Totally-closed assembled sound insulation barrier for tunnel engineering and mounting method of totally-closed assembled sound insulation barrier
Through the design of a fully enclosed assembled sound insulation barrier, the combination of V-shaped grooves and fixed steel ropes of the fixed base layer is solved, and the existing tunnel sound insulation barrier is low in degree and difficult to install, achieving efficient installation and fitting effect.
Patent Information
- Application Number
- CN202510033311.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-09
- Publication Date
- 2025-03-14
AI Technical Summary
The existing sound insulation barriers in the tunnel are usually integrated structures and have low modularity, which leads to transportation difficulties and increases transportation costs. At the same time, since the top of the tunnel is arc-shaped, the existing sound insulation barriers are consistent in arc and cannot fit closely with the top of the tunnel, resulting in installation difficulties.
A fully enclosed assembled sound insulation barrier is adopted, including sound insulation layer, fixed base layer, fixed steel rope, limit buckle and positioning nail. It is divided into multiple trapezoidal blocks through the V-shaped groove of the fixed base layer. The combination of fixed steel rope and limit buckle is used to achieve the connection and fixation of multiple trapezoidal blocks, which can closely fit the top of the arc tunnel.
The high modularity of sound insulation barrier is achieved, which is easy to install and transport. At the same time, through the design of the V-shaped groove, it can better fit the top of the tunnel, solving the problem of difficulty in installing the existing sound insulation barrier.
Smart Images

Figure CN119616545A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel sound insulation barriers, and in particular to a fully enclosed assembled sound insulation barrier for tunnel engineering and an installation method thereof. Background Art
[0002] Tunnel engineering is an inevitable part of modern urban construction. It plays an important role in transportation, water supply, gas supply and other fields. However, the noise and vibration generated by the tunnel after it is opened to traffic often cause discomfort to the surrounding residents. Usually, a barrier for sound insulation is installed in the tunnel. However, the current tunnel sound insulation barrier is usually an integrated structure, which is non-detachable and has a low degree of modularization, which makes transportation difficult and increases a lot of transportation costs. In addition, since the top of the tunnel is curved, the existing sound insulation barrier has a consistent curvature and cannot fit tightly to the top of the tunnel, which makes installation difficult. Therefore, in order to solve the above problems, a fully enclosed assembled sound insulation barrier and an installation method for a tunnel project are provided. Summary of the invention
[0003] In view of the deficiencies in existing tunnel noise barrier technology, the purpose of the present invention is to provide a fully enclosed assembled noise barrier and installation method for tunnel engineering, which has the advantages of high modularity and easy installation.
[0004] To achieve the above-mentioned purpose, a technical solution adopted by the present invention is: a fully enclosed assembled sound insulation barrier for tunnel engineering, comprising a sound insulation layer, a shaping base layer, a shaping steel rope, a limit buckle and a positioning nail, wherein a sound insulation layer is provided on one side of the shaping base layer, and a plurality of V-shaped grooves are provided on the end surface of the other side of the shaping base layer, wherein the V-shaped grooves divide the shaping base layer into a plurality of trapezoidal blocks, wherein the shaping steel rope is arranged in the shaping base layer, wherein the middle part of the shaping steel rope is fixed to the middle part of the shaping base layer, and the two ends of the shaping steel rope slide axially in the shaping base layer, wherein the shaping steel rope is used to connect a plurality of trapezoidal blocks, and the end surfaces of the plurality of trapezoidal blocks are all provided with limit buckles for fixing the shaping steel rope, wherein the positioning nail is arranged at the center of the end surface of the shaping base layer and passes through the sound insulation layer, wherein a recessed positioning hole is provided on one side of the shaping base layer, and a protruding positioning pin is provided on the other side of the shaping base layer;
