Bridge dynamic construction and resource allocation method based on BIM technology

By using BIM technology to establish dynamic construction and resource allocation methods in bridge construction, the problems of lag in construction progress adjustment and low resource turnover are solved, and more efficient construction progress control and resource management are achieved.

CN119578757APending Publication Date: 2025-03-07CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411591994.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-08
Publication Date
2025-03-07

AI Technical Summary

Technical Problem

During the bridge construction process, due to the complex and changeable construction conditions, there is a lag in the construction organization design based on the actual progress of the site, resulting in low turnover efficiency of resources such as machinery and materials.

Method used

Using the dynamic construction and resource allocation method of bridges based on BIM technology, by establishing a bridge BIM model in the BIM system, the bridge is divided into multiple components, the construction process is divided and the project quantity is counted, the construction progress plan and the project quota requirement plan are automatically generated, and dynamic adjustments are made according to the actual construction progress to realize resource allocation.

Benefits of technology

Through refined BIM models and dynamic adjustment plans, the real-time construction progress and resource turnover utilization rate are improved, planning lag is avoided, and construction efficiency and resource management are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119578757A_ABST
    Figure CN119578757A_ABST
Patent Text Reader

Abstract

The invention relates to a BIM technology-based bridge dynamic construction and resource allocation method. The method comprises the steps of establishing a BIM model of a bridge in a BIM system, dividing the bridge into a plurality of components, dividing construction procedures, and performing engineering quantity statistics; inputting the construction process, the theoretical time length and the connection sequence of each component in the BIM system, and automatically generating a bridge project construction progress plan; determining a corresponding project quota, inputting the project quota of each process in the BIM system, and automatically generating a project quota demand plan; correcting and dynamically adjusting the bridge project construction progress plan and the project quota demand plan according to the actual construction progress; and allocating resources according to the bridge project construction progress plan and the project quota demand plan. According to the BIM technology-based bridge dynamic construction and assembly and resource allocation method provided by the invention, the whole construction period is controlled based on the BIM technology, and the theoretical plan is dynamically adjusted according to the input actual construction progress condition, so that plan lag is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge construction, and in particular to a bridge dynamic assembly and resource allocation method based on BIM technology. Background Art

[0002] At present, with the continuous development of bridge technology, the complexity of bridge structure and construction is increasing. The entire bridge construction process is usually divided into multiple processes, each of which involves corresponding engineering quotas, such as personnel, machinery, and material inputs, and different processes are connected in time. When dealing with complex bridge construction, due to the complex and changeable construction conditions, the construction organization design is adjusted according to the actual progress of the site. For example, if the execl table is used, due to the mutual influence between different processes and engineering quotas, the adjustment is only made through the execl table. Not only is the process complicated, but it is also relatively lagging, which leads to low efficiency in the turnover of resources such as machinery and materials between different projects. Summary of the invention

[0003] The present application provides a method for dynamic bridge construction and resource allocation based on BIM technology, which solves the technical problems of delayed construction adjustment according to actual progress and low resource turnover rate in related technologies.

[0004] The present application embodiment provides a bridge dynamic construction and resource allocation method based on BIM technology, which includes the following steps:

[0005] Establishing a BIM model of the bridge in the BIM system, dividing the bridge into multiple components according to the BIM model, dividing the construction process of each component, and performing engineering quantity statistics;

[0006] Enter the construction process, theoretical duration and connection sequence of each component into the BIM system to automatically generate a construction schedule for the bridge project;

[0007] Determine the corresponding engineering quota according to the engineering quantity of each component, enter the engineering quota of each process into the BIM system, and automatically generate an engineering quota demand plan in combination with the construction schedule of the bridge project;

[0008] The construction schedule and engineering quota demand plan of the bridge project are revised according to the actual construction progress, and the construction schedule and engineering quota demand plan of the bridge project are dynamically adjusted;

[0009] Resources are allocated according to the bridge project construction schedule and engineering quota demand plan.

[0010] In one embodiment, the engineering quantity statistics are performed by sub-items of the project.

[0011] In one embodiment, the components of the bridge include at least pile foundations, abutments, piers, main towers, main beams, and cable-stayed cables.

[0012] In one embodiment, the bridge project construction schedule and the engineering quota demand plan are modified according to the actual construction progress, and the bridge project construction schedule and the engineering quota demand plan are dynamically adjusted, including:

[0013] The actual construction time of the previous process is entered into the BIM system to dynamically generate the bridge project construction schedule and engineering quota demand plan for the next process.

[0014] In one implementation, when the actual construction time of the previous process is entered into the BIM system, the actual start time and the actual completion time of the process are entered on a daily basis to correct the theoretical duration.

