Middle division zone filling construction equipment
By integrating the detection module and control module into the filling construction equipment in the middle zone, the density and humidity of the filling can be detected and adjusted in real time, which solves the problems of low intelligence of traditional equipment and difficulty in controlling the quality of the filling, and achieves a more efficient , safe filling effect.
Patent Information
- Application Number
- CN202411285876.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-13
- Publication Date
- 2025-01-24
AI Technical Summary
Traditional middle-dividing belt fill construction equipment has low intelligence and is prone to deviating from the central partition belt, affecting safety and efficiency, and failing to effectively measure and adjust the fill quality.
Design a medium -band -filled land construction equipment, including transport vehicles, detection modules and control modules. The detection module is used to detect the density and humidity of each layer of soil, and the control module adjusts the soil conveyor and vibrator power according to the test results to ensure the quality of the soil filling at each layer.
Through real-time detection and adjustment, the density and humidity control of the filling are improved, ensuring the filling effect, improving construction efficiency and safety, and reducing energy consumption.
Smart Images

Figure CN119352600A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of road construction, and in particular relates to a center-dividing strip filling construction device. Background Art
[0002] In road construction projects, the central median refers to a strip-shaped facility set up along the longitudinal direction of the road to separate lanes. In order to ensure the driving safety and proper functions of expressways and first-class highways, median strips should be set up. They play an irreplaceable and important role in highway engineering.
[0003] During the construction of the central median, the filling work on the central median is often carried out after the asphalt pavement construction on both sides is completed. In the traditional earth shoulder filling and central median filling construction, a dump truck full of soil is used to transport the filling soil to the construction site, and then the dump truck is reversed horizontally on the asphalt pavement. After it is in place, the soil is poured out from the rear of the car. This traditional dump truck has a low degree of intelligence and is easy to deviate from the central median during operation, which affects the safety of the operation, reduces the efficiency of the construction, and increases the workload of the staff. For this reason, Chinese patent CN220598551U discloses a central median filling method. The equipment comprises a vehicle body and a carriage arranged on the vehicle body, a material pushing assembly is arranged in the carriage, the carriage has a first side door and a second side door opened on both sides of the moving direction of the vehicle body, and the material pushing assembly pushes the material in the carriage from the first side door and / or the second side door; it can improve the filling efficiency of the center-dividing belt and improve the construction efficiency; however, during the filling process of the center-dividing belt, parameters such as the compaction degree of the soil and the moisture content of the soil will affect the quality of the results of the center-dividing belt filling construction, and in the above scheme, the filling quality is not measured, and the filling scheme is not adjusted according to the measurement results, and the filling effect is insufficient. Therefore, a center-dividing belt filling construction equipment with good filling effect is needed. Summary of the invention
[0004] In order to solve the above problems existing in the prior art, the present invention provides a kind of center-dividing belt filling construction equipment, which has the characteristics of good filling effect.
[0005] The purpose of the present invention can be achieved through the following technical solutions:
[0006] A kind of construction equipment for filling soil in a center belt, comprises a transport vehicle and a control module, the transport vehicle comprises a hopper and a detection module, the hopper is used to transport soil in batches to one side of the transport vehicle, the detection module is used to detect the density of the upper layer of backfill soil after ramming, the control module is electrically connected to the hopper and the detection module respectively, the control module increases the volume of the soil transported in a single batch when the density exceeds a threshold value, and the control module reduces the volume of the soil transported in a single batch when the density is lower than the threshold value.
[0007] As a preferred technical solution of the present invention, the control module is pre-input with a compaction threshold M0, the detection module is used to detect the compaction degree M of the previous layer of backfill soil after ramming and upload it to the control module, and the control module instructs the hopper to transport soil with a volume of V×A1 in batches to one side of the transport vehicle, wherein A1=M / M0×c, and c is a pre-input constant.
