Method and system for evaluating collaborative contribution degree of business expansion power connection engineering project

Through the calculation industry's expansion of the relevant indicators and weights of the power connection project, the synergistic contribution is evaluated, and the problem of lack of quantitative analysis of collaborative management in the existing technology is solved, and the precise control and service quality improvement of project collaborative management is achieved.

CN119180532APending Publication Date: 2024-12-24国网福建省电力有限公司营销服务中心 +3
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202311844813.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-12-28
Publication Date
2024-12-24

AI Technical Summary

Technical Problem

There is a lack of quantitative analysis methods in the prior art to evaluate the synergistic contribution of industry expansion power engineering projects, resulting in limited quality and efficiency of collaborative management.

Method used

By obtaining project data, engineering data and electrical equipment data, we calculate relevant indicators such as project connection capacity level, distribution network operation balance level, electrical equipment comprehensive load level, project volume and customer satisfaction, and calculate the synergistic contribution degree based on weights. Achieve quantitative analysis and weak link positioning.

Benefits of technology

It has realized quantitative analysis of the coordination level of industry expansion power connection projects, provided scientific basis for management and incentives, and improved service quality and collaborative management effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119180532A_ABST
    Figure CN119180532A_ABST
Patent Text Reader

Abstract

The invention relates to the field of energy digitization, and provides a method and a system for evaluating the collaborative contribution degree of a business expansion power connection engineering project. The method comprises the steps of obtaining project data, engineering data and electrical equipment data according to a to-be-evaluated business expansion power connection engineering project; based on the project data, the engineering data and the electrical equipment data, calculating related indexes including a project capacitance level, a project distribution network operation balance level, an electrical equipment comprehensive load level, a project amount, a project time limit standard degree and customer satisfaction; based on the project power connection capacity level, the project distribution network operation balance level, the electrical equipment comprehensive load level, the project work amount, the project time limit standard degree and the customer satisfaction degree, combined with the set weights of the related indexes, the weighted sum is calculated, and the business expansion power connection project collaborative contribution degree is obtained so as to be used for positioning weak projects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of energy digitalization, and in particular to a method and system for evaluating the collaborative contribution of a business expansion and power connection engineering project. Background Art

[0002] The statements in this section merely provide background information related to the present invention and do not necessarily constitute prior art.

[0003] The business expansion and power connection project involves the participation and collaboration of multiple departments such as marketing, operation and maintenance, and materials. There are different project types according to different customer needs and actual grid operating conditions. Designing the coordination coefficient of each project based on the engineering construction content will help to quantitatively analyze the level of collaborative management of business expansion of engineering projects, and achieve precise collaborative management and control of business expansion and power connection projects to meet new changes and new requirements in the implementation of investment extension policies and optimization of the business environment, respond to customer service demands in a timely manner, and improve service quality.

[0004] At present, there is no quantitative analysis method for the collaborative evaluation of business expansion and power connection projects. The overall evaluation is mainly based on qualitative subjective evaluation, which mainly includes department satisfaction evaluation, 360 evaluation and other methods. This evaluation method is difficult to reflect the collaborative contribution of different projects and affects the quality and efficiency of the overall management of project power connection. Summary of the invention

[0005] In order to solve the technical problems in the above-mentioned background technology that the effect and contribution of the collaborative work of business expansion and power connection cannot be quantified and evaluated, the present invention provides a method and system for evaluating the collaborative contribution of business expansion and power connection engineering projects. The present invention can quantitatively analyze the overall contribution level of projects participating in the collaborative service of business expansion and power connection, and implement targeted management and incentive measures.

[0006] In order to achieve the above object, the present invention adopts the following technical solution:

[0007] A first aspect of the present invention provides a method for evaluating the collaborative contribution of a business expansion and power connection engineering project.

