflating interface; 4-tail brush; 41-connecting ring; 5-station end wall; 6-tunnel gate; 7-shield; 8-reaction support frame; 9-soil; 10-shield receiving base; 100-tunnel segment; 110-grouting hole; 120-solid sealing body. DETAILED DESCRIPTION

[0062] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention is further described in detail below in conjunction with specific implementation methods.

[0063] Please refer to Figure 1-6 As shown, an embodiment of the present application provides a shield 7 receiving system, including an embedded steel ring 2, a piston component 1 and a first elastic sealing component 21, the embedded steel ring 2 is provided with a plurality of first elastic sealing components 21 distributed circumferentially along the inner wall, the piston component 1 is arranged in a receiving channel formed by at least the embedded steel ring 2, and the outer periphery of the piston component 1 forms a sliding seal with the receiving channel through the first elastic sealing component 21.

[0064] Among them, the embedded steel ring 2 is set at the station tunnel door 6, and the piston member 1 can be used in conjunction with the embedded steel ring 2, and cooperate with the first elastic sealing component 21 installed on the inner side of the receiving channel to form a sliding seal, so that the piston member 1 can be easily moved in the receiving channel and can be sealed while moving. The embedded steel ring 2 used to form the receiving channel cooperates with the piston member 1 to receive the shield 7. For example, the reception of the shield 7 in the waterless formation can be achieved through the cooperation of the embedded steel ring 2 and the piston member 1. In the case of a certain amount of muddy water or a large amount of muddy water, the reception of the shield 7 can be achieved by extending the length of the receiving channel and increasing the seal.

[0065] Please refer to Figure 1 As shown, in the embodiment of the present application, the piston member 1 is open at one end in the axial direction and closed at the other end, and the open end of the piston member 1 forms a receiving chamber 13 for filling the excavation protection medium for partial entry of the shield 7.

[0066] The piston member 1 is installed in the receiving channel for sliding sealing, and can also have a longer length and be located in the embedded steel ring 2 and the channel member extending the receiving channel at the same time, such as the sleeve 3. The piston member 1 prevents water and soil leakage by sliding sealing with the embedded steel ring 2 and / or sleeve 3 while moving in the embedded steel ring 2 and / or sleeve 3. One end of the piston member 1 is open and the other end is closed, so that the piston member 1 can form a receiving chamber 13 at the open end, and the receiving chamber 13 is used to fill the excavation protection medium such as soil, sand or mortar, while the closed end can be supported and cooperate with the sliding seal of the periphery and the embedded steel ring 2 and / or sleeve 3 to prevent water and soil leakage. The excavation protection medium can not only make the moving component have a larger weight to help maintain the water and soil pressure balance when the shield 7 is excavated, but also can protect the shield 7 when it enters the accommodating chamber 13. At the same time, after entering, the piston component 1 can also cover the end of the shield 7 and move more stably. During the movement, the piston component 1 can simultaneously play the role of moving and positioning in the embedded steel ring 2 and / or sleeve 3 and the role of sliding and sealing with the embedded steel ring 2 and / or sleeve 3. In this way, the length of the sleeve 3 can be greatly reduced by the piston component 1, and the sleeve 3 can even be unnecessary. When the shield 7 is received in a waterless formation, the embedded steel ring 2 that cooperates with the sliding seal can be used for reception.

[0067] Through the above technical scheme, a housing cavity 13 which is open at one end and closed at the other end and formed at the open end can be filled with an excavation protection medium for the shield machine 7 to excavate. The filled excavation protection medium can not only make the piston component 1 have a larger weight, which is beneficial to maintain the water and soil pressure balance and protect the piston component 1 during the excavation of the shield machine 7, but also enable the piston component 1 to move relatively stably with the advancement of the shield machine 7 after the shield machine 7 partially enters the housing cavity 13. At the same time, the piston component 1 maintains a sliding seal with the embedded steel ring 2 and / or the sleeve 3, so that the shield machine 7 can be received, and the situation that the sleeve 3 needs a longer length and a driving device is avoided. In addition, in combination with the embedded steel ring 2 and the first elastic sealing assembly 21, sealing can be achieved during the receiving process of the shield machine 7, and the receiving construction is more convenient and simple.

