Circular venue steel structure sliding construction method
By installing circular tracks on a circular venue and using their sliding installation of steel pipe trusses, the problem of multiple movements of lifting equipment and high-altitude operations during traditional lifting is solved, and simple and efficient steel structure installation is achieved, which improves construction safety Sex and efficiency.
Patent Information
- Application Number
- CN202411383962.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-12-10
AI Technical Summary
During the lifting process of the steel structure of the circular venue, the steel pipe trusses are heavy and require multiple transitions to hoist. The lifting equipment is high in specifications, the lifting is difficult, and the construction area is limited, which increases safety risks.
Install ring tracks on a circular venue, use lifting equipment to lift steel pipe trusses to the track, and slide along the track to the installation position to fix the connection, avoid multiple movements of the lifting equipment and simplify the lifting process.
It reduces the number of movements of lifting equipment, reduces the difficulty of lifting, improves construction efficiency and safety, shortens the construction cycle, and reduces the risks of workers' high-altitude operations.
Smart Images

Figure CN119102377A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of truss steel structure construction of a circular ring-shaped space venue, and in particular to a circular venue steel structure sliding construction method. Background Art
[0002] With the rapid development of society, people's enthusiasm for sports is getting higher and higher. In order to meet the needs of the people, the demand for the construction of new venues in major cities has continued to surge. At the same time, the shapes and structural structures of various venues are becoming more and more complex. Various spatial steel tube trusses + roof chord-supported lattice shells have emerged. In order to solve the hoisting problem, the following problems must be solved: 1. The weight of a single truss of the spatial tube truss is large, and it requires cranes to transfer and hoist in multiple places, and many aerial splicing. The lifting equipment has high specifications and is difficult to lift; 2. In order to meet the construction, the assembly site requires a wide range; 3. The local location may be limited, and the lifting requirements are higher; 4. Reduce high-altitude operations and reduce safety risks. Summary of the invention
[0003] The present application provides a circular stadium steel structure sliding construction method, aiming to solve at least one of the above problems.
[0004] The present application provides a circular stadium steel structure sliding construction method, which is mainly used for the installation of steel pipe truss steel structure of circular stadium, and is characterized by:
[0005] At least one circular track is installed on the circular venue, and the circular track is arranged concentrically with the circular venue;
[0006] Using a lifting device to hoist the first steel pipe truss onto the annular track at the hoisting station, so as to slide with the annular track;
[0007] Move the first steel tube truss along the circular track until it completely leaves the hoisting station;
[0008] The second steel pipe truss is hoisted onto the annular track by using the hoisting equipment again at the hoisting station;
[0009] The second steel tube truss is fixedly connected to the first steel tube truss, and moved along the circular track until it completely leaves the hoisting station;
[0010] Repeat the above steps until all steel tube trusses are installed.
[0011] The above circular stadium steel structure sliding construction method sets up a circular track in advance. It only needs lifting equipment to lift the steel pipe truss to the circular track at the lifting station, and then move the steel pipe truss to the installation position by the circular track. There is no need to move the lifting equipment during the entire installation process, which effectively solves the problem of traditional installation technology requiring lifting equipment to be transferred to multiple locations for lifting and the difficulty of lifting. The lifting is simple, efficient, short in construction period and safe.
[0012] In the technical solution of one embodiment, in the step 1, three circular tracks are installed on the circular venue, the three circular tracks are arranged concentrically with the circular venue, and the three circular tracks are arranged from outside to inside and from low to high.
[0013] In the technical solution of one embodiment, each steel tube truss is divided into three independent parts at the bottom, middle and top, which are successively hoisted by lifting equipment until they are slidably matched with three circular tracks, and then the three independent parts are fixedly connected into a whole.
[0014] In the technical solution of one embodiment, the three circular tracks are respectively a first circular track, a second circular track and a third circular track, and the first circular track, the second circular track and the third circular track are arranged from outside to inside and from low to high; wherein, the first circular track and the second circular track are fixedly installed on the circular venue, and the third circular track adopts an independent circular support system to stand inside the circular venue.
