Power investment prediction analysis system and method based on data fusion
Through data fusion analysis of the driving conditions and charging needs of new energy vehicles on highways, the layout of charging equipment is planned in segments, which solves the problem of unreasonable charging equipment planning in the existing technology, and improves the convenience of charging of new energy vehicles and resource utilization. efficiency.
Patent Information
- Application Number
- CN202411708460.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-27
- Publication Date
- 2024-12-27
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing charging equipment planning lacks effective data support, resulting in unreasonable distribution of charging stations, affecting the travel experience of new energy vehicle drivers, and simple statistical data is difficult to adapt to the rapidly changing market demand, resulting in uneven distribution of charging equipment.
Using a power investment prediction and analysis system based on data fusion, the location and vehicle information of highways are obtained on highways, and the driving conditions and charging needs of new energy vehicles are counted in sections, and the charging equipment investment and installation of each highway section is calculated. , ensure that the charging equipment is layout reasonably and fully.
It realizes the flexibly adjusting the density and location of charging equipment according to the conditions of different highway sections, reducing the planning workload, ensuring that charging equipment meets actual needs, and improving user experience and resource utilization efficiency.
Smart Images

Figure CN119204607A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electric power investment forecasting and analysis, and in particular to an electric power investment forecasting and analysis system and method based on data fusion. Background Art
[0002] With the development and popularization of new energy vehicle technology, more and more new energy vehicles are beginning to appear on highways. In order to meet the charging needs of these new energy vehicles during long-distance driving, it is particularly important to rationally plan the charging equipment on highways.
[0003] However, existing charging equipment planning often lacks effective data support, resulting in unreasonable distribution of charging stations, which not only affects the travel experience of new energy vehicle drivers, but also causes waste of resources.
[0004] At present, the planning of charging equipment mainly relies on empirical estimates or simple statistical data, and lacks in-depth analysis of key factors such as the charging demand of new energy vehicles. In addition, with the advancement of new energy vehicle technology and the growth of market ownership, simple charging equipment planning methods are difficult to adapt to rapidly changing market demands.
[0005] In addition, the existing planning method for charging equipment is not comprehensive enough. It only plans certain sections of the highway, resulting in uneven distribution of charging equipment, which in turn reduces the convenience of choosing new energy for charging. Summary of the invention
[0006] The present invention provides a power investment forecasting and analysis system and method based on data fusion, which are used to promote the solution of the problems mentioned in the above background technology.
[0007] The present invention provides the following technical solution: a method for predicting and analyzing electric power investment based on data fusion, Optionally, a power investment forecasting and analysis method based on data fusion is characterized by comprising: Get the location of a highway toll station on a highway, divide the highway into sections, record each section of the highway as a highway section, and get the length of each highway section; The expressway section is specifically the expressway section between two adjacent expressway toll stations; Obtain information about expressway service areas on expressway sections; Count the number of new energy vehicles among the vehicles passing through the expressway toll station and obtain vehicle information of new energy vehicles; Determine whether the new energy vehicle needs to be charged while driving on the highway according to the vehicle information of the new energy vehicle obtained; If a new energy vehicle needs to be charged while driving on a highway, the location of the highway service area where the new energy vehicle is charged is obtained; Obtain the number of vehicles on the highway, calculate the percentage, and determine the investment and installation of charging equipment based on the percentage.
[0008] Optionally, the location of a toll station on a highway is obtained, and the highway is divided into sections, each section of the divided highway is recorded as a highway section, and the length of each highway section is obtained, specifically: Determine the starting point and end point of the expressway, obtain the number of toll stations on the expressway, and divide the expressway into sections according to the toll stations; Obtain the distance between the midpoint of each expressway section and the starting point of the expressway, and record the expressway sections in order from small to large as the first expressway section, the second expressway section, the third expressway section, and so on, the Nth expressway section according to the distance between the midpoint of each expressway section and the starting point of the expressway; The midpoint of the expressway section is specifically the midpoint of the expressway between two expressway toll stations at both ends of the expressway section; Get the lengths of the first expressway section, the second expressway section, the third expressway section, and so on, and record them as X 1 , X 2 , X 3 ...X N .
