Pipe body butt joint structure and pipe body butt joint method
By setting up operating parts and connecting pipes in the steel pipe docking structure, the problem of insufficient axial space during steel pipe docking is solved, an efficient docking process is achieved, and construction efficiency and stability are improved.
Patent Information
- Application Number
- CN202411625654.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-14
- Publication Date
- 2025-01-17
AI Technical Summary
During the steel pipe docking process, there is no moving space on the axial outward side of the steel pipes on both sides, making it difficult to achieve docking and low construction efficiency.
Design a pipe body docking structure, by providing an operating member and a connecting pipe on the pipe wall of the first pipe body, the connecting pipe can move without occupying axial space, so as to realize the first pipe body and the second pipe body docking. The operating member is movably arranged in the mounting hole, one end of the connecting pipe is located in the first tube body, the other end can be extended and inserted into the second tube body, and is connected by welding or magnetic suction to achieve stable docking.
When there is no moving space in the axial direction of the first pipe body and the second pipe body, the movement of the connecting pipe is realized through the operating parts, which improves the construction efficiency of steel pipe docking, and ensures the stability of docking and the convenience of construction.
Smart Images

Figure CN119321506A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of pipe body docking, and in particular to a pipe body docking structure and a pipe body docking method. Background Art
[0002] At present, the problem of steel pipe docking is often encountered in engineering projects. However, when there is no movable space on the axial outer sides of the steel pipes on both sides, it is difficult to achieve docking of the steel pipes on both sides, the construction efficiency is low, and there is room for improvement. Summary of the invention
[0003] The present application aims to solve at least one of the technical problems existing in the prior art. To this end, the present application proposes a pipe body docking structure, which can realize the movement of the connecting pipe through an operating member when there is no movable space in the axial direction of the first pipe body and the second pipe body, thereby realizing the docking of the first pipe body and the second pipe body, thereby facilitating improving construction efficiency.
[0004] According to the tube body docking structure of the embodiment of the present application, it includes: a first tube body, having a first docking end; a second tube body, having a second docking end, the second docking end is used to be arranged opposite to the first docking end; a connecting tube, which can be movably arranged in the first tube body, one end of the connecting tube is located in the first tube body, and the other end is suitable for extending out of the first tube body and being used to be inserted into the second tube body; an operating member, which is connected to the connecting tube, the operating member is movably penetrated through the tube wall of the first tube body, and the operating member is suitable for moving along the extension direction of the first tube body.
[0005] According to the pipe body docking structure of the embodiment of the present application, the operating member can be movably arranged on the pipe wall of the first pipe body and connected to the connecting pipe, so that the arrangement of the operating member does not need to occupy the axial space between the first pipe body and the second pipe body. In this way, even if there is no movable space in the axial direction of the first pipe body and the second pipe body, the movement of the connecting pipe can be achieved through the operating member, and then the docking of the first pipe body and the second pipe body can be achieved, which is beneficial to improve construction efficiency.
[0006] According to the tube body docking structure of some embodiments of the present application, a mounting hole is opened on the tube wall of the first tube body, the operating member is movably inserted into the mounting hole, and the mounting hole is arranged close to the first docking end.
[0007] According to the tube body docking structure of some embodiments of the present application, in the extension direction of the first tube body, the minimum length of the mounting hole is greater than the minimum distance between the first docking end and the mounting hole.
[0008] According to the pipe body docking structure of some embodiments of the present application, the wall thickness of the portion of the connecting pipe opposite the mounting hole is greater than or equal to the wall thickness of the first pipe body.
[0009] According to the tube body docking structure of some embodiments of the present application, an end of the operating member away from the connecting tube protrudes from the outer peripheral wall of the first tube body.
[0010] According to the pipe body docking structure of some embodiments of the present application, the outer diameter of the connecting pipe is smaller than the inner diameter of the first pipe body.
[0011] According to the pipe body docking structure of some embodiments of the present application, the operating member is connected to the connecting pipe by welding.
[0012] According to the pipe body docking structure of some embodiments of the present application, the operating member is magnetically connected to the connecting pipe.