[0005] Preferably, the outer edge of the positioning pin also has a limiting ring protruding from the positioning pin body;
[0006] Preferably, the sound insulation layer is made of a tough material;
[0007] Preferably, the inner wall of the positioning hole further has a concave annular groove, and the annular groove is used to engage with the limiting ring on the outer edge of the positioning pin;
[0008] Preferably, the middle part of the limit buckle has a through hole for inserting the shaping steel rope, the end of the limit buckle extending out of the shaping base layer has a flange head, and the end of the limit buckle extending into the shaping base layer has an embedded pin;
[0009] Preferably, the trapezoidal block in the shaping base layer has an embedding groove corresponding to the insertion position of the limit buckle, the embedding groove is used to embed the embedding pin, and the embedding groove is used to fix the limit buckle in the shaping base layer to fix the shaping steel rope;
[0010] A method for installing a fully enclosed assembled noise barrier for a tunnel project comprises the following steps:
[0011] S1. Installation location positioning: First, the noise barrier is clamped by the installation fixture, and then the noise barrier is moved to the installation location by the robotic arm;
[0012] S2. Noise barrier splicing: The noise barriers are moved closer to each other by operating the robotic arm, so that the positioning pin on one side of the noise barrier is inserted into the positioning hole on the other side of the noise barrier. At this time, the annular groove in the positioning hole is engaged with the limiting ring on the outer edge of the positioning pin, thereby completing the splicing of the noise barriers;
[0013] S3. Fixing the noise barrier to the wall: The mechanical arm drives the clamp to nail the noise barrier into the wall, so that the positioning nails set at the center of the end surface of the fixed base are nailed into the wall to fix it, so that the noise barrier can fit the wall tightly;
[0014] S4. Shaping of the noise barrier: After the noise barrier is fixed on the wall, since the sound insulation layer is made of a tough material, the V-shaped groove on the end face of the shaping base layer divides the shaping base layer into multiple trapezoidal blocks, so that the noise barrier can fit the tunnel top more closely by squeezing the V-shaped groove. At this time, the pneumatic component on the control fixture is used to push the limit buckle into the shaping base layer, so that the shaping steel rope is relatively fixed to the multiple trapezoidal blocks, and ensure that the V-shaped groove will not rebound after being squeezed;
[0015] The beneficial effects of the present invention are: 1. By inserting the positioning pin on one side of the sound barrier into the positioning hole on one side of the other sound barrier, the annular groove in the positioning hole is engaged with the limiting ring on the outer edge of the positioning pin, thereby realizing the splicing between the sound barriers; 2. A plurality of V-shaped grooves are provided on the end face of the shaping base layer, and the plurality of V-shaped grooves divide the shaping base layer into a plurality of trapezoidal blocks, so that when the sound barrier is attached to the top of the tunnel, it can be squeezed by the V-shaped groove to obtain an effect of better fitting the inner wall of the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a cross-sectional structural view of the present invention;
[0017] Figure 2 This is a cross-sectional structural view of the present invention in an installed state;
[0018] Figure 3 This is a cross-sectional structural view of the top state of the tunnel fitted in the present invention;
[0019] Figure 4 For the present invention Figure 3 A partial magnified view of area I in the middle. DETAILED DESCRIPTION
[0020] The preferred embodiments of the present invention are described in detail below in conjunction with the accompanying drawings so that the advantages and features of the present invention can be more easily understood by those skilled in the art, thereby making a clearer and more definite definition of the protection scope of the present invention.
[0021] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.
