Wind power construction foundation mold capable of enhancing sealing performance, improving supporting performance and being convenient to mount and dismount

By using the design of multi -seal seams and blocking boards in the basic mold of wind power, the problem of leakage and deformation of existing molds during construction has been solved, and higher sealing performance and convenient installation and disassembly are achieved, ensuring the foundation of the foundation, and ensuring the foundation. The quality and stability of construction.

CN119332684AInactive Publication Date: 2025-01-21HENAN SECOND ELECTRIC POWER CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411742994.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-29
Publication Date
2025-01-21
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During construction, the joints of existing wind power foundation molds are linear and prone to leakage. They are easily deformed by concrete casting pressure, affecting the quality of the foundation, and inconvenient installation and disassembly.

Method used

Adopt multiple seams of seams composed of two plug -in (insert) blocking grooves and two inserted (inserted) storage grooves, combined with the cooperation of the blocking board and the storage slot The dual fixation of bolts and second bolts enhance the stability of the mold.

Benefits of technology

It greatly improves the sealing performance of the template seams, simplifies the installation and disassembly process, enhances the stability of the mold, and ensures the quality of infrastructure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119332684A_ABST
    Figure CN119332684A_ABST
Patent Text Reader

Abstract

In order to enhance sealing, improve supporting performance and facilitate mounting and dismounting of the wind power construction foundation mold, the technical problems that leakage is prone to occurring in the existing construction process, mold deformation is prone to occurring, and mounting and dismounting are inconvenient are solved, the wind power construction foundation mold comprises an inner mold section and an outer mold section, one end of a mold plate is connected with an insertion section, and the other end of the mold plate is connected with an insertion connection section; the insertion section is matched with the insertion section; the insertion section and the insertion section are sleeved with sealing gaskets; a first reinforcing hole is formed in the insertion section, a second reinforcing hole is formed in the insertion section, and a reinforcing plate is inserted into the first reinforcing hole and the second reinforcing hole; an original single linear seam is changed into multiple multi-sealing seams composed of the two insertion blocking grooves and the two insertion containing grooves, a possible slurry flowing path is changed, the sealing performance of the formwork seams is greatly improved, meanwhile, the sealing performance is improved, and meanwhile the sealing performance of the formwork seams is improved. And mounting and dismounting can be conveniently and rapidly achieved through cooperation of the blocking plate and the multiple insertion containing grooves, and only insertion and butt joint are needed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of wind power construction, in particular to a wind power construction foundation mould which has enhanced sealing, improved supporting performance and is portable for installation and disassembly. Background Art

[0002] Wind power foundation mold is an important part of wind power equipment construction. Its quality, mold structure and construction method directly affect the performance and service life of wind power equipment. Wind power foundation mold is a mold used to make wind power base template. It has the advantages of easy use, short production cycle and low cost.

[0003] Wind power foundations are mostly cast-in-place reinforced concrete foundations, such as Figure 1 The figure shows the shape of the existing wind power foundation, which is a pedestal type. The foundation is mainly composed of a mold and poured reinforced concrete. The entire foundation consists of two parts: a base plate and a column. The base plate is circular, and the outer circumference of the base plate and the column needs to be fixed with a foundation mold for concrete pouring.

[0004] The original mold structure is relatively simple, with a smooth circumferential surface on the inside and hollow reinforcement ribs on the outside. It is fixed with a manual hoist and a wire rope outer hoop.

[0005] During mold construction, the mold joints must be tight, but the existing molds are aligned when spliced, and there is a straight joint between the two. This joint is only handled by affixing double-sided tape, but a large amount of concrete slurry is poured into the mold, which can easily cause the concrete slurry to break through the double-sided tape or leak from the gaps. Especially for the mold at the bottom plate, since the bottom plate and the column are pedestal-type, the poured concrete has an impact to automatically flow to the mold. Therefore, the straight mold is more prone to leakage.

[0006] In addition, due to the flow of liquid during concrete pouring and the impact force of the tilted platform on the mold, the mold is easily deformed, broken, or knocked down by stamping, thus affecting the construction quality of the foundation.

[0007] In addition, the mold is currently installed and disassembled manually or by crane, which can easily cause inaccuracies during alignment and installation. After alignment, a large number of tension bolts and external hoop steel bars are required for fixing. A large amount of manual labor is required during disassembly, making installation and disassembly very inconvenient.

[0008] On this basis, the present invention provides a wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly to solve the above technical problems. Summary of the invention

[0009] In view of the above situation, in order to overcome the defects of the prior art, the present invention provides a wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly. The present invention has a novel structure and ingenious conception, and effectively solves the technical problems of the existing wind power foundation molds in which the joints are linear and prone to leakage during construction, the molds are easily deformed by the pressure of concrete pouring, affecting the foundation quality, and the installation and disassembly are inconvenient.

[0010] A wind power construction foundation mold with enhanced sealing, improved supporting performance, portable installation and disassembly, the foundation mold is composed of multiple templates, each template includes an inner mold section and an outer mold section connected in one piece, characterized in that one end of the template is connected in one piece with an insertion section, and the other end is connected in one piece with a plug-in section, and the insertion section and the plug-in section match; The insertion section is coaxial with the template and is placed in the middle of the template. Two insertion blocking grooves and two insertion receiving grooves are provided on the inner and outer sides of the insertion section. The two insertion blocking grooves and the two insertion receiving grooves on the same side are arranged alternately, and the two insertion blocking grooves and the two insertion receiving grooves on different sides are arranged alternately. The plug-in section is coaxial with the template and is placed at both ends of the template. The inner and outer sides of the plug-in section are both provided with two plug-in blocking grooves and two plug-in receiving grooves corresponding to the two insertion blocking grooves and the two insertion receiving grooves. The two plug-in blocking grooves and the two plug-in receiving grooves on the same side are arranged alternately, and the two plug-in blocking grooves and the two plug-in receiving grooves on different sides are arranged alternately. A plurality of first compression springs are fixed in the insertion blocking groove and the plug-in blocking groove, and the first compression springs are fixedly connected with a blocking plate, and the other end of the blocking plate is placed in the insertion receiving groove and the plug-in receiving groove; The insertion section and the plug-in section are provided with sealing pads corresponding to the plug-in receiving groove and the insertion receiving groove; A first reinforcement hole is formed on the outer side of the insertion section and at one end away from the insertion section end, and a second reinforcement hole in an L shape matching the first reinforcement hole is formed on the outer side of the plug-in section and at one end close to the plug-in section end, and reinforcement plates are inserted into the first reinforcement hole and the second reinforcement hole; The reinforcing plate and the corresponding insertion section are provided with a first bolt hole, and a first bolt is installed in the first bolt hole; The reinforcing plate, the corresponding plug-in section and the insertion section are provided with second bolt holes, and second bolts are installed in the second bolt holes.

