Equipment maintenance standard man-hour determination method and system
By dividing the equipment maintenance process into multiple processes and using the reverse impulse probability method to correct the actual working hours, combined with the unit price calculation of the working hours, the problem of large errors in the standard working hours of equipment maintenance is solved, the accuracy and cost control of working hours are achieved, and production is improved Plan reliability and operational efficiency.
Patent Information
- Application Number
- CN202411266413.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-10
- Publication Date
- 2024-12-17
AI Technical Summary
The standard working hours of existing equipment maintenance mainly rely on workers' experience estimation, and there are false reporting of working hours and large errors, resulting in uncertain equipment maintenance schedules and difficult to control costs, affecting production planning and production scheduling.
The equipment maintenance process is divided into multiple processes, the reference working hours are set, and the standard working hours are calculated through the reverse impulse probability method and actual working hours correction, and the standard working hours are calculated based on the unit price of working hours to ensure the accuracy and consistency of working hours data.
It effectively solves the problems of large standard working hours errors and uncertain equipment maintenance schedules, realizes the accuracy and cost control of working hours data, avoids false reporting of working hours, and improves the reliability and operational efficiency of production plans.
Smart Images

Figure CN119151498A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of man-hour accounting, and in particular relates to a method and system for determining standard man-hours for equipment maintenance. Background Art
[0002] The statements in this section merely provide background information related to the present invention and do not necessarily constitute prior art.
[0003] The working hours data during the equipment maintenance process is the basis for determining the time it takes for the equipment to be put back into production. Standard working hours provide an accurate assessment of the time required for equipment maintenance, which can help companies better plan production and schedule tasks.
[0004] However, the existing standard working hours for equipment maintenance are mostly reported by workers based on their experience. This method not only has the problem of false reporting of working hours, but also has large errors in this estimation method, which can easily lead to problems such as uncertain equipment maintenance schedules, difficult to control equipment maintenance costs, and impact on production scheduling. Summary of the invention
[0005] In order to solve the technical problems existing in the above-mentioned background technology, the present invention provides a method and system for determining the standard working hours for equipment maintenance. For the diagnosis process, the troubleshooting process is considered and the problem that every path cannot be checked is not allowed. The reference working hours are used to correct the actual working hours, and the actual working hours are used to adjust the reference working hours to achieve a more balanced standard working hours, which effectively solves the problems of large errors in standard working hours and uncertain equipment maintenance period.
[0006] In order to achieve the above object, the present invention adopts the following technical solution:
[0007] A first aspect of the present invention provides a method for determining standard working hours for equipment maintenance, comprising:
[0008] Divide the equipment maintenance process into several procedures and set the reference working hours for each procedure;
[0009] After each failure, the actual working hours of each process are obtained; for the diagnosis process, the actual working hours are corrected based on the reference working hours using the reverse probability method; for each process, the cumulative difference between the reference working hours and the actual working hours is calculated, and the reference working hours are adjusted based on the cumulative difference;
[0010] Based on the reference working hours and the actual working hours, the standard working hours are calculated.
[0011] Furthermore, the reference working time for each process is set using a model scheduling method.
[0012] Furthermore, the standard working hours are:
[0013]
[0014] in, represents the reference working time of the nth process; tn represents the actual working time of the nth process; when Will The value is 1; when Will is the actual calculated value.
[0015] Furthermore, the steps of the inverse probability method include:
[0016] When fault diagnosis has only one stage, if The actual working time is t2, otherwise, the revised actual working time is
[0017] When fault diagnosis has only two stages, if The actual working time is t2, otherwise, the revised actual working time is
[0018] When fault diagnosis has three or more stages, if The actual working time is t3, otherwise, the revised actual working time is
[0019] Among them, t2 is the actual working time of the diagnostic process obtained, is the reference working time of the diagnosis process, k1, k2 and k3 are set values, and k1<k2<k3.
[0020] Furthermore, based on the accumulated difference, the method for adjusting the reference working hours is:
[0021]
[0022] Where m represents the number of failures. It represents the reference working time of the nth process after the last failure, and tnm represents the actual working time of the nth process after the mth failure. represents the reference working time of the nth process after the mth failure, Indicates the reference working time of the nth process after this failure.