[0015] In one embodiment, allocating resources according to the revised construction schedule and engineering quota requirement plan of the bridge project includes:

[0016] Establishing a resource waiting library in the BIM system;

[0017] Determine the idle resources of a project according to the revised construction schedule of the bridge project and the engineering quota demand plan, and enter the idle resources into the resource waiting to be transferred library;

[0018] The required resources are determined based on the revised construction schedule of the bridge project and the engineering quota demand plan of other projects, and the resources are automatically matched through the resource pool.

[0019] In one embodiment, the resource waiting library includes a company-level proprietary equipment library and a company-owned material library.

[0020] In one implementation, when automatically matching resources, the matching priority is determined based on the distance.

[0021] In one implementation, the closer the distance between the resource and the project, the higher the priority.

[0022] In one embodiment, the dynamic construction and resource allocation method for bridges based on BIM technology also includes: classifying and entering the total contract price corresponding to each process, and automatically generating actual output value statistics based on the actual construction progress of each process.

[0023] The beneficial effects brought by the technical solution provided in the embodiments of the present application include:

[0024] The present application provides a method for dynamic construction and resource allocation of bridges based on BIM technology. The entire construction period is controlled based on BIM technology. The bridge is divided into multiple components through a refined BIM model. The construction process, theoretical duration, connection sequence and engineering quota of each component are then entered into the BIM system. The construction schedule plan and engineering quota demand plan of the bridge project are automatically generated, and refined statistics are realized. The theoretical plan is dynamically adjusted according to the actual construction progress entered. The operation is more convenient and real-time, and the plan is avoided from being delayed. At the same time, resources can be allocated simultaneously to improve the turnover utilization rate of equipment and materials. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0026] Figure 1 It is a flowchart of a method for dynamic bridge construction and resource allocation based on BIM technology in one embodiment of the present invention. DETAILED DESCRIPTION

[0027] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0028] The embodiment of the present application provides a method for dynamic bridge construction and resource allocation based on BIM technology, which can solve the technical problems of delayed construction adjustment according to actual progress and low resource turnover rate in related technologies.

[0029] Reference Figure 1 As shown, Figure 1 It is a flowchart of a method for dynamic bridge construction and resource allocation based on BIM technology in one embodiment of the present invention.

[0030] This embodiment provides a bridge dynamic construction and resource allocation method based on BIM technology, which includes the following steps:

[0031] Step S1, establishing a BIM model of the bridge in the BIM system, dividing the bridge into multiple components according to the BIM model, dividing the construction process of each component, and performing engineering quantity statistics;

[0032] Step S2: input the construction process, theoretical duration and connection sequence of each component into the BIM system to automatically generate a construction schedule for the bridge project;

[0033] Step S3: Determine the corresponding engineering quota according to the engineering quantity of each component, enter the engineering quota of each process into the BIM system, and automatically generate the engineering quota demand plan in combination with the bridge project construction schedule;

[0034] Step S4: modifying the bridge project construction schedule and the engineering quota demand plan according to the actual construction progress, and dynamically adjusting the bridge project construction schedule and the engineering quota demand plan;

[0035] Step S5: Allocate resources according to the bridge project construction schedule and engineering quota demand plan.

[0036] This embodiment provides a method for dynamic construction and resource allocation of bridges based on BIM technology. The entire construction period is controlled based on BIM technology. The bridge is divided into multiple components through a refined BIM model. The construction process, theoretical duration, connection sequence and engineering quota of each component are entered into the BIM system. The bridge project construction schedule and engineering quota demand plan are automatically generated, and refined statistics are achieved. The theoretical plan is dynamically adjusted according to the actual construction progress entered, which makes the operation more convenient and more real-time, avoiding plan delays. At the same time, resources can be allocated simultaneously to improve the turnover utilization rate of equipment and materials.

[0037] Each step is described and explained in detail below.

[0038] The meanings of some nouns are as follows:

[0039] BIM: The definition of BIM by the International BIM Alliance (BuildingSMARTInternational) is:

[0040] BIM is an abbreviation of the English phrase, which stands for three different but interrelated functions.

[0041] Building Information Modeling (BIM) is a business process that generates building information and applies it to the design, construction and operation of a building, allowing stakeholders to access the same information simultaneously through the interoperability of different technology platforms.

[0042] Building Information Model (BIM): It is a digital expression of the physical and functional characteristics of a facility. It can be used as a source of information knowledge shared by relevant stakeholders of the facility and become a reliable basis for decision-making throughout the life cycle of the facility, including planning.

[0043] Building Information Management (BIM): It is the organization and control of business processes by using information in digital models, with the aim of improving the effectiveness of information sharing throughout the life cycle of assets. Its benefits include centralized and intuitive communication, early comparison of options, sustainability, effective design, professional integration, site control, completion data, etc., which can be used to effectively develop processes and models for the entire life cycle of assets from planning to retirement.