[0011] Preferably, a support member is additionally installed on the outer mold section on the outer side surface of the template, a slide is provided inside the support member, an upper pressing groove is provided in the middle, the lower end of the upper pressing groove is connected to the lower pressing groove, the upper and lower ends of the slide are respectively provided with symmetrically arranged upper through holes and lower through holes, a roller is rotatably installed in the slide, both ends of the roller are connected with compression columns through a second spring, the compression column can slide in the upper through hole or the lower through hole, a first toothed disk is provided on the end surface of the compression column, a locking sleeve is correspondingly fixed to the outer side of the lower through hole, a locking column cylinder is installed in the locking sleeve, and a second toothed disk matching the first toothed disk is provided on the end of the locking column cylinder, a support sleeve is fixedly provided on the roller, and the support sleeve is integrally connected with a support rod placed in the upper pressing groove and the lower pressing groove.

[0012] Preferably, the compression columns are all connected with pull rings via connecting ropes.

[0013] Preferably, a tightening sleeve is also fixed to the outside of the locking sleeve, and a bidirectional screw rod with opposite threads is rotatably installed between the locking sleeve and the tightening sleeve. The two ends of the bidirectional screw rod are respectively threadedly connected with a locking column and a tightening sleeve that are slidably installed in the locking sleeve and the tightening sleeve. The end of the locking column is provided with a second toothed disc, the end of the tightening sleeve is provided with a third toothed disc, and a rotating rod is provided in the tightening sleeve.

[0014] Preferably, the end of the rotating rod is provided with a fourth toothed disc matching the third toothed disc, and a prying tube is fixed between the two rotating rods.

[0015] Preferably, the locking sleeve and the pressing sleeve are provided with sliding holes, and the locking column and the pressing sleeve are fixed with sliding columns which can slide in the locking sleeve and the pressing sleeve.

[0016] Preferably, a pressing groove is provided at the upper end of the support member, and a blocking bar is rotatably mounted on the lower pressing groove.

[0017] Preferably, locking holes are provided at the upper and lower ends of the outer mold section, arc-shaped screws are passed through the locking holes, and screw bolts are tightened at the ends of the screws.

[0018] Preferably, a tightening hole is provided on the port surface of the tightening sleeve, a clamping groove is provided in the tightening hole, a clamping spring is installed in the clamping groove, the clamping spring is connected to a clamping block, an insertion column is fixed to the end surface of the rotating rod, an arc-shaped insertion head is fixed to the end of the insertion column, an insertion ring is fixed on the insertion column, and a switching head is slidably installed between the insertion head and the insertion ring.

[0019] The present invention has the following technical effects.

[0020] 1. The present invention changes the original single straight seam into a multi-channel multi-sealed seam consisting of two inserted (plugged) blocking grooves and two inserted (plugged) receiving grooves, changes the possible slurry flow path, and greatly improves the sealing performance of the template seam. At the same time, while improving the sealing performance, the blocking plate and the multiple inserted (plugged) receiving grooves are coordinated to facilitate and quickly realize installation and disassembly, which can be realized by only inserting and docking. At the same time, the simple double bolts of the first bolt and the second bolt can be fixed multiple times, which can not only reinforce the inserted section and the reinforcement plate, but also stabilize the reinforcement plate, the inserted section, and the plugged section, thereby realizing double insurance.

[0021] 2. The present invention can conveniently and quickly support the template through the support rod provided by the outer mold section. When not in use, the prying tube is fixed in the pressing groove, and the support rod is pressed into the upper pressing groove and the lower pressing groove. The neatness of the template can be ensured when not in use, and it can be conveniently and quickly pulled out when in use. The support rod and the prying rod can achieve dual support for the template and are easy to operate.

[0022] 3. The insertion section and the plug-in of the present invention as a whole are convenient and quick to install, the blocking plate and the insertion (plug-in) storage groove can realize quick installation and disassembly, the structure of the support rod and the prying tube can realize quick support and resetting, and the prying tube can realize upward lifting or left-right pulling, which is convenient for disassembly. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings: Figure 1 The invention discloses a pile platform constructed by using a foundation cap-shaped mold.

[0024] Figure 2 It is a three-dimensional schematic diagram of the plug-in state of two templates of the present invention.

[0025] Figure 3 It is a cross-sectional view and a partially enlarged schematic diagram of the plug-in state of two templates of the present invention.

[0026] Figure 4 It is a cross-sectional view and a partially enlarged schematic diagram of the template of the present invention.

[0027] Figure 5 It is a three-dimensional schematic diagram of the template insertion section of the present invention.

[0028] Figure 6 This is a three-dimensional schematic diagram of the support rod and the prying tube of the present invention being opened.

[0029] Figure 7 It is an enlarged stereoscopic schematic diagram of the support rod and the prying tube of the present invention.

[0030] Figure 8 It is a cross-sectional perspective schematic diagram of the roller, locking sleeve and tightening sleeve of the present invention.

[0031] Fig. 9 It is a schematic sectional front view of the roller, locking sleeve and top tightening sleeve of the present invention.

[0032] Fig.10 It is a schematic cross-sectional view of the template of the present invention.

