Integral hoisting construction method for steel grid, truss and electromechanical facilities
By adopting a deformable, sliding, and fixed trough box and conduit installation method during the grid lifting process, the problem of trough box and conduit deformation after the grid lifting is solved, the synchronous construction of mechanical and electrical engineering is achieved, the construction quality and safety are improved, and the cost is reduced.
Patent Information
- Application Number
- CN202411199364.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2025-10-21
- Estimated Expiration
- 2044-08-29
AI Technical Summary
In the prior art, mechanical and electrical engineering construction after the grid is lifted causes the trough box and the conduit to deform and cannot be effectively fixed, affecting the construction quality and safety.
The deformable sliding fixed trough box and conduit installation method is adopted. Through flexible connecting belts, sliding rail angle steels and fixing components, it is ensured that the trough box and conduit can slide freely under the load of the grid to avoid deformation, and the mechanical and electrical engineering construction can be carried out simultaneously.
The stability and ductility of the trough box and the conduit are achieved, the risk of working at height is avoided, the construction efficiency and quality are improved, and the cost is reduced.
Smart Images

Figure CN119308515B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, and in particular to a construction method for integrally lifting a steel grid, a truss, and electromechanical facilities. Background Art
[0002] After the grid and trusses are assembled, they are lifted to the designed position, and then the electrical trough boxes, conduits, cables are laid, and lamps are installed and powered on for testing. The trough boxes and conduits are fixed in the grid. In the current existing technology, the mechanical and electrical engineering work is carried out after the grid is lifted. The connections between the trough boxes and conduits are fixed without deformation. After the grid and enclosure projects are completed, the grid will deflect again under its own weight, and the trough boxes and conduits that are not fixed without deformation will also deform as the grid deflects. Summary of the Invention
[0003] In view of this, the object of the present invention is to provide a method for integrally lifting a steel grid, a truss and electromechanical facilities.
[0004] The invention provides a method for integrally lifting the steel grid, trusses, and electromechanical facilities using the following technical solutions:
[0005] A method for integrally lifting a steel grid, trusses, and electromechanical facilities comprises a truss and a grid, wherein the lowest elevation of the truss is lower than the lowest elevation of the grid. The method comprises the following steps:
[0006] S1. Set up supports on the foundation ground, assemble the steel balls and rods on the supports in sequence according to the construction drawings to form a unit grid, and simultaneously measure the arch elevation and unit size to ensure they meet the requirements of the specifications;
[0007] S2. When the grid is about to be completed and the trusses are assembled, the mechanical and electrical engineering construction begins;
[0008] S3. Since the first truss level is lower than the grid, the steel balls and rods for assembling the first truss level are pre-lifted to a certain height. The steel balls and rods are then lifted to the appropriate height to install the lamps and assemble the first truss level. The lifting system uses a hydraulic lifter and computer-controlled synchronous lifting. When the lifting reaches the designated position, the lifting power and hydraulic oil valve are turned off, and support columns are installed on the four sides of the grid.
[0009] S4. The grid, trusses of different heights and electromechanical components are hoisted as a whole. The hydraulic lifting is controlled by a computer to move back and forth. When the whole structure is hoisted to a suitable position, the enclosure structure is installed and unloaded. After all load construction is completed, the supports and independent columns are fixed. At the same time, each side of the grid is reliably connected to the grounding protection body.
[0010] Furthermore, in step S2, the electromechanical engineering construction includes the construction of a trough box module and a conduit module. The trough box module includes a trough box and a mounting bracket arranged on a grid. The mounting bracket is provided with a guide angle steel for installing the trough box. A grounding wire is provided at a position 20 to 30 meters between the trough box and the guide angle steel. Grounding wires are provided at the starting and ending ends of the guide angle steel to connect with the protective conductor.
[0011] Furthermore, a flexible connecting belt is provided between two adjacent trough boxes.
[0012] Furthermore, a slide rail angle steel is provided on the mounting bracket, a slider is provided on the side of the guide groove angle steel, and the slider is slidably provided in the slide rail angle steel.
[0013] Furthermore, a door-shaped frame is provided on the mounting bracket, and a fixing component for fixing the trough box is provided on the door-shaped frame.
