Ground elevation control device and construction method

By using components such as poles, fixing pads, and hooks in the ground elevation control device, the problems of easy damage to mortar spots and difficulty in large-area scanning of the leveling instrument in ground elevation control are solved, thereby improving the flatness of concrete pouring and structural strength, and increasing construction efficiency and accuracy.

CN119266495APending Publication Date: 2025-01-07CHINA CONSTR EIGHTH ENG GRP SHENZHEN CONSTR TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411651966.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-19
Publication Date
2025-01-07

AI Technical Summary

Technical Problem

In existing technologies, ground elevation control measures using mortar spots are easily damaged, and leveling instruments have difficulty completing large-area scanning, resulting in uneven ground surfaces after concrete pouring.

Method used

A ground elevation control device, including uprights, fixing pads, and mounting nails, is used. The uprights are fixed on the floor slab and have scales and hooks on them for elevation identification and to support the steel mesh. Combined with the use of connecting rods and threaded rods, the flatness of the concrete pouring and the structural strength are ensured.

Benefits of technology

It improved the flatness and structural strength of the finished concrete surface, reduced the occurrence of pole tipping, improved construction efficiency and precision, and ensured the accuracy of ground elevation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119266495A_ABST
    Figure CN119266495A_ABST
Patent Text Reader

Abstract

The invention relates to a ground elevation control device and a construction method, and relates to the technical field of building components, the device comprises a vertical rod, the lower end of the vertical rod is fixedly connected with a fixing gasket, the fixing gasket is provided with a plurality of fixing holes, the fixing holes are provided with mounting nails from top to bottom in a penetrating mode, and the mounting nails extend to the lower portion of the fixing gasket; and scales are arranged on the outer surface of the vertical rod and are used for identifying the elevation. The fixing gasket is arranged on the upper end face of the floor slab, then a plurality of mounting nails penetrate through the fixing holes and are driven into the floor slab, fixing of the fixing gasket is completed, the situation that the vertical rods topple over during follow-up concrete pouring can be effectively reduced, the vertical rods are arranged on the floor slab, then concrete can be poured on the floor slab, and the concrete pouring efficiency is improved. And after the poured concrete reaches the specific scales of the multiple vertical rods, pouring can be stopped, construction is completed, the flatness of the poured face of each vertical rod can be checked, and then the flatness of the poured face is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building components, and in particular to a ground elevation control device and a construction method. Background Art

[0002] At present, when constructing basements and some ground projects, they are all reinforced concrete floors. After pouring is completed, the surface layer is polished, and then the building surface construction work is carried out on the reinforced concrete floor.

[0003] At present, in the construction process, the ground elevation control measures usually use ash cakes or laser leveling. However, there are problems such as ash cakes are easily damaged and the leveling instrument is difficult to complete the entire large-area scan, which can easily lead to uneven ground after the concrete is poured. Summary of the invention

[0004] In order to solve the above problems, the present application provides a ground elevation control device and a construction method.

[0005] In a first aspect, the present application provides a ground elevation control device, which adopts the following technical solution: A ground elevation control device comprises a vertical pole, wherein the lower end of the vertical pole is fixedly connected with a fixing gasket, a plurality of fixing holes are opened on the fixing gasket, and mounting nails are passed through the plurality of fixing holes from top to bottom. The mounting nails extend to the bottom of the fixing gasket and are used to fix the vertical pole. The outer surface of the vertical pole is provided with a scale for elevation identification.

[0006] By adopting the above technical solution, during installation, a fixing gasket is placed on the upper end surface of the floor slab, and then a number of installation nails are passed through the fixing holes and driven into the interior of the floor slab to complete the fixation of the fixing gasket, which can effectively reduce the occurrence of the vertical pole tipping over during the subsequent concrete pouring; at this time, the vertical pole has been fixed to the upper end of the floor slab; by arranging a plurality of vertical poles on the floor slab, concrete can be poured on the floor slab, and after the poured concrete reaches the specific scales of a number of vertical poles, the pouring can be stopped to complete the construction, and the flatness of the poured surface can be checked on a plurality of vertical poles, thereby improving the flatness of the poured surface.

