Turbulent flow pipe grid supporting and connecting structure
By using fixed channel steel and limit plate structure in the desulfurization tower, the problem of loosening of turbulent pipe grid components caused by traditional fixation methods is solved, the reliability and stability of the support connection are improved, and the efficient and safe operation of the desulfurization tower is ensured. .
Patent Information
- Application Number
- CN202411740299.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-29
- Publication Date
- 2025-02-18
AI Technical Summary
The traditional fixing method of turbulent pipe grid assembly can easily lead to loosening of bolts, causing a chain reaction, resulting in overall loosening of turbulent pipe grid assembly, affecting the normal operation and safety of the desulfurization tower.
Fixed channel steel and multiple support beams arranged at intervals along their length direction. A screw is provided at the top of the support beam. The screw is arranged in the fixed channel steel. Several groups of symmetrical turbulent pipe grid components are installed on the screw. Tighten the plate, and set limit plates between each two adjacent turbulent pipe grid components in the fixed channel steel.
Through the setting of fixed channel steel and limit plates, the lateral movement of the turbulent pipe grid assembly is limited and mutual constraints are formed, ensuring that even if one of the compression plates is loose, it will not affect other turbulent pipe grid assembly, improving the reliability of supporting connections Sex and stability.
Smart Images

Figure CN119455610A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of desulfurization absorption towers, and in particular to a turbulent pipe grid support connection structure. Background Art
[0002] In the desulfurization process of modern industry, the dual-zone reaction model of the desulfurization tower based on the turbulent liquid holding zone and the spray absorption zone has been widely used. Among them, the turbulent pipe grid device is arranged in the absorption tower as a key component. The turbulent liquid holding zone formed above it can make SO2 be efficiently removed twice in the turbulent liquid holding zone and the spray absorption zone, which is of great significance for improving the desulfurization efficiency and reducing pollutant emissions.
[0003] The traditional way of fixing the turbulent tube grid assembly is usually to directly fix the turbulent tube grid assembly with the help of the fixing bolts and nuts welded on the support beam inside the desulfurization tower. However, in the actual operation process, this fixing method exposes many problems. Due to the harsh working environment, the turbulent tube grid assembly will continue to be subjected to various impacts during operation. These impacts directly act on the fixing bolts. Over time, it is very easy to cause the bolts to loosen. Once some bolts are loose, a chain reaction will be triggered, which may cause several turbulent tube grid assemblies to loosen as a whole. When this happens, the outer wall of the absorption tower will vibrate violently, which will not only affect the normal operation of the desulfurization tower and reduce the desulfurization effect, but also may damage the overall structure of the desulfurization tower, bringing safety hazards. Moreover, during the operation of the desulfurization tower, it is difficult to directly and effectively eliminate this hidden danger, which brings great challenges to the continuity and stability of industrial production. Therefore, it is urgent to develop a more reliable and stable turbulent tube grid support connection structure to overcome the deficiencies in the existing technology and ensure the efficient and safe operation of the desulfurization tower. Summary of the invention
[0004] The object of the present invention is to provide a turbulence tube grid support connection structure to improve the integrity of multiple groups of turbulence tube grid components and improve the reliability of turbulence tube grid support.
[0005] The present invention provides a turbulence tube grid support connection structure, comprising a fixed channel steel and a plurality of support beams spaced apart along the length direction thereof, a screw rod is provided at the top end of the support beam, the screw rod is passed through the fixed channel steel, a plurality of groups of mutually symmetrical turbulence tube grid assemblies are arranged along the length direction of the fixed channel steel, a clamping plate for clamping the turbulence tube grid assemblies is installed on the screw rod, a limiting plate is provided between each two adjacent groups of the turbulence tube grid assemblies in the fixed channel steel, the limiting plate is passed through the screw rod.
[0006] Furthermore, each group of the turbulence tube grid assemblies includes two mounting slot frames symmetrically installed in the fixed channel steel, and multiple turbulence tubes are fixedly installed on the outer side of each mounting slot frame, and the ends of the multiple turbulence tubes are fixedly installed on the mounting slot frame at equal intervals; the bottom end of the mounting slot frame is pressed between the fixed channel steel and the clamping plate near the screw rod.