[0068] In one embodiment, please continue to refer to Figure 1 As shown, the piston component 1 includes an end closure member 12 and a cylindrical member 11, wherein the end closure member 12 is connected to the inner side of the cylindrical member 11 and closes one end of the cylindrical member 11, and the outer periphery of the cylindrical member 11 forms a sliding seal with the receiving channel through a first elastic sealing assembly 21.

[0069] The cylindrical member 11 can have a large outer peripheral area and cooperate with the embedded steel ring 2 and / or the sleeve 3 in a sliding and sealing manner, and can also play a better role in moving and positioning. In combination with the end closure member 12, a receiving chamber 13 filled with excavation protection medium and for the end of the shield 7 to enter can be formed, and the structural design is more reasonable and practical. In the specific implementation process, the cylindrical member 11 and the end closure member 12 can be connected in an integral manner such as welding or integrally molded, or can be connected by a detachable connection method such as bolts, without limitation. The end closure member 12 is an end cover.

[0070] In order to improve the structural stability of the piston member 1, Figure 1 and Figure 2 As shown, further, an extension portion 14 extending in the axial direction is provided at one closed end of the cylindrical member 11 , and a reinforcement portion is provided between the extension portion 14 and the end closing member 12 .

[0071] In this way, the extension portion 14 can be used to facilitate the arrangement of a reinforcement portion, which can be supported between the extension portion 14 and the end closure member 12 to prevent the end closure member 12 from being easily deformed and damaged during the excavation of the shield 7. The extension portion 14 can also further increase the contact area of ​​the sliding seal with the embedded steel ring 2 and / or sleeve 3, which is more conducive to forming a reliable seal.

[0072] Specifically, the reinforcement portion may be a triangular rib or reinforcement plate 15 , which may be multiple and distributed along the circumferential direction, so that the structural stability of the piston component 1 can be better.

[0073] Since the piston member 1 is used to receive the shield 7, the volume will be relatively large. If it is an integrated structure, it will be inconvenient to transport and install. Therefore, in the embodiment of the present application, Figure 2 As shown, the piston component 1 may include a plurality of splicing parts distributed along the circumferential direction, and two adjacent splicing parts are connected by flange connection or welding.

[0074] By being divided into multiple splicing parts, it can be more convenient, quicker, more flexible during installation and transportation, and it is also easier to replace.

[0075] In the specific implementation process, the piston component 1 may include two upper and lower splicing parts spliced ​​to each other, and the extension portion 14 of each splicing part is welded to the end closing component through a triangular reinforcement plate 15. The upper and lower splicing parts are connected at the end closing component through a flange plate 123 and welded at the front end of the cylindrical member 11.

[0076] In order to facilitate filling the excavation protection medium into the accommodating cavity 13, Figure 2As shown, the closed end of the piston member 1 is provided with a filling portion which is in communication with the accommodating chamber 13 to fill the accommodating chamber 13 with the excavation protection medium. The filling portion may be a filling port 121 provided on the end closure member 12, and the filling port 121 may be openable and closable by a cover plate connected by bolts, so that the filling port 121 may be opened during filling and closed after filling.

[0077] In addition, an entrance and exit 122 for personnel to enter and exit may be provided on the end closure 12, and the entrance and exit 122 may also be opened and closed, so that personnel can enter to perform cleaning, installation or maintenance.

[0078] In order to improve the sealing performance of shield 7 during reception and better adapt to the construction environment with water strata, please refer to Figure 4-7 As shown, in an embodiment of the present application, it may also include a sleeve 3 coaxially connected to the embedded steel ring 2, the sleeve 3 and the embedded steel ring 2 together form the receiving channel, and the sleeve 3 is provided with a plurality of groups of second elastic sealing components 31 distributed along the circumferential direction to form a sliding seal with the piston member 1.

[0079] The sleeve 3 is coaxially connected to the embedded steel ring 2, which is equivalent to an extension of the receiving channel, that is, the length of the embedded steel ring 2 can be extended by the sleeve 3. The inner wall of the sleeve 3 is provided with a second elastic sealing component 31, which can form a sliding seal with the piston member 1, so that the piston member 1 can also be sealed when moving in the sleeve 3, and can form a multi-pass seal with the first elastic sealing component 21 in the embedded steel ring 2. During the receiving process of the shield 7, as the receiving of the shield 7 proceeds, the first sealing component and the second sealing component can be pressed against the piston member 1, the outer wall of the shield 7 and the tunnel segment 100 in turn, which can achieve sealing during the entire receiving process of the shield 7 and further improve the sealing effect.