[0008] A method for evaluating the collaborative contribution of a business expansion and power connection project includes:

[0009] According to the business expansion and power connection project to be evaluated, obtain project data, engineering data and electrical equipment data;

[0010] Based on project data, engineering data and electrical equipment data, calculate relevant indicators, including: project power connection capacity level, project distribution network operation balance level, electrical equipment comprehensive load level, project engineering quantity, project time limit compliance and customer satisfaction;

[0011] Based on the project power connection capacity level, project distribution network operation balance level, electrical equipment comprehensive load level, project engineering volume, project time limit compliance and customer satisfaction, combined with the weights of the set relevant indicators, the weighted sum is calculated to obtain the collaborative contribution of the business expansion and power connection project, which is used to locate weak projects.

[0012] Furthermore, the power connection capacity level of the project is:

[0013] C pj =C pd / C pt / C at / C vl

[0014] Among them, C pj is the project connection capacity level, C pd The capacity reported for the project, C pt is the power type capacity of the project, C at is the project acceptance type capacity, C vl It is the voltage level capacity of the project.

[0015] Furthermore, the distribution network operation balance level of the project is:

[0016] L pb =C pd / C tdn

[0017] Among them, L pb is the project distribution network operation balance level, C pd For project power connection and installation capacity, C tdn It is the total capacity of the distribution network in the substation area.

[0018] Furthermore, the comprehensive load level of the electrical equipment is:

[0019]

[0020] Among them, L cl is the comprehensive load level of electrical equipment, is the maximum power sum of all electrical equipment, P frs is the probability of each device running simultaneously, is the sum of the power factors of each device, L dnm It is the maximum load of the distribution network.

[0021] Furthermore, the project volume is:

[0022] Q p =L c / M c

[0023] Among them, Q pis the project volume, L c is the cable length, M c It is the overall construction mileage of the project.

[0024] Furthermore, the project time limit is:

[0025] C pt =(TLAR ba +TLAR sr +TLAR pc +TLAR dr +TLAR ii +TLAR ca +TLAR cp ) / 7

[0026] Among them, TLAR ba TLAR is the time limit compliance rate of business acceptance link sr TLAR is the time limit achievement rate of the power supply plan response phase pc TLAR is the time limit achievement rate of supporting engineering links. dr TLAR is the time limit achievement rate of the facility review phase ii TLAR is the time limit achievement rate of the intermediate inspection link ca TLAR is the time limit compliance rate of the completion acceptance phase. cp It is the time limit compliance rate for meter installation and power connection.

[0027] Furthermore, the customer satisfaction is:

[0028] S c =T cs / T tv

[0029] Among them, S c For customer satisfaction, T cs is the number of visits to satisfied customers, T tv is the total number of visits.

[0030] A second aspect of the present invention provides a system for evaluating the collaborative contribution of business expansion and power connection engineering projects.

[0031] An evaluation system for collaborative contribution of a business expansion and power connection project includes:

[0032] A data acquisition module is configured to: acquire project data, engineering data and electrical equipment data according to the business expansion and power connection project to be evaluated;

[0033] An indicator calculation module is configured to calculate relevant indicators based on project data, engineering data and electrical equipment data, including: project power connection capacity level, project distribution network operation balance level, electrical equipment comprehensive load level, project engineering quantity, project time limit compliance and customer satisfaction;

[0034] The evaluation module is configured as follows: based on the project power connection capacity level, the project distribution network operation balance level, the comprehensive load level of electrical equipment, the project engineering volume, the project time limit compliance and customer satisfaction, combined with the weights of the set relevant indicators, the weighted sum is calculated to obtain the collaborative contribution of the business expansion and power connection project, which is used to locate weak projects.

[0035] A third aspect of the present invention provides a computer-readable storage medium.

[0036] A computer-readable storage medium stores a computer program, which, when executed by a processor, implements the steps in the method for evaluating the collaborative contribution of a business expansion and power connection engineering project as described in the first aspect above.

[0037] A fourth aspect of the present invention provides a computer device.

[0038] A computer device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the steps in the method for evaluating the collaborative contribution of a business expansion and power connection engineering project as described in the first aspect above are implemented.