[0023] Furthermore, the process includes: a preparation process, a diagnosis process, a cover and accessory disassembly process, a component mechanical disassembly process, a component electrical disassembly process, a cover and accessory installation process, a component mechanical installation process, a component electrical installation process, a test process and a finishing process.
[0024] Furthermore, the standard working hours are used in combination with the working hour unit price to calculate the standard working hour fee;
[0025] The unit price of working hours is determined by the personnel qualifications, statutory holiday time periods and the management commission of the dispatching unit.
[0026] A second aspect of the present invention provides a system for determining standard working hours for equipment maintenance, comprising:
[0027] Divide the equipment maintenance process into several procedures and set the reference working hours for each procedure;
[0028] After each failure, the actual working hours of each process are obtained; for the diagnosis process, the actual working hours are corrected based on the reference working hours using the reverse probability method; for each process, the cumulative difference between the reference working hours and the actual working hours is calculated, and the reference working hours are adjusted based on the cumulative difference;
[0029] Based on the reference working hours and the actual working hours, the standard working hours are calculated.
[0030] A third aspect of the present invention provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps in the method for determining standard working hours for equipment maintenance as described above.
[0031] The fourth aspect of the present invention provides a computer device, including a computer-readable storage medium, a processor, and a computer program stored on the computer-readable storage medium and executable on the processor, wherein when the processor executes the program, the steps in the method for determining the standard working hours for equipment maintenance as described above are implemented.
[0032] Compared with the prior art, the present invention has the following beneficial effects:
[0033] The present invention aims at the diagnosis process, takes into account the troubleshooting process and does not allow the problem of troubleshooting every path. It uses reference working hours to correct the actual working hours, and uses the actual working hours to adjust the reference working hours to achieve a more balanced standard working time, effectively solving the problems of large errors in standard working hours and uncertain equipment maintenance periods. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0035] Figure 1 This is a flow chart of a method for determining standard working hours for equipment maintenance according to the first embodiment of the present invention;
[0036] Figure 2 This is a logic diagram for calculating the labor hour unit price in the first embodiment of the present invention.
[0037] Figure 3It is a structural diagram of a computer device according to a fourth embodiment of the present invention. DETAILED DESCRIPTION
[0038] To make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0039] It should be noted that the following detailed descriptions are all illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.
[0040] Embodiment 1
[0041] This embodiment provides a method for determining standard man-hours for equipment maintenance.
[0042] This embodiment provides a method for determining the standard working hours for equipment maintenance, such as Figure 1 As shown, the following steps are included:
[0043] Step 1: Classify and grade the processes.
[0044] First, the whole process of equipment maintenance is divided into six standard procedures: preparation, diagnosis, disassembly, installation, testing and finishing. Each type of standard procedure can be further subdivided into specific process contents, and each process content can be rated, which is divided into four levels: auxiliary process, ordinary process, key process and critical process. As shown in Table 1, there are differences in the qualification requirements for operators at different levels of processes, and the hourly price of operators with different qualifications is different. Regarding the content of the labor time quota, each equipment maintenance labor time quota is obtained by adding up the standard labor time of each process of the content. In this way, by calculating the standard labor time of each process, the labor time quota of the entire equipment maintenance can be determined in disguise.
[0045] The process can be deleted or added according to the actual fault handling situation, and the corresponding process level needs to be judged by the technicians. The process level determines only the upper limit of personnel qualifications. For example, the highest qualification of personnel for ordinary processes is intermediate workers. The number of people in each type of work is filled in Table 1 according to the actual situation. A, Β, Γ, Δ represent the number of people in each type of work.
[0046] Table 1. Classification level of fault handling process and personnel qualification and working hours
[0047]
[0048]
[0049] Step 2: Calculate the standard working hours of the process.
[0050] Considering the current situation, it takes time to accumulate actual working hours data, but settlement requires a reasonable quota of working hours. The supervisor requirement method in the experience evaluation method can be used to formulate a reference working time for maintenance of components of different complexity through review. Alternatively, the reference working hours are determined by using the MODAPTS method (Modular Arrangement of PTS), which uses intermediate work as a model, directly measures the first occurrence of a failure, and completes a certain amount of work at a normal working speed and in a standard working method under standard working conditions and environments, thereby determining the reference working hours. (n represents the number of the process), used in the standard working time formula.
[0051] Step 3: Calculate the standard working hours for key processes.