[0009] Optionally, the obtaining of information about a highway service area on a highway section is specifically as follows: Obtain the number of expressway service areas on the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section; The two toll stations of the first expressway section are respectively the No. 1 starting point toll station and the No. 1 terminal toll station, the two toll stations of the second expressway section are respectively the No. 2 starting point toll station and the No. 2 terminal toll station, the two toll stations of the third expressway section are respectively the No. 3 starting point toll station and the No. 3 terminal toll station... The two toll stations of the Nth expressway section are respectively the No. N starting point toll station and the N terminal toll station; The distance between the No. 1 starting point toll station and the starting point of the expressway is less than the distance between the No. 1 terminal toll station and the starting point of the expressway, the distance between the No. 2 starting point toll station and the starting point of the expressway is less than the distance between the No. 2 terminal toll station and the starting point of the expressway, the distance between the No. 3 starting point toll station and the starting point of the expressway is less than the distance between the No. 3 terminal toll station and the starting point of the expressway... The distance between the No. N starting point toll station and the starting point of the expressway is less than the distance between the No. N terminal toll station and the starting point of the expressway; Get the distance between each highway service area and the No. 1 starting point toll station on the first highway section, get the distance between each highway service area and the No. 2 starting point toll station on the second highway section, get the distance between each highway service area and the No. 3 starting point toll station on the third highway section...get the distance between each highway service area and the No. N starting point toll station on the Nth highway section.
[0010] Optionally, counting the number of new energy vehicles among vehicles passing through the expressway toll station and obtaining new energy vehicle information of the new energy vehicles is specifically as follows: The number of new energy vehicles passing through starting point toll station No. 1, terminal toll station No. 1, starting point toll station No. 2, terminal toll station No. 2, starting point toll station No. 3, terminal toll station No. 3... starting point toll station No. N, terminal toll station N in the past year are counted respectively; Obtain vehicle information of the counted new energy vehicles; The vehicle information includes the battery power of the new energy vehicle before the new energy vehicle passes through the highway toll station and enters the highway, the battery power of the new energy vehicle before the new energy vehicle passes through the highway toll station and exits the highway, the distance traveled by the new energy vehicle on the highway, and the maximum distance that the new energy vehicle can travel when the battery is fully charged.
[0011] Optionally, judging whether the new energy vehicle needs to be charged during driving on the highway according to the acquired vehicle information of the new energy vehicle is specifically as follows: S1. Obtain two toll stations that new energy vehicles pass through on the expressway; S2: The toll station closer to the starting point of the expressway is the first toll station, and the other toll station is the last toll station; S3. If there is no expressway toll station between the first toll station and the last toll station, the distance between the first toll station and the last toll station is the length of the expressway section between the first toll station and the last toll station; S4. If there is a high-speed toll station between the first-end toll station and the last-end toll station, the distance between the first-end toll station and the last-end toll station is the sum of the distances of multiple high-speed sections between the first-end toll station and the last-end toll station; S5. Obtain the power of the new energy vehicle when it passes through the first-end toll station, and obtain the maximum distance that the new energy vehicle can travel with this power; S6. If the distance between the first toll station and the last toll station is greater than the maximum distance that a new energy vehicle can travel with this amount of electricity, the new energy vehicle is marked as a charging vehicle; S7. If the distance between the first toll station and the last toll station is less than or equal to the maximum distance that a new energy vehicle can travel with this power, the new energy vehicle will not be marked.
[0012] Optionally, if the new energy vehicle needs to be charged while driving on the highway, the location of the highway service area where the new energy vehicle is charged is obtained, specifically: S8. Mark all expressway service areas between the first toll station and the last toll station, where the distance from the first toll station does not exceed the maximum driving distance of a new energy vehicle at the current power level; S9. Select the expressway service area farthest from the first toll station among all marked expressway service areas and record it as the charging service area; S10. According to steps S1 to S9, the number of times each expressway service area is recorded as a charging service area in the expressway in the past year is obtained.
[0013] Optionally, the number of vehicles on the expressway is obtained, the proportion is calculated, and the investment and installation of charging equipment are determined according to the proportion, specifically: Count the total number of new energy vehicles traveling on the expressway in the past year, and obtain the total number of new energy vehicles traveling on the first expressway section, the second expressway section, the third expressway section, and the Nth expressway section in the past year; Calculate the ratio of the total number of new energy vehicles driving on the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section in the past year to the total number of new energy vehicles driving on the expressway in the past year; According to the ratio, the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section are sorted in order from large to small; Obtain the target number of charging equipment installed on highways; Calculate the target number of charging equipment to be placed on each highway section, specifically: The target number of charging equipment installed on each expressway section is proportional to the ratio of the total number of new energy vehicles running on the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section in the past year to the total number of new energy vehicles running on the expressway in the past year; Calculate the target number of charging equipment to be placed in each expressway service area on each expressway section, specifically: The target number of charging equipment to be installed at each highway service area on each highway section is directly proportional to the ratio of the number of times each highway service area has been recorded as a charging service area to the total number of new energy vehicles traveling on the highway section in the past year.