[0039] Compared with the prior art, the present invention has the following beneficial effects:

[0040] The present invention will realize for the first time the quantitative analysis of the coordination level of business expansion and power connection projects, scientifically measure the collaborative contribution of project power connection, and provide a direct basis for the overall project collaborative management and control.

[0041] The present invention realizes the analysis of the differences in the coordination levels of different projects in the overall business expansion and power connection work, realizes the precise positioning of the weak links in the coordination of business expansion and power connection, and implements targeted improvements and enhancements.

[0042] The present invention introduces the project collaborative contribution degree and quantifies the department collaborative contribution, providing a basis for project differentiation and personalized incentives, helping to establish a value orientation of active collaboration and co-creation, establishing a virtuous cycle of evaluation and promotion, and improving the overall quality and efficiency of business expansion and power connection services.

[0043] Through quantitative analysis of the project collaborative system, the present invention can promote the accumulation of overall business expansion and power connection collaborative management and control data, establish a business expansion collaborative data analysis system, and promote the digital transformation of business expansion and power connection work.

[0044] The project coordination coefficient of the present invention can provide experience reference for the coordinated management of other engineering projects, and provide a quantitative analysis method for government-enterprise coordination, cross-department coordination, and department content coordination in the power service process. BRIEF DESCRIPTION OF THE DRAWINGS

[0045] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.

[0046] Figure 1 It is a flow chart of the method for evaluating the collaborative contribution of a business expansion and power connection engineering project shown in the present invention. DETAILED DESCRIPTION

[0047] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

[0048] It should be noted that the following detailed descriptions are all illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.

[0049] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit exemplary embodiments according to the present invention. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.

[0050] It should be noted that the flowcharts and block diagrams in the accompanying drawings illustrate the possible implementation architecture, functions and operations of the methods and systems according to various embodiments of the present disclosure. It should be noted that each box in the flowchart or block diagram can represent a module, a program segment, or a part of a code, and the module, program segment, or a part of a code may include one or more executable instructions for implementing the logical functions specified in each embodiment. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in an order different from that marked in the accompanying drawings. For example, two boxes represented in succession can actually be executed substantially in parallel, or they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the flowchart and / or block diagram, and the combination of boxes in the flowchart and / or block diagram can be implemented using a dedicated hardware-based system that performs a specified function or operation, or can be implemented using a combination of dedicated hardware and computer instructions.

[0051] Embodiment 1

[0052] like Figure 1 As shown, this embodiment provides a method for evaluating the collaborative contribution of business expansion and power connection engineering projects. This embodiment uses the method applied to a server as an example. It can be understood that the method can also be applied to a terminal, and can also be applied to a system including a terminal and a server, and is implemented through the interaction between the terminal and the server. The server can be an independent physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server that provides basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network servers, cloud communications, middleware services, domain name services, security services CDN, and big data and artificial intelligence platforms. The terminal can be a smart phone, a tablet computer, a laptop computer, a desktop computer, a smart speaker, a smart watch, etc., but is not limited to this. The terminal and the server can be directly or indirectly connected via wired or wireless communication, which is not limited in this application. In this embodiment, the method includes the following steps:

[0053] According to the business expansion and power connection project to be evaluated, obtain project data, engineering data and electrical equipment data;

[0054] Based on project data, engineering data and electrical equipment data, calculate relevant indicators, including: project power connection capacity level, project distribution network operation balance level, electrical equipment comprehensive load level, project engineering quantity, project time limit compliance and customer satisfaction;

[0055] Based on the project power connection capacity level, project distribution network operation balance level, electrical equipment comprehensive load level, project engineering volume, project time limit compliance and customer satisfaction, combined with the weights of the set relevant indicators, the weighted sum is calculated to obtain the collaborative contribution of the business expansion and power connection project, which is used to locate weak projects.

[0056] The present embodiment is described in detail below:

[0057] First, determine the indicator framework for project collaborative quality and efficiency evaluation.