[0080] Furthermore, the axial length of the piston member 1 is greater than or equal to the distance between the second elastic sealing component 31 and the first elastic sealing component 21 so as to form a sliding seal with the embedded steel ring 2 and the sleeve 3 at the same time.

[0081] In this way, the outer periphery of the piston member 1 can cover the embedded steel ring 2 and the sleeve 3 at the same time when ready to receive, so that its outer peripheral surface is in contact with the first elastic sealing component 21 and the second elastic sealing component 31 at the same time to achieve multi-pass sealing, thereby more effectively preventing water and soil leakage.

[0082] In one application scenario, when receiving the shield 7 in a waterless stratum or a stratum with low water pressure, the reception can be carried out through the cooperation between the piston member 1 and the embedded steel ring 2. By setting a tail brush 4 at the outer end of the embedded steel ring 2 (i.e., the side close to the station), the tail brush 4 can form multiple seals with the first elastic sealing component 21 in the embedded steel ring 2, which can meet the sealing requirements of the reception of the shield 7. At the same time, in this scenario, the tail brush 4 can also be provided with a first adjustment component for adjusting the pressing force. The first adjustment component is used to adjust the pressing force of the elastic tail brush 4, so that the tail brush 4 has a greater pressing force to press on the piston member 1 or the outer wall of the shield 7 to form a more effective seal.

[0083] In another application scenario, a sleeve 3 is provided for a water-bearing formation with relatively high water pressure. In order to enhance the sealing between the end of the sleeve 3 and the piston member 1 or the shield 7, a tail brush 4 is provided at the end of the sleeve 3 away from the embedded steel ring 2. The tail brush 4 is provided at the end of the sleeve 3, and a flange connection portion 32 is provided at the end of the sleeve 3. The tail brush 4 is fixed on the flange connection portion 32 along the circumferential direction to form the last seal on the outside. At the same time, in this scenario, a tail brush 4 is provided at the end of the sleeve 3 away from the embedded steel ring 2. The tail brush 4 is provided with a second adjustment component for adjusting the pressing force. The second adjustment component is used to adjust the pressing force of the tail brush 4, so that the tail brush 4 has a greater pressing force to press against the outer wall of the piston member 1 or the shield 7 to form a more effective seal.

[0084] In the specific implementation process, the first elastic sealing component 21, the second elastic sealing component 31 and the tail brush 4 can adopt spring steel plate brushes, which are fixed to the inner wall along the circumferential direction and can be arranged in multiple paths along the circumferential direction, so as to form a sealing structure with better sealing performance; of course, the first elastic sealing component 21, the second elastic sealing component 31 and the tail brush 4 can also adopt the existing sealing structure without limitation.

[0085] When the first elastic sealing component 21, the second elastic sealing component 31 and the tail brush 4 are spring steel brushes, their pressing force will change due to the change in the diameter of the pressed object. When the outer wall of the shield 7 and the tunnel segment 100 are pressed and sealed, their pressing force may not be sufficient to achieve effective sealing only by their own elastic force. The first elastic sealing component 21 and the second elastic sealing component 31 can also be provided with a third adjustment component for adjusting their pressing force, so as to achieve a better sealing effect more flexibly.

[0086] The first adjustment component and the second adjustment component structure provided on the tail brush 4 preferably adopt the same structure. For example, a steel wire can be used to pass through the connecting ring 41 on each spring steel plate brush of the tail brush 4 to connect the tail brushes 4 in series, and then the steel wire is operated by a hand winch to adjust the pressing force of the tail brush 4.

[0087] In a preferred embodiment of the third adjustment component, Figure 5 and Figure 6 As shown, the first elastic sealing component 21 includes a plurality of first spring steel plate brushes distributed in a circle along the circumferential direction, and the third adjustment component arranged on the first elastic sealing component 21 may include a first air bag 24 arranged between adjacent first elastic sealing components 21, and the first air bag 24 is provided with a first air inlet, and the first air inlet is connected to an external first air pump through a first air path 23 buried in the embedded steel ring 2, and the first air bag 24 can be inflated by the first air pump, and the elastic free end of the first spring steel plate brush can be squeezed by inflation, so that the elastic free end of the spring moves inward and is tightly pressed against the piston member 1, the outer wall of the shield 7 or the tunnel segment 100.