[0014] Optionally, a power investment forecasting and analysis system based on data fusion is characterized by comprising: Highway section data acquisition module: obtain the location of a highway toll station on a highway, divide the highway into sections, record each section of the highway as a highway section, and obtain the length of each highway section; Highway section data acquisition module: obtains information about highway service areas on highway sections; Vehicle information statistics module: count the number of new energy vehicles passing through the expressway toll station and obtain vehicle information of new energy vehicles; Data analysis module: judging whether the new energy vehicle needs to be charged while driving on the highway according to the vehicle information of the new energy vehicle obtained, and if the new energy vehicle needs to be charged while driving on the highway, obtaining the location of the highway service area where the new energy vehicle needs to be charged; Data calculation module: obtain the number of vehicles on the highway, calculate the proportion, and determine the investment and installation of charging equipment based on the proportion.
[0015] The present invention has the following beneficial effects: 1. This data fusion-based power investment forecasting and analysis method divides the highway into sections when planning the placement of charging equipment. The density and location of charging equipment can be flexibly adjusted according to the different conditions of each section of the highway, making the layout of charging piles more reasonable and reducing the planning workload.
[0016] 2. The power investment forecasting and analysis method based on data fusion divides the highway into sections and obtains the information of the highway service areas on each highway section, which is conducive to having a sufficient information basis for the subsequent planning of charging equipment.
[0017] 3. The data fusion-based power investment forecasting and analysis method can obtain information on the battery power of new energy vehicles passing through highway toll stations by counting the number of new energy vehicles passing through highway toll stations in the past year. It can understand the new energy vehicle flow and charging demand of different highway sections, so as to plan the layout and quantity of charging equipment in a targeted manner, accurately evaluate charging demand, and ensure that the setting of charging equipment can meet actual needs.
[0018] 4. This data fusion-based electricity investment forecasting and analysis method ranks vehicles according to the ratio of the total number of new energy vehicles traveling on each highway section to the total number of new energy vehicles traveling on the entire highway. This can more accurately evaluate the charging needs of different sections, ensure that charging facilities are set up where they are most needed, and improve the overall user experience.
[0019] 5. This data fusion-based power investment forecasting and analysis method plans each highway section simultaneously when planning charging equipment, making the planning more comprehensive and specific, preventing uneven distribution of charging equipment, and improving the convenience of charging new energy vehicles. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a schematic diagram of a flow chart of the present invention. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] Embodiment 1, refer to Figure 1 , a power investment forecasting and analysis method based on data fusion, characterized by: including: Get the location of the toll station on a highway and divide the highway into sections. The density and location of charging equipment can be flexibly adjusted according to the different conditions of each section of the highway, making the layout of charging piles more reasonable and reducing the workload of planning. Each section of the highway after segmentation is recorded as a highway section, and the length of each highway section is obtained; The expressway section is specifically the expressway section between two adjacent expressway toll stations; Obtain information about expressway service areas on expressway sections; Count the number of new energy vehicles among the vehicles passing through the expressway toll station and obtain vehicle information of new energy vehicles; Determine whether the new energy vehicle needs to be charged while driving on the highway according to the vehicle information of the new energy vehicle obtained; If a new energy vehicle needs to be charged while driving on a highway, the location of the highway service area where the new energy vehicle is charged is obtained; Obtain the number of vehicles on the highway, calculate the percentage, and determine the investment and installation of charging equipment based on the percentage.
[0023] The method of obtaining the location of a toll station on a highway, dividing the highway into sections, recording each section of the highway as a highway section, and obtaining the length of each highway section is specifically as follows: Determine the starting point and end point of the expressway, obtain the number of toll stations on the expressway, and divide the expressway into sections according to the toll stations; dividing the expressway into sections according to toll stations can more accurately reflect the traffic flow and service area distribution, which is helpful for formulating more targeted charging equipment planning; Obtain the distance between the midpoint of each expressway section and the starting point of the expressway, and record the expressway sections in order from small to large as the first expressway section, the second expressway section, the third expressway section, and so on, the Nth expressway section according to the distance between the midpoint of each expressway section and the starting point of the expressway; The midpoint of the expressway section is specifically the midpoint of the expressway between two expressway toll stations at both ends of the expressway section; Get the lengths of the first expressway section, the second expressway section, the third expressway section, and so on, and record them as X 1 , X 2 , X 3 ...X N , the length of each highway section can be obtained to subsequently determine whether new energy vehicles need to be charged.