[0008] As a preferred technical solution of the present invention, the detection module also includes a soil moisture sensor, which is used to detect the humidity of the previous layer of backfill soil and upload it to the control module. The control module reduces the volume of the soil transported in a single batch when the humidity exceeds a threshold value, and increases the volume of the soil transported in a single batch when the humidity is lower than the threshold value.
[0009] As a preferred technical solution of the present invention, the soil moisture sensor is used to detect the humidity S of the upper layer of backfill soil and upload it to the control module. The control module instructs the hopper to transport soil with a volume of V×A1×A2 in batches to one side of the transport vehicle, where A2=S0 / S×d, and d is a pre-input constant.
[0010] As a preferred technical solution of the present invention, the hopper includes a vibrator, and the vibrator is used to apply vibration to the soil in the hopper.
[0011] As a preferred technical solution of the present invention, the vibrator is electrically connected to a control module, and the control module reduces the power of the vibrator when the density exceeds a threshold value, and increases the power of the vibrator when the density is lower than the threshold value.
[0012] As a preferred technical solution of the present invention, the control module is pre-input with a reference power P0, and the control module adjusts the power of the vibrator to P, wherein P=M0 / M×e×P0, and e is a pre-input constant.
[0013] As a preferred technical solution of the present invention, it also includes a control panel, which is electrically connected to the control module and is used to input the values of M0, c, d, S0, M0 and e.
[0014] The beneficial effects of the present invention are:
[0015] (1) By setting up a detection module to detect the compactness of each layer of fill, and adjusting the soil delivery amount of the next layer of fill according to the detection results, the thickness of each layer of fill is adjusted, so as to increase the soil delivery amount when the compactness is high, thereby improving the construction efficiency, and reduce the soil delivery amount when the compactness is low, thereby reducing the thickness of each layer of fill to ensure the fill effect;
[0016] (2) By setting up a humidity sensor to detect the soil, and reducing the filling thickness when the soil humidity is high after filling, it is ensured that the relatively soft soil with high humidity is fully compacted, thereby improving the filling effect, and improving the construction efficiency when the humidity is low and there is no need for full compaction;
[0017] (3) By setting a vibrator to vibrate the soil in the hopper according to the degree of compaction, when the soil density is low and the agglomerated soil has a greater impact on the overall filling effect, the vibration power is increased to reduce the amount of agglomerated soil as much as possible; when the soil density is high and the agglomerated soil has a smaller impact on the overall filling effect, the vibration power is reduced, thereby reducing energy consumption. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to facilitate understanding by those skilled in the art, the present invention is further described below with reference to the accompanying drawings.
[0019] Figure 1 It is a structural schematic diagram of the present invention;
[0020] Figure 2 It is a schematic diagram of the cross-sectional structure of the hopper of the present invention;
[0021] Figure 3 This is a control loop block diagram of the present invention.
[0022] Description of main component symbols:
[0023] In the figure: 1, transport vehicle; 2, hopper; 21, discharge port; 22, push shovel; 3, control module; 31, probe; 32, cantilever. DETAILED DESCRIPTION
[0024] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation methods, structures, features and effects of the present invention are described in detail below in conjunction with the accompanying drawings and preferred embodiments.
[0025] See also Figure 1-3 , a mid-dividing belt filling construction equipment, comprising a transport vehicle 1, the transport vehicle 1 comprising a hopper 2, the hopper 2 is used to transport soil in batches to one side of the transport vehicle 1;
[0026] Specifically, in this embodiment, the hopper 2 is a quadrangular prism-shaped hollow structure placed on the transport vehicle 1 and transported by the transport vehicle 1. Soil is stored in the hopper 2. A discharge port 21 is provided on one of the side walls of the quadrangular prism-shaped hopper 2. The position of the discharge port 21 ensures that the soil in the hopper 2 can fall into the side or rear of the transport vehicle 1 after leaving the hopper 2 from the discharge port 21. At the same time, a push shovel 22 is provided in the hopper 2. The push shovel 22 is arranged toward the discharge port 21. The push shovel 22 is a structure that can be extended toward the discharge port 21, and is used to push the soil from the hopper 2 to the discharge port 21 during the extension and retraction process, thereby completing the transportation of the soil to the belts in the fill soil.