[0013] The present application also proposes a pipe body docking method.
[0014] According to the tube body docking method of the embodiment of the present application, which is used for the tube body docking structure described in any of the above embodiments, the tube body docking method includes: installing the connecting tube in the first tube body; arranging the first docking end and the second docking end relative to each other; moving the connecting tube so that one end of the connecting tube extends out of the first tube body until the connecting tube is plugged into the second tube body.
[0015] According to some embodiments of the present application, the pipe body docking method also includes: welding the connecting pipe to the first pipe body when the connecting pipe is inserted into the second pipe body; moving the first pipe body or the second pipe body until the distance between the first docking end and the second docking end is a preset distance; and welding the first docking end to the second docking end when the distance between the first docking end and the second docking end is a preset distance.
[0016] The advantages of the pipe body docking method and the above-mentioned pipe body docking structure over the prior art are the same, and will not be described in detail here.
[0017] Additional aspects and advantages of the present application will be given in part in the following description, and in part will become obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0019] Figure 1 A schematic diagram of a pipe body docking structure according to an embodiment of the present application;
[0020] Figure 2 A schematic diagram of a pipe body docking structure of an embodiment of the present application with an operating member removed;
[0021] Figure 3 A schematic diagram of a first tube according to an embodiment of the present application;
[0022] Figure 4 It is an assembly diagram of the first pipe body, the connecting pipe and the operating member of the embodiment of the present application;
[0023] Figure 5 The process of the pipe body docking method of the embodiment of the present application is as follows Figure 1 ;
[0024] Figure 6 The process of the pipe body docking method of the embodiment of the present application is as follows Figure 2 .
[0025] Reference numerals:
[0026] Pipe body docking structure 10;
[0027] The first tube body 1; the first butt end 11; the mounting hole 12; the second tube body 2; the second butt end 21; the connecting tube 3; and the operating member 4. DETAILED DESCRIPTION
[0028] In order to better understand the technical solutions provided by the embodiments of this specification, the technical solutions of the embodiments of this specification are described in detail below through the accompanying drawings and specific embodiments. It should be understood that the embodiments of this specification and the specific features in the embodiments are detailed descriptions of the technical solutions of the embodiments of this specification, rather than limitations on the technical solutions of this specification. In the absence of conflict, the embodiments of this specification and the technical features in the embodiments can be combined with each other.
[0029] In this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that there is any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that the process, method, article or equipment including a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, method, article or equipment. In the absence of more restrictions, the elements limited by the statement "comprise one..." do not exclude the existence of other identical elements in the process, method, article or equipment including the elements. The term "more than two" includes two or more than two situations.
[0030] Please refer to the following Figure 1-6 The pipe body docking structure 10 according to the embodiment of the present application is described.
[0031] like Figure 1As shown, the pipe body docking structure 10 according to the embodiment of the present application includes: a first pipe body 1, a second pipe body 2, a connecting pipe 3 and an operating member 4.
[0032] like Figure 1 As shown, the first tube body 1 has a first butt end 11, the second tube body 2 has a second butt end 21, the second butt end 21 is used to be arranged opposite to the first butt end 11, the connecting tube 3 is movably arranged on the first tube body 1, one end of the connecting tube 3 is located in the first tube body 1, and the other end is suitable for extending out of the first tube body 1 and being used for being inserted into the second tube body 2, the operating member 4 is connected to the connecting tube 3, the operating member 4 is movably penetrated through the tube wall of the first tube body 1, and the operating member 4 is suitable for moving along the extension direction of the first tube body 1.
[0033] Therefore, even when there is no movable space in the axial direction of the first tube body 1 and the second tube body 2, the movement of the connecting tube 3 can be achieved through the operating member 4, thereby achieving the docking of the first tube body 1 and the second tube body 2, which is beneficial to improving the construction efficiency.
[0034] It is understandable that at least one of the first tube body 1 and the second tube body 2 can be a steel tube, a plastic tube or a tube made of other materials, and the material of the connecting tube 3 can be the same as that of the first tube body 1, or the material of the connecting tube 3 can be different from that of the first tube body 1, which is not limited here.