[0052] Equipment fault diagnosis is a key process in the fault handling process, and the reverse probability method is used here for calculation. First, the diagnostic process is divided into stages and paths. There may be multiple diagnostic paths in each diagnostic stage. In the actual fault diagnosis process, the operator may not immediately choose the correct path for each diagnostic stage. There is a troubleshooting process, but there are certain skill requirements for the operator, and it is not allowed to check every path in each diagnostic stage. Therefore, reverse reasoning is used here. After determining the correct path for each stage, an intermediate worker is selected to check the correct path according to the process and record the reference working hours. However, it is reasonable to choose the wrong path. Therefore, it is necessary to combine the probability while back-calculating. The probability of correct path selection in the first three stages of diagnosis is set to 50%, 70%, and 90% respectively. From the fourth stage onwards, the probability of correct path selection is required to be 100%. In summary, the actual working time t2 value selection principle of the diagnosis stage is shown in Table 2.
[0053] Table 2. Principles for selecting the actual working time t2 in the diagnosis phase
[0054]
[0055] Step 4. This embodiment uses the reference working time and actual working time balance method to calculate the standard working time for each process. The reference working time can be determined in two ways. In order to make the standard working time more in line with reality, it is necessary to use the actual working time to adjust the reference working time to achieve a more balanced standard working time.
[0056] Specifically, the reference working hours are continuously adjusted and revised based on the accumulated data. m represents the number of failures. The reference working hours are continuously adjusted according to the revised formula. Make adjustments.
[0057] Revised formula: Where m represents the number of failures. It represents the reference working time of the nth process after the last failure, and tnm represents the actual working time of the nth process after the mth failure. represents the reference working time of the nth process after the mth failure, It indicates the reference working time of the nth process after this failure, that is, the adjusted reference working time.
[0058] Step 5: Standard working hours formula:
[0059]
[0060] Note: when Will The value is 1.
[0061] when Will According to the actual calculated value.
[0062] 在 In this embodiment, after obtaining the working time quota (standard working time) f(t), the standard working time fee = The formula of standard working hours × unit working hour price can be used to calculate the cost of the entire spare parts maintenance process.
[0063] After the working hour quota f(t) is determined, the next issue to be solved is the working hour price Q. The working hour price is affected by many factors. Here we mainly select three factors, such as personnel qualifications, statutory holiday time period and dispatch unit management commission, to calculate the working hour price Q.
[0064] (1) The impact of labor skills on the unit price of labor hours.
[0065] The skill level of the staff in the process of equipment failure handling directly affects the principal of the labor hour price. The skill requirements of the staff are made in combination with the process level. While ensuring the quality of fault handling, high-low matching (high-skilled personnel operating low-value processes) is avoided. According to the annual human resources market wage price and enterprise labor cost information of a certain province and city, as shown in Table 3, the median annual salary of personnel with corresponding skill levels is calculated according to the formula for the labor hour price principal as follows: Calculation of labor hour price principal W = S / (12*21.75*8). Note: S represents the median annual salary of personnel with corresponding skill levels, 12 represents a total of 12 months in a year, 21.75 represents the number of working days per month, and 8 represents the working hours per day.
[0066] Table 3: Salary levels of employees in enterprises by job level (unit: 10,000 yuan / year)
[0067]
[0068] (2) The impact of statutory holidays on the unit price of working hours.
[0069] At present, the working hour system implemented is that the daily working hours of workers do not exceed eight hours and the average weekly working hours do not exceed 44 hours.
[0070] For workers who are paid on a piece-rate basis, the employer shall reasonably determine their labor quotas and piece-rate remuneration standards based on the working hour system.
[0071] Employers shall ensure that employees have at least one day off per week.
[0072] The overtime pay standards in the local province are as follows:
[0073] Extended working hours: If the working hours are extended beyond the daily statutory standard working hours, overtime wages should be paid at a rate not less than 150% of the hourly wage base.
[0074] Overtime on rest days: When work is arranged on rest days (including Saturdays, Sundays and other statutory rest days), if compensatory leave cannot be arranged, overtime wages should be paid at a rate not less than 200% of the daily or hourly wage base.
[0075] Overtime on statutory holidays: When work is arranged on statutory holidays, overtime wages should be paid at a rate not less than 300% of the daily or hourly wage base.