[0014] Furthermore, the fixing assembly includes a lower pressure plate pressed on the top cover of the trough box, two anti-deformation plates symmetrically arranged on the lower pressure plate and a spring arranged between the two anti-deformation plates, and the top of the anti-deformation plate and the spring are arranged at the bottom of the door-type frame top rod.
[0015] Furthermore, the catheter module includes a catheter and a catheter bracket installed on a grid. A grounding wire is provided between the catheter and the catheter bracket, and the grounding wire can be extended and retracted with the catheter. The lamp is installed on the catheter bracket, and the catheter is connected to the trough box and a grounding wire is provided. The wires in the trough box are connected to the lamp through the catheter.
[0016] Furthermore, a sliding sleeve is provided on the catheter support, and the catheter passes through the sliding sleeve and can move inside the sliding sleeve.
[0017] Furthermore, the catheter support is provided with a fixing pipe clamp for fixing the catheter.
[0018] Furthermore, a hose is provided at the end of the conduit away from the trough box, the hose is connected to the lamp, and the wires in the trough box are connected to the lamp through the conduit and the hose.
[0019] In summary, the present invention has at least one of the following beneficial effects: the electromechanical work is completed synchronously when the grid is assembled, the trough box and the conduit are installed in a deformable sliding and fixed manner, the trough box and the conduit can slide freely and will not loosen when the grid is wound under load, and has reliable stability and ductility. The lamps are installed and powered on for acceptance when the grid and truss are assembled, and the electromechanical quality can be effectively guaranteed; thereby avoiding the safety risks brought by working at heights, while improving work efficiency and saving construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1Schematic diagram of the structure of the connection between the grid and trusses at different elevations according to the embodiment of the present invention Figure 1 ;
[0021] Figure 2 Schematic diagram of the structure of the connection between the grid and trusses at different elevations according to the embodiment of the present invention Figure 2 ;
[0022] Figure 3 Schematic diagram of the structure of the connection between the grid and trusses at different elevations according to the embodiment of the present invention Figure 3 ;
[0023] Figure 4 This is a schematic diagram of the structure of the connection between the trough boxes according to an embodiment of the present invention;
[0024] Figure 5 This is a structural diagram of the trough box installation according to an embodiment of the present invention;
[0025] Figure 6 This is a schematic structural diagram of a fixing assembly according to an embodiment of the present invention;
[0026] Figure 7 This is a schematic diagram of the structure of the catheter module installation according to an embodiment of the present invention;
[0027] Figure 8 This is a schematic diagram of the structure of the catheter installation according to an embodiment of the present invention;
[0028] Figure 9 This is a cross-sectional schematic diagram of the installation of a catheter according to an embodiment of the present invention.
[0029] Description of reference numerals:
[0030] 1. Truss; 2. Grid; 3. Support; 4. Independent column; 5. Lamp; 6. Support column; 7. Trough box module; 71. Trough box; 72. Mounting bracket; 73. Guide angle steel; 74. Slide rail angle steel; 75. Slider; 76. Door frame; 77. Fixing assembly; 771. Lower pressure plate; 772. Anti-deformation plate; 773. Spring; 78. Connecting belt; 8. Conduit module; 81. Conduit; 82. Conduit bracket; 83. Sliding sleeve; 84. Hose; 85. Fixing pipe clamp. DETAILED DESCRIPTION
[0031] The following describes the embodiments of the present invention through specific examples. Those skilled in the art will readily understand the other advantages and benefits of the present invention from the disclosure herein. The present invention may also be implemented or applied through various other specific embodiments, and the details in this specification may be modified or altered based on different viewpoints and applications without departing from the spirit of the present invention.
[0032] The following is combined with Figure 1-9 The present invention is described in further detail.