[0058] The synergy quality and efficiency of the business expansion and power connection project reflects the quality of the project power connection service, and reflects the overall work service contribution of different projects to the company's high-quality completion of the business expansion and power connection project implementation and meeting the customer's power demand. The evaluation indicator framework includes project implementation benefits, project implementation complexity, project time limit compliance, and project customer satisfaction.

[0059] Secondly, quantitatively analyze the project collaborative contribution indicators.

[0060] 1. Project implementation benefits mainly include the project power connection capacity level and the project distribution network operation balance level.

[0061] (1) The power connection capacity is the overall capacity level of the project after all power connection works are completed and the customer's power facilities are connected to the grid. 10kV, 35kV, and 110kV projects are divided according to voltage levels, and new installation and capacity expansion projects are determined according to project acceptance types: single-post and non-single-post projects are determined according to project power type, and single power and dual power projects are further distinguished. The project power connection capacity level is:

[0062] C pj =C pd / C pt / C at / C vl

[0063] Among them, C pj is the project connection capacity level, C pd The capacity reported for the project, C pt is the power type capacity of the project, C at is the project acceptance type capacity, C vl It is the voltage level capacity of the project.

[0064] The calculation formula for project capacity is as follows:

[0065] For low voltage users, E i C iee is the capacity of the i-th device.

[0066] For users above T i P ta It is the sum of the nominal apparent powers of the receiving transformers connected to the power system.

[0067] (2) The project distribution network operation balance level indicates the impact of the project capacity access on the distribution network operation stability. It is measured by the project capacity to the total distribution network capacity margin. The higher the proportion, the better the project distribution network operation balance level (cannot exceed the total distribution network capacity). The project distribution network operation balance level is:

[0068] L pb =C pd / C tdn

[0069] Among them, L pb is the project distribution network operation balance level, C pd For project power connection and installation capacity, C tdn It is the total capacity of the distribution network in the substation area.

[0070] Specifically, the total capacity of the distribution network in the substation is based on the rated capacity and load rate of the main transformer of the distribution network in the substation. The load rate refers to the ratio of the actual load of the transformer to the rated capacity, which is generally about 80%. For example, a 1000kVA distribution transformer can supply 800kVA of capacity at a load rate of 80%. Therefore, the total capacity of the distribution network in the substation can be calculated according to 800kVA. Therefore, the total capacity of the distribution network in the substation = 80% * rated capacity of the main transformer.

[0071] 2. Project implementation complexity

[0072] The complexity of project implementation is mainly calculated based on the comprehensive load level of electrical equipment and the project engineering volume. The comprehensive load level of electrical equipment is calculated based on the type and power of the customer's electrical equipment. The comprehensive load level of electrical equipment is:

[0073]

[0074] Among them, L cl is the comprehensive load level of electrical equipment, is the maximum power sum of all electrical equipment, P drs is the probability of each device running simultaneously, is the sum of the power factors of each device, L dnm It is the maximum load of the distribution network.

[0075] The project volume is:

[0076] Q p =L c / M c

[0077] Among them, Q p is the project volume, L c is the cable length, M c It is the overall construction mileage of the project.

[0078] 3. Project time limit achievement

[0079] C pt =(TLAR ba +TLAR sr +TLAR pc +TLAR dr +TLAR ii +TLAR ca +TLAR cp ) / 7

[0080] Among them, TLAR ba TLAR is the time limit compliance rate of business acceptance link sr TLAR is the time limit achievement rate of the power supply plan response phase pcTLAR is the time limit achievement rate of supporting engineering links. dr TLAR is the time limit achievement rate of the facility review phase ii TLAR is the time limit achievement rate of the intermediate inspection link ca TLAR is the time limit compliance rate of the completion acceptance phase. cp It is the time limit compliance rate for meter installation and power connection.

[0081] Among them, the time limit achievement rate of each link = the achievement rate of each link * the proportion of link duration.