[0015] In the technical solution of one embodiment, the annular support system includes lattice columns in a circular array, and the third annular track is fixedly mounted on the lattice columns; and circular tube single column supports are arranged between the lattice columns.
[0016] In the technical solution of one embodiment, after each three steel tube trusses are hoisted and fixedly connected, the three steel tube trusses are moved to the installation position; three steel tube trusses are hoisted and fixedly connected again, and also moved to the corresponding installation position, and so on, until all steel tube trusses are hoisted; finally, all steel tube trusses are fixedly connected.
[0017] In the technical solution of one embodiment, after each steel tube truss is hoisted, the steel tube truss is moved to the installation position, and so on, until the hoisting of all steel tube trusses is completed; finally, all steel tube trusses are fixedly connected.
[0018] In the technical solution of one embodiment, in the step one, a plurality of groups of pushing devices are evenly installed at the circular track, and the pushing devices are used to push the steel pipe truss to move along the circular track within their pushing range, and the pushing ranges of adjacent pushing devices overlap.
[0019] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application, it can be implemented in accordance with the contents of the specification. In order to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are listed below. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The drawings in this application are used to illustrate preferred embodiments, so as to facilitate a person skilled in the art to clearly understand various other advantages and benefits, and should not be considered as limiting this application. In addition, the same reference numerals are used to represent the same components in all the drawings.
[0021] Figure 1 The three-dimensional modeling of the circular stadium in the embodiment of the present application Figure 1 .
[0022] Figure 2 The three-dimensional modeling of the circular stadium in the embodiment of the present application Figure 2 .
[0023] Figure 3 The three-dimensional modeling of the circular stadium in the embodiment of the present application Figure 3 .
[0024] Figure 4 The three-dimensional modeling of the circular stadium in the embodiment of the present application Figure 4 .
[0025] Figure 5 The three-dimensional modeling of the circular stadium in the embodiment of the present application Figure 5 .
[0026] Figure 6 The three-dimensional modeling of the circular stadium in the embodiment of the present application Figure 6 .
[0027] Explanation of the accompanying drawings: 10 - circular venue; 11 - steel pipe truss; 21 - first circular track; 22 - second circular track; 23 - third circular track; 30 - lifting equipment. DETAILED DESCRIPTION
[0028] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with specific embodiments. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0029] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0030] In the description of the embodiments of the present application, the meaning of "multiple" is more than two (including two), unless otherwise clearly and specifically limited. The orientation or positional relationship indicated by the technical terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc. is based on the orientation or positional relationship shown in the accompanying drawings, which is only for the convenience of describing the embodiments of the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the embodiments of the present application.
[0031] In the description of the embodiments of the present application, unless otherwise clearly specified and limited, technical terms such as "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal connection of two elements or the interaction relationship between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the embodiments of the present application can be understood according to the specific circumstances.
[0032] See also Figure 1-6 The embodiment of the present application provides a circular stadium steel structure sliding construction method, which is mainly used to install a steel structure composed of a plurality of steel pipe trusses 11 on a circular stadium 10.
[0033] Embodiment 1
[0034] A circular stadium steel structure sliding construction method comprises the following steps:
[0035] Step 1: See Figure 1 At least one circular track is installed on the circular venue 10, and the circular track is arranged concentrically with the circular venue 10 and also concentrically with the steel structure composed of a plurality of steel pipe trusses 11.
[0036] Step 2: See Figure 2 , a lifting device 30 is used to lift the first steel tube truss 11 onto the circular track at the lifting station, and the steel tube truss 11 is slidably matched with the circular track.
[0037] Step 3: See Figure 3 , move the first steel tube truss 11 along the circular track until it completely leaves the hoisting station to make room for the next steel tube truss 11 to be hoisted.