[0033] Reference numerals: 1-template; 2-inner mold section; 3-outer mold section; 4-insertion section; 5-plug-in section; 6-insertion blocking groove; 7-insertion receiving groove; 8-plug-in blocking groove; 9-plug-in receiving groove; 10-first compression spring; 11-blocking plate; 12-first reinforcement hole; 13-second reinforcement hole; 14-reinforcement plate; 15-first bolt hole; 16-first bolt; 17-second bolt; 18-support member; 19-slideway; 20-upper pressing groove; 21-lower pressing groove; 22-upper through hole; 23-lower through hole; 24-roller; 25-second spring; 26-compression column; 27-first toothed disc; 28-lock Tightening sleeve; 29-locking column; 30-second toothed disc; 31-supporting sleeve; 32-supporting rod; 33-connecting rope; 34-pulling ring; 35-tightening sleeve; 36-bidirectional screw rod; 37-tightening sleeve; 38-third toothed disc; 39-rotating rod; 40-fourth toothed disc; 41-prying tube; 42-sliding hole; 43-sliding column; 44-pressing groove; 45-stop bar; 46-locking hole; 47-screw; 48-screw bolt; 49-tightening hole; 50-clamping groove; 51-clamping spring; 52-clamping block; 53-insertion column; 54-insertion head; 55-insertion ring; 56-switching head. DETAILED DESCRIPTION

[0034] The above and other technical contents, features and effects of the present invention are described in detail below with reference to the attached Figures 1 to 10 The details of the embodiments will be clearly presented. The contents mentioned in the following embodiments are all based on the drawings in the specification.

[0035] Exemplary embodiments of the present invention will be described below with reference to the accompanying drawings.

[0036] The present invention is a wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly. It is mainly used for concrete construction and pouring of wind power foundations. The foundation mold is constructed and installed by multiple templates 1 to form a circle. Each individual template 1 is arc-shaped. The general structure of each template 1 includes an inner mold segment 2 and an outer mold segment 3, which are connected as one piece. The inner mold segment 2 has a smooth surface and is used to adhere to concrete and shape the concrete into a circle. The outer mold segment 3 is used to reinforce, support, install and disassemble the inner mold segment.

[0037] An arc-shaped insertion section 4 and a plug-in section 5 are integrally connected at both ends of the template 1 . The insertion section 4 of one template 1 is matched and docked with the plug-in section 5 of another template 1 , and the plug-in section 5 of one template 1 is matched and docked with the insertion section 4 of another template 1 .

[0038] It should be noted that the insertion section 4 is coaxial with the template 1 and has a thickness less than that of the template 1. The insertion section 4 is placed in the middle of the thickness of the template 1. Two insertion blocking grooves 6 and two insertion receiving grooves 7 are provided on the inner and outer sides of the insertion section 4. The two insertion blocking grooves 6 and the two insertion receiving grooves 7 on the same side are staggered, the two insertion blocking grooves 6 on different sides are staggered, and the two insertion receiving grooves 7 on different sides are staggered.

[0039] Similarly, the plug-in section 5 is coaxial with the template 1 and its overall thickness is shorter than that of the template 1, but its position is placed at both ends of the outer side and the inner side of the template 1. Two plug-in blocking grooves 8 and two plug-in receiving grooves 9 are provided on the inner side of the inner side of the plug-in section 5 and the inner side of the outer side. The two plug-in blocking grooves 8 and the two plug-in receiving grooves 9 are staggered, the two plug-in blocking grooves 8 on different surfaces are staggered, and the two plug-in receiving grooves 9 on different surfaces are staggered.

[0040] A plurality of first compression springs 10 are fixed in the insertion blocking groove 6 and the plug-in blocking groove 8, and the first compression spring 10 is fixedly connected with a blocking plate 11, which is partially placed in the insertion blocking groove 6 or the plug-in blocking groove 8, and partially placed in the corresponding plug-in receiving groove 9 or the insertion receiving groove 7.

[0041] It should also be emphasized that the end of the blocking plate 11 that is located outside is an arc-shaped chamfer.

[0042] At the same time, the two ends of the insertion (plugging) blocking groove 6 (8) and the insertion (plugging) receiving groove 7 (9) are chamfered slopes, and the corresponding blocking plate 11 is also a chamfered slope.

[0043] At the joint between the insertion section 4 and the plug-in section 5 , a sealing gasket is mounted at the joint, and the shape of the sealing gasket corresponds to the shape of the plug-in receiving groove 9 and the insertion receiving groove 7 .

[0044] In order to facilitate the fixation and disassembly of the insertion section 4 and the plug-in section 5 and to improve the stability during matching, a first reinforcement hole 12 is opened on the outer side surface of the insertion section 4 and at an end away from the end of the insertion section 4, and a second reinforcement hole 13 is opened on the outer side surface of the plug-in section 5 and at an end close to the end of the plug-in section 5. The second reinforcement hole 13 matches the first reinforcement hole 12, and a reinforcement plate 14 is removed and installed in the first reinforcement hole 12 and the second reinforcement hole 13 to lock the plug-in end 5 and the insertion end 4.

[0045] In order to fix the reinforcement plate 14, a first bolt hole 15 is opened in the reinforcement plate 14 and the corresponding insertion section 4, and a first bolt 16 is installed in the first bolt hole 15; a second bolt hole 16 is opened in the reinforcement plate 14 and the corresponding plug-in section 5 and the corresponding insertion section 4, and a second bolt 17 is installed in the second bolt hole 16.

[0046] Specific embodiments: During the construction of the existing basic mold, since the joint is a linear joint, the joint is only pasted with double-sided tape, which is prone to leakage. However, during the jointing of the basic mold of the present invention, one template 1 is first installed manually or by hoisting, and then the insertion section 4 (plug-in section 5) of the other template 1 is matched to the previous plug-in section 5 (insertion section 4) in sequence.

[0047] More specifically, the sealing gasket is pre-installed on the insertion section 4, and then in the process of the insertion section 4 being inserted into the plug-in section 5, for example, the plug-in section 5 moves toward the insertion section 4, the plug-in section 5 presses down the blocking plate 11 in the insertion section 4, and the insertion section 4 presses down the blocking plate 11 in the plug-in section 5 and then passes through in sequence. When the plug-in section 5 is against the insertion section 4, the blocking plate 11 enters the insertion receiving groove 7 and the plug-in receiving groove 9 respectively. At this time, the insertion section 4 and the plug-in section 5 are sealed and connected (with the sealing gasket). At the same time, the insertion section 4 and the plug-in section 5 form a multi-bend line, and the insertion section 4 and the plug-in section 5 are locked through the blocking plate 11. The insertion section 4 and the plug-in section 5 are locked and cannot be removed, thereby completing the locking that is convenient for installation.