[0088] Correspondingly, the third adjustment component arranged on the second elastic sealing component 31 has a structure basically the same as the third adjustment component on the first elastic sealing component 21, except that the second air bag 33 included in the third adjustment component is connected to the second air pump through the second air path passing through the sleeve 3, and the second air path is connected to the second air pump through the inflation interface 34.

[0089] In addition, the embedded steel ring may not be provided with the first elastic sealing component. If the production of the cast-in-place ring beam of the tunnel and the station end wall 5 is not considered in the later stage, the installation of the first elastic sealing component 21 may be cancelled. Fig.18 As shown, only the second elastic sealing assembly 31 and the tail brush 4 are used for sealing, so that the length of the piston member 1 can be shortened, which ensures the safe reception of the shield 7 without much change in the operation process. However, the piston member 11 will be shorter and more solid in structure, making it easier to operate during the reception process and more conducive to installation and removal.

[0090] In an embodiment of the present application, a reaction force support device and a shield receiving base 10 are also included. The reaction force support device is used to support the piston member 1 before the piston member 1 moves with the shield 7, and the shield receiving base 10 is used to support the piston member 1 and / or the shield 7.

[0091] The reaction force support device can support and fix the piston member 1, which can help the piston member 1 to more stably resist the excavation force of the shield 7 during the excavation process, so that the reaction force support device can be removed after the shield 7 enters the accommodating cavity 13 of the piston member 1, and the piston member 1 will move with the advancement of the shield 7. The shield receiving base 10 is mainly used for supporting the shield 7 when receiving it, and of course it can also support the piston member 1 and facilitate installation.

[0092] Specifically, the reaction force support device may include a reaction force support frame 8, which is connected to the end closure member 12 and provides oblique support.

[0093] Please refer to Figure 8-14 As shown, based on the above-mentioned shield system 7, an embodiment of the present application also provides a shield receiving method 7, comprising the following steps:

[0094] Step S1: Before the shield machine 7 enters the receiving area of ​​the shield machine 7, a plurality of first elastic sealing components 21 distributed along the circumferential direction are installed on the inner wall of the embedded steel ring 2 of the tunnel portal 6 at the receiving end of the shield machine 7, and a piston member 1 is installed on the inner side of the embedded steel ring 2, and the first elastic sealing component 21 is pressed against the outer periphery of the piston member 1, and a sliding seal is formed between the piston member 1 and the embedded steel ring 2 through the first elastic sealing component 21, wherein one end of the piston member 1 in the axial direction is open and the other end is closed, and the open end of the piston member 1 forms a accommodating cavity 13 for filling with excavation protection medium for partial entry of the shield machine 7.

[0095] When the shield 7 is received in the waterless stratum, the following steps are also included:

[0096] Step S2: Install a tail brush 4 at one end of the embedded steel ring 2 close to the station, and the tail brush 4 is pressed against the outer wall of the piston component 1.

[0097] Step S3: Install the reaction force support device on the rear side of the piston member 1, and fill the accommodating cavity 13 in the piston member 1 with soil 9 and make the soil 9 dense. In this step, the reaction force support device can support the piston member 1 before it moves with the shield 7, so that the shield 7 can enter the accommodating cavity 13 of the piston member 1 more stably, which also makes the reception more stable.

[0098] Step S4: Shield machine 7 receives the shield 7. Shield machine 7 cuts into the soil 9 in the accommodating cavity 13 of piston member 1 from the station end wall 5. When the cutter head of shield machine 7 approaches the closed end of piston member 1, shield machine 7 stops excavating, and the reaction force support device is removed and shield receiving base 10 is installed in front of piston member 1. In this step, after shield machine 7 excavates into piston member 1, shield machine 7 switches from excavation mode to propulsion mode, and through propulsion, piston member 1 can slide forward on shield receiving base 10 to receive. Such a forward mode is more stable, reliable and safer than full excavation reception.