[0082] 4. Customer Satisfaction

[0083] Customer satisfaction is the overall level of customer satisfaction with the project power connection service, which is based on the customer's complaint rate and satisfaction evaluation, and is based on the customer's telephone interview records. Customer satisfaction is:

[0084] S c =T cs / T tv

[0085] Among them, S c For customer satisfaction, T cs is the number of visits to satisfied customers, T tv is the total number of visits.

[0086] Finally, determine the weight design of each indicator.

[0087] The analytic hierarchy process and Delphi method are used to design the weights of each indicator.

[0088] The first step is to establish a hierarchical model. The hierarchical model can divide complex problems into three levels according to the purpose of evaluation, namely the target level, the criterion level and the indicator level. Based on this, the synergy quality and efficiency indicator system of the power expansion project is divided into two levels. The first level is the target level, namely the synergy quality and efficiency of the power expansion project, and the second level is the criterion level, including four evaluation dimensions: project implementation benefits, project implementation difficulty, project time limit compliance, and project customer satisfaction.

[0089] The second step is to construct a judgment matrix. The judgment matrix of the hierarchical analysis method is shown in Table 1. In the construction matrix, experts in this field compare the importance of indicators in pairs based on theory and experience, and assign scores to them. The scores are based on the 1-9 scale proposed by Professor Sate, as shown in Table 2:

[0090] Table 1. Judgment matrix constructed by AHP

[0091]

[0092]

[0093] Table 2 Definition of Sate Standard

[0094]

[0095] The third step is hierarchical single sorting. Hierarchical single sorting refers to the process of calculating the relative importance weights of each factor at each level according to a certain calculation method and performing consistency checks. The weight calculation process is as follows (n is the order of the judgment matrix):

[0096] (1) Calculate the product M of each row element in the judgment matrix A i :

[0097]

[0098] (2) Calculate M i The nth root of

[0099]

[0100] (3) Vector After normalization, the result is the weight of each indicator factor:

[0101]

[0102] (4) Perform consistency check. In the above scoring process, there may be some contradictions due to human subjective influence, so the matrix needs to be checked for consistency. The steps are as follows:

[0103] 1) Calculate the maximum eigenvalue of the judgment matrix:

[0104]

[0105] 2) Calculate the consistency deviation index:

[0106]

[0107] 3) Calculate the random consistency ratio CR:

[0108]

[0109] If CR < 0.1, it means that the matrix meets the consistency test, where RI is the average random consistency index, which can be obtained by querying the average random consistency index table, as shown in Table 3:

[0110] Table 3 Average random consistency index

[0111] Degree 1 2 3 4 5 6 7 8 9 RI 0 0 0.52 0.89 1.12 1.26 1.36 1.41 1.46

[0112] Step 4: derive the calculation results. This embodiment uses Yaahp as an auxiliary software for the analytic hierarchy process (AHP), which can accurately and quickly calculate the weights of each indicator. Based on the existing expert scoring data, the judgment matrix is ​​constructed with the help of Yaahp software. The weights of each indicator derived by Yaahp are shown in Table 4:

[0113] Table 4 Weight distribution table of project expansion synergy quality and efficiency evaluation indicators

[0114]

[0115] Finally, based on the relevant indicators of project implementation benefits, project implementation difficulty, project time limit achievement and project customer satisfaction, combined with the set weights, the project business expansion and power connection synergy quality and efficiency value is calculated.

[0116] In order to illustrate the feasibility of the present invention, the data of business expansion and power connection in a certain city in September 2023 are selected. The project data, engineering data, and electrical equipment data are shown in Tables 5, 6, 7, 8, 9, and 10:

[0117] Table 5 Project capacity data

[0118]

[0119] Table 6 Data on the time limit achievement rate of each link of the project

[0120]

[0121]

[0122] Table 7 Duration ratio of each stage of the project

[0123]

[0124] Table 8 Customer satisfaction data

[0125] Number of satisfied visits Total visits Customer Satisfaction 8 8 100%

[0126] Table 9 Engineering data

[0127] Project cable length (m) Overall construction mileage of the project (m) 700 5626

[0128] Table 10 Electrical equipment data

[0129]

[0130]

[0131] Carry out quantitative calculation of each indicator. Calculate the results of each indicator based on the extracted data.