[0048] The sealing line has changed from the original single linear seal to Figure 3 The sealing lines shown are as follows: a1-b1-c1-d1-e1-f1-g1-h1-i1-j1-k1-l1-m1-n1-o1-p1-q1-r1-s1-t1-u 1-v1-w1-x1-y1-z1-a2-b2-c2-d2-e2-f2-g2-h2-i2-j2-k2-l2-m2-n2-o2.

[0049] or a1-b1-c1-d1-e1-f1-g1-h1-i1-j1-k1-l1-m1-n1-o1-p1-q1-r1-s1-t1-u1-v1-w1-x1-y1-z1-a2-b2-c2-d2-e2-f2-g2-h2-i2-j2-k3.

[0050] This instantly transforms the original single seam into an extremely complex sealing line, greatly improving the sealing of the seam and reducing leakage.

[0051] It should be noted that, since the length of the integrally connected insertion section 4 and plug-in section 5 is limited, if the length is too long to improve the sealing circuit, the single plug-in section 4 and insertion section 5 are likely to cause insufficient strength. Therefore, in multiple tests, the combination of two insertion (plug-in) receiving grooves 7 (9) and two insertion (plug-in) blocking grooves 6 (8) is the best performance sealing circuit.

[0052] It should also be noted that the two plug-in (insertion) blocking grooves 8 (6) and the two plug-in (insertion) receiving grooves 9 (7) are cross-arranged to form reverse cross-sealing lines, which can also greatly improve the sealing effect.

[0053] In addition, for the insertion section 4, the insertion (plugging) blocking grooves 6 (8) and the insertion (plugging) receiving grooves 7 (9) on the inner and outer sides are also arranged crosswise, which can ensure the strength of the insertion section 4 and the plugging section 5, otherwise it is easy to cause the strength of some positions to be reduced.

[0054] Therefore, under the arrangement of the two insertion (plugging) blocking grooves 6 (8) and the two insertion (plugging) receiving grooves 7 (9), in combination with the cross arrangement of the two insertion (plugging) blocking grooves 6 (8) and the two insertion (plugging) receiving grooves 7 (9) on the same surface, and the cross arrangement of the two insertion (plugging) blocking grooves 6 (8) and the two insertion (plugging) receiving grooves 7 (9) on different surfaces, not only can the sealing performance be greatly enhanced, but also the installation and fixing can be facilitated.

[0055] It should also be noted that the insertion section 4 and the plug-in section 5 can be docked not only in the left-right direction of the circumferential direction, but also from top to bottom.

[0056] After the insertion section 4 and the plug-in section 5 are matched and docked, the reinforcement plate 14 is inserted into the first reinforcement hole 12 and the second reinforcement hole 13. At this time, the outer circumference of the template 1 is still a complete arc, but at this time, the reinforcement plate 14 reinforces and presses the insertion section 4 and the plug-in section 5 at the same time, and the pressure end of the reinforcement plate 14 is provided with two rows of first bolt holes 15 and second bolt holes 16. The first bolt holes 15 fix the reinforcement plate 14 and the insertion section 4, and the reinforcement plate 14 presses the insertion section 4 and the plug-in section 5, thereby completing the fixation of the insertion section 4 and the plug-in section 5.

[0057] The second bolts 17 directly and completely fix the reinforcing plate 14 , the inserting section 4 and the plug-in section 5 , so that more than twice the multiple safety fixation can be achieved through simply two rows of first bolt holes 15 and second bolt holes 16 .

[0058] At this point, the sealing performance will be greatly improved after the base mold is docked.

[0059] Since the foundation mold is used for enclosure concrete pouring, and the pouring shape is an inclined pedestal shape, in order to improve the strength of the foundation mold during concrete pouring, the foundation mold is supported. Currently, the mold support is mainly through the outer wooden pile support.

[0060] The present invention is that a vertical, overall rectangular support member 18 is fixed on the outer template 3 on the outer side surface of the template 1, a slideway 19 is partially opened on the upper end portion of the support member 18, the bottom of the support member 18 is sealed, and a packaging plate is fixed on the upper part, an upper pressing groove 20 is reserved on the packaging plate, and a lower pressing groove 21 is opened in the solid part of the lower end of the support member 18, and the upper pressing groove 20 and the lower pressing groove 21 are connected, that is, the slideway 19 is only a part, which is about 1 / 2 of the length of the support member 18, and an upper through hole 22 and a lower through hole 23 are respectively opened at both ends of the upper and lower ends of the slideway 19 part.

[0061] A roller 24 is installed in a rolling and sliding manner in the slideway 19. The interior of the two ends of the roller 24 is a cavity with openings. A second spring 25 is fixed to the bottom of the roller 24. A compression column 26 is fixed to the second spring 25. The compression column 26 slides in the roller 24 via a slide rail, so that the compression column 26 can only slide in the roller 24. When the compression column 26 rotates, it drives the roller 24 to rotate together. The compression column 26 is partially placed in the roller 24 and partially placed outside the roller 24. The end surface of the compression column 26 is provided with a first toothed disc 27.

[0062] A locking sleeve 28 is fixed at a corresponding position on the outer side of the lower through hole 23. The interior of the locking sleeve 28 is a cavity, and a locking cylinder 29 is installed inside the cavity. The locking cylinder 29 is provided with a second toothed disc 30 at one end close to the support member 18. The second toothed disc 30 matches the first toothed disc 27. When the first toothed disc 27 and the second toothed disc 30 are connected, the first toothed disc 27 cannot rotate.

[0063] A support sleeve 31 is fixedly sleeved on the roller 24 . The support sleeve 31 is placed at the upper pressing groove 20 . The support sleeve 31 is integrally connected with a support rod 32 of the upper pressing groove 20 and the lower pressing groove 21 .

[0064] It should be noted that initially, the roller 24 is placed at the position of the upper through hole 22 , the compression column 26 passes through the upper through hole 22 and is placed outside, and the support rod 32 is placed at the upper pressing groove 20 and the lower pressing groove 21 , flush with the surface of the support member 18 .