[0099] Step S5: The shield 7 is advanced, and the shield 7 and the piston member 1 pushed by the shield 7 move together on the shield receiving base 10. When the piston member 1 leaves the first elastic sealing component 21 installed in the embedded steel ring 2, the first elastic sealing component 21 is pressed against the outer shell of the shield 7. In this step, the pressing object of the first elastic sealing component 21 is changed from the piston member 1 to the outer shell of the shield 7, and the sealing transition is more connected and reliable under the action of its elastic seal.

[0100] Step S6: The shield 7 pushes the piston member 1 to continue sliding on the shield receiving base 10 until the shield tail of the shield 7 leaves the inner area of ​​the embedded steel ring 2, and the tail brush 4 is pressed against the outer shell of the shield 7. In this step, the tail brush 4 is also pressed against the outer shell of the shield 7 by the piston member 1, so that an effective seal can be formed on the outermost side.

[0101] Step S7: dismantle the piston member 1, the shield 7 and the shield receiving base 10, and the receiving work of the shield 7 is completed.

[0102] Through the above-mentioned receiving method, the shield 7 in the waterless formation can be received, and the shield 7 can be received mainly through the cooperation between the embedded steel ring 2 and the piston component 1. In this way, the use of other channel components such as the sleeve 3 can be avoided, thereby achieving the purpose of reducing costs, improving receiving efficiency and making operation more convenient.

[0103] Please refer to Figure 15-17 As shown, when the shield machine 7 receives the water-bearing stratum, in addition to the same step S1, the following different steps are also included:

[0104] Step S02: The sleeve 3 is installed on the outer side of the piston member 1, the sleeve 3 is coaxially connected with the embedded steel ring 2, and the second elastic sealing component 31 installed in the sleeve 3 is pressed against the outer periphery of the piston member 1, and the piston member 1 forms a sliding seal with the piston member 1 through the second elastic sealing component 31. In this step, the sleeve 3 is used as an extension of the receiving channel, and it can form a sliding seal with the piston member 1 through the second elastic sealing component 31, so that when receiving, the piston member 1 can form a seal with the sleeve 3 and the embedded steel ring 2 at the same time, and can form a triple seal with the tail brush 4, which greatly enhances the sealing performance for water-containing formations.

[0105] Step S03: Install the tail brush 4 at the end of the sleeve 3 away from the embedded steel ring 2, and press the tail brush 4 against the outer wall of the piston member 1; in this step, the tail brush 4 can be tightened by the hand winch through the second adjustment component, so that this circle of spring steel plate brush will be reliably pressed against the outer surface of the piston member 1, and the spring steel plate brush will have better water-stopping ability.

[0106] Step S04: Install the reaction force support device on the rear side of the piston member 1, and fill the accommodating cavity 13 in the piston member 1 with soil 9 and make the soil 9 dense. In this step, the reaction force support device can support the piston member 1 before it moves with the shield 7, so that the shield 7 can enter the accommodating cavity 13 of the piston member 1 more stably, which also makes the reception more stable.

[0107] Step S05: Shield machine 7 receives the shield 7. Shield machine 7 cuts into the soil 9 in the accommodating cavity 13 of piston member 1 from the station end wall 5. When the cutter head of shield machine 7 approaches the closed end of piston member 1, shield machine 7 stops excavating, and the reaction force support device is removed and shield receiving base 10 is installed in front of piston member 1. In this step, after shield machine 7 excavates into piston member 1, shield machine 7 switches from excavation mode to propulsion mode, and through propulsion, piston member 1 can slide forward on shield receiving base 10 to receive. This advancing mode is more stable, reliable and safer than full excavation reception.

[0108] Step S06: The shield 7 is advanced, and the shield 7 and the piston member 1 pushed by the shield 7 move together on the shield receiving base 10. When the piston member 1 leaves the first elastic sealing component 21 installed in the embedded steel ring 2, the first elastic sealing component 21 is pressed against the outer shell of the shield 7. In this step, the pressing object of the first elastic sealing component 21 is changed from the piston member 1 to the outer shell of the shield 7, and the sealing transition is more connected and reliable under the action of its elastic seal.

[0109] Step S07: The shield 7 pushes the piston member 1 to continue sliding on the shield receiving base 10. When the piston member 1 leaves the inner area of ​​the sleeve 3, the second elastic sealing component 31 in the sleeve 3 is pressed against the outer shell of the shield 7.