[0035] For example, the first tube body 1 and the second tube body 2 are both steel tubes, and the connecting tube 3 is also a steel tube. The steel tube can be a round steel tube or a rectangular steel tube, wherein the inner diameters of the first tube body 1 and the second tube body 2 are the same, the inner diameter of the connecting tube 3 is smaller than the inner diameter of the first tube body 1, and the outer peripheral wall of the connecting tube 3 is suitable for fitting and connecting with the inner wall of the first tube body 1 and / or the second tube body 2, so that the inner wall of the first tube body 1 and / or the second tube body 2 can play a certain guiding role in the movement of the connecting tube 3.
[0036] The operating member 4 may include a handle or a push rod, etc. The operating member 4 may be movably disposed through the tube wall of the first tube body 1 and connected to the connecting tube 3, and the operating member 4 is suitable for moving along the extension direction of the first tube body 1, so that the operating member 4 can drive the connecting tube 3 to move synchronously along the extension direction of the first tube body 1.
[0037] Among them, it can be understood that, since the operating member 4 can be movably penetrated through the tube wall of the first tube body 1 and is connected to the connecting tube 3, the operating member 4 is actually located on the radial outside of the connecting tube 3. In this way, the setting of the operating member 4 will not occupy the axial space of the first tube body 1 and the second tube body 2. In this way, even if there is no axial space for movement between the first tube body 1 and the second tube body 2, the movement of the connecting tube 3 can be achieved through the operating member 4, thereby achieving the docking of the first tube body 1 and the second tube body 2.
[0038] For example, in some usage scenarios, the second docking end 21 is arranged opposite to the first docking end 11, for example, the second docking end 21 is arranged opposite to the first docking end 11, or the second docking end 21 is arranged opposite to the first docking end 11 at a certain angle. At this time, the operating member 4 can be controlled to drive the connecting tube 3 to move synchronously along the extension direction of the first tube body 1, so that the other end of the connecting tube 3 extends out of the first tube body 1 and is inserted into the second tube body 2, thereby realizing the docking of the first tube body 1 and the second tube body 2. After the first tube body 1 and the second tube body 2 are docked, the connecting tube 3 can be welded to the first tube body 1, and the first tube body 1 and the second tube body 2 can be welded to ensure the docking stability of the first tube body 1 and the second tube body 2.
[0039] Therefore, when there is no movable space in the axial direction of the first tube body 1 and the second tube body 2 , the movement of the connecting tube 3 can be achieved through the operating member 4 , thereby achieving the docking of the first tube body 1 and the second tube body 2 .
[0040] The connection between the operating member 4 and the connecting pipe 3 may be a fixed connection, a detachable connection or a dynamic connection, which is not limited here.
[0041] According to the pipe body docking structure 10 of the embodiment of the present application, the operating member 4 can be movably arranged on the pipe wall of the first pipe body 1 and connected to the connecting pipe 3, so that the arrangement of the operating member 4 does not need to occupy the axial space between the first pipe body 1 and the second pipe body 2. In this way, even if there is no movable space in the axial direction of the first pipe body 1 and the second pipe body 2, the movement of the connecting pipe 3 can be achieved through the operating member 4, and then the docking of the first pipe body 1 and the second pipe body 2 can be achieved, which is beneficial to improve the construction efficiency.
[0042] In some embodiments, Figure 2 and Figure 3 As shown, the wall of the first tube body 1 is provided with a mounting hole 12, and as shown in FIG. Figure 4 As shown, the operating member 4 is movably disposed in the mounting hole 12 , and the mounting hole 12 is arranged close to the first docking end 11 .
[0043] Thus, the interference between the tube wall of the first tube body 1 and the operating member 4 can be avoided, so as to facilitate the design that the operating member 4 can be movably arranged on the tube wall of the first tube body 1 and connected to the connecting tube 3. At the same time, the mounting hole 12 is arranged close to the first docking end 11, so as to reduce the movement stroke of the operating member 4, thereby reducing the difficulty of operation. In particular, after the first tube body 1 and the second tube body 2 are docked, the connecting tube 3 and the first tube body 1 can be welded at the mounting hole 12, thereby reducing the difficulty of welding the connecting tube 3 and the first tube body 1.