[0027] After the soil of the middle belt is transported, the workers carry out the filling construction. In this embodiment, the construction is divided into multiple layers of filling. At the beginning of the construction, the conveyor pulls the hopper 2 to move along the middle belt to transport soil to various places of the middle belt. After the first layer of soil of the middle belt filling is transported, the workers use a tamping machine to compact the first layer of filling. Subsequently, the conveyor pulls the hopper 2 to move along the middle belt to transport soil to various places of the middle belt. After the second layer of soil of the middle belt filling is transported, the workers use a tamping machine to compact the second layer of filling, and so on, until the filling construction of the middle belt is completed;
[0028] In the above process, in some construction scenarios, the operators can only use small-sized tamping machines with relatively low power to tamp the soil. At this time, when too much soil is transported at one time, the small-sized tamping machine cannot tamp the thicker soil layer with sufficient effect, resulting in insufficient filling effect. For this reason, the conveying vehicle also includes a control module 3, and the conveying vehicle also includes a detection module. The detection module is used to detect the compaction degree of the previous layer of backfill soil. The control module 3 is electrically connected to the hopper 2 and the detection module respectively. The control module 3 increases the volume of the soil transported in a single batch when the compaction degree exceeds the threshold value, and reduces the volume of the soil transported in a single batch when the compaction degree is lower than the threshold value.
[0029] When in use, the hopper 2 pushes the push shovel 22 to transport soil in batches to one side of the transport vehicle 1. The detection module is used to detect the compactness of the previous layer of backfill soil. The control module 3 increases the volume of the soil transported in a single batch when the compactness exceeds the threshold, and reduces the volume of the soil transported in a single batch when the compactness is lower than the threshold.
[0030] At the same time, the detection module includes a probe 31 that can be close to or away from the soil layer and a plurality of pressure sensors arranged on the surface of the probe 31. The plurality of pressure sensors are electrically connected to the control module 3. The control module 3 drives the probe 31 to approach the soil layer. When the plurality of pressure sensors are in contact with the soil layer, the pressure from the soil layer on the probe 31 is uploaded to the control module 3. The control module 3 determines the compaction degree according to the pressure data. In this embodiment, a cantilever 32 is arranged at the rear of the transport vehicle 1. The probe 31 is arranged at one end of the cantilever 32. The cantilever 32 drives the probe 31 to approach the soil layer when detecting.
[0031] Meanwhile, a compaction threshold value M0 is pre-input into the control module 3. The detection module is used to detect the compaction degree M of the backfill soil of the upper layer and upload it to the control module 3. The control module 3 instructs the hopper 2 to batch-transport soil with a volume of V×A1 to one side of the transport vehicle 1, where A1 = M / M0×c, and c and V are pre-input constants;
[0032] When the compaction degree M detected by the control module 3 is relatively high, it means that the current process and equipment can better ensure the compaction degree of the upper layer of fill soil. At this time, the soil thickness of each layer of fill construction can be increased to improve the construction efficiency, and then the median strip can be filled as soon as possible to improve the construction efficiency. At this time, the value of A1 = M / M0×c is relatively large. When the control module 3 instructs the hopper 2 to batch-transport soil with a volume of V×A1 to one side of the transport vehicle 1, the construction efficiency is improved when the compaction degree is relatively high; similarly, when the value of M is relatively low, it means that the current process and equipment cannot better ensure the compaction degree of the upper layer of fill soil. At this time, the thickness of each layer of fill needs to be reduced so that the rammer can better compact each layer of fill. At this time, the value of A1 = M / M0×c is relatively small. When the control module 3 instructs the hopper 2 to batch-transport soil with a volume of V×A1 to one side of the transport vehicle 1, the filling effect is ensured when the compaction degree is relatively low;
[0033] By setting up a detection module to detect the compaction degree of each layer of fill soil, and adjusting the soil delivery volume of the next layer of fill according to the detection result, thereby adjusting the thickness of each layer of fill soil, the soil delivery volume is increased when the compaction degree is relatively high, thereby improving the construction efficiency, and the soil delivery volume is reduced when the compaction degree is relatively low, thereby reducing the thickness of each layer of fill soil to ensure the filling effect.