[0044] Project quota: refers to the quantity standards of labor, materials, construction machinery and equipment, construction days and related rates required to complete a qualified construction and installation project of specified measurement units under normal construction conditions.

[0045] Sub-item project: A sub-item project is a component of a single or unit project, which is a project that divides a single or unit project into several sub-items according to structural parts, road section length, construction characteristics or construction tasks; a sub-item project is a component of a sub-item project, which is a project that divides a sub-item project into several sub-items or projects according to different construction methods, materials, processes and road section lengths. It is the smallest construction project that cannot be divided any further.

[0046] In one embodiment, in step S1, the engineering quantity statistics are performed by engineering quantity statistics according to the sub-items of the project.

[0047] Through the above scheme, the engineering quantity statistics are carried out by dividing the project into parts and sub-items, and the engineering quantity statistics are more detailed, which is convenient for better organization of construction and management.

[0048] In one embodiment, in step S1, the components of the bridge include at least pile foundations, abutments, piers, main towers, main beams, and cable stays.

[0049] Through the above scheme, the bridge is divided into various main components. Of course, in other embodiments, the bridge can also be divided into more components or other forms according to actual conditions. The finer the division, the more accurate and detailed the subsequent calculation resources will be.

[0050] In step S2, the construction procedures of each component are sorted in order and then entered, and the preceding and succeeding procedures are set. The theoretical duration can be determined based on existing engineering experience, and the automatically generated bridge project construction schedule is a theoretical plan.

[0051] In step S3, when determining the corresponding engineering quota according to the engineering quantity of each component, the amount of personnel, machinery, and materials required for the engineering quantity of each process are calculated according to the corresponding specifications as resource input; when automatically generating the engineering quota demand plan in combination with the bridge project construction schedule, the plan can be generated by year, month, day or other requirements.

[0052] In one embodiment, in step S4, the bridge project construction schedule and the engineering quota demand plan are revised according to the actual construction progress, and the dynamic adjustment of the bridge project construction schedule and the engineering quota demand plan includes:

[0053] The actual construction time of the previous process is entered into the BIM system to dynamically generate the bridge project construction schedule and engineering quota demand plan for the next process.

[0054] Through the above scheme, the construction schedule of the bridge project can be dynamically adjusted according to the actual construction progress, and the engineering quota demand plan can be dynamically adjusted synchronously. The corresponding resource requirements such as personnel, machinery, and materials can be automatically calculated and counted synchronously.

[0055] In one embodiment, when the actual construction time of the previous process is entered into the BIM system, the actual start time and the actual completion time of the process are entered on a daily basis to correct the theoretical duration.

[0056] Through the above solution, the actual start time and actual completion time of the process are entered on a daily basis, and the actual construction time is controlled more accurately, which helps to improve the efficiency of the overall construction period control.

[0057] In one embodiment, step S5, allocating resources according to the revised bridge project construction schedule and engineering quota demand plan, includes:

[0058] Step S51, establishing a resource waiting library in the BIM system;

[0059] Step S52: determining the idle resources of a certain project according to the revised bridge project construction schedule and engineering quota demand plan, and entering the idle resources into the resource waiting to be transferred library;

[0060] Step S53: Determine the required resources based on the revised bridge project construction schedule and engineering quota demand plan of other projects, and automatically match the resources through the resource to-be-adjusted library.

[0061] Through the above solution, resources are automatically matched according to the dynamically adjusted bridge project construction schedule and engineering quota demand plan, which improves the turnover utilization rate of resources, enables the scheduling of materials across projects and subsidiaries, and reduces costs.

[0062] In one embodiment, the resource waiting library includes a company-level self-owned equipment library and a company-owned material library.

[0063] In one embodiment, when automatically matching resources, the matching priority is determined according to the distance. Of course, in other embodiments, other priority principles can also be adopted.

[0064] In one embodiment, the closer the resource is to the project, the higher the priority.

[0065] Through the above scheme, the regulation cost can be effectively controlled because the shorter the distance, the lower the freight.

[0066] In one embodiment, the method for dynamic bridge construction and resource allocation based on BIM technology also includes: classifying and entering the total contract price corresponding to each process, and automatically generating actual output value statistics based on the actual construction progress of each process.

[0067] The above scheme will help to count the completed project volume and actual output value and better organize the construction.

[0068] It should be noted that the above-mentioned serial numbers of the embodiments of the present application are only for description and do not represent the advantages and disadvantages of the embodiments. The terms "including" and "having" in the specification and claims of the present application and the above-mentioned drawings and any of their variations are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device comprising a series of steps or units is not limited to the listed steps or units, but optionally also includes steps or units that are not listed, or optionally also includes other steps or units inherent to these processes, methods, products or devices. The terms "first", "second" and "third" and the like are described to distinguish different objects, etc., and do not represent the order of precedence, nor do they limit that "first", "second" and "third" are different types.