[0024] The step of obtaining the information of the expressway service area on the expressway section is as follows: Obtain the number of expressway service areas on the first expressway section, the second expressway section, the third expressway section, and so on the Nth expressway section; when planning, each expressway service area is within the planning scope to ensure that charging equipment covers a more comprehensive coverage and more fully meets the demand for new energy charging; The two toll stations of the first expressway section are respectively the No. 1 starting point toll station and the No. 1 terminal toll station, the two toll stations of the second expressway section are respectively the No. 2 starting point toll station and the No. 2 terminal toll station, the two toll stations of the third expressway section are respectively the No. 3 starting point toll station and the No. 3 terminal toll station... The two toll stations of the Nth expressway section are respectively the No. N starting point toll station and the N terminal toll station; The distance between the No. 1 starting point toll station and the starting point of the expressway is less than the distance between the No. 1 terminal toll station and the starting point of the expressway, the distance between the No. 2 starting point toll station and the starting point of the expressway is less than the distance between the No. 2 terminal toll station and the starting point of the expressway, the distance between the No. 3 starting point toll station and the starting point of the expressway is less than the distance between the No. 3 terminal toll station and the starting point of the expressway... The distance between the No. N starting point toll station and the starting point of the expressway is less than the distance between the No. N terminal toll station and the starting point of the expressway; Get the distance between each highway service area and the No. 1 starting point toll station on the first highway section, get the distance between each highway service area and the No. 2 starting point toll station on the second highway section, get the distance between each highway service area and the No. 3 starting point toll station on the third highway section... Get the distance between each highway service area and the No. N starting point toll station on the Nth highway section, get the distance between each highway service area and the starting point toll station on the highway section, combined with the length of each highway section, which is conducive to the subsequent judgment of whether new energy vehicles need to be charged, and the judgment of the location where new energy vehicles are charged.
[0025] The counting of the number of new energy vehicles among the vehicles passing through the expressway toll station and obtaining the new energy vehicle information of the new energy vehicles is specifically as follows: The number of new energy vehicles passing through starting point toll station No. 1, terminal toll station No. 1, starting point toll station No. 2, terminal toll station No. 2, starting point toll station No. 3, terminal toll station No. 3... starting point toll station No. N, terminal toll station N in the past year is counted respectively. The data of the past year can better capture the changes in the use trend of new energy vehicles, which is very important for planning charging facilities, and can also predict future demand, which helps to make more reasonable investment decisions; Obtain vehicle information of the counted new energy vehicles; The vehicle information includes the battery power of the new energy vehicle before it passes through the highway toll station to get on the highway, the battery power of the new energy vehicle before it passes through the highway toll station to get off the highway, the driving distance of the new energy vehicle on the highway, and the maximum distance that the new energy vehicle can travel when the battery is fully charged. By obtaining the above information, the new energy vehicle flow rate and the charging demand of different highway sections can be understood, so as to plan the layout and quantity of charging equipment in a targeted manner, accurately evaluate the charging demand, and ensure that the setting of charging equipment can meet actual needs.