[0038] Step 4: See Figure 4 , the lifting equipment 30 is used again to lift the second steel tube truss 11 to the annular track at the lifting station, and the steel tube truss 11 is slidably matched with the annular track.
[0039] Step 5: Fix the second steel tube truss 11 to the first steel tube truss 11 through a connector, and move it along the circular track until it completely leaves the lifting station to make room for the next steel tube truss 11 to be lifted.
[0040] Step 6: See Figure 6 , repeat the above steps 2 to 5, and so on, until all the steel tube trusses 11 are installed.
[0041] The above-mentioned circular stadium steel structure sliding construction method sets up the circular track in advance. It only needs the lifting equipment 30 to lift the steel pipe truss 11 to the circular track at the lifting station, and then move the steel pipe truss 11 to the installation position by the circular track. The lifting equipment 30 does not need to be moved during the entire installation process, which effectively solves the problem of requiring 30 lifting equipments to transfer and lift in multiple places and the difficulty of lifting in the traditional installation process; and the lifting is simple, efficient, short in construction period and high in safety.
[0042] Embodiment 2
[0043] A circular stadium steel structure sliding construction method comprises the following steps:
[0044] Step 1: See Figure 1 At least one circular track is installed on the circular venue 10, and the circular track is arranged concentrically with the circular venue 10 and also concentrically with the steel structure composed of a plurality of steel pipe trusses 11.
[0045] Step 2: See Figure 2 , a lifting device 30 is used to lift the first steel tube truss 11 onto the circular track at the lifting station, and the steel tube truss 11 is slidably matched with the circular track.
[0046] Step 3: Move the first steel tube truss 11 along the circular track to the installation position. It should be noted that the installation position of the first steel tube truss 11 refers to the fixed position on the circular stadium 10 when it constitutes the steel structure.
[0047] Step 4: Repeat the above step 3 until all the steel tube trusses 11 are hoisted. Figure 6 .
[0048] Step 5: Finally, all the steel tube trusses 11 are fixedly connected by connecting pieces.
[0049] The above circular stadium steel structure sliding construction method sets up a circular track in advance, and only requires the lifting equipment 30 to lift the steel tube truss 11 to the circular track at the lifting station, and then move the steel tube truss 11 to the installation position by the circular track. The lifting equipment 30 does not need to be moved during the entire installation process, which well solves the problem of the need for lifting equipment 30 to transfer and lift in multiple places and the difficulty of lifting in the traditional installation process; and the lifting is simple, efficient, short in construction period, and highly safe. Moreover, by lifting a steel tube truss 11, moving a steel tube truss 11 to the installation position, and finally performing the overall fixed connection, it is relatively labor-saving and prevents the difficulty of moving due to too many connections of the steel tube truss 11.
[0050] Embodiment 3
[0051] Step 1: See Figure 1 At least one circular track is installed on the circular venue 10, and the circular track is arranged concentrically with the circular venue 10 and also concentrically with the steel structure composed of a plurality of steel pipe trusses 11.
[0052] Step 2: See Figure 2 , a lifting device 30 is used to lift the first steel tube truss 11 onto the circular track at the lifting station, and the steel tube truss 11 is slidably matched with the circular track.
[0053] Step 3: See Figure 3 , move the first steel tube truss 11 along the circular track until it completely leaves the hoisting station to make room for the next steel tube truss 11 to be hoisted.
[0054] Step 4: See Figure 4 , the lifting equipment 30 is used again to sequentially lift the second and third steel pipe trusses 11 onto the circular track at the lifting station.
[0055] Step 5: See Figure 5 The first, second and third steel tube trusses 11 are first fixedly connected by connecting pieces, and then moved to the installation position along the circular track. It should be noted that the installation position of the steel tube trusses 11 refers to the fixed position on the circular stadium 10 when the steel structure is formed.
[0056] Step 6: See Figure 6 Repeat the above steps 2 to 5, and so on, until all the steel tube trusses 11 are installed, and finally all the steel tube trusses 11 are fixedly connected into an integral steel structure.