[0022] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "provided with", and "set" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be internal communication between two elements. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0023] See also Figures 1 to 4 , the embodiment of the present invention includes:
[0024] A fully enclosed assembled sound insulation barrier for tunnel engineering, comprising a sound insulation layer 1, a shaping base layer 2, a shaping steel rope 3, a limit buckle 4 and a positioning nail 5, wherein the sound insulation layer 1 is provided on one side of the shaping base layer 2, and a plurality of V-shaped grooves 6 are provided on the end surface of the other side of the shaping base layer 2, wherein the V-shaped grooves 6 divide the shaping base layer 2 into a plurality of trapezoidal blocks 21, wherein the shaping steel rope 3 is arranged in the shaping base layer 2, wherein the middle part of the shaping steel rope 3 is fixed to the middle part of the shaping base layer 2, and the two ends of the shaping steel rope 3 slide axially in the shaping base layer 2, wherein the shaping steel rope 3 is used to connect the plurality of trapezoidal blocks 21, and the end surfaces of the plurality of trapezoidal blocks 21 are all provided with a limit buckle 4 for fixing the shaping steel rope 3, wherein the positioning nail 5 is arranged at the center of the end surface of the shaping base layer 2 and passes through the sound insulation layer 1, wherein a recessed positioning hole 7 is provided on one side of the shaping base layer 2, and a protruding positioning pin 8 is provided on the other side of the shaping base layer 2;
[0025] The outer edge of the positioning pin 8 also has a limiting ring 81 protruding from the body of the positioning pin 8;
[0026] The sound insulation layer 1 is made of a tough material;
[0027] The inner wall of the positioning hole 7 also has a concave annular groove 71, and the annular groove 71 is used to be embedded with the limiting ring 81 on the outer edge of the positioning pin 8;
[0028] The middle part of the limit buckle 4 has a through hole for inserting the shaping steel rope 3, the end of the limit buckle 4 extending out of the shaping base layer 2 has a flange head 41, and the end of the limit buckle 4 extending into the shaping base layer 2 has an embedded pin 42;
[0029] The trapezoidal block 21 in the shaping base layer 2 has an embedding groove 22 corresponding to the insertion position of the limit buckle 4, and the embedding groove 22 is used to embed the embedding pin 42. The embedding groove 22 is used to fix the limit buckle 4 in the shaping base layer 2 to fix the shaping steel rope 3;
[0030] A method for installing a fully enclosed assembled noise barrier for a tunnel project comprises the following steps:
[0031] Installation location positioning: First, the noise barrier will be clamped with an installation fixture, and then the noise barrier will be moved to the installation location by a robotic arm;
[0032] Noise barrier splicing: The sound barriers are moved closer to each other by operating the mechanical arm, so that the positioning pin 8 on one side of the sound barrier is inserted into the positioning hole 7 on the other side of the sound barrier. At this time, the annular groove 71 in the positioning hole 7 is engaged with the limiting ring 81 on the outer edge of the positioning pin 8, thereby completing the splicing of the sound barriers;
[0033] The sound insulation barrier is fixed on the wall: the mechanical arm drives the clamp to nail the sound insulation barrier into the wall, so that the positioning nail 5 set at the center of the end surface of the fixed base layer 2 is nailed into the wall to fix it, so that the sound insulation barrier can fit the wall tightly;
[0034] Noise barrier shaping: After the noise barrier is fixed on the wall, since the sound insulation layer 1 is made of a tough material, the V-shaped groove 6 on the end surface of the shaping base layer 2 divides the shaping base layer 2 into a plurality of trapezoidal blocks 21, so that the noise barrier can fit the tunnel top more closely by squeezing the V-shaped groove 6. At this time, the pneumatic component on the control fixture is used to push the limit buckle 4 into the shaping base layer 2, so that the shaping steel rope 3 is relatively fixed to the plurality of trapezoidal blocks 21, and ensures that the squeezed V-shaped groove 6 will not rebound;
[0035] Through the above settings, in the actual working process, its specific working principle is as follows:
[0036] Installation location positioning: First, the noise barrier will be clamped with an installation fixture, and then the noise barrier will be moved to the installation location by a robotic arm;
[0037] Noise barrier splicing: The sound barriers are moved closer to each other by operating the mechanical arm, so that the positioning pin 8 on one side of the sound barrier is inserted into the positioning hole 7 on the other side of the sound barrier. At this time, the annular groove 71 in the positioning hole 7 is engaged with the limiting ring 81 on the outer edge of the positioning pin 8, thereby completing the splicing of the sound barriers;