[0026] The method of determining whether the new energy vehicle needs to be charged during driving on the highway according to the acquired vehicle information of the new energy vehicle is specifically as follows: S1. Obtain two toll stations that new energy vehicles pass through on the expressway; S2: The toll station closer to the starting point of the expressway is the first toll station, and the other toll station is the last toll station, that is, new energy vehicles enter the expressway through the first toll station and exit the expressway through the last toll station; S3. If there is no expressway toll station between the first-end toll station and the last-end toll station, the distance between the first-end toll station and the last-end toll station is the length of the expressway section between the first-end toll station and the last-end toll station. If a new energy vehicle enters the expressway at the fifth starting toll station and exits the expressway at the fifth terminal toll station, the first-end toll station is the fifth starting toll station and the last-end toll station is the fifth terminal toll station. At this time, there is no expressway toll station between the first-end toll station and the last-end toll station. The distance between the first-end toll station and the last-end toll station is the length of the fifth expressway section. S4. If there is a highway toll station between the head-end toll station and the tail-end toll station, the distance between the head-end toll station and the tail-end toll station is the sum of the distances of multiple highway sections between the head-end toll station and the tail-end toll station. If a new energy vehicle enters the highway at the No. 4 starting toll station and exits the highway at the No. 5 terminal toll station, the head-end toll station is the No. 4 starting toll station and the tail-end toll station is the No. 5 terminal toll station. At this time, there are the No. 4 terminal toll station and the No. 5 starting toll station between the head-end toll station and the tail-end toll station. The distance between the head-end toll station and the tail-end toll station is: the sum of the lengths of the fourth highway section and the fifth highway section. S5. Obtain the power of the new energy vehicle when it passes through the first-end toll station, and obtain the maximum distance that the new energy vehicle can travel with this power; S6. If the distance between the first toll station and the last toll station is greater than the maximum distance that the new energy vehicle can travel with this power, it means that the power of the new energy vehicle at this time cannot support the new energy vehicle to travel to the destination, so the new energy vehicle needs to be charged, and the new energy vehicle is marked as a charging vehicle; S7. If the distance between the first toll station and the last toll station is less than or equal to the maximum distance that the new energy vehicle can travel with this power, it means that the power of the new energy vehicle at this time can support the new energy vehicle to travel to the destination, so the new energy vehicle does not need to be charged, and the new energy vehicle will not be marked.
[0027] If the new energy vehicle needs to be charged while driving on the highway, the location of the highway service area where the new energy vehicle is charged is obtained, specifically: S8. Mark all expressway service areas between the first toll station and the last toll station, where the distance from the first toll station does not exceed the maximum driving distance of new energy vehicles at the current power level. New energy vehicles can be charged in these expressway service areas; S9. Select the expressway service area farthest from the first toll station among all marked expressway service areas and record it as the charging service area. This method can minimize unnecessary charging times, improve charging efficiency, and provide necessary support for new energy vehicles. S10. According to steps S1 to S9, the number of times each expressway service area is recorded as a charging service area in the expressway in the past year is obtained.
[0028] The method of obtaining the number of vehicles on the expressway, calculating the proportion, and determining the investment and installation of charging equipment according to the proportion is as follows: The total number of new energy vehicles traveling on the expressway in the past year is counted, and the total number of new energy vehicles traveling on the first expressway section, the second expressway section, the third expressway section, and the Nth expressway section in the past year are obtained respectively. The charging demand of each expressway section can be obtained according to the counted number of times; Calculate the ratio of the total number of new energy vehicles driving on the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section in the past year to the total number of new energy vehicles driving on the expressway in the past year; According to the ratio, the first expressway section, the second expressway section, the third expressway section, and the Nth expressway section are ranked in descending order. The larger the ratio, the higher the ranking, and the greater the demand for charging equipment. Obtain the target number of charging equipment installed on highways; Calculate the target number of charging equipment to be placed on each highway section, specifically: The target number of charging equipment installed on each expressway section is proportional to the ratio of the total number of new energy vehicles running on the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section in the past year to the total number of new energy vehicles running on the expressway in the past year; Calculate the target number of charging equipment to be placed in each expressway service area on each expressway section, specifically: The target number of charging equipment to be installed at each highway service area on each highway section is directly proportional to the ratio of the number of times each highway service area has been recorded as a charging service area in the past year to the total number of new energy vehicles traveling on the highway section in the past year. By sorting the highway sections based on the ratio of the total number of new energy vehicles traveling on each highway section to the total number of new energy vehicles traveling on the entire highway, we can more accurately assess the charging needs of different sections, ensure that charging facilities are set up where they are most needed, and improve the overall user experience.
[0029] Embodiment 2, a power investment forecasting and analysis system based on data fusion, characterized by comprising: Highway section data acquisition module: obtain the location of a highway toll station on a highway, divide the highway into sections, record each section of the highway as a highway section, and obtain the length of each highway section; Highway section data acquisition module: obtains information about highway service areas on highway sections; Vehicle information statistics module: count the number of new energy vehicles passing through the expressway toll station and obtain vehicle information of new energy vehicles; Data analysis module: judging whether the new energy vehicle needs to be charged while driving on the highway according to the vehicle information of the new energy vehicle obtained, and if the new energy vehicle needs to be charged while driving on the highway, obtaining the location of the highway service area where the new energy vehicle needs to be charged; Data calculation module: obtain the number of vehicles on the highway, calculate the proportion, and determine the investment and installation of charging equipment based on the proportion.