[0033] The embodiment of the present invention discloses a method for integrally lifting a steel grid, a truss and electromechanical facilities. Figures 1-9 The overall lifting construction method of the steel grid, truss and electromechanical facilities includes truss 1 and grid 2, wherein the lowest level of truss 1 is lower than the lowest level of grid 2. The construction method adopts the following steps:
[0034] Step 1: Set up the support 3 on the foundation ground, assemble the steel balls and rods on the support 3 in sequence according to the construction drawings to form a unit grid, and simultaneously measure the arch elevation and unit size to ensure they meet the requirements of the specifications;
[0035] Step 2: When the grid 2 is about to be completed and assembled with the truss 1, start the mechanical and electrical engineering construction;
[0036] Step 3: Since the elevation of the first layer of truss 1 is lower than that of grid 2, the steel balls and rods for assembling the first layer of truss 1 are pre-lifted to a certain height, and then the lamps 5 and the steel balls and rods for assembling the first layer of truss 1 are installed and lifted to a suitable height. The lifting system uses a hydraulic lifter and computer-controlled synchronous lifting. When it reaches the designated position, the lifting power supply and hydraulic oil valve are turned off, and support columns 6 are set on the four sides of grid 2. The lamps 5 are connected to the wiring of the control box and then powered on for acceptance.
[0037] Step 4: The grid 2, trusses 1 of different heights and electromechanical components are lifted as a whole. The computer controls the hydraulic lifting process to move back and forth. When the whole structure is lifted to the appropriate position, the enclosure structure is installed and unloaded. After all load construction is completed, the support 3 and the independent column 4 are fixed. At the same time, each side of the grid 2 is reliably connected to the grounding protection body.
[0038] In this embodiment, the electromechanical engineering construction in step S2 includes the construction of a trough box module 7 and a conduit module 8. The trough box module 7 includes a trough box 71 and a mounting bracket 72 arranged on the grid 2. The mounting bracket 72 is provided with a guide angle steel 73 for installing the trough box 71. Grounding wires are set at the 20~30m position of the trough box 71 and the guide angle steel 73. Grounding wires are set at the starting and ending ends of the guide angle steel 73 to connect with the protective conductor.
[0039] In this embodiment, a flexible connecting belt 78 is provided between two adjacent trough boxes 71 to provide a buffer when the two adjacent trough boxes 71 move.
[0040] In this embodiment, a slide rail angle steel 74 is provided on the mounting bracket 72, and a slider 75 is provided on the side of the guide groove angle steel 73. The slider 75 is slidably set in the slide rail angle steel 74. When the grid 2 deflects downward, the slot box 71 can move inside the slide rail angle steel 74 along with the guide groove angle steel 73.
[0041] In this embodiment, a door-shaped frame 76 is further provided on the mounting bracket 72 , and a fixing assembly 77 for fixing the trough box 71 is provided on the door-shaped frame 76 .
[0042] In this embodiment, the fixing assembly 77 includes a lower pressure plate 771 pressed on the top cover of the trough box 71, two anti-deformation plates 772 symmetrically arranged on the lower pressure plate 771, and a spring 773 arranged between the two anti-deformation plates 772. The top of the anti-deformation plate 772 and the spring 773 are arranged at the bottom of the top rod of the door-shaped frame 76, so that the cover of the trough box 71 is in a compressed state at any time.
[0043] In this embodiment, the catheter module 8 includes a catheter 81 and a catheter bracket 82 installed on the grid 2. A grounding wire is set at the position of the catheter 81 and the catheter bracket 82. The grounding wire can be extended and retracted with the catheter 81. The lamp 5 is installed on the catheter bracket 82. The catheter 81 is connected to the trough box 71 and a grounding wire is set. The wires in the trough box 71 are connected to the lamp 5 through the catheter 81.
[0044] In this embodiment, a sliding sleeve 83 is provided on the catheter support 82 , and the catheter 81 passes through the sliding sleeve 83 and can move inside the sliding sleeve 83 .
[0045] In this embodiment, a fixing pipe clamp 85 for fixing the pipe 81 is provided on the pipe bracket 82 .
[0046] In this embodiment, a hose 84 is provided at the end of the conduit 81 away from the trough box 71 . The hose 84 is connected to the lamp 5 . The wires in the trough box 71 are connected to the lamp 5 through the conduit 81 and the hose 84 .
[0047] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and are not limiting. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the purpose and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.