[0110] Step S08: The shield 7 pushes the piston member 1 to continue sliding on the shield receiving base 10 until the shield tail of the shield 7 leaves the inner area of ​​the embedded steel ring 2, at which time the first elastic sealing component 21 in the embedded steel ring 2 is pressed against the outer surface of the tunnel segment 100. In this step, the combined sealing structure composed of the embedded steel ring 2, the spring steel plate brush, and the tunnel segment 100 also blocks the passage of muddy water outside the station into the station, and the combined sealing structure formed by the embedded steel ring 2, the sleeve 3, the spring steel ring brush, and the outer shell of the shield 7 can also block the passage of muddy water outside the station into the station. At this time, the first airbag 24 between the spring steel plate brushes can be sealed and inflated through the first air path 23. After the first airbag 24 is inflated, the soil 9 on the outside of the spring steel plate brush is squeezed and cannot move. In this way, the inflated first airbag 24 will squeeze the spring steel plate brush, making the spring steel plate brush closer to the outer surface of the tunnel segment 100, thereby enhancing the water-stopping ability of the spring steel plate brush. During the later production of the ring beam of the tunnel portal 6, the tunnel segment 100 near the station at the tunnel portal 6 is removed, and the tunnel segment 100 The waterproof ability between the embedded steel ring 2 will be weakened. With the spring steel plate brush, the water-stopping sealing ability of this position will be significantly improved. Moreover, these spring steel plate brushes close to the soil body 9 do not need to be removed, nor will they affect the later production of the tunnel portal 6 ring beam. They can also prevent mud and water outside the station from entering the station during the production of the tunnel portal 6 ring beam. During the production of the tunnel portal 6 ring beam, the mud and water outside the station are blocked from entering the station through the gap between the embedded steel ring 2 and the tunnel segment 100. This is the main purpose of setting these spring steel plate brushes.

[0111] Step S09: Grouting is performed to reinforce the soil 9 outside the tunnel through the grouting holes 110 on the tunnel segments 100 built by the shield 7. After the grouting solidifies, a solid seal 120 is formed to prevent muddy water from entering the station. In this step, the solid seal 120 formed by the solidification of the mortar can effectively block the passage of muddy water outside the station into the station.

[0112] Step S10: dismantle the piston member 1, the sleeve 3, the shield 7 and the shield receiving base 10, and the receiving work of the shield 7 is completed.

[0113] Through the above-mentioned receiving method, the shield machine 7 in the water-containing stratum can be received, and the shield machine 7 can be received through the cooperation of the embedded steel ring 2, the sleeve 3, and the piston member 1. In this way, the use of a longer sleeve 3 can be avoided, thereby achieving the purpose of reducing costs, improving receiving efficiency and making operation more convenient.

[0114] It is understandable that the above-mentioned waterless formation is not absolute, and also includes formations with low water pressure. The waterless formation is only distinguished under the premise of meeting the clear definition, so it does not only refer to the waterless formation. Similarly, the water formation is relative to the waterless formation, including the formation with high water pressure, which can be selected and used according to the sealing capacity of this application without limitation.

[0115] It should be noted that if the production of the cast-in-place ring beam of the tunnel and the station end wall 5 is not considered, the installation of the first elastic sealing component 21 can be cancelled. Fig.18 As shown, only the second elastic sealing assembly 31 and the tail brush 4 are used for sealing, so that the piston member 1 can be shortened, which ensures the safe reception of the shield 7 while the operation process does not change much. However, the piston member 1 will be shorter, the structure will be more solid, it will be easier to operate during the reception process, and it will be more conducive to installation and removal.

[0116] In one application scenario, combined with Fig.19 As shown, in order to achieve equal inner diameter reception of the mobile piston and the embedded steel ring, a transition ring 25 connected between the sleeve 3 and the embedded steel ring 2 may also be included, and the inner diameter of the transition ring 25, the inner diameter of the embedded steel ring 2 and the inner diameter of the mobile piston are consistent. The front end of the transition ring 25 is connected to the embedded steel ring 2, and the transition ring 25 and the sleeve 3 are connected by a flange. After the inner diameter of the sleeve 3 is enlarged, the inner diameter of the mobile piston can be guaranteed to be consistent with the inner diameter of the embedded steel ring 2.