[0038] The sound insulation barrier is fixed on the wall: the mechanical arm drives the clamp to nail the sound insulation barrier into the wall, so that the positioning nail 5 set at the center of the end surface of the fixed base layer 2 is nailed into the wall to fix it, so that the sound insulation barrier can fit the wall tightly;
[0039] Noise barrier shaping: After the noise barrier is fixed on the wall, since the sound insulation layer 1 is made of a tough material, the V-shaped groove 6 on the end surface of the shaping base layer 2 divides the shaping base layer 2 into a plurality of trapezoidal blocks 21, so that the noise barrier can fit the tunnel top more closely by squeezing the V-shaped groove 6. At this time, the pneumatic component on the control fixture is used to push the limit buckle 4 into the shaping base layer 2, so that the shaping steel rope 3 is relatively fixed to the plurality of trapezoidal blocks 21, and ensures that the squeezed V-shaped groove 6 will not rebound;
[0040] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A fully enclosed assembled noise barrier for tunnel engineering, characterized in that: It includes a sound insulation layer, a shaping base layer, a shaping steel rope, a limit buckle and a positioning nail. A sound insulation layer is provided on one side of the shaping base layer, and a plurality of V-shaped grooves are opened on the end surface of the other side of the shaping base layer. The V-shaped grooves divide the shaping base layer into a plurality of trapezoidal blocks. The shaping steel rope is arranged in the shaping base layer, and the middle part of the shaping steel rope is fixed to the middle part of the shaping base layer. Both ends of the shaping steel rope slide axially in the shaping base layer. The shaping steel rope is used to connect a plurality of trapezoidal blocks. The end surfaces of the plurality of trapezoidal blocks are all provided with limit buckles for fixing the shaping steel rope. The positioning nail is arranged at the center of the end surface of the shaping base layer and passes through the sound insulation layer. A recessed positioning hole is provided on one side of the shaping base layer, and a protruding positioning pin is provided on the other side of the shaping base layer.
2. A fully enclosed assembled noise barrier for tunnel engineering according to claim 1, characterized in that: The outer edge of the positioning pin also has a limiting ring protruding from the positioning pin body.
3. A fully enclosed assembled noise barrier for tunnel engineering according to claim 1, characterized in that: The sound insulation layer is made of a tough material.
4. A fully enclosed assembled noise barrier for tunnel engineering according to claim 1, characterized in that: The inner wall of the positioning hole also has a recessed annular groove, and the annular groove is used to be engaged with the limiting ring on the outer edge of the positioning pin.
5. The fully enclosed assembled noise barrier for tunnel engineering according to claim 1, characterized in that: The middle part of the limit buckle is provided with a through hole for inserting the shaping steel rope, the end of the limit buckle extending out of the shaping base layer is provided with a flange head, and the end of the limit buckle extending into the shaping base layer is provided with an embedding pin.
6. A fully enclosed assembled noise barrier for tunnel engineering according to claim 1, characterized in that: The trapezoidal block in the shaping base layer has an embedding groove corresponding to the insertion position of the limit buckle, and the embedding groove is used to engage the embedding pin. The embedding groove is used to fix the limit buckle in the shaping base layer to fix the shaping steel rope.
7. A method for installing a fully enclosed assembled noise barrier for a tunnel project, comprising the following steps: S1. Installation location positioning: First, the noise barrier is clamped by the installation fixture, and then the noise barrier is moved to the installation location by the robotic arm; S2. Noise barrier splicing: The noise barriers are moved closer to each other by operating the robotic arm, so that the positioning pin on one side of the noise barrier is inserted into the positioning hole on the other side of the noise barrier. At this time, the annular groove in the positioning hole is engaged with the limiting ring on the outer edge of the positioning pin, thereby completing the splicing of the noise barriers; S3. Fixing the noise barrier to the wall: The mechanical arm drives the clamp to nail the noise barrier into the wall, so that the positioning nails set at the center of the end surface of the fixed base are nailed into the wall to fix it, so that the noise barrier can fit the wall tightly; S4. Shaping of the sound barrier: After the sound barrier is fixed on the wall, since the sound insulation layer is made of tough material, the V-shaped groove on the end face of the shaping base layer divides the shaping base layer into multiple trapezoidal blocks, so that the sound barrier can fit the tunnel top more closely by extruding the V-shaped groove. At this time, the pneumatic component on the control fixture is used to push the limit buckle into the shaping base layer, so that the shaping steel rope is relatively fixed to the multiple trapezoidal blocks, and ensure that the V-shaped groove will not rebound after being extruded.