[0076] According to regulations: when employees work night shifts, employers should pay night shift subsidies based on the employees' wages.
[0077] The specific subsidy standard is generally calculated based on 20% of the worker's daily wage, and the minimum is not less than 10% of the daily wage.
[0078] The calculation method for night shift pay subsidy is: night shift pay subsidy = daily salary × subsidy standard. The subsidy standard is generally 20%, and the minimum is not less than 10%.
[0079] Based on the general company situation, the day shift is 8:00-16:40, and there is no clear regulation on the night shift time period, which is tentatively set at 20:00-5:00.
[0080] The impact of statutory holiday periods on the hourly rate is that in different holiday periods, the principal of the hourly rate is multiplied by different multiples, as shown in Table 4.
[0081] Table 4. Multiples of the unit price of working hours in different time periods on statutory holidays (b)
[0082]
[0083]
[0084] (3) The impact of labor dispatch unit management fees on the unit price of labor hours.
[0085] The management fees of labor dispatch units mainly include labor relations management fees, social security and provident fund payment service fees, daily service fees, personnel recruitment fees, etc.
[0086] Specific charging standards: According to the scale of outsourcing, after on-site inspection, targeted accounting is carried out. Enterprises need to charge labor dispatch management fees according to the assessed industry qualification level standards, that is to say: the management fee charging standard of the first-level labor dispatch enterprise is 8-17% of the total salary of the dispatched employees; the management fee charging guidance price of the second-level labor dispatch enterprise is 8-14% of the total salary of the dispatched employees; the management fee charging standard of the third-level labor dispatch enterprise is 8-12% of the total salary of the dispatched employees; the management fee charging guidance price of the fourth-level labor dispatch enterprise is 8-10% of the total salary of the dispatched employees. The present invention adopts the minimum coefficient of 8% to adjust the principal of the unit price of working hours.
[0087] like Figure 2 As shown in the figure, after summarizing the above three factors, the labor skill specifies the labor hour unit price principal W, the statutory holiday period adjusts the labor hour unit price principal multiple b, and the labor dispatch unit management fee revises the labor hour unit price principal coefficient s. Thus, the formula of labor hour unit price Q is obtained: Q = b*W*(1+s).
[0088] Calculation of standard maintenance costs: Equipment failure maintenance costs are calculated by the standard labor hours x labor hour unit price, that is, the standard labor hours for each process stage x the sum of the corresponding labor hour unit price.
[0089] The present embodiment provides a method for determining standard working hours for equipment maintenance. With respect to the diagnostic process, the troubleshooting process is considered and the problem of not being able to troubleshoot every path is not allowed. The actual working hours are corrected using reference working hours, and the reference working hours are adjusted using actual working hours to achieve a more balanced standard working hours, which effectively solves the problems of large errors in standard working hours and uncertain equipment maintenance periods.
[0090] This embodiment provides a method for determining standard working hours for equipment maintenance, which controls working hours and avoids false reporting of working hours, thereby making equipment maintenance costs more reasonable.
[0091] The present embodiment provides a method for determining standard working hours for equipment maintenance, which adopts a method combining a scientific calculation method with actual process implementation to formulate a reasonable standard working hour quota.
[0092] The present embodiment provides a method for determining the standard working hours for equipment maintenance, which only requires manual determination of the process classification and grading, and can automatically calculate the maintenance cost based on the actual number of operators and the actual working time of each process.
[0093] This embodiment provides a method for determining standard working hours for equipment maintenance, which combines big data statistics to scientifically calculate the working hour unit price standard for personnel of different skill levels and makes skill requirements for different processes.
[0094] Standard working hours ensure that workers can receive reasonable compensation after working standard hours, which helps to safeguard the basic economic rights and interests of workers. Standard working hours help companies estimate and control production costs more accurately and avoid cost overruns caused by unclear working hours. By setting standard working hours, companies can motivate employees to improve work efficiency and reduce unnecessary waste of working hours, thereby improving overall operational efficiency. Based on the calculation of standard working hours, companies can allocate human resources and equipment resources more reasonably to ensure the smooth completion of production or maintenance tasks.