[0007] Optionally, a plurality of hooks are arranged vertically and evenly spaced on one side in the length direction of the vertical pole, including a horizontal pole and a vertical pole, the end of the horizontal pole away from the vertical pole is fixedly connected to the vertical pole, the vertical pole is fixedly connected to the upper end of the horizontal pole, and the end of the horizontal pole close to the vertical pole is fixedly connected to the vertical pole.

[0008] By adopting the above technical solution, before pouring, a steel mesh is usually built into the area that needs to be poured. The staff can place the steel mesh on the upper end of the hook and complete the layout of the steel mesh by placing the steel mesh on the upper ends of several horizontal bars, thereby improving the structural strength of the subsequent concrete floor. The staff does not need to use stirrups to support the steel mesh, thereby improving the efficiency of the construction and the functionality of the ground elevation control device, which can not only support the steel mesh, but also identify the elevation.

[0009] Optionally, a connecting rod is also included, which is detachably connected to the upper end of the vertical pole, and the outer surface of the connecting rod is also provided with a scale for elevation identification.

[0010] By adopting the above technical solution, if the thickness of the concrete to be poured is large, a connecting rod can be installed at the upper end of the vertical pole to increase the height of the scale, and then the concrete can be poured. After pouring to a specific height of the connecting rod, the connecting rod located at the upper end of the pouring ground can be cut off, which has high applicability.

[0011] Optionally, hooks are also arranged vertically at equal intervals on one side of the connecting rod in the length direction.

[0012] By adopting the above technical solution, if the thickness of the concrete to be poured is large, a steel mesh can also be placed on the hook of the connecting rod, thereby improving the structural strength of the subsequent concrete. The workers do not need to use stirrups to support the steel mesh, thereby improving the efficiency of the construction. It can also improve the functionality of the ground elevation control device, which can not only support the steel mesh, but also identify the elevation.

[0013] Optionally, a threaded rod extends from the lower end of the connecting rod, and a threaded groove adapted to the threaded rod is formed at the upper end of the vertical rod.

[0014] By adopting the above technical solution, the connection between the vertical pole and the connecting rod is completed by screwing the threaded rod into the inside of the threaded groove, which has a simple structure and convenient connection.

[0015] Optionally, the connecting rod and the vertical rod are both made of plastic.

[0016] By adopting the above technical solution, the connecting rods and vertical poles made of plastic are easier to process and have lower costs. When the designed thickness of the concrete does not match the device modulus, it can be processed by horizontal cutting along the entire scale line position to meet on-site use requirements, and it is more convenient to cut the connecting rods and vertical poles.

[0017] Optionally, some of the hooks are made of metal.

[0018] By adopting the above technical solution, the metal hooks can well support the steel mesh, thereby improving the stability of the steel mesh.

[0019] Optionally, a plurality of marking holes are provided on the vertical pole and the connecting rod, the marking holes correspond to the scales, the height of the marking holes is the same as the height of the corresponding scales, and a plurality of marking holes are provided on the side of the vertical pole away from the hook, and marking plates matching the marking holes can be inserted into the plurality of marking holes for elevation identification.

[0020] By adopting the above technical solution, after determining the height to be poured, the marking plate is inserted into the marking hole in the opposite direction of the determined scale, thereby improving the convenience of positioning the concrete height during subsequent pouring.

[0021] By adopting the above technical solution, after determining the height to be poured, In a second aspect, the present application provides a construction method for a ground elevation control device.

[0022] A construction method for a ground elevation control device comprises the following steps: S1: Place the fixing gasket on the floor slab, drive the installation nails through several fixing holes and into the floor slab, fix the fixing gasket on the floor slab, if the concrete pouring thickness exceeds 50mm, screw the threaded rod of the connecting rod into the screw hole of the vertical rod; S2: Repeat step S1 to install vertical poles at the four corners of the floor slab, and then install multiple vertical poles at equal intervals on the floor slab between the vertical poles; S3: placing a plurality of reinforcing bars horizontally in sequence on the hooks at the lowest height where no reinforcing bars are currently placed; placing a plurality of reinforcing bars on the hooks at the second-to-last height, crossing with the previously placed reinforcing bars; S4: Repeat step S3 to complete the layout of the steel mesh.