[0069] In the description of the embodiments of the present application, "exemplary", "for example" or "for example" are used to indicate examples, illustrations or descriptions. Any embodiment or design described as "exemplary", "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "exemplary", "for example" or "for example" is intended to present related concepts in a specific way.

[0070] In the description of the embodiments of the present application, unless otherwise specified, “ / ” means or, for example, A / B can mean A or B; the “and / or” in the text is merely a description of the association relationship of associated objects, indicating that three relationships may exist, for example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone. In addition, in the description of the embodiments of the present application, “multiple” refers to two or more than two.

[0071] In some processes described in the embodiments of the present application, multiple operations or steps that appear in a specific order are included, but it should be understood that these operations or steps may not be executed in the order in which they appear in the embodiments of the present application or in parallel, and the sequence number of the operation is only used to distinguish between different operations, and the sequence number itself does not represent any execution order. In addition, these processes may include more or fewer operations, and these operations or steps may be executed in sequence or in parallel, and these operations or steps may be combined.

[0072] The above are only preferred embodiments of the present application, and are not intended to limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made using the contents of the present application specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present application.

Claims

1. A bridge dynamic construction and resource allocation method based on BIM technology, characterized in that: It includes the following steps: Establishing a BIM model of the bridge in the BIM system, dividing the bridge into multiple components according to the BIM model, dividing the construction process of each component, and performing engineering quantity statistics; Enter the construction process, theoretical duration and connection sequence of each component into the BIM system to automatically generate a construction schedule for the bridge project; Determine the corresponding engineering quota according to the engineering quantity of each component, enter the engineering quota of each process into the BIM system, and automatically generate the engineering quota demand plan in combination with the construction schedule of the bridge project; The construction schedule and engineering quota demand plan of the bridge project are revised according to the actual construction progress, and the construction schedule and engineering quota demand plan of the bridge project are dynamically adjusted; Resources are allocated according to the bridge project construction schedule and engineering quota demand plan.

2. The method for dynamic bridge construction and resource allocation based on BIM technology as claimed in claim 1, characterized in that: The engineering quantity statistics mentioned above refers to the engineering quantity statistics according to the sub-projects.

3. The method for dynamic bridge construction and resource allocation based on BIM technology as claimed in claim 1, characterized in that: The components of the bridge at least include pile foundations, abutments, piers, main towers, main beams, and inclined cables.

4. The method for dynamic bridge construction and resource allocation based on BIM technology as claimed in claim 1, characterized in that: The said modifying the bridge project construction schedule and the engineering quota demand plan according to the actual construction progress, and dynamically adjusting the bridge project construction schedule and the engineering quota demand plan comprises: The actual construction time of the previous process is entered into the BIM system to dynamically generate the bridge project construction schedule and engineering quota demand plan for the next process.

5. The method for dynamic bridge construction and resource allocation based on BIM technology as claimed in claim 4, characterized in that: When entering the actual construction time of the previous process in the BIM system, the actual start time and actual completion time of the process are entered on a daily basis to correct the theoretical duration.

6. The method for dynamic bridge construction and resource allocation based on BIM technology as claimed in claim 1, characterized in that: The resource allocation according to the revised construction schedule and engineering quota requirement plan of the bridge project includes: Establishing a resource waiting library in the BIM system; Determine the idle resources of a project according to the revised construction schedule of the bridge project and the engineering quota demand plan, and enter the idle resources into the resource waiting to be transferred library; The required resources are determined based on the revised construction schedule of the bridge project and the engineering quota demand plan of other projects, and the resources are automatically matched through the resource pool.

7. The method for dynamic bridge construction and resource allocation based on BIM technology as claimed in claim 6, characterized in that: The resource waiting library includes the company-level self-owned equipment library and self-owned material library.

8. The method for dynamic bridge construction and resource allocation based on BIM technology as claimed in claim 6, characterized in that: When automatically matching resources, the matching priority is determined based on distance.

9. The method for dynamic bridge construction and resource allocation based on BIM technology as claimed in claim 8, characterized in that: The closer the resource is to the project, the higher the priority.

10. The method for dynamic bridge construction and resource allocation based on BIM technology as claimed in claim 1, characterized in that: The method for dynamic bridge construction and resource allocation based on BIM technology also includes: classifying and entering the total contract price corresponding to each process, and automatically generating actual output value statistics based on the actual construction progress of each process.

Citation Information

Cited By

  • Five-dimensional mapping adaptive progress regulation and control system and method for electromechanical engineering of data center

    CN120725405A

  • Bridge construction progress management method and system based on BIM

    CN121168943A