[0034] In the above process, specifically, the humidity of the backfill soil will also affect the filling effect. When the soil humidity is relatively high, the thickness of each layer of fill needs to be reduced to ensure that the soil with a relatively high humidity and relatively soft texture is fully compacted. For this reason, the detection module also includes a soil humidity sensor. The soil humidity sensor is used to detect the humidity of the backfill soil of the upper layer and upload it to the control module 3. The control module 3 reduces the volume of soil transported in a single batch when the humidity exceeds the threshold value, and the control module 3 increases the volume of soil transported in a single batch when the humidity is lower than the threshold value;
[0035] Specifically, the soil humidity sensor is used to detect the humidity S of the backfill soil of the upper layer and upload it to the control module 3. The control module 3 instructs the hopper 2 to batch-transport soil with a volume of V×A1×A2 to one side of the transport vehicle 1, where A2 = S0 / S×d, d is a pre-input constant, S≥S0, and when the detection result shows S < S0, S = S0 is taken;
[0036] When the soil moisture is high, the filling thickness of each layer needs to be reduced to ensure that the relatively soft soil with high moisture is fully compacted. At this time, the value of A2=S0 / S×d is low. When the control module 3 instructs the hopper 2 to transport the soil with a volume of V×A1×A2 in batches to one side of the transport vehicle 1, the filling thickness of each layer is corrected downward when the humidity is high to ensure that the relatively soft soil with high moisture is fully compacted.
[0037] When the soil moisture is low, there is no need to reduce the thickness of each layer of fill to ensure construction efficiency. At this time, the value of A2=S0 / S×d is high. When the control module 3 instructs the hopper 2 to transport the soil with a volume of V×A1×A2 in batches to one side of the transport vehicle 1, the thickness of each layer of fill is corrected upward when the humidity is high, ensuring that the humidity is low and the construction efficiency is improved without the need for full tamping;
[0038] By setting up humidity sensors to detect the soil and reducing the filling thickness when the soil humidity is high after filling, it is ensured that the relatively soft soil with high humidity is fully compacted, thereby improving the filling effect and improving the construction efficiency when the humidity is low and there is no need for full compaction.
[0039] During the transportation of soil, when it is not filled into the center dividing belt, there is a probability that the soil will clump in the hopper 2. After the clumped soil is filled into the center dividing belt, under the protection of other soils, the force of the tamping machine on the clumps cannot break the clumps, and the clumped soil is likely to be unable to be compacted by the tamping machine, affecting the filling effect. For this reason, the hopper 2 includes a vibrator, which is used to vibrate the soil in the hopper 2;
[0040] By providing a vibrator to vibrate the soil in the hopper 2, the influence of soil agglomeration on the filling effect is reduced.
[0041] In the above process, when the soil density is low, the agglomerated soil will further reduce the overall filling effect on the basis of the low density, that is, in this case, the filling effect is that the redundancy of the potential agglomerated soil is low, and at this time, it is necessary to further increase the vibration power to reduce the probability of soil agglomeration. When the soil density is high, the filling effect is that the redundancy of the potential agglomerated soil is high, and there is no need for excessively high vibration power to save energy. For this reason, the vibrator is electrically connected to the control module 3, and the control module 3 reduces the power of the vibrator when the density exceeds the threshold, and the control module 3 increases the power of the vibrator when the density is lower than the threshold;
[0042] Specifically, the control module 3 is pre-input with a reference power P0, and the control module 3 adjusts the power of the vibrator to P, where P=M0 / M×e×P0, and e is a pre-input constant;
[0043] When the compaction degree M is high, it means that the filling effect is a high redundancy of potential agglomerated soil, and there is no need for excessively high vibrating power. At this time, the value of P=M0 / M×e×P0 is low. When the control module 3 adjusts the power of the vibrator to P, the vibrating power is reduced when the compaction degree is high and the filling effect is good;
[0044] When the compaction degree M is low, it means that the filling effect in this case is low redundancy of potential agglomerated soil, and the vibration power needs to be further increased. At this time, the value of P=M0 / M×e×P0 is high. When the control module 3 adjusts the power of the vibrator to P, the vibration power is increased when the compaction degree is low and the filling effect is poor;
[0045] By making the control module 3 adjust the vibration power according to the density of the previous layer of fill, the vibration power is reduced when the density is high and the fill effect is that the redundancy of the potential agglomerated soil is high, and an excessively high vibration power is not needed; the vibration power is increased when the fill effect is that the redundancy of the potential agglomerated soil is low and the vibration power needs to be further increased.