[0057] The above circular stadium steel structure sliding construction method sets up a circular track in advance, and only needs the lifting equipment 30 to lift the steel tube truss 11 to the circular track at the lifting station, and then move the steel tube truss 11 to the installation position by the circular track. The lifting equipment 30 does not need to be moved during the entire installation process, which solves the problem of the traditional installation process requiring lifting equipment 30 to transfer and lift in multiple places, and the difficulty of lifting and lifting; and the lifting is simple, efficient, short in construction period, and highly safe. In addition, connecting the steel tube trusses 11 in groups of three first and then moving them to the installation position can prevent the difficulty of moving due to too many connections, while also achieving installation efficiency.
[0058] Based on any of the above embodiments, in some specific implementations, three circular tracks are installed on the circular venue 10. The three circular tracks are arranged concentrically with the circular venue 10. The three circular tracks are arranged from outside to inside and from low to high. Figure 1 The three annular tracks support the upper, middle and lower parts of the steel tube truss 11 respectively, so that it can move stably without deformation.
[0059] It is understandable that setting three paths is the most preferred here, and it is understandable that more than two paths can achieve the above effect.
[0060] In a further specific embodiment, each steel tube truss 11 corresponds to three circular tracks, and is divided into three independent parts, namely, the lower, middle and upper parts, which are sequentially hoisted by the lifting equipment 30 until they are slidably matched with the three circular tracks, and then the three independent parts are fixedly connected into a whole. Dividing each larger and heavier steel tube truss 11 into three smaller and lighter parts, and hoisting them in three times, can reduce the pressure of the hoisting equipment 30, make the hoisting more stable, reduce the requirements for the hoisting equipment 30, and facilitate the operation and reduce the cost.
[0061] Specifically, the three circular tracks are respectively a first circular track 21, a second circular track 22 and a third circular track 23, and the first circular track 21, the second circular track 22 and the third circular track 23 are arranged from outside to inside and from low to high; Figure 1 As shown, the first annular track 21 and the second annular track 22 are fixedly mounted on the circular stadium 10, and the third annular track 23 is supported inside the circular stadium 10 by an independent annular support system to ensure overall stability.
[0062] The annular support system includes lattice columns in an annular array, and the third annular track 23 is fixedly mounted on the lattice columns; and circular tube single column supports are arranged between the lattice columns to further increase the overall stability.
[0063] Based on any of the above embodiments, in some specific implementations, multiple groups of jacking devices are evenly installed at the annular track, and the jacking devices are used to push the steel tube truss 11 to move along the annular track within their jacking ranges, and the jacking ranges of adjacent jacking devices overlap. The steel tube truss 11 is pushed into place in a relay form by multiple groups of jacking devices.
[0064] It is understandable that the jacking device commonly uses a hydraulic cylinder, and the jacking range refers to the maximum telescopic range of the hydraulic cylinder.
[0065] It should be noted that the hydraulic cylinder can use a common hydraulic cylinder system in the construction field, mainly including a hydraulic pump source system and a synchronous control system, etc. The synchronous control system controls the angular velocity of each jacking point of the steel tube truss 11 on the first circular track 21, the second circular track 22 and the third circular track 23, respectively, so that they can run synchronously and slide in an orderly manner. The existing hydraulic cylinder system is used and will not be described in detail.
[0066] In summary, the circular stadium steel structure sliding construction method provided by this application has the following technical effects:
[0067] 1. Complex structural parts such as steel structural members (steel tube trusses 11, grids) of different sizes, specifications and weights can be slid to the designated installation positions through the circular track, and the construction method is simple.
[0068] 2. The rotating and sliding ring track design is adopted to reduce the displacement of lifting equipment by more than 30 times, reduce the basic conditions required for the lifting equipment to occupy 30 positions, save space, shorten the construction period, greatly improve construction efficiency, save costs, and shorten the construction period.