[0044] In some embodiments, Figure 1As shown, in the extension direction of the first tube body 1 , the minimum length of the mounting hole 12 is greater than the minimum distance between the first butt end 11 and the mounting hole 12 .
[0045] For example Figure 1 As shown, the minimum length of the mounting hole 12 is L1, the minimum distance between the first butt end 11 and the mounting hole 12 is L2, and L1 is greater than L2.
[0046] Thus, when the operating member 4 moves in the mounting hole 12 along the extension direction of the first tube body 1, the maximum stroke of the operating member 4 is greater than the minimum distance between the first docking end 11 and the mounting hole 12, so that when the operating member 4 moves to the position closest to the first docking end 11, the other end of the connecting tube 3 can definitely extend out of the first docking end 11, thereby facilitating the other end of the connecting tube 3 to extend out of the first tube body 1 and be inserted into the second tube body 2, thereby achieving docking between the first tube body 1 and the second tube body 2.
[0047] In some embodiments, in the extension direction of the first tube body 1 , the length of the connecting tube 3 is greater than the sum of the maximum distance from the mounting hole 12 to the first docking end 11 and the length of the mounting hole 12 .
[0048] For example, in this way, when the operating member 4 moves to the position closest to the first docking end 11, the other end of the connecting tube 3 can definitely extend out of the first docking end 11, thereby facilitating the other end of the connecting tube 3 to extend out of the first tube body 1 and be inserted into the second tube body 2, thereby achieving the docking of the first tube body 1 and the second tube body 2.
[0049] At the same time, it can ensure that when the operating member 4 moves to the position closest to the first docking end 11, the installation hole 12 is still partially blocked by the wall of the connecting pipe 3 to avoid leakage of the first tube body 1 at the installation hole 12.
[0050] In some embodiments, the wall thickness of the portion of the connecting tube 3 opposite to the mounting hole 12 is greater than or equal to the wall thickness of the first tube body 1 .
[0051] Therefore, when the first tube body 1 and the second tube body 2 are connected via the connecting tube 3 and the tube wall of the connecting tube 3 blocks the mounting hole 12, the effective cross-section of the portion of the connecting tube 3 opposite to the mounting hole 12 is not less than the effective cross-section of the first tube body 1, thereby balancing the stress and avoiding the problem of stress concentration at the portion of the connecting tube 3 opposite to the mounting hole 12.
[0052] In some embodiments, one end of the operating member 4 away from the connecting tube 3 protrudes from the outer peripheral wall of the first tube body 1 .
[0053] Therefore, it is convenient for the operator to operate the operating member 4 outside the outer peripheral wall of the first tube body 1 , so as to reduce the difficulty of operating the operating member 4 .
[0054] In some embodiments, the outer diameter of the connecting tube 3 is smaller than the inner diameter of the first tube body 1. For example, the difference between the inner diameter of the first tube body 1 and the outer diameter of the connecting tube 3 is greater than or equal to 1 mm and less than or equal to 5 mm. This makes it easier to assemble the connecting tube 3 and the first tube body 1.
[0055] In some embodiments, the inner diameter of the connecting tube 3 is slightly smaller than the inner diameter of the first tube body 1 and / or the second tube body 2. In this way, after the first tube body 1 and the second tube body 2 are docked, the occupation of the internal space of the first tube body 1 and / or the second tube body 2 by the connecting tube 3 can be reduced.
[0056] In some embodiments, the operating member 4 is connected to the connecting pipe 3 by welding, thereby facilitating the connection strength between the operating member 4 and the connecting pipe 3, thereby enhancing the connection stability between the two.
[0057] In other embodiments, the operating member 4 is connected to the connecting tube 3 by magnetic attraction. This facilitates the connection stability between the operating member 4 and the connecting tube 3 and facilitates the assembly and disassembly of the operating member 4. Of course, in other embodiments, the connection between the operating member 4 and the connecting tube 3 may be by snap-on, plug-in or other connection methods, which are not limited here.