[0132] (1) Project benefits.

[0133] Project power connection capacity level = project reported capacity / single-post project capacity / newly installed project capacity / 10kV project capacity = 0.00000011%.

[0134] Project distribution network operation balance level = project power connection capacity / total distribution network capacity in the substation = 48%

[0135] (2) Difficulty of project implementation.

[0136] The comprehensive load level of electrical equipment = the sum of the maximum power of all electrical equipment * the probability of simultaneous operation of each equipment * the sum of the power factors of all electrical equipment / the maximum load of the distribution network = 1.67

[0137] Project engineering quantity = project cable length / project overall construction mileage = 12.44%

[0138] (3) Project time limit compliance rate = average time limit compliance rate of all links = 13.38%

[0139] (4) Customer satisfaction = number of satisfied customers / total number of visits = 100%

[0140] Evaluate the synergistic contribution of each project. Calculate the synergistic quality and efficiency of the project business expansion and power connection according to the weight of each indicator = 0.00000011%*10%+48%*10%+1.67*10%+12.44%*10%+13.38%*30%+100%*30%=0.57

[0141] The project contributions are ranked based on the results, and the contribution degree of each project is ranked, so as to reward excellent projects and warn lagging projects.

[0142] Embodiment 2

[0143] This embodiment provides a system for evaluating the collaborative contribution of business expansion and power connection engineering projects.

[0144] An evaluation system for collaborative contribution of a business expansion and power connection project includes:

[0145] A data acquisition module is configured to: acquire project data, engineering data and electrical equipment data according to the business expansion and power connection project to be evaluated;

[0146] An indicator calculation module is configured to calculate relevant indicators based on project data, engineering data and electrical equipment data, including: project power connection capacity level, project distribution network operation balance level, electrical equipment comprehensive load level, project engineering quantity, project time limit compliance and customer satisfaction;

[0147] The evaluation module is configured as follows: based on the project power connection capacity level, the project distribution network operation balance level, the comprehensive load level of electrical equipment, the project engineering volume, the project time limit compliance and customer satisfaction, combined with the weights of the set relevant indicators, the weighted sum is calculated to obtain the collaborative contribution of the business expansion and power connection project, which is used to locate weak projects.

[0148] It should be noted that the data acquisition module, index calculation module and evaluation module are the same as the examples and application scenarios implemented by the steps in Embodiment 1, but are not limited to the contents disclosed in Embodiment 1. It should be noted that the modules as part of the system can be executed in a computer system such as a set of computer executable instructions.

[0149] Embodiment 3

[0150] This embodiment provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the steps in the method for evaluating the collaborative contribution of a business expansion and power connection engineering project as described in the first embodiment above are implemented.

[0151] Embodiment 4

[0152] This embodiment provides a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the program, the steps in the method for evaluating the collaborative contribution of a business expansion and power connection engineering project as described in the first embodiment above are implemented.

[0153] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of hardware embodiments, software embodiments, or embodiments combining software and hardware. Furthermore, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage and optical storage, etc.) containing computer-usable program code.

[0154] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0155] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0156] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process in the computer or other programmable device. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0157] A person skilled in the art can understand that all or part of the processes in the above-mentioned embodiments can be implemented by instructing the relevant hardware through a computer program, and the program can be stored in a computer-readable storage medium, and when the program is executed, it can include the processes of the embodiments of the above-mentioned methods. The storage medium can be a disk, an optical disk, a read-only memory (ROM) or a random access memory (RAM), etc.