[0023] In summary, the present application includes at least one of the following beneficial technical effects: 1. During installation, place the fixing gasket on the upper end surface of the floor slab, then pass several installation nails through the fixing holes, and drive the installation nails into the interior of the floor slab to complete the fixing of the fixing gasket, which can effectively reduce the occurrence of the vertical pole tipping during the subsequent concrete pouring; at this time, the vertical pole has been fixed to the upper end of the floor slab, and by laying out multiple vertical poles on the floor slab, concrete can be poured on the floor slab. When the poured concrete reaches the specific scale of several vertical poles, the pouring can be stopped to complete the construction. The flatness of the poured surface can be checked on multiple vertical poles, thereby improving the flatness of the poured surface; 2. Before pouring, steel mesh is usually built into the area to be poured. The staff can place the steel mesh on the upper end of the hook. By placing the steel mesh on the upper end of several horizontal bars, the steel mesh is laid out, thereby improving the structural strength of the subsequent concrete floor. The staff does not need to use stirrup bars to support the steel mesh, thereby improving the efficiency of construction and the functionality of the ground elevation control device, which can not only play the role of supporting the steel mesh, but also play the role of elevation identification; 3. If the thickness of the concrete to be poured is large, a steel mesh can also be placed on the hook of the connecting rod to improve the structural strength of the subsequent concrete. The workers do not need to use stirrups to support the steel mesh, thereby improving the efficiency of the construction and improving the functionality of the ground elevation control device, which can not only support the steel mesh, but also identify the elevation. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram showing the vertical pole in the first embodiment.

[0025] Figure 2 It is a schematic diagram highlighting the fixing holes in the first embodiment.

[0026] Figure 3 It is a schematic diagram highlighting the vertical poles and the steel mesh in the first embodiment.

[0027] Figure 4 It is a schematic diagram highlighting the connecting rod in the first embodiment.

[0028] Figure 5 It is a schematic diagram of the overall structure of the first embodiment.

[0029] Figure 6 It is a schematic diagram highlighting the marked hole in the second embodiment.

[0030] Figure 7 It is a schematic diagram of highlighting the target plate in the second embodiment.

[0031] Figure 8 It is a schematic diagram highlighting the vertical poles and steel bars in the third embodiment.

[0032] Explanation of the reference numerals: 1. vertical pole; 11. threaded groove; 2. fixing gasket; 21. fixing hole; 22. mounting nail; 3. hook; 31. horizontal pole; 32. vertical pole; 4. connecting rod; 41. threaded rod; 5. marking hole; 6. marking plate. DETAILED DESCRIPTION

[0033] The present application is further described in detail below in conjunction with all the accompanying drawings.

[0034] The embodiments of the present application disclose a ground elevation control device and a construction method.

[0035] In a first aspect, an embodiment of the present application discloses a ground elevation control device.

[0036] Reference Figure 1 and Figure 2 , a ground elevation control device, comprising a vertical pole 1, the vertical pole 1 is 50mm long and 12mm in diameter; a 2mm thick fixing gasket 2 is fixedly connected to the lower end of the vertical pole 1, the vertical pole 1 and the fixing gasket 2 are arranged perpendicular to each other, the vertical pole 1 is arranged at the axis of the fixing gasket 2, and four fixing holes 21 with a diameter of 2mm are opened on the fixing gasket 2. The four fixing holes 21 are penetrated from top to bottom with mounting nails 22. During installation, the fixing gasket 2 is placed on the upper end surface of the floor slab, and then a plurality of mounting nails 22 are passed through the fixing holes 21, and the mounting nails 22 are driven into the interior of the floor slab, and the mounting nails 22 are extended to the bottom of the fixing gasket 2 to fix the vertical pole 1, which can effectively reduce the occurrence of the vertical pole 1 toppling during the subsequent concrete pouring; at this time, the vertical pole 1 has been fixed to the upper end of the floor slab, and multiple ground elevation control devices can be arranged on the floor slab, which can be placed according to the corner position of the ground separation joint, or can be densely arranged according to the integer multiple relationship of the separation joint width, so as to improve the precision requirement of large-area construction.

[0037] The installation nails 22 in this embodiment are preferably cement nails, which can fix the fixing gasket 2 on the floor.

[0038] When constructing the floor slab, the construction workers can also pre-embed the vertical pole 1 and the fixing gasket 2 into the floor slab, so that the vertical pole 1 extends to the top of the floor slab, which can further save the construction efficiency.