[0065] When the construction of the basic mold is completed, the support rod 32 is rotated upward to the angle of the subsequent inclined support, the support rod 32 is pulled out of the upper pressing groove 20 and the lower pressing groove 21, and then the compression columns 26 on both sides are slid inward, so that the compression columns 26 enter the slide 19 through the upper through hole 22, and then the support rod 32 is pulled downward, and the support rod 32 drives the roller 24 to slide downward in the slide 19. When sliding to the position of the lower through hole 23, the compression column 26 pops outward under the action of the second spring 25, and the compression column 26 enters the locking sleeve 28 after passing through the lower through hole 23. At this time, the first toothed disc 27 is docked with the second toothed disc 30. Since the second toothed disc 30 cannot rotate, the second toothed disc 30 limits the first toothed disc 27 and locks the first toothed disc 27. At the same time, the support rod 32 is supported on the ground, which is convenient for the support rod 32 to support the ground.

[0066] When the template 1 is removed, the compression column 26 is pulled inward, the first toothed disc 27 is disengaged from the second toothed disc 30, and the compression column 26 enters the slideway 19 from the lower through hole 23, and the support rod 32 is used to push the roller 24 upward so that the roller 24 returns to the position of the upper through hole 22. At this time, the compression column 26 passes through the upper through hole 22 again under the action of the second spring 25, and then the support rod 32 is rotated downward to return the support rod 32 to the original position of the upper pressing groove 20 and the lower pressing groove 21.

[0067] The support rod 32 is used to improve the supporting performance of the basic mold and the compressive strength of the basic mold. At the same time, it is integrally connected with the template 1, which is convenient for transportation and operation, and does not require additional supporting templates.

[0068] It should be further explained that, in order to facilitate the pulling of the two compression columns 26, a sliding pull ring 34 is connected to the inner side of each compression column 26 via a connecting rope 33, the pull ring 34 is arranged on the support rod 32, and the connecting rope 33 is placed on the support rod 32 through the upper through hole 22 (lower through hole 23), the slide 19, and the upper pressing groove 20.

[0069] Furthermore, a tightening sleeve 35 is coaxially fixed to the outside of the locking sleeve 28. The locking sleeve 28 and the tightening sleeve 35 are not integrally connected. The interior of the locking sleeve 28 and the tightening sleeve 35 is a hollow cavity with both ends transparent. A bidirectional screw rod 36 with opposite screw threads is rotatably installed between the locking sleeve 28 and the tightening sleeve 35. A rotating drum is fixed in the middle of the bidirectional screw rod 36. The rotating drum is placed between the locking sleeve 28 and the tightening sleeve 35. The threads on the sides are respectively threadedly connected with a locking cylinder 29 and a tightening sleeve 37. The tightening sleeve 35 is slidably installed in the locking sleeve 28. The tightening sleeve 37 is slidably installed in the tightening sleeve 35. A second toothed disc 30 is provided at the end of the locking cylinder 29. The second toothed disc 30 matches the first toothed disc 27. A third toothed disc 38 is provided at the end of the tightening sleeve 37 for locking the subsequent rotating rod 39. A rotating rod 39 is rotatably and slidably provided in the tightening sleeve 35.

[0070] It should be noted that the locking sleeve 28 and the pressing sleeve 35 are fixedly connected by welding to a fixing plate of the outer mold segment 3 .

[0071] Furthermore, a fourth toothed disc 40 is provided at the end of the rotating rod 32, and the fourth toothed disc 40 can match the third toothed disc 38. A transverse prying tube 41 is fixed between the two rotating rods 32, and the interior of the prying tube 41 is a hollow cavity with both ends being transparent.

[0072] It should be noted that in the initial position, the fourth toothed disc 40 is not docked with the third toothed disc 38, and the rotating rod 32 can rotate in the tightening sleeve 35. After the rotating rod 32 is slid, the fourth toothed disc 40 is docked with the third toothed disc 38, and the rotating rod 32 is locked and cannot rotate.

[0073] In order to better realize the cooperation between the locking column 29 and the tightening sleeve 37 and the bidirectional screw rod 36, and realize that the locking column 29 and the tightening sleeve 37 can slide, a sliding hole 42 is opened on the locking sleeve 28 and the tightening sleeve 35, and a sliding column 43 that can slide in the locking sleeve 29 and the tightening sleeve 35 is fixed on the locking column 29 and the tightening sleeve 37, thereby limiting the locking column 29 and the tightening sleeve 37.

[0074] Furthermore, a pressing groove 44 is opened at the upper end of the support member 18. In the initial position, the prying tube 41 is clamped in the pressing groove 44, and then the support rod 32 is pressed on the prying tube 41, and a baffle 45 is rotatably installed on the lower pressing groove 21. One end of the baffle 45 is rotatably installed on one side of the lower pressing groove 21, and the other end of the baffle 45 is disassembled and fastened to the other end of the lower pressing groove 21, so as to lock and fix the support rod 32.

[0075] In order to reinforce the basic mold again, a plurality of locking holes 46 are opened at the upper and lower ends of the outer mold section 3. The locking holes 46 are opened on the rib plate of the outer mold section 3. A coaxial arc-shaped screw 47 is penetrated through the locking holes 46. The end of the screw 47 is tightened with a screw bolt 48, which presses the rib plate of another template 1.

[0076] Further, in order to lock the prying tube 41, the prying tube 41 needs to be locked when it is not in use in the initial position, and needs to be locked when supporting the ground. A tightening hole 49 is provided on the end surface of the tightening sleeve 37, and a clamping groove 50 is provided in the tightening hole 49. A clamping spring 51 is installed in the clamping groove 50. The clamping spring 51 is connected to a clamping block 52. The end of the clamping block 52 is provided with a chamfered surface, wherein the cut surface is at the end away from the support rod 32, that is, the outer side, and the inner part is Vertically, an insertion column 53 is fixed to the end surface of the rotating rod 32, an insertion ring 55 is fixed on the insertion column 53, an arc-shaped insertion head 54 is fixed to the end of the insertion column 53, the insertion head 54 is provided with an embedded groove in the direction close to the insertion ring 55, and a switching head 56 on the insertion column 53 is slidably installed between the insertion head 54 and the insertion ring 55, and both ends of the switching head 56 are beveled surfaces, that is, it is composed of two rings with trapezoidal cross-sections spliced ​​together, and the middle part of the splicing is the highest.