Claims
1. A method for integrally lifting a steel grid, trusses, and electromechanical facilities, characterized by: It comprises a truss (1) and a grid (2), wherein the lowest level of the truss (1) is lower than the lowest level of the grid (2), and the construction method adopts the following steps: S1. Set a support (3) on the foundation ground, assemble the steel balls and rods on the support (3) in sequence according to the construction drawings to form a unit grid, and simultaneously measure the arch elevation and unit size to ensure they meet the requirements of the specification; S2, when the grid (2) is about to be completed and the truss (1) is assembled, the mechanical and electrical engineering construction begins; S3. Since the elevation of the first layer of the truss (1) is lower than that of the grid (2), the steel balls and rods of the first layer of the truss (1) are pre-lifted to a certain height, and then the lamps (5) and the steel balls and rods of the first layer of the truss (1) are installed and lifted to a suitable height. The lifting system adopts a hydraulic lifter and computer-controlled synchronous lifting. When the lifting power and hydraulic oil valve are turned off, support columns (6) are set on the four sides of the grid (2); S4, the grid (2) and the trusses (1) of different heights and the electromechanical system are hoisted as a whole, and the hydraulic lifting is controlled by a computer to move back and forth. When the whole is hoisted to a suitable position, the enclosure structure is installed and unloaded. After all the load construction is completed, the support (3) and the independent column (4) are fixed, and at the same time, each side of the grid (2) is reliably connected to the ground protection body; In step S2, the electromechanical engineering construction includes the construction of a trough box module (7) and a conduit module (8), wherein the trough box module (7) includes a trough box (71) and a mounting bracket (72) arranged on the grid (2), wherein the mounting bracket (72) is provided with a guide angle steel (73) for mounting the trough box (71), and a grounding wire is provided at a position 20 to 30 m between the trough box (71) and the guide angle steel (73), and the starting and ending ends of the guide angle steel (73) are both provided with grounding wires connected to a protective conductor; A flexible connecting belt (78) is provided between two adjacent trough boxes (71); The mounting bracket (72) is provided with a slide rail angle steel (74), and the side of the guide groove angle steel (73) is provided with a slider (75), and the slider (75) is slidably provided in the slide rail angle steel (74); A door-shaped frame (76) is also provided on the mounting bracket (72), and a fixing assembly (77) for fixing the trough box (71) is provided on the door-shaped frame (76).
2. The method for integrally lifting steel grids, trusses, and electromechanical facilities according to claim 1 is characterized in that: The fixing assembly (77) includes a lower pressure plate (771) pressed on the top cover of the trough box (71), two anti-deformation plates (772) symmetrically arranged on the lower pressure plate (771), and a spring (773) arranged between the two anti-deformation plates (772), and the top of the anti-deformation plate (772) and the spring (773) are arranged at the bottom of the top rod of the door frame (76).
3. The method for integrally lifting the steel grid, trusses, and electromechanical facilities according to claim 1 is characterized in that: The conduit module (8) comprises a conduit (81) and a conduit bracket (82) mounted on the grid (2); a grounding wire is provided between the conduit (81) and the conduit bracket (82); the grounding wire can be extended or retracted along with the conduit (81); the lamp (5) is mounted on the conduit bracket (82); the conduit (81) is connected to the trough box (71) and a grounding wire is provided; and the electric wires in the trough box (71) are connected to the lamp (5) via the conduit (81).
4. The method for integrally lifting the steel grid, trusses, and electromechanical facilities according to claim 3 is characterized by: A sliding sleeve (83) is provided on the catheter support (82), and the catheter (81) passes through the sliding sleeve (83) and is movable within the sliding sleeve (83).
5. The method for integrally lifting the steel grid, trusses, and electromechanical facilities according to claim 4 is characterized in that: The catheter support (82) is provided with a fixing pipe clamp (85) for fixing the catheter (81).
6. The method for integrally lifting steel grids, trusses, and electromechanical facilities according to claim 3 is characterized by: A hose (84) is provided at the end of the conduit (81) away from the trough box (71), and the hose (84) is connected to the lamp (5). The wires in the trough box (71) are connected to the lamp (5) through the conduit (81) and the hose (84).
Citation Information
Patent Citations
Roof grid elevating method
CN105064697A
Hydraulic pressure lifting integral installation method for integrated electromechanical system in steel structure space truss roof
CN107165420A