[0039] Reference Figure 1 and Figure 2 The outer surface of the vertical pole 1 is provided with a scale for elevation identification. After installing multiple ground elevation control devices, the scale elevation needs to be uniformly reviewed to reduce the measurement error caused by the uneven original foundation surface. For the position where the elevation error exists on the original foundation surface, appropriate padding or cutting can be carried out after verification. Only after the scale elevation is verified, large-scale construction can be carried out to ensure the accuracy of large-area ground construction with precise scale; then concrete can be poured on the floor slab. After the poured concrete reaches the specific scale of several vertical poles 1, the pouring can be stopped to complete the construction. The flatness of the poured surface can be checked on multiple vertical poles 1, thereby improving the flatness of the poured surface.

[0040] Reference Figure 1 and Figure 2Before pouring, a steel mesh is usually built into the area where pouring is required. Four hooks 3 for placing steel bars are arranged vertically and evenly on one side of the length direction of the vertical pole 1. The distance between adjacent hooks 3 is 10 mm to meet the requirements of different steel mesh pad heights. By providing hooks 3 of more heights for selection, the effect of convenient construction is achieved.

[0041] Reference Figure 2 and Figure 3 After several vertical poles 1 are installed on the floor slab, the steel mesh can be placed.

[0042] Among them, the steel mesh is a mesh formed by a number of steel bars of different heights and perpendicular to each other.

[0043] Reference Figure 2 and Figure 3 The hook 3 includes a horizontal rod 31 and a vertical rod 32. The length of the horizontal rod 31 is 5 mm. The end of the horizontal rod 31 away from the vertical rod 1 is fixedly connected to the vertical rod 32. The vertical rod 32 is fixedly connected to the upper end of the horizontal rod 31. The end of the horizontal rod 31 close to the vertical rod 1 is fixedly connected to the vertical rod 1. Reference Figure 2 and Figure 3 , the staff can place several steel bars on the upper end of the hook 3 with the lowest height among the several vertical poles 1, and then place several steel bars on the upper end of the hook 3 with the second to last height among the several vertical poles 1, so that the two groups of steel bars are arranged in a perpendicular and crossed direction to each other; then repeat the above steps again to complete the arrangement of the steel mesh. The staff does not need to use stirrups to support the steel mesh, thereby improving the construction efficiency and the functionality of the ground elevation control device. The hook 3 can be used to support the steel mesh, and the scale on the vertical pole 1 can be used to identify the elevation.

[0044] Reference Figure 2 and Figure 3 By laying out steel mesh, the structural strength and stability of concrete can be significantly improved after the subsequent pouring of concrete, effectively enhancing the bearing capacity of the building; and by evenly distributing the load, the steel mesh can reduce stress concentration in the structure, prevent the occurrence of cracks, and extend the service life of the ground structure.

[0045] Reference Figure 1 and Figure 2 After the steel mesh is laid out, the concrete can be poured. After pouring to a specific height of the vertical pole 1, the remaining part of the vertical pole 1 located at the upper end of the pouring ground can be cut off after the concrete is completely solidified. Depending on the working conditions, the vertical pole 1 can also be cut after determining the pouring height of the concrete before pouring the concrete. The staff can make a choice according to different working conditions.

[0046] The vertical pole 1 is made of plastic material, which is convenient to process and has low cost. It is also easier to cut the vertical pole 1 when cutting it, thereby improving the efficiency of the construction.

[0047] Reference Figure 4 and Figure 5 The ground elevation control device also includes a connecting rod 4, which is detachably connected to the upper end of the vertical pole 1. If the thickness of the concrete to be poured is large and the height of the vertical pole 1 is not high enough, the connecting rod 4 can be installed on the upper end of the vertical pole 1. The outer surface of the connecting rod 4 is also provided with a scale for elevation identification, and then the height of the scale is increased, and then the concrete can be poured. After pouring to a specific height of the connecting rod 4, after the concrete is completely solidified, the connecting rod 4 located at the upper end of the pouring ground can be cut off, which has high applicability.

[0048] Among them, according to different working conditions, the connecting rod 4 can also be cut after determining the pouring height of the concrete before pouring the concrete, and the staff can make a choice according to different working conditions.