[0030] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0031] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A power investment forecasting and analysis method based on data fusion, characterized by: include: Get the location of a highway toll station on a highway, divide the highway into sections, record each section of the highway as a highway section, and get the length of each highway section; The expressway section is specifically the expressway section between two adjacent expressway toll stations; Obtain information about expressway service areas on expressway sections; Count the number of new energy vehicles among the vehicles passing through the expressway toll station and obtain vehicle information of new energy vehicles; Determine whether the new energy vehicle needs to be charged while driving on the highway according to the vehicle information of the new energy vehicle obtained; If a new energy vehicle needs to be charged while driving on a highway, the location of the highway service area where the new energy vehicle is charged is obtained; Obtain the number of vehicles on the highway, calculate the percentage, and determine the investment and installation of charging equipment based on the percentage.
2. The method for predicting and analyzing electric power investment based on data fusion according to claim 1 is characterized in that: The method of obtaining the location of a toll station on a highway, dividing the highway into sections, recording each section of the highway as a highway section, and obtaining the length of each highway section is specifically as follows: Determine the starting point and end point of the expressway, obtain the number of toll stations on the expressway, and divide the expressway into sections according to the toll stations; Obtain the distance between the midpoint of each expressway section and the starting point of the expressway, and record the expressway sections in order from small to large as the first expressway section, the second expressway section, the third expressway section, and so on, according to the distance between the midpoint between the expressway toll stations at both ends of each expressway section and the starting point of the expressway; The midpoint of the expressway section is specifically the midpoint of the expressway between two expressway toll stations at both ends of the expressway section; The midpoint of the expressway section is specifically the midpoint of the expressway between two adjacent toll stations; Get the lengths of the first expressway section, the second expressway section, the third expressway section, and so on, and record them as X1, X2, X3, and so on, respectively. N .
3. The power investment forecasting and analysis method based on data fusion according to claim 1 is characterized by: The step of obtaining the information of the high-speed service area on the high-speed road section is as follows: Obtain the number of expressway service areas on the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section; The two toll stations of the first expressway section are respectively the No. 1 starting point toll station and the No. 1 terminal toll station, the two toll stations of the second expressway section are respectively the No. 2 starting point toll station and the No. 2 terminal toll station, the two toll stations of the third expressway section are respectively the No. 3 starting point toll station and the No. 3 terminal toll station... The two toll stations of the Nth expressway section are respectively the No. N starting point toll station and the N terminal toll station; The distance between the No. 1 starting point toll station and the starting point of the expressway is less than the distance between the No. 1 terminal toll station and the starting point of the expressway, the distance between the No. 2 starting point toll station and the starting point of the expressway is less than the distance between the No. 2 terminal toll station and the starting point of the expressway, the distance between the No. 3 starting point toll station and the starting point of the expressway is less than the distance between the No. 3 terminal toll station and the starting point of the expressway... The distance between the No. N starting point toll station and the starting point of the expressway is less than the distance between the No. N terminal toll station and the starting point of the expressway; Get the distance between each highway service area and the No. 1 starting point toll station on the first highway section, get the distance between each highway service area and the No. 2 starting point toll station on the second highway section, get the distance between each highway service area and the No. 3 starting point toll station on the third highway section...get the distance between each highway service area and the No. N starting point toll station on the Nth highway section.
4. The power investment forecasting and analysis method based on data fusion according to claim 1 is characterized by: The counting of the number of new energy vehicles among the vehicles passing through the expressway toll station and obtaining the new energy vehicle information of the new energy vehicles is specifically as follows: The number of new energy vehicles passing through starting point toll station No. 1, terminal toll station No. 1, starting point toll station No. 2, terminal toll station No. 2, starting point toll station No. 3, terminal toll station No. 3... starting point toll station No. N, terminal toll station N in the past year are counted respectively; Obtain vehicle information of the counted new energy vehicles; The vehicle information includes the battery power of the new energy vehicle before the new energy vehicle passes through the highway toll station and enters the highway, the battery power of the new energy vehicle before the new energy vehicle passes through the highway toll station and exits the highway, the distance traveled by the new energy vehicle on the highway, and the maximum distance that the new energy vehicle can travel when the battery is fully charged.