[0077] When it is necessary to lock the prying tube 41, the prying tube 41 is slid into the tightening sleeve 35, so that the third toothed disc 38 and the fourth toothed disc 40 are docked. At the same time, the insertion head 54 enters the tightening hole 49, and the insertion head 54 pushes the clamping block 52 to move into the clamping groove 50, so that the insertion head 54 passes smoothly. At this time, the prying tube 41 is locked and cannot move, thereby achieving the locking of the prying tube 41. When it is necessary to unlock, it continues to slide inward, and the beveled surface of the switching head 56 presses the clamping block 52 to move into the clamping groove 50, so that the switching head 56 passes through the clamping block 52, and then the prying tube 41 is pulled outward to move, and the clamping block 52 pushes the switching head 56 to move toward the insertion head 54, and a part of the switching head 56 enters the embedded groove of the insertion head 54, and then the switching head 56 and the insertion head 54 are together, and the clamping block 52 slides out smoothly along the beveled surface of the switching head 56.

[0078] In a more specific embodiment, after the basic template is docked, the retaining bar 45 is removed, the support rod 32 is rotated upward, the prying tube 41 is flipped outward and rotated downward until it is supported on the ground, the pull ring 34 is pulled, the compression column 26 is pulled into the slide 19, and the support rod 32 is pulled downward. The support rod 32 drives the roller 24 to move downward. When it moves to the position of the lower through hole 23, the compression column 26 enters the locking sleeve 28 through the lower through hole 23 under the action of the second spring 25, and the support rod 32 is rotated to a suitable position to support it on the ground. The first toothed disc 27 matches and docks with the second toothed disc 30 to achieve the locking of the support rod 32, and the support rod 32 cannot rotate.

[0079] At the same time, the prying tube 41 is flipped over and supported on the ground, and double insurance support is achieved through the support rod 32 and the prying tube 41.

[0080] The sliding rod 32 is rotated in the direction of the tightening sleeve 35, and the insertion head 54 at the end of the rotating rod 32 enters the tightening hole 49 and is locked by the clamping block 52. At the same time, the third toothed disc 38 and the fourth toothed disc 40 are matched and docked, and are firmly locked, so that the prying tube 41 cannot rotate.

[0081] In order to further lock the first toothed disc 27 and the second toothed disc 30 , the third toothed disc 38 and the fourth toothed disc 40 , the rotating drum is rotated, and the bidirectional screw rod 36 drives the second toothed disc 30 and the third toothed disc 38 to move toward the first toothed disc 27 and the fourth toothed disc 40 to further increase the locking force.

[0082] When the mold needs to be removed, the prying tube 41 is turned upward or at a certain angle to the pressing groove 44, and then the support rod 32 is returned to the upper pressing groove 20 and the lower pressing groove 21, and then locked with the blocking bar 45. After that, a prying rod (removal tool) is inserted into one end or both ends of the prying tube 41 or penetrated horizontally to shake and pry upward. It can also be disassembled upward together with a crane, or it can be disassembled in the left and right directions after passing through the prying tube. That is, the template 1 can be disassembled in two ways: left and right directions and upward.

[0083] It should be noted that when removing the template 1, it is necessary to release the first bolt 16, the second bolt 16, the reinforcing plate 14, the screw 47, the screw bolt 48, etc. in advance, and the blocking plate 11 is set at an inclined arc, so it can be removed by prying it horizontally or lifting it upward.

[0084] The basic mold also needs to pay attention to the following when constructing: 1) Before construction, the template should be arranged according to the foundation dimensions.

[0085] 2) The design and selection of templates and their connection tools should comply with relevant specifications, and qualified templates and template connection tools must be selected. Those that are severely deformed, damaged, or have obvious surface damage shall not be used.

[0086] 3) The template joints must be tight to prevent leakage. The template system adopts a standardized combined round steel template system, the template is leveled, and the release agent is applied to ensure that the application is even, not too thick, not flowing, and not missing. Polishing should be done to achieve the original color of the steel template, the surface is smooth and flat, the flatness is less than 1mm, and the template corners must be straight, flat, and clean. When selecting the template, check the template structure and parts, complete, consistent plate eyes, and stack them in piles for easy control and use in the same part, which is conducive to controlling the tightness and flatness of the combined steel template joints.

[0087] (2) Formwork removal 1) When dismantling the formwork, follow the principle of supporting first and then dismantling, and dismantling the rear support first; dismantle the non-load-bearing formwork first, and then the load-bearing formwork; from top to bottom, dismantle the lateral support first, and then the vertical support.

[0088] 2) The formwork in any part can only be removed when the concrete reaches the specified strength. Non-load-bearing formwork should not be removed until the concrete strength can ensure that its surface and edges are not damaged by formwork removal. The concrete strength should not be less than 1.2MPa.

[0089] (1) Concrete supply The concrete is supplied by a commercial concrete plant. We contact two or more commercial concrete mixing stations to prepare for emergencies. Tank trucks are used for transportation, and concrete pump trucks and manual labor are used to pour the concrete.

[0090] (2) Concrete pouring 1) Before pouring concrete, check and ensure that: the elevation, position and cross-sectional dimensions of the formwork meet the design requirements, the formwork joints are tight and the support is stable; the number, spacing, bending position of the steel bars, the number and position of joints in the same cross-section of the components, the thickness of the steel bar protective layer, etc. meet the specifications and design requirements; the position and quantity of the buried iron parts, reserved holes for pipes and bolts, etc. are correct. After acceptance, pouring can be carried out.

[0091] 2) After the steel bars are tied and the formwork is supported, check the horizontality of the upper anchor plate before pouring concrete. Concrete can only be poured after it meets the requirements.

[0092] 3) After the installation of the anchor assembly is completed, apply to the supervision project for hidden project acceptance first. Before pouring the concrete under the lower anchor plate, the anchor nut under the lower anchor plate must be confirmed by the supervision project acceptance signature before pouring.

[0093] 4) During the concrete pouring process, the main thing to do is to protect the anchor bolt assembly and wrap the entire upper part of the anchor bolt with plastic sheeting to prevent the upper anchor plate and anchor bolt from being contaminated or damaged during concrete pouring.

[0094] 5) Before pouring concrete, detailed technical instructions shall be given to the construction personnel on the pouring sequence, pouring method, location of construction joints, mix ratio, quality requirements, etc.