[0158] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for evaluating the collaborative contribution of a business expansion and power connection project, characterized in that: include: According to the business expansion and power connection project to be evaluated, obtain project data, engineering data and electrical equipment data; Based on project data, engineering data and electrical equipment data, calculate relevant indicators, including: project power connection capacity level, project distribution network operation balance level, electrical equipment comprehensive load level, project engineering quantity, project time limit compliance and customer satisfaction; Based on the project power connection capacity level, project distribution network operation balance level, electrical equipment comprehensive load level, project engineering volume, project time limit compliance and customer satisfaction, combined with the weights of the set relevant indicators, the weighted sum is calculated to obtain the collaborative contribution of the business expansion and power connection project, which is used to locate weak projects.

2. The method for evaluating the collaborative contribution of a business expansion and power connection project according to claim 1 is characterized in that: The connection capacity level of the project is: C pj =C pd / C pt / C at / C vl Among them, C pj is the project power connection capacity level, C pd The capacity reported for the project, C pt is the power type capacity of the project, C at is the project acceptance type capacity, C vl It is the voltage level capacity of the project.

3. The method for evaluating the collaborative contribution of a business expansion and power connection project according to claim 1 is characterized in that: The distribution network operation balance level of the project is: L pb =C pd / C tdn Among them, L pb is the project distribution network operation balance level, C pd For project power connection and installation capacity, C tdn It is the total capacity of the distribution network in the substation area.

4. The method for evaluating the collaborative contribution of a business expansion and power connection project according to claim 1 is characterized in that: The comprehensive load level of the electrical equipment is: Among them, L cl is the comprehensive load level of electrical equipment, is the maximum power sum of all electrical equipment, P frs is the probability of each device running simultaneously, is the sum of the power factors of each device, L dnm It is the maximum load of the distribution network.

5. The method for evaluating the collaborative contribution of a business expansion and power connection project according to claim 1 is characterized in that: The project volume is: Q p =L c / M c Among them, Q p is the project volume, L c is the cable length, M c It is the overall construction mileage of the project.

6. The method for evaluating the collaborative contribution of a business expansion and power connection project according to claim 1 is characterized in that: The time limit for achieving the project is: C pt =(TLAR ba +TLAR sr +TLAR pc +TLAR dr +TLAR ii +TLAR ca +TLAR cp ) / 7 Among them, TLAR ba TLAR is the time limit compliance rate of business acceptance link sr TLAR is the time limit achievement rate of the power supply plan response phase pc TLAR is the time limit achievement rate of supporting engineering links. dr TLAR is the time limit achievement rate of the facility review phase ii TLAR is the time limit achievement rate of the intermediate inspection link ca TLAR is the time limit compliance rate of the completion acceptance phase. cp It is the time limit compliance rate for meter installation and power connection.

7. The method for evaluating the collaborative contribution of a business expansion and power connection project according to claim 1 is characterized in that: The customer satisfaction is: S c =T cs / T tv Among them, S c For customer satisfaction, T cs is the number of visits to satisfied customers, T tv is the total number of visits.

8. A system for evaluating the collaborative contribution of a business expansion and power connection project, characterized in that: include: A data acquisition module is configured to: acquire project data, engineering data and electrical equipment data according to the business expansion and power connection project to be evaluated; An indicator calculation module is configured to calculate relevant indicators based on project data, engineering data and electrical equipment data, including: project power connection capacity level, project distribution network operation balance level, electrical equipment comprehensive load level, project engineering quantity, project time limit compliance and customer satisfaction; The evaluation module is configured as follows: based on the project power connection capacity level, the project distribution network operation balance level, the comprehensive load level of electrical equipment, the project engineering volume, the project time limit compliance and customer satisfaction, combined with the weights of the set relevant indicators, the weighted sum is calculated to obtain the collaborative contribution of the business expansion and power connection project, which is used to locate weak projects.

9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the steps in the method for evaluating the collaborative contribution of a business expansion and power connection engineering project as described in any one of claims 1-7 are implemented.

10. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the steps in the method for evaluating the collaborative contribution of a business expansion and power connection engineering project as described in any one of claims 1-7 are implemented.