[0007] Furthermore, a connecting plate is welded to one side of the two symmetrically installed mounting slot frames away from the support beam.
[0008] Furthermore, the bottom end of the screw rod is welded to the top end of the support beam.
[0009] Furthermore, the thickness of the limiting plate is the same as the thickness of the mounting slot frame.
[0010] Furthermore, the mounting slot frame of the turbulent tube grid assembly close to one end of the absorption tower wall is clamped on the screw rod through two clamping plates, and a supporting rib plate for supporting the screw rod is fixedly installed on the absorption tower wall.
[0011] Furthermore, a pad is provided between the fixed channel steel and the support beam, and the pad is passed through the screw rod.
[0012] Furthermore, a fastening nut is mounted on the screw rod in cooperation with the top end of the clamping plate.
[0013] Furthermore, the pad is made of PP material.
[0014] Furthermore, a plurality of the support beams are arranged at equal intervals along the length direction of the fixed channel steel.
[0015] The beneficial effects of the present technical solution are as follows: in the present solution, the fixed channel steel limits the lateral movement of the turbulence tube grid assembly by means of slotting, and by providing a limit plate between every two adjacent groups of turbulence tube grid assemblies in the fixed channel steel, mutual constraints are formed between the multiple groups of turbulence tube grid assemblies, and even if one clamping plate is loose, other turbulence tube grid assemblies will not be affected due to the provision of the fixed channel steel and the limit plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0017] Figure 1 This is a diagram of the connection structure between the support beam and the turbulence tube grid assembly in the present invention.
[0018] Figure 2 It is a partial top view of the turbulence tube grid support connection structure of the present invention.
[0019] Figure 3 This is a structural diagram of the connection between the turbulent tube grid assembly and the absorption tower wall in the present invention.
[0020] Figure 4 It is a side view of the local structure of the turbulence tube grid support connection structure in the present invention.
[0021] Explanation of the reference numerals: 1-support beam, 2-turbulence tube grid assembly, 201-mounting trough frame, 202-turbulence tube, 3-fixing channel steel, 4-screw, 5-pad, 6-pressure plate, 7-fastening nut, 8-limiting plate, 9-support rib plate. DETAILED DESCRIPTION
[0022] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0023] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0024] In addition, the terms "first" and "second" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, "multiple" means two or more, unless otherwise clearly and specifically defined. In addition, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal connection of two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0025] Example 1
[0026] like Figure 1-Figure 4 As shown, the present invention provides a turbulence tube grid support connection structure, including a fixed channel steel 3 and a plurality of support beams 1 arranged at intervals along the length direction thereof, the plurality of support beams 1 being arranged at equal intervals along the length direction of the fixed channel steel 3, a screw rod 4 being welded to the top end of the support beam 1, the screw rod 4 being inserted into the fixed channel steel 3, a plurality of groups of mutually symmetrical turbulence tube grid assemblies 2 being erected along the length direction of the fixed channel steel 3, each group of turbulence tube grid assemblies 2 including two mounting slot frames 201 symmetrically mounted in the fixed channel steel 3, a plurality of turbulence tubes 202 being fixedly mounted on the outer side of each mounting slot frame 201, the ends of the plurality of turbulence tubes 202 being fixedly mounted on the mounting slot frame 201 at equal intervals; a clamping plate 6 for clamping the turbulence tube grid assembly 2 is mounted on the screw rod 4, the bottom end of the mounting slot frame 201 close to the screw rod 4 is compressed between the fixed channel steel 3 and the clamping plate 6, a fastening nut 7 is mounted on the screw rod 4 at the top end of the clamping plate 6 for fastening the clamping plate 6. In order not to affect the pressing plate 6 pressing the installation slot frame 201 , in this embodiment, the thickness of the limiting plate 8 is the same as the thickness of the installation slot frame 201 .
[0027] In order to stabilize the two mutually symmetrical groups of turbulent tube grid assemblies 2, a connecting plate is welded to the side of the two symmetrically installed mounting slot frames 201 away from the support beam 1, and the connecting plate is welded to the two mounting slot frames 201 respectively.