[0046] In order to facilitate the input of constants such as M0, c, d, S0, M0 and e, a control panel is also included. The control panel is electrically connected to the control module 3 and is used to input the values of M0, c, d, S0, M0 and e.
[0047] The working principle and use process of the present invention:
[0048] The hopper 2 pushes the shovel 22 to transport soil in batches to one side of the transport vehicle 1. The detection module is used to detect the density of the previous layer of backfill soil. The control module 3 increases the volume of the soil transported in a single batch when the density exceeds the threshold, and reduces the volume of the soil transported in a single batch when the density is lower than the threshold.
[0049] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. A mid-division belt filling construction equipment, characterized in that: It includes a transport vehicle and a control module. The transport vehicle includes a hopper and a detection module. The hopper is used to transport soil in batches to one side of the transport vehicle. The detection module is used to detect the compaction degree of the upper layer of backfill soil after ramming. The control module is electrically connected to the hopper and the detection module respectively. When the compaction degree exceeds a threshold value, the control module increases the volume of the soil transported in a single batch. When the compaction degree is lower than the threshold value, the control module reduces the volume of the soil transported in a single batch.
2. A center-dividing belt filling construction equipment according to claim 1, characterized in that: The control module is pre-input with a compaction threshold M0, the detection module is used to detect the compaction degree M of the previous layer of backfill soil after ramming and upload it to the control module, and the control module instructs the hopper to transport soil with a volume of V×A1 in batches to one side of the transport vehicle, where A1=M / M0×c, and c is a pre-input constant.
3. A center-dividing belt filling construction equipment according to claim 2, characterized in that: The detection module also includes a soil moisture sensor, which is used to detect the moisture of the previous layer of backfill soil and upload it to the control module. The control module reduces the volume of the soil transported in a single batch when the humidity exceeds a threshold, and increases the volume of the soil transported in a single batch when the humidity is lower than the threshold.
4. A center-dividing belt filling construction equipment according to claim 3, characterized in that: The soil moisture sensor is used to detect the moisture S of the upper layer of backfill soil and upload it to the control module. The control module instructs the hopper to transport soil with a volume of V×A1×A2 in batches to one side of the transport vehicle, where A2=S0 / S×d, and d is a pre-input constant.
5. The center-dividing belt filling construction equipment according to claim 1 is characterized in that: The hopper includes a vibrator for applying vibrations to the soil in the hopper.
6. A center-dividing belt filling construction equipment according to claim 5, characterized in that: The vibrator is electrically connected to a control module, and the control module reduces the power of the vibrator when the density exceeds a threshold value, and increases the power of the vibrator when the density is lower than the threshold value.
7. A center-dividing belt filling construction equipment according to claim 6, characterized in that: The control module is pre-input with a reference power P0, and the control module adjusts the power of the vibrator to P, wherein P=M0 / M×e×P0, and e is a pre-input constant.
8. The center-dividing belt filling construction equipment according to claim 1 is characterized by: It also includes a control panel, which is electrically connected to the control module and is used to input the values of M0, c, d, S0, M0 and e.
Citation Information
Patent Citations
Middle dividing zone soil filling equipment
CN220598551U