[0117] The first elastic sealing component 21 in the text can be a sealing system composed of two or more tail brushes according to actual needs, and there is no limitation. The second elastic sealing component 31 in the text can be a sealing system composed of two or more tail brushes. The more the second elastic sealing components 31 are, the longer the length of the sleeve 3 can be appropriately extended. The more the second elastic sealing components 31 are, the higher the sealing ability of the receiving system is, which is more suitable for receiving occasions with high groundwater pressure or deeper burial depth. Therefore, the adaptability of this patent is relatively strong.

[0118] The elastic sealing component 21 and the second elastic sealing component 31 herein may be spring steel wire brushes, spring steel plate brushes, or sealing plates made of rubber or polyurethane, without limitation.

[0119] In addition, the first airbag 24 can be eliminated, and the first air path 23 can be replaced by a shield tail grease injection pipeline. When the first elastic sealing component 21 is required to function, shield tail grease is injected into the cavity between the first elastic sealing components 21 through the shield tail grease pipeline for sealing. Correspondingly, the second airbag 33 can also be eliminated, and the inflation interface 34 can be replaced by a shield tail grease injection pipeline. When the second elastic seal is required to function, shield tail grease is injected into the cavity between the second elastic sealing components 31 through the shield tail grease pipeline for sealing.

[0120] The above are only preferred embodiments of the present invention. It should be noted that the above preferred embodiments should not be regarded as limiting the present invention, and the protection scope of the present invention should be based on the scope defined by the claims. For ordinary technicians in this technical field, several improvements and modifications can be made without departing from the spirit and scope of the present invention, and these improvements and modifications should also be regarded as the protection scope of the present invention.

Claims

1. A shield receiving system, It is characterized in that It comprises an embedded steel ring, a piston component and a first elastic sealing component, wherein the embedded steel ring is provided with a plurality of first elastic sealing components distributed along the circumference of the inner wall, the piston component is arranged in a receiving channel formed by at least the embedded steel ring, and the outer periphery of the piston component forms a sliding seal with the receiving channel through the first elastic sealing component; The piston component is open at one end in the axial direction and closed at the other end. The open end of the piston component forms an accommodating chamber for filling a tunneling protection medium for the shield part to enter.

2. A shield receiving system as claimed in claim 1, It is characterized in that The piston component comprises an end closure member and a cylindrical member. The end closure member is connected to the inner side of the cylindrical member and closes one end of the cylindrical member. The outer periphery of the cylindrical member forms a sliding seal with the receiving channel through a first elastic sealing assembly.

3. A shield receiving system as claimed in claim 2, It is characterized in that An extension portion extending in the axial direction is provided at one closed end of the cylindrical member, and a reinforcement portion is provided between the extension portion and the end closing member.

4. A shield receiving system as claimed in claim 2, It is characterized in that The end closure is provided with a filling portion which is communicated with the accommodating cavity so as to fill the accommodating cavity with a tunneling protection medium.

5. A shield receiving system as claimed in claim 1, It is characterized in that The piston component comprises a plurality of splicing parts distributed along the circumferential direction, and two adjacent splicing parts are connected by flange connection or welding.

6. A shield receiving system as claimed in claim 1, It is characterized in that It also includes a sleeve coaxially connected to the embedded steel ring, the sleeve and the embedded steel ring together form the receiving channel, and the sleeve is provided with a plurality of groups of second elastic sealing components distributed along the circumferential direction to form a sliding seal with the piston component.

7. A shield receiving system as claimed in claim 6, It is characterized in that The axial length of the piston component is greater than or equal to the distance between the second elastic sealing component and the first elastic sealing component so as to form a sliding seal with the embedded steel ring and the sleeve at the same time.

8. A shield receiving system as claimed in claim 6, It is characterized in that It also includes a transition ring connected between the sleeve and the embedded steel ring, and the inner diameter of the transition ring, the inner diameter of the embedded steel ring and the inner diameter of the moving piston are consistent.

9. A shield receiving system according to any one of claims 1 to 5, It is characterized in that A tail brush is provided at the outer end of the embedded steel ring, and the tail brush is provided with a first adjustment component for adjusting the pressing force.