[0095] 6) During the concrete construction, insert vibrator is used to vibrate and compact the concrete. The upper surface of the concrete is leveled with an extended wooden plate and smoothed with a wooden trowel. During the vibration process, the steel bars should be strictly kept straight, and the position and thickness of the protective layer of the steel bars should be correct. A special person should be assigned to observe the formwork, steel bars, embedded parts, embedded bolts, etc. to ensure that there is no movement or deformation, and any problems should be dealt with in a timely manner.

[0096] 7) During the concrete construction process, the slump of concrete should be tested frequently using a slump bucket. If any problem is found, the commercial concrete station should be notified in time for adjustment.

[0097] (3) Concrete maintenance Water the concrete immediately after initial setting, and cover its surface with plastic film for curing to keep the concrete surface moist and ensure the growth of concrete strength. The curing time for ordinary concrete is not less than 7 days. The curing time for concrete with slow-setting admixtures or with anti-seepage requirements is not less than 14 days. During rainy season construction, rainy season construction measures shall be implemented. The formwork can be removed only when the concrete strength meets the specification requirements, and measures shall be taken to protect the finished product and prevent secondary pollution and damage.

[0098] (1) General requirements for embedding embedded parts 1) All materials used must comply with the requirements of the construction drawings. The materials must have a quality certificate from the manufacturer and their quality must not be lower than that of the current national standards.

[0099] 2) If substitute materials are used, the quality certificate and trial results of the substitute materials shall be submitted to the tenderer for approval. Substitute materials not approved by the tenderer shall not be used.

[0100] 3) If the construction drawings need to be modified, prior approval must be obtained from the tenderer, and the position of the modified embedded parts should avoid interference with other embedded parts.

[0101] (2) Buried installation of fixings 1) All kinds of fixing parts shall be purchased and processed according to the requirements of the construction drawings.

[0102] 2) After the fixings are installed in place and measured and checked to be correct, they can be fixed immediately.

[0103] 3) The installation of embedded fixings for the electrical part shall comply with the construction drawings and relevant specifications.

[0104] 4) During the entire construction period, take care to protect all embedded fixings to prevent them from damage and deformation.

[0105] 1. After pouring concrete, do a good job of thermal insulation and moisture maintenance of concrete, slowly cool it down, give full play to its creep characteristics, and reduce temperature stress.

[0106] 2. The foundation base plate should be kept moisturized for a long time (not less than 14 days) to delay the cooling time and speed.

[0107] 3. Strengthen the vibration of concrete, improve the density and tensile strength of concrete, reduce shrinkage and deformation, and ensure construction quality.

[0108] 4. After pouring, remove the surface slurry in time, strengthen early maintenance, and improve the tensile strength and elastic modulus of concrete at the early stage or corresponding age.

[0109] 5. Use covering + watering for heat preservation and maintenance.

[0110] 6. Strengthen temperature measurement and temperature monitoring and management, implement information control, control the temperature changes in the concrete at any time, ensure that the temperature difference between the inside and outside is controlled within 25°C, and adjust the insulation and maintenance measures in time to prevent the temperature gradient of the concrete from being too large, so as to effectively control the occurrence of harmful cracks. The temperature measurement adopts electronic temperature measurement, and directly reads the actual temperature of each temperature measurement point.

[0111] 7. The base plate of this project is relatively thick, and multiple temperature measuring points are set up. The temperature measuring points are arranged in representative places, and electronic thermometers are used for temperature measurement. Special personnel are assigned to protect the embedded temperature measuring wires to prevent damage during concrete pouring. The upper, middle and lower three layers of temperature measuring points are arranged as a group. After the large volume of concrete is poured, it must be monitored to detect the surface temperature of the concrete and the temperature of the center of the structure. In order to take corresponding measures to ensure the construction quality of the concrete. When the temperature difference between the inside and the surface of the concrete exceeds 25°C, emergency measures such as deepening the watering curing layer of the concrete should be taken in time to increase the surface temperature of the concrete, reduce the temperature difference between the inside and the outside, and avoid cracks due to excessive temperature difference.

[0112] 8. The arrangement requirements of temperature control monitoring points are as follows: four temperature measuring points are arranged at the center of the foundation and 6.0m away from the edge of the foundation, and three temperature measuring points are arranged at each point along the height of the foundation (surface, center, and foundation bottom surface temperature measuring points), for a total of 12 temperature measuring points. The surface temperature measuring point is arranged 450mm inside the upper surface of the foundation, the bottom surface temperature measuring point is arranged 750mm above the bottom surface of the foundation, and the center temperature measuring point is arranged at the midpoint of the line connecting the surface and bottom surface temperature measuring points.

[0113] The present invention has the following technical effects.

[0114] 1. The present invention changes the original single straight seam into a multi-sealed seam consisting of two inserted (plugged) blocking grooves and two inserted (plugged) receiving grooves, which greatly improves the sealing performance of the template seam. At the same time, while improving the sealing performance, the blocking plate and the multiple receiving grooves are coordinated to facilitate and quickly realize installation and disassembly, which can be realized by simply inserting and docking. At the same time, the simple double bolts of the first bolt and the second bolt can be fixed multiple times, which can not only reinforce the inserted section and the reinforcement plate, but also reinforce the reinforcement plate, the inserted section, and the plug-in section, thereby realizing double insurance.

[0115] 2. The present invention can conveniently and quickly support the template through the support rod provided by the outer mold section. When not in use, the prying tube is fixed in the pressing groove, and the support rod is pressed into the upper pressing groove and the lower pressing groove. The neatness of the template can be ensured when not in use, and it can be conveniently and quickly pulled out when in use. The support rod and the prying rod can achieve dual support for the template and are easy to operate.

[0116] 3. The insertion section and the plug-in of the present invention as a whole are convenient and quick to install, the blocking plate and the insertion (plug-in) storage groove can realize quick installation and disassembly, the structure of the support rod and the prying tube can realize quick support and resetting, and the prying tube can realize upward lifting or left-right pulling, which is convenient for disassembly.

[0117] Although the content of the present invention has been described in detail through the above preferred embodiments, it should be appreciated that the above description should not be considered as limiting the present invention. After reading the above content, various modifications and substitutions of the present invention will be obvious to those skilled in the art. Therefore, the protection scope of the present invention should be defined by the attached claims.