[0069] 3. The rotating and sliding ring track design greatly reduces the aerial assembly work. At the same time, other different components (purlins, curtain wall embedded parts, walkways, pipe supports) can be installed to the steel tube truss 11 at the same time without considering deformation and weight requirements.
[0070] 4. The construction process is simple and repeated construction is conducive to improving work efficiency.
[0071] 5. Reduce workers' high-altitude operations, greatly reduce safety risks, and improve social benefits;
[0072] 6. The construction period is shortened, the construction period is guaranteed, and it can be completed and put into use ahead of schedule, which has benefits for people's livelihood.
[0073] 7. Reduce the difficulty of construction workers' operations, saving time and effort.
[0074] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person of ordinary skill in the art should understand that the technical solutions described in the aforementioned embodiments can still be modified, or some or all of the technical features therein can be replaced by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present application, and they should all be included in the scope of the claims and specification of the present application. In particular, as long as there is no contradiction or conflict, the various technical features mentioned in the embodiments can be combined in any way. The present application is not limited to the specific embodiments disclosed herein, but includes all technical solutions that fall within the scope of the claims.
Claims
1. A circular stadium steel structure sliding construction method, mainly used for the installation of steel pipe truss steel structure of circular stadium, characterized in that: include: At least one circular track is installed on the circular venue, and the circular track is arranged concentrically with the circular venue; Using a lifting device to hoist the first steel pipe truss onto the annular track at the hoisting station, so as to slide with the annular track; Move the first steel tube truss along the circular track until it completely leaves the hoisting station; The second steel pipe truss is hoisted onto the annular track by using the hoisting equipment again at the hoisting station; The second steel tube truss is fixedly connected to the first steel tube truss, and moved along the circular track until it completely leaves the hoisting station; Repeat the above steps until all steel tube trusses are installed.
2. The circular stadium steel structure sliding construction method according to claim 1, characterized in that: In the step 1, three circular tracks are installed on the circular venue, the three circular tracks are arranged concentrically with the circular venue, and the three circular tracks are arranged from outside to inside and from low to high.
3. The circular stadium steel structure sliding construction method as claimed in claim 2, characterized in that: Each steel tube truss is divided into three independent parts at the bottom, middle and top. They are lifted in sequence by lifting equipment until they are slidably matched with the three circular tracks, and then the three independent parts are fixedly connected into a whole.
4. The circular stadium steel structure sliding construction method according to claim 2, characterized in that: The three circular tracks are respectively the first circular track, the second circular track and the third circular track, which are arranged from outside to inside and from low to high; wherein, the first circular track and the second circular track are fixedly installed on the circular venue, and the third circular track is erected inside the circular venue using an independent circular support system.
5. The circular stadium steel structure sliding construction method according to claim 4, characterized in that: The annular support system comprises lattice columns in an annular array, and the third annular track is fixedly mounted on the lattice columns; and circular tube single column supports are arranged between the lattice columns.
6. The circular stadium steel structure sliding construction method according to claim 1, characterized in that: After each three steel tube trusses are hoisted and fixedly connected, the three steel tube trusses are moved to the installation position; three steel tube trusses are hoisted and fixedly connected again, and also moved to the corresponding installation position, and so on, until all steel tube trusses are hoisted; finally, all steel tube trusses are fixedly connected.
7. The circular stadium steel structure sliding construction method according to claim 1, characterized in that: After each steel tube truss is hoisted, the steel tube truss is moved to the installation position, and so on, until the hoisting of all steel tube trusses is completed; finally, all steel tube trusses are fixedly connected.
8. The circular stadium steel structure sliding construction method according to claim 1, characterized in that: In the step 1, a plurality of groups of pushing devices are evenly installed at the annular track, and the pushing devices are used to push the steel pipe truss within its pushing range to move along the annular track, and the pushing ranges of adjacent pushing devices overlap.
Citation Information
Cited By
High-altitude assembling and mounting method for roof steel structure of large gymnasium
CN119737058A