10. A shield receiving system according to any one of claims 6 to 8, It is characterized in that A tail brush is arranged at one end of the sleeve away from the embedded steel ring.

11. A shield receiving system as claimed in claim 10, It is characterized in that The embedded steel ring is not provided with a first elastic sealing component.

12. A shield receiving system as claimed in claim 6, It is characterized in that The first elastic sealing component and the second elastic sealing component are both provided with a third adjustment component for adjusting the pressing force.

13. A shield receiving system as claimed in claim 1, It is characterized in that It also includes a reaction force support device and a shield receiving base. The reaction force support device is used to support the piston component before the piston component moves with the shield, and the shield receiving base is used to support the piston component and / or the shield.

14. A shield receiving method, It is characterized in that The following steps are involved: Before the shield enters the shield receiving area, a plurality of first elastic sealing components distributed along the circumferential direction are installed on the inner wall of the embedded steel ring of the tunnel door at the shield receiving end, and a piston component is installed on the inner side of the embedded steel ring, the first elastic sealing component is pressed against the outer circumference of the piston component, and the piston component forms a sliding seal with the embedded steel ring through the first elastic sealing component, wherein one end of the piston component in the axial direction is open and the other end is closed, and the open end of the piston component forms a receiving cavity for filling the excavation protection medium for the shield part to enter; When shield receiving the waterless stratum, the following steps are also included: A tail brush is installed at one end of the embedded steel ring close to the station, and the tail brush is pressed against the outer wall of the piston component; A reaction force support device is installed on the rear side of the piston component, and the accommodating cavity in the piston component is filled with soil and the soil is compacted; The shield receives the shield. The shield cuts into the soil in the piston component accommodating cavity from the station end wall. When the shield cutterhead approaches the closed end of the piston component, the shield stops excavating, and the reaction force support device is removed and the shield receiving base is installed in front of the piston component. The shield advances, and the shield and the piston member pushed by the shield move together on the shield receiving base. When the piston member leaves the first elastic sealing component installed in the embedded steel ring, the first elastic sealing component is pressed against the outer shell of the shield; The shield pushes the piston member to continue sliding on the shield receiving base until the shield tail leaves the inner area of ​​the embedded steel ring, and the tail brush is pressed against the outer shell of the shield; The piston components, shield and shield receiving base are dismantled, and the shield receiving work is completed.

15. A shield receiving method as claimed in claim 14, It is characterized in that When receiving water-bearing formations, the following steps are also included: A sleeve is installed on the outer side of the piston component, the sleeve is coaxially connected to the embedded steel ring, and a second elastic sealing component installed in the sleeve is pressed against the outer periphery of the piston component, and the piston component forms a sliding seal with the piston component through the second elastic sealing component; A tail brush is installed at the end of the sleeve away from the embedded steel ring, and the tail brush is pressed against the outer wall of the piston component; A reaction force support device is installed on the rear side of the piston component, and the accommodating cavity in the piston component is filled with soil and the soil is compacted; The shield receives the shield. The shield cuts into the soil in the piston component accommodating cavity from the station end wall. When the shield cutterhead approaches the closed end of the piston component, the shield stops excavating, and the reaction force support device is removed and the shield receiving base is installed in front of the piston component. The shield advances, and the shield and the piston member pushed by the shield move together on the shield receiving base. When the piston member leaves the first elastic sealing component installed in the embedded steel ring, the first elastic sealing component is pressed against the outer shell of the shield; The shield pushes the piston member to continue sliding on the shield receiving base. When the piston member leaves the inner area of ​​the sleeve, the second elastic sealing component in the sleeve is pressed against the outer shell of the shield. The shield pushes the piston member to continue sliding on the shield receiving base until the shield tail leaves the inner area of ​​the embedded steel ring. At this time, the first elastic sealing component in the embedded steel ring is pressed against the outer surface of the tunnel segment; Grouting is carried out to reinforce the soil outside the tunnel through the grouting holes on the shield-built tunnel segments. After the grouting solidifies, it forms a solid seal to prevent mud and water from entering the station. The piston component, sleeve, shield and shield receiving base are removed, and the shield receiving work is completed.

Citation Information

Cited By

  • Shield construction sealing system and shield construction method

    CN119981927A