Claims

1. A wind power construction foundation mold with enhanced sealing, improved support performance, and portable installation and disassembly, wherein the foundation mold is composed of a plurality of templates (1) installed, each template (1) comprising an inner mold section (2) and an outer mold section (3) connected in one piece, characterized in that: One end of the template (1) is integrally connected with an insertion section (4), and the other end is integrally connected with an insertion section (5), and the insertion section (4) and the insertion section (5) match; The insertion section (4) is coaxial with the template (1) and is placed in the middle of the template (1). The inner and outer sides of the insertion section (4) are provided with two insertion blocking grooves (6) and two insertion receiving grooves (7). The two insertion blocking grooves (6) and two insertion receiving grooves (7) on the same surface are arranged alternately, and the two insertion blocking grooves (6) and two insertion receiving grooves (7) on different surfaces are arranged alternately. The plug-in section (5) is coaxial with the template (1) and is disposed at both ends of the template (1); the inner and outer side surfaces of the plug-in section (5) are provided with two plug-in blocking grooves (8) and two plug-in receiving grooves (9) corresponding to the two insertion blocking grooves (6) and the two insertion receiving grooves (7); the two plug-in blocking grooves (8) and the two plug-in receiving grooves (9) on the same side are arranged in a staggered manner, and the two plug-in blocking grooves (8) and the two plug-in receiving grooves (9) on different sides are arranged in a staggered manner; A plurality of first compression springs (10) are fixed in the insertion blocking groove (6) and the plug-in blocking groove (8), and the first compression springs (10) are fixedly connected to a blocking plate (11), and the other end of the blocking plate (11) is placed in the insertion receiving groove (7) and the plug-in receiving groove (9); The insertion section (4) and the plug-in section (5) are provided with sealing gaskets corresponding to the plug-in receiving groove (9) and the insertion receiving groove (7); A first reinforcement hole (12) is provided on the outer side surface of the insertion section (4) and at one end away from the end of the insertion section (4); a second reinforcement hole (13) in an L shape matching the first reinforcement hole (12) is provided on the outer side surface of the plug-in section (5) and at one end close to the end of the plug-in section (5); and reinforcement plates (14) are inserted into the first reinforcement hole (12) and the second reinforcement hole (13); The reinforcing plate (14) and the corresponding insertion section (4) are provided with a first bolt hole (15), and a first bolt (16) is installed in the first bolt hole (15); The reinforcing plate (14), the corresponding plug-in section (5), and the insertion section (4) are provided with a second bolt hole (16), and a second bolt (17) is installed in the second bolt hole (16).

2. The wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly according to claim 1 is characterized in that: A support member (18) is installed on the outer mold section (3) on the outer side of the template (1), a slideway (19) is provided inside the support member (18), an upper pressing groove (20) is provided in the middle, the lower end of the upper pressing groove (20) is connected to the lower pressing groove (21), the upper end and the lower end of the slideway (19) are respectively provided with symmetrically arranged upper through holes (22) and lower through holes (23), a roller (24) is rotatably installed in the slideway (19), and both ends of the roller (24) are connected to compression columns (26) via second springs (25), and the compression columns (26) can be inserted into the upper through holes (22) and lower through holes (23). The roller (24) slides in the hole (22) or the lower through hole (23), the end surface of the compression column (26) is provided with a first toothed disc (27), the outer side of the lower through hole (23) is fixed with a locking sleeve (28), a locking column (29) is installed in the locking sleeve (28), and the end of the locking column (29) is provided with a second toothed disc (30) matching the first toothed disc (27), and the upper sleeve of the roller (24) is fixedly provided with a supporting sleeve (31), and the supporting sleeve (31) is integrally connected with a supporting rod (32) disposed in the upper pressing groove (20) and the lower pressing groove (21).

3. The wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly according to claim 2 is characterized in that: The compression columns (26) are all connected to pull rings (34) via connecting ropes (33).

4. The wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly according to claim 2 is characterized in that: A tightening sleeve (35) is also fixed to the outer side of the locking sleeve (28), and a bidirectional screw rod (36) with opposite threads is rotatably installed between the locking sleeve (28) and the tightening sleeve (35). The two ends of the bidirectional screw rod (36) are respectively threadedly connected to a locking column (29) and a tightening sleeve (37) slidably installed in the locking sleeve (28) and the tightening sleeve (35). The end of the locking column (29) is provided with a second toothed disc (30), and the end of the tightening sleeve (37) is provided with a third toothed disc (38). A rotating rod (39) is provided in the tightening sleeve (35).

5. The wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly according to claim 4 is characterized in that: The end of the rotating rod (39) is provided with a fourth toothed disc (40) matching the third toothed disc (38), and a prying tube (41) is fixed between the two rotating rods (39).

6. The wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly according to claim 5 is characterized in that: The locking sleeve (28) and the pressing sleeve (35) are provided with sliding holes (42), and the locking column (29) and the pressing sleeve (37) are provided with sliding columns (43) capable of sliding in the locking sleeve (28) and the pressing sleeve (35).

7. The wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly according to claim 6 is characterized in that: A pressing groove (44) is formed at the upper end of the support member (18), and a stop bar (45) is rotatably mounted on the lower pressing groove (21).

8. The wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly according to claim 7 is characterized in that: The upper and lower ends of the outer mold section (3) are both provided with locking holes (46), an arc-shaped screw rod (47) is inserted into the locking hole (46), and a screw rod bolt (48) is tightened at the end of the screw rod (47).

9. The wind power construction foundation mold with enhanced sealing, improved supporting performance, and portable installation and disassembly according to claim 8 is characterized in that: The end surface of the abutting sleeve (37) is provided with a abutting hole (49), a clamping groove (50) is provided in the abutting hole (49), a clamping spring (51) is installed in the clamping groove (50), the clamping spring (51) is connected to a clamping block (52), an insertion column (53) is fixed to the end surface of the rotating rod (39), an arc-shaped insertion head (54) is fixed to the end of the insertion column (53), an insertion ring (55) is fixed to the insertion column (54), and a switching head (56) is slidably installed between the insertion head (54) and the insertion ring (55).