5. The method for predicting and analyzing electric power investment based on data fusion according to claim 1 is characterized in that: The method of determining whether the new energy vehicle needs to be charged during driving on the highway according to the acquired vehicle information of the new energy vehicle is specifically as follows: S1. Obtain two toll stations that new energy vehicles pass through on the expressway; S2: The toll station closer to the starting point of the expressway is the first toll station, and the other toll station is the last toll station; S3. If there is no expressway toll station between the first toll station and the last toll station, the distance between the first toll station and the last toll station is the length of the expressway section between the first toll station and the last toll station; S4. If there is a high-speed toll station between the first-end toll station and the last-end toll station, the distance between the first-end toll station and the last-end toll station is the sum of the distances of multiple high-speed sections between the first-end toll station and the last-end toll station; S5. Obtain the power of the new energy vehicle when it passes through the first-end toll station, and obtain the maximum distance that the new energy vehicle can travel with this power; S6. If the distance between the first toll station and the last toll station is greater than the maximum distance that a new energy vehicle can travel with this amount of electricity, the new energy vehicle is marked as a charging vehicle; S7. If the distance between the first toll station and the last toll station is less than or equal to the maximum distance that a new energy vehicle can travel with this power, the new energy vehicle will not be marked.
6. The method for predicting and analyzing electric power investment based on data fusion according to claim 1 is characterized in that: If the new energy vehicle needs to be charged while driving on the highway, the location of the highway service area where the new energy vehicle is charged is obtained, specifically: S8. Mark all expressway service areas between the first toll station and the last toll station, where the distance from the first toll station does not exceed the maximum driving distance of a new energy vehicle at the current power level; S9. Select the expressway service area farthest from the first toll station among all marked expressway service areas and record it as the charging service area; S10. According to steps S1 to S9, the number of times each expressway service area is recorded as a charging service area in the expressway in the past year is obtained.
7. The method for predicting and analyzing electric power investment based on data fusion according to claim 1 is characterized by: The method of obtaining the number of vehicles on the expressway, calculating the proportion, and determining the investment and installation of charging equipment according to the proportion is as follows: Count the total number of new energy vehicles traveling on the expressway in the past year, and obtain the total number of new energy vehicles traveling on the first expressway section, the second expressway section, the third expressway section, and the Nth expressway section in the past year; Calculate the ratio of the total number of new energy vehicles driving on the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section in the past year to the total number of new energy vehicles driving on the expressway in the past year; According to the ratio, the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section are sorted in order from large to small; Obtain the target number of charging equipment installed on highways; Calculate the target number of charging equipment to be placed on each highway section, specifically: The target number of charging equipment installed on each expressway section is proportional to the ratio of the total number of new energy vehicles running on the first expressway section, the second expressway section, the third expressway section, ... the Nth expressway section in the past year to the total number of new energy vehicles running on the expressway in the past year; Calculate the target number of charging equipment to be placed in each expressway service area on each expressway section, specifically: The target number of charging equipment to be installed at each highway service area on each highway section is directly proportional to the ratio of the number of times each highway service area has been recorded as a charging service area to the total number of new energy vehicles traveling on the highway section in the past year.
8. A system using the power investment forecasting and analysis method based on data fusion as claimed in claim 1, characterized in that: include: Highway section data acquisition module: obtain the location of a highway toll station on a highway, divide the highway into sections, record each section of the highway as a highway section, and obtain the length of each highway section; Highway section data acquisition module: obtains information about highway service areas on highway sections; Vehicle information statistics module: count the number of new energy vehicles passing through the expressway toll station and obtain vehicle information of new energy vehicles; Data analysis module: judging whether the new energy vehicle needs to be charged while driving on the highway according to the vehicle information of the new energy vehicle obtained, and if the new energy vehicle needs to be charged while driving on the highway, obtaining the location of the highway service area where the new energy vehicle needs to be charged; Data calculation module: obtain the number of vehicles on the highway, calculate the proportion, and determine the investment and installation of charging equipment based on the proportion.
Citation Information
Patent Citations
An expressway charging station planning method considering service areas and vehicle accidents
CN109190935A
Power charging station site selection and layout method and device
CN111523714A
Electric vehicle charging station site selection method based on user behaviors
CN115344653A
Expressway micro-grid capacity configuration method and system considering charging pile planning
CN117391349A
Arterial highway network public charging infrastructure layout method
CN117973817A