[0049] Reference Figure 4 and Figure 5 A threaded rod 41 is extended from the lower end of the connecting rod 4, and a threaded groove 11 adapted to the threaded rod 41 is opened at the upper end of the vertical rod 1; the connection between the vertical rod 1 and the connecting rod 4 is completed by screwing the threaded rod 41 into the threaded groove 11, which has a simple structure and is convenient to connect.

[0050] Among them, the connecting rod 4 is also made of plastic. The connecting rod 4 made of plastic is easier to process and has lower cost. When the design thickness of the concrete does not match the device modulus, it can be processed by horizontal cutting along the entire scale line position to meet on-site use requirements. It is more convenient to cut the connecting rod 4 and the vertical pole 1.

[0051] Reference Figure 4 and Figure 5 Hooks 3 are also arranged vertically at equal intervals on one side of the length direction of the connecting rod 4. The staff can also place steel mesh on the hooks 3 of the connecting rod 4, thereby improving the structural strength of the subsequent concrete. There is no need to use stirrups to support the steel mesh, thereby improving the efficiency of construction.

[0052] Reference Figure 4 and Figure 5 The hooks 3 on the vertical pole 1 and the connecting rod 4 are both made of steel. The steel hooks 3 can hook the steel mesh to meet the thickness requirement of the steel mesh protective layer. After pouring concrete, the hooks 3 can also play an anchoring effect with the ground concrete, thereby strengthening the connection between concrete and steel bars and further improving the structural strength of the ground.

[0053] The working principle of a ground elevation control device in an embodiment of the present application is as follows: first, a fixed gasket 2 is placed on the upper end surface of the floor slab, and then a cement nail is passed through the fixing hole 21, and the cement nail is driven into the floor slab to fix the fixed gasket 2, and a plurality of ground elevation control devices are installed on the floor slab in sequence, and then a steel mesh is placed on the hook 3 to improve the structural strength of the concrete after pouring, and then the concrete can be poured; if the thickness of the concrete to be poured is relatively large, a connecting rod 4 can be threadedly connected to the upper end of the vertical pole 1 to increase the height of the scale, and a steel mesh can be placed on the hook 3 of the connecting rod 4 to improve the structural strength of the concrete after pouring, and then the concrete can be poured. After pouring to a specific height of the connecting rod 4, the connecting rod 4 located at the upper end of the pouring ground can be cut off, and the applicability is relatively high.

[0054] Embodiment 2: Reference Figure 6 and Figure 7 The difference between the second embodiment and the first embodiment lies in the different arrangements of the vertical rod 1 and the connecting rod 4.

[0055] Reference Figure 6 and Figure 7 A number of marking holes 5 are provided on the vertical pole 1 and the connecting rod 4. The marking holes 5 correspond to the scales. The height of the marking holes 5 is the same as the height of the corresponding scales. A number of marking holes 5 are provided on the side of the vertical pole 1 away from the hook 3. A number of marking holes 5 can be inserted with marking plates 6 adapted to the marking holes 5 for elevation identification. After determining the height to be poured, the marking plate 6 is inserted into the marking hole 5 in the opposite direction of the determined scale. When the staff is pouring, they can slowly pour by checking the distance between the concrete liquid level and the marking plate 6, thereby improving the convenience of locating the concrete height during pouring.

[0056] Embodiment three: Reference Figure 8 The difference between the third embodiment and the above embodiments is that the setting of the hook 3 is different.

[0057] Reference Figure 8 There are four hooks 3 on the vertical pole 1, which are arranged as the first hook, the second hook, the third hook and the fourth hook from top to bottom; the first hook and the third hook are both vertically slidably connected to the vertical pole 1; when placing the steel mesh, first place a number of steel bars on the fourth hook of the vertical pole 1, and then place a number of steel bars on the third hook of the vertical pole 1. At this time, the third hook is pressed and slides along the height direction of the vertical pole 1. At this time, the steel bar fits on the steel bar hung on the fourth hook, and the subsequent staff can easily tie the steel bars, thereby improving the convenience of the staff in construction.

[0058] Among them, the first hook and the third hook are slidably connected to the vertical pole 1, which is a prior art. The first hook and the third hook can be slid on the vertical pole 1, and no more details will be given in this embodiment.