[0028] A limit plate 8 is provided between each two adjacent groups of turbulence tube grid assemblies 2 in the fixed channel steel 3. The limit plate 8 is passed through the screw rod 4. The limit plate 8 can be a cross-shaped or T-shaped structure, which is selected according to the setting position of the turbulence tube grid assembly 2. At the same time, the opening size of the limit plate 8 and the screw rod 4 should take into account the offset distance of the limit plate 8 to protect the screw rod 4 from being directly impacted by the turbulence tube grid assembly 2.
[0029] The mounting slot frame 201 of the turbulent tube grid assembly 2 close to one end of the absorption tower wall is clamped on the screw rod 4 through two clamping plates 6, and a supporting rib plate 9 for supporting the screw rod 4 is fixedly installed on the absorption tower wall.
[0030] A pad 5 made of PP material is provided between the fixed channel steel 3 and the support beam 1. The pad 5 is inserted into the screw 4. The fixed channel steel 3 is damped by the pad 5. At the same time, the frequently vibrating turbulent grid assembly 2 is damped by the fixed channel steel 3, thereby reducing the impact strength of the anti-corrosion layer on the support beam 1.
[0031] In the present embodiment, the fixed channel steel 3 limits the lateral movement of the turbulence tube grid assembly 2 by means of slotting, and by providing a limit plate 8 between every two adjacent groups of turbulence tube grid assemblies 2 in the fixed channel steel 3, mutual constraints are formed between the multiple groups of turbulence tube grid assemblies 2. Even if one clamping plate 6 is loose, the other turbulence tube grid assemblies 2 will not be affected due to the provision of the fixed channel steel 3 and the limit plate 8.
[0032] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A turbulence tube grid support connection structure, characterized in that: It comprises a fixed channel steel and a plurality of support beams spaced apart along its length direction, a screw is provided at the top end of the support beam, the screw is passed through the fixed channel steel, a plurality of groups of mutually symmetrical turbulence tube grid assemblies are arranged along the length direction of the fixed channel steel, a clamping plate for clamping the turbulence tube grid assemblies is installed on the screw; a limit plate is provided between each two adjacent groups of the turbulence tube grid assemblies in the fixed channel steel, the limit plate is passed through the screw.
2. The turbulence tube grid support connection structure according to claim 1, characterized in that: Each group of the turbulence tube grid assemblies includes two mounting slot frames symmetrically installed in the fixed channel steel, and multiple turbulence tubes are fixedly installed on the outer side of each mounting slot frame, and the ends of the multiple turbulence tubes are fixedly installed on the mounting slot frame at equal intervals; the bottom end of the mounting slot frame is pressed between the fixed channel steel and the clamping plate near the screw rod.
3. The turbulence tube grid support connection structure according to claim 2, characterized in that: A connecting plate is welded to one side of the two symmetrically installed mounting slot frames away from the support beam.
4. The turbulence tube grid support connection structure according to claim 2, characterized in that: The thickness of the limiting plate is the same as the thickness of the mounting slot frame.
5. The turbulence tube grid support connection structure according to claim 1, characterized in that: The bottom end of the screw rod is welded to the top end of the support beam.
6. The turbulence tube grid support connection structure according to claim 2, characterized in that: The mounting slot frame of the turbulent tube grid assembly close to one end of the absorption tower wall is clamped on the screw rod through two clamping plates, and a supporting rib plate for supporting the screw rod is fixedly installed on the absorption tower wall.
7. The turbulence tube grid support connection structure according to claim 1, characterized in that: A pad is provided between the fixed channel steel and the support beam, and the pad is passed through the screw rod.
8. The turbulence tube grid support connection structure according to claim 1, characterized in that: A fastening nut is mounted on the screw rod at the top end of the pressing plate.
9. The turbulence tube grid support connection structure according to claim 7, characterized in that: The backing plate is made of PP material.
10. The turbulence tube grid support connection structure according to claim 1, characterized in that: The plurality of support beams are arranged at equal intervals along the length direction of the fixed channel steel.
Citation Information
Patent Citations
Quickly-assembled reinforced green building formwork
CN111809859A
Fabricated building curtain wall and assembling method thereof
CN116556560A
Energy-saving desulfurization effect-improving device
CN209254482U
Turbulence device used in wet desulphurization absorption tower
CN214598122U
Building curtain wall connecting mechanism
CN216973754U