Prefabricated pier column assembly type steam curing cover
Through prefabricated assembled construction and segment assembly assembled assembled steaming hoods, combined with intelligent temperature control system, the problem that existing devices cannot adapt to changes in pier lengths is solved, and efficient and highly adaptable pier column maintenance is achieved.
Patent Information
- Application Number
- CN202411535911.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-31
- Publication Date
- 2025-03-18
- Estimated Expiration
- 2044-10-31
AI Technical Summary
The overall structure of the existing prefabricated pier column maintenance device is fixed, and it cannot adapt to changes in the length of the pier column, resulting in long maintenance time, poor insulation effect, and difficult to control quality.
Prefabricated prefabricated steaming hoods with prefabricated construction and segment assembly are used to form a sealed kiln body according to the length of the pier column to achieve highly adaptable maintenance.
It has improved the degree of prefabrication of bridge components, shortened construction time, reduced labor intensity, improved maintenance quality and work efficiency, and is suitable for pier and column structures of various shapes and sizes.
Smart Images

Figure CN119635813A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of municipal engineering and highway bridge reinforced concrete component pier column maintenance construction, and in particular to an assembled steam curing cover for prefabricated pier columns. Background Art
[0002] Prefabricated bridge components are widely used in municipal and highway projects. At present, the maintenance of prefabricated piers is usually carried out under natural curing or simple steam curing shed conditions. The curing time is long, the thermal insulation effect is poor, and the curing quality is difficult to control. The existing curing device usually has a relatively fixed overall structure. The space size in the steam curing kiln is difficult to change, and it cannot match the change in the length of the prefabricated pier. The prefabricated steam curing cover for prefabricated piers can be assembled with segmented steam curing covers as the length of the pier changes. The prefabricated curing cover has high curing efficiency, low heat loss, and is easy to install and disassemble. It can be flexibly produced in open-air factories or construction sites and has strong adaptability. At the same time, prefabricated concrete components also have the advantages of greatly improving the environmental conditions of the construction site, saving raw materials, speeding up construction, and being reusable. Summary of the invention
[0003] The purpose of the present invention is to provide a prefabricated pier assembly steam curing cover, which can improve the industrialization level of bridge component prefabrication, can be assembled in sections, and is suitable for pier structures of various shapes and sizes.
[0004] In order to achieve the above-mentioned purpose, the present invention provides a prefabricated pier column assembled steaming hood, comprising an assembled steaming hood and an intelligent temperature control system base, wherein the intelligent temperature control system base is installed on a prefabricated pier column base, the assembled steaming hood adopts an assembleable design, and a plurality of assembled steaming hoods are sequentially spliced according to the length of the pier column, and are installed on the intelligent temperature control system base to form a kiln body that seals the pier column, a steam pipe and a water spray pipe are installed on the intelligent temperature control system base, a water pipe corresponding to the steam pipe and the water spray pipe is installed in the assembled steaming hood, the water pipe is connected to a nozzle, a temperature and humidity probe is also installed in the assembled steaming hood, the temperature and humidity probe feeds back the signal in the kiln to a maintenance system host through a data line, and the maintenance system host sends a control signal to the intelligent temperature control system base to control the opening / closing of the solenoid valves in the steam pipe and the water spray pipe.
[0005] Furthermore, steel ground beams are arranged at fixed intervals on the pier foundation, and the steel ground beams are connected to the embedded steel plates in the pier foundation by bolts. I-beams are densely arranged on the steel ground beams, and the I-beams are used to provide a stable foundation for producing piers.
[0006] Furthermore, channel steels are arranged around the table top of the pier foundation, and the base of the intelligent temperature control system is installed in the channel steels. The channel steels are sealed with water to seal steam and store condensed water.
[0007] Furthermore, the base of the intelligent temperature control system is made of high-temperature resistant rock wool sandwich color steel plate, the steam pipe and the water spray pipe are arranged in the base, and a positioning pin is provided on the top of the base of the intelligent temperature control system.
[0008] Furthermore, a positioning sleeve is pre-buried at a corresponding position of the bottom of the assembled steaming hood, a positioning pin is provided at the top of the assembled steaming hood, and the top of the assembled steaming hood can be completely closed by a sealing steel plate.
[0009] Furthermore, the assembled steam-curing hood is made of high-strength concrete, the inner side of the assembled steam-curing hood is coated with a high-temperature resistant ceramic coating, and a sandwich insulation board is arranged inside the assembled steam-curing hood.
[0010] Furthermore, the water pipes are several and symmetrically arranged on the inner wall of the assembled steaming hood, the bottom of the water pipes is connected with the steam pipe inlet and the water spray pipe, and the top of the water pipes is provided with an outlet to connect with the water pipes on the upper layer.
[0011] Furthermore, the assembled steam curing hood is provided with a working window for placing sample blocks under the same curing conditions and for simultaneously observing the curing conditions of the piers.
[0012] Furthermore, the assembled steaming hood can be customized according to the shape of the pier to adapt to different pier shapes.
[0013] The present invention has the following beneficial effects and improvements:
[0014] 1. The assembled steam curing hood of the present invention adopts prefabricated assembly construction and segment assembly, which can be applied to pier structures of various shapes and sizes, can speed up the construction process, reduce labor intensity, improve work efficiency, and meet the needs of industrialized production of pier products.
[0015] 2. The intelligent control system adopted in the present invention can realize the scientific, standardized and automated concrete curing process, reduce the influence of human factors, improve the curing quality and extend the service life of concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0017] Figure 1 Schematic diagram of the assembly of the assembled steaming hood according to an embodiment of the present invention.
[0018] Figure 2It is a schematic structural diagram of a pier column base according to a preferred embodiment of the present invention.
[0019] Figure 3 Schematic diagram of the structure of the intelligent temperature control system base according to an embodiment of the present invention.
[0020] Figure 4 The figure is a schematic structural diagram of an assembled steaming hood according to an embodiment of the present invention.
[0021] Figure 5 The figure is a layout diagram of the water pipe according to an embodiment of the present invention.
[0022] Description of reference numerals:
[0023] 1- pier column base, 2- intelligent temperature control system base, 3- assembled steam curing hood, 11- steel ground beam, 1- I-beam, 21- positioning pin, 22- steam pipe, 23- water spray pipe, 24- channel steel, 31- positioning sleeve, 32- positioning pin, 33- sealing steel plate, 34- water pipe, 35- working window, 36-, 37- lifting ears, 38- sandwich insulation board, 39- temperature and humidity probe. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0025] In the following description, reference is made to “some embodiments”, which describes a subset of all possible embodiments, but it can be understood that “some embodiments” can be the same subset or different subsets of all possible embodiments and can be combined with each other without conflict.
[0026] If similar descriptions of "first / second" appear in the application documents, the following explanation is added. In the following description, the terms "first\second\third" involved are used to distinguish similar objects and do not represent a specific ordering of the objects. It can be understood that "first\second\third" can be interchanged in a specific order or sequence where permitted, so that the embodiments of the present application described herein can be implemented in an order other than that illustrated or described herein.
[0027] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein are only for the purpose of describing the embodiments of this application and are not intended to limit this application.
[0028] like Figure 1 As shown, the assembled steaming hood of the embodiment of the invention comprises a pier column base 1, an assembled steaming hood 3 and an intelligent temperature control system base 2. The intelligent temperature control system base 2 is installed on the pier column base 1, and the assembled steaming hood 3 adopts an assembled design. According to the length of the pier column