[0095] Embodiment 2
[0096] This embodiment provides a system for determining standard working hours for equipment maintenance, which specifically includes:
[0097] Divide the equipment maintenance process into several procedures and set the reference working hours for each procedure;
[0098] After each failure, the actual working hours of each process are obtained; for the diagnosis process, the actual working hours are corrected based on the reference working hours using the reverse probability method; for each process, the cumulative difference between the reference working hours and the actual working hours is calculated, and the reference working hours are adjusted based on the cumulative difference;
[0099] Based on the reference working hours and the actual working hours, the standard working hours are calculated.
[0100] Considering the current situation, it takes time to accumulate actual working hours data, but settlement requires a reasonable quota of working hours. The supervisor requirement method in the experience evaluation method can be used to formulate a reference working time for maintenance of components of different complexity through review. Alternatively, the reference working hours are determined by using the MODAPTS method (Modular Arrangement of PTS), which uses intermediate work as a model, directly measures the first occurrence of a failure, and completes a certain amount of work at a normal working speed and in a standard working method under standard working conditions and environments, thereby determining the reference working hours. (n represents the number of the process), used in the standard working time formula.
[0101] The standard working hours are:
[0102]
[0103] in, represents the reference working time of the nth process; tn represents the actual working time of the nth process; when Will The value is 1; when Will is the actual calculated value.
[0104] Among them, the processes include: preparation process, diagnosis process, outer cover and accessories disassembly process, component mechanical disassembly process, component electrical disassembly process, outer cover and accessories installation process, component mechanical installation process, component electrical installation process, testing process and finishing process.
[0105] The steps of the inverse probability method include:
[0106] When fault diagnosis has only one stage, if The actual working time is t2, otherwise, the revised actual working time is
[0107] When fault diagnosis has only two stages, if The actual working time is t2, otherwise, the revised actual working time is
[0108] When fault diagnosis has three or more stages, if The actual working time is t3, otherwise, the revised actual working time is
[0109] Among them, t2 is the actual working time of the diagnostic process obtained, is the reference working time of the diagnosis process, k1, k2 and k3 are set values, and k1<k2<k3.
[0110] Among them, the reference working time for each process is set using the model scheduling method.
[0111] Wherein, based on the accumulated difference, the method for adjusting the reference working hours is:
[0112]
[0113] Where m represents the number of failures. It represents the reference working time of the nth process after the last failure, and tnm represents the actual working time of the nth process after the mth failure. represents the reference working time of the nth process after the mth failure, Indicates the reference working time of the nth process after this failure.
[0114] Among them, standard working hours are used in combination with the labor unit price to calculate the standard labor fee;
[0115] The unit price of working hours is determined by the personnel qualifications, statutory holiday time periods and the management commission of the dispatching unit.
[0116] The present embodiment provides a system for determining standard working hours for equipment maintenance. With respect to the diagnostic process, the system takes into account the troubleshooting process and cannot allow the problem of troubleshooting every path. It uses reference working hours to correct actual working hours, and uses actual working hours to adjust reference working hours to achieve a more balanced standard working hours, thereby effectively solving the problems of large errors in standard working hours and uncertain equipment maintenance periods.
[0117] This embodiment provides a system for determining standard working hours for equipment maintenance, which controls working hours and avoids false reporting of working hours, thereby making equipment maintenance costs more reasonable.
[0118] The present embodiment provides a system for determining standard working hours for equipment maintenance, which adopts a method combining scientific calculation methods with actual process implementation to formulate a reasonable standard working hour quota.
[0119] The present embodiment provides a system for determining standard working hours for equipment maintenance, which only requires manual determination of the process classification and grading, and can automatically calculate the maintenance costs based on the actual number of operators and the actual working time of each process.
[0120] This embodiment provides a system for determining standard working hours for equipment maintenance, which combines big data statistics to scientifically calculate the working hour unit price standard for personnel of different skill levels and makes skill requirements for different processes.
[0121] Standard working hours ensure that workers can receive reasonable compensation after working standard hours, which helps to safeguard the basic economic rights and interests of workers. Standard working hours help companies estimate and control production costs more accurately and avoid cost overruns caused by unclear working hours. By setting standard working hours, companies can motivate employees to improve work efficiency and reduce unnecessary waste of working hours, thereby improving overall operational efficiency. Based on the calculation of standard working hours, companies can allocate human resources and equipment resources more reasonably to ensure the smooth completion of production or maintenance tasks.