[0058] like Figure 5 As shown, the present application also proposes a pipe body docking method.
[0059] The pipe body docking method according to an embodiment of the present application is used for the pipe body docking structure 10 of any one of the above embodiments.
[0060] Please refer to Figure 5 , pipe body docking methods include:
[0061] S10: Install the connecting tube 3 in the first tube body 1. That is, insert the connecting tube 3 from the first butt end 11 into the first tube body 1 to facilitate the subsequent movement of the connecting tube 3.
[0062] S20: The first butt end 11 and the second butt end 21 are arranged opposite to each other. For example, the second butt end 21 and the first butt end 11 are arranged opposite to each other, or the second butt end 21 and the first butt end 11 are arranged opposite to each other at a certain angle, so that the first tube body 1 and the second tube body 2 can be initially positioned.
[0063] S30: Move the connecting tube 3 so that one end of the connecting tube 3 extends out of the first tube body 1 until the connecting tube 3 is plugged into the second tube body 2. In this way, the first tube body 1 and the second tube body 2 can be docked.
[0064] In some embodiments, please refer to Figure 6 The pipe body docking method also includes:
[0065] S40: When the connecting pipe 3 is inserted into the second pipe body 2, the connecting pipe 3 is welded to the first pipe body 1. In this way, the connecting pipe 3 and the first pipe body 1 can be relatively fixed, thereby preventing the connecting pipe 3 from malfunctioning and affecting subsequent operations.
[0066] S50: Move the first tube body 1 or the second tube body 2 until the distance between the first butt end 11 and the second butt end 21 is a preset distance. For example, the first tube body 1 may be moved toward the direction close to the second tube body 2 so that the distance between the first butt end 11 and the second butt end 21 is a preset distance, so as to facilitate subsequent welding of the first tube body 1 and the second tube body 2.
[0067] Alternatively, the second tube body 2 can be moved in a direction close to the first tube body 1 so that the distance between the first butt end 11 and the second butt end 21 is a preset distance, so as to facilitate the subsequent welding of the first tube body 1 and the second tube body 2; or, the first tube body 1 and the second tube body 2 can be moved at the same time so that the first tube body 1 and the second tube body 2 are relatively close, and the distance between the first butt end 11 and the second butt end 21 is a preset distance, so as to facilitate the subsequent welding of the first tube body 1 and the second tube body 2.
[0068] S60: When the distance between the first butt end 11 and the second butt end 21 is a preset distance, the first butt end 11 and the second butt end 21 are welded.
[0069] For example, the preset distance is 5 mm-15 mm, which indicates that the distance between the first butt end 11 and the second butt end 21 is relatively close, so as to facilitate welding of the first butt end 11 and the second butt end 21 and reduce the difficulty of welding the first butt end 11 and the second butt end 21 .
[0070] In some usage scenarios, when the above-mentioned pipe body docking method is used to dock the pipe body docking structure 10, the specific docking method is as follows:
[0071] 1) A mounting hole 12 is partially opened on the wall of the first tube body 1 near the first butt end 11, the height of the mounting hole 12 is slightly larger than the size of the operating member 4, and the length of the mounting hole 12 is larger than the minimum distance between the mounting hole 12 and the first butt end 11;
[0072] 2) Insert the connecting tube 3 into the first tube body 1 from the first butt end 11;
[0073] 3) The operating member 4 is welded in the area corresponding to the connecting pipe 3 and the mounting hole 12. The operating member 4 should be welded along the mounting hole 12 in the radial direction of the first tube body 1 to facilitate holding and reduce the space occupied in the axial direction of the connecting pipe 3. The operating member 4 is located on the side of the area corresponding to the connecting pipe 3 and the mounting hole 12 away from the first butt end 11;
[0074] 4) Place the second tube body 2 at the designated position and align the second docking end 21 with the first docking end 11. Push the connecting tube 3 into the second tube body 2 through the operating member 4, align the first docking end 11 with the second docking end 21, and leave a gap of 5 mm to 15 mm between the first docking end 11 and the second docking end 21.