[0059] In a second aspect, an embodiment of the present application discloses a construction method of a ground elevation control device.

[0060] A construction method for a ground elevation control device comprises the following steps: S1: Place the fixing gasket 2 on the floor slab, drive the mounting nails 22 through the fixing holes 21 and into the floor slab, fix the fixing gasket 2 on the floor slab, and if the concrete pouring thickness exceeds 50 mm, screw the threaded rod 41 of the connecting rod 4 into the screw hole of the vertical rod 1; S2: Repeat step S1 to install poles 1 at the four corners of the floor, and then install multiple poles 1 at equal intervals on the floor between the poles 1; S3: placing a plurality of reinforcing bars horizontally in sequence on the hook 3 of the lowest height where no reinforcing bars are currently placed; placing a plurality of reinforcing bars on the hook 3 of the second-to-last height, crossing with the previously placed reinforcing bars; S4: Repeat step S3 to complete the layout of the steel mesh.

[0061] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A ground elevation control device, comprising a pole (1), characterized in that: The lower end of the vertical pole (1) is fixedly connected to a fixing gasket (2), and a plurality of fixing holes (21) are provided on the fixing gasket (2). A mounting nail (22) is passed through the plurality of fixing holes (21) from top to bottom, and the mounting nail (22) extends to the bottom of the fixing gasket (2) and is used to fix the vertical pole (1). The outer surface of the vertical pole (1) is provided with a scale for elevation identification.

2. A ground elevation control device according to claim 1, characterized in that: A plurality of hooks (3) are arranged vertically and evenly spaced on one side of the vertical pole (1) in the length direction, comprising a horizontal pole (31) and a vertical pole (32); one end of the horizontal pole (31) away from the vertical pole (1) is fixedly connected to the vertical pole (32); the vertical pole (32) is fixedly connected to the upper end of the horizontal pole (31); and one end of the horizontal pole (31) close to the vertical pole (1) is fixedly connected to the vertical pole (1).

3. A ground elevation control device according to claim 2, characterized in that: It also comprises a connecting rod (4), which is detachably connected to the upper end of the vertical rod (1), and the outer surface of the connecting rod (4) is also provided with a scale for elevation identification.

4. A ground elevation control device according to claim 3, characterized in that: Hooks (3) are also arranged vertically and at equal intervals on one side of the connecting rod (4) in the length direction.

5. A ground elevation control device according to claim 4, characterized in that: A threaded rod (41) extends from the lower end of the connecting rod (4), and a threaded groove (11) adapted to the threaded rod (41) is formed at the upper end of the vertical rod (1).

6. A ground elevation control device according to claim 3, characterized in that: The connecting rod (4) and the vertical rod (1) are both made of plastic.

7. A ground elevation control device according to claim 3, characterized in that: The plurality of hooks (3) are all made of metal.

8. A ground elevation control device according to claim 5, characterized in that: The vertical pole (1) and the connecting rod (4) are both provided with a plurality of marking holes (5), the marking holes (5) corresponding to the scales, the height of the marking holes (5) being the same as the height of the corresponding scales, the plurality of marking holes (5) being provided on a side of the vertical pole (1) away from the hook (3), and marking plates (6) adapted to the marking holes (5) being inserted into the plurality of marking holes (5) for elevation identification.

9. A construction method for a ground elevation control device, characterized in that: The construction of a ground elevation control device as claimed in claim 5 comprises the following steps: S1: Place the fixing gasket (2) on the floor slab, pass the mounting nails (22) through the fixing holes (21) and drive them into the floor slab, fix the fixing gasket (2) on the floor slab, and if the thickness of the concrete pouring exceeds 50 mm, screw the threaded rod (41) of the connecting rod (4) into the screw hole of the vertical rod (1); S2: Repeat step S1 to install vertical poles (1) at the four corners of the floor slab, and then install multiple vertical poles (1) at equal intervals on the floor slab between the vertical poles (1); S3: placing a plurality of reinforcing bars horizontally in sequence on the hook (3) at the lowest height where no reinforcing bars are currently placed; placing a plurality of reinforcing bars on the hook (3) at the second-to-last height, crossing with the previously placed reinforcing bars; S4: Repeat step S3 to complete the layout of the steel mesh.