[0122] It should be noted here that each module in this embodiment corresponds to each step in Example 1 one by one, and the specific implementation process is the same, which will not be repeated here.
[0123] Embodiment 3
[0124] This embodiment provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the steps in the method for determining standard working hours for equipment maintenance as described in the first embodiment above are implemented.
[0125] Embodiment 4
[0126] This embodiment provides a computer device, such as Figure 3As shown, it includes a computer-readable storage medium 1003, a processor 1001, a communication interface 1002, and a computer program stored on the computer-readable storage medium 1003 and executable on the processor 1001, wherein the processor 1001, the communication interface 1002, and the computer-readable storage medium 1003 can be connected via a bus or other means. The communication interface 1002 is used to receive and send data, and when the processor 1001 executes the program, the steps in the method for determining the standard working hours for equipment maintenance described in the first embodiment are implemented.
[0127] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0128] These computer program instructions may also be stored in a computer readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer readable memory produce an article of manufacture including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0129] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0130] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for determining standard working hours for equipment maintenance, characterized in that: include: Divide the equipment maintenance process into several procedures and set the reference working hours for each procedure; After each failure, the actual working hours of each process are obtained; for the diagnosis process, the actual working hours are corrected based on the reference working hours using the reverse probability method; For each process, the cumulative difference between the reference working time and the actual working time is calculated, and the reference working time is adjusted based on the cumulative difference; Based on the reference working hours and the actual working hours, the standard working hours are calculated.
2. A method for determining standard equipment maintenance man-hours according to claim 1, characterized in that: The reference working time for each process is set using the model scheduling method.
3. A method for determining standard equipment maintenance man-hours as claimed in claim 2, characterized in that: The standard working hours are: in, represents the reference working time of the nth process; tn represents the actual working time of the nth process; when Will The value is 1; when Will is the actual calculated value.
4. A method for determining standard equipment maintenance man-hours according to claim 3, characterized in that: The steps of the inverse probability method include: When fault diagnosis has only one stage, if The actual working time is t2, otherwise, the revised actual working time is When fault diagnosis has only two stages, if The actual working time is t2, otherwise, the revised actual working time is When fault diagnosis has three or more stages, if The actual working time is t3, otherwise, the revised actual working time is Among them, t2 is the actual working time of the diagnostic process obtained, is the reference working time of the diagnosis process, k1, k2 and k3 are set values, and k1<k2<k3.
5. A method for determining standard equipment maintenance man-hours as claimed in claim 4, characterized in that: Based on the accumulated difference, the method for adjusting the reference working hours is: Where m represents the number of failures. It represents the reference working time of the nth process after the last failure, and tnm represents the actual working time of the nth process after the mth failure. represents the reference working time of the nth process after the mth failure, Indicates the reference working time of the nth process after this failure.
6. A method for determining standard working hours for equipment maintenance according to any one of claims 1 to 5, characterized in that: The processes include: a preparation process, a diagnosis process, a cover and accessory disassembly process, a component mechanical disassembly process, a component electrical disassembly process, a cover and accessory installation process, a component mechanical installation process, a component electrical installation process, a test process and a finishing process.
7. A method for determining standard equipment maintenance man-hours according to any one of claims 1 to 5, characterized in that: The standard working hours are used in combination with the working hour unit price to calculate the standard working hour fee; The unit price of working hours is determined by the personnel qualifications, statutory holiday time periods and the management commission of the dispatching unit.
8. A system for determining standard working hours for equipment maintenance, characterized in that: include: Divide the equipment maintenance process into several procedures and set the reference working hours for each procedure; After each failure, the actual working hours of each process are obtained; for the diagnosis process, the actual working hours are corrected based on the reference working hours using the reverse probability method; For each process, the cumulative difference between the reference working time and the actual working time is calculated, and the reference working time is adjusted based on the cumulative difference; Based on the reference working hours and the actual working hours, the standard working hours are calculated.
9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the steps in a method for determining standard working hours for equipment maintenance as described in any one of claims 1 to 7 are implemented.
10. A computer device comprising a computer-readable storage medium, a processor, and a computer program stored in the computer-readable storage medium and executable on the processor, characterized in that: When the processor executes the program, the steps in the method for determining the standard working hours for equipment maintenance as described in any one of claims 1 to 7 are implemented.