[0075] 5) The first butt joint end 11 and the second butt joint end 21 are butt-jointed by welding the first tube body 1 and the second tube body 2.
[0076] 6) After the first tube body 1 and the second tube body 2 are butt-jointed, the operating member 4 is statically cut off, and the first tube body 1 and the connecting tube 3 are welded.
[0077] Of course, in the above-mentioned specific docking method, the operation sequence is only used for illustration and does not necessarily limit the operation sequence. In some other usage scenarios, the operation sequence may be adjusted as needed.
[0078] It should be noted that in the above embodiments, the description of each embodiment has its own emphasis, and for parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0079] The above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
[0080] Although the preferred embodiments of this specification have been described, those skilled in the art may make additional changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of this specification.
[0081] Obviously, those skilled in the art can make various changes and modifications to this specification without departing from the spirit and scope of this specification. Thus, if these modifications and variations of this specification fall within the scope of the claims of this specification and their equivalents, this specification is also intended to include these modifications and variations.
Claims
1. A pipe body butt joint structure (10), characterized in that: include: A first tube body (1) having a first butt end (11); The second tube body (2) has a second butt joint end (21), and the second butt joint end (21) is used to be arranged opposite to the first butt joint end (11); A connecting tube (3) is movably arranged on the first tube body (1), one end of the connecting tube (3) is located in the first tube body (1), and the other end is suitable for extending out of the first tube body (1) and being inserted into the second tube body (2); An operating member (4) is connected to the connecting tube (3); the operating member (4) is movably arranged through the tube wall of the first tube body (1); and the operating member (4) is suitable for moving along the extension direction of the first tube body (1).
2. The pipe body docking structure (10) according to claim 1, characterized in that: The wall of the first tube body (1) is provided with a mounting hole (12), the operating member (4) is movably inserted into the mounting hole (12), and the mounting hole (12) is arranged close to the first docking end (11).
3. The pipe body docking structure (10) according to claim 2, characterized in that: In the extension direction of the first tube body (1), the minimum length of the mounting hole (12) is greater than the minimum distance between the first butt end (11) and the mounting hole (12).
4. The pipe body docking structure (10) according to claim 2, characterized in that: The wall thickness of the portion of the connecting pipe (3) opposite to the mounting hole (12) is greater than or equal to the wall thickness of the first pipe body (1).
5. The pipe body docking structure (10) according to claim 2, characterized in that: One end of the operating member (4) away from the connecting tube (3) protrudes from the outer peripheral wall of the first tube body (1).
6. The pipe body docking structure (10) according to claim 1, characterized in that: The outer diameter of the connecting pipe (3) is smaller than the inner diameter of the first pipe body (1).
7. The pipe body docking structure (10) according to any one of claims 1 to 6, characterized in that: The operating member (4) is connected to the connecting pipe (3) by welding.
8. The pipe body docking structure (10) according to any one of claims 1 to 6, characterized in that: The operating member (4) is magnetically connected to the connecting pipe (3).
9. A pipe body butt joint method, used for the pipe body butt joint structure (10) according to any one of claims 1 to 8, characterized in that: The pipe body docking method comprises: Installing the connecting pipe (3) in the first pipe body (1); The first butt joint end (11) and the second butt joint end (21) are arranged opposite to each other; The connecting tube (3) is moved so that one end of the connecting tube (3) extends out of the first tube body (1) until the connecting tube (3) is plugged into the second tube body (2).
10. The pipe body docking method according to claim 9, characterized in that: Also includes: When the connecting pipe (3) is inserted into the second pipe body (2), the connecting pipe (3) and the first pipe body (1) are welded; Moving the first tube body (1) or the second tube body (2) until the distance between the first butt end (11) and the second butt end (21) reaches a preset distance; When the distance between the first butt joint end (11) and the second butt joint end (21) is a preset distance, the first butt joint end (11) and the second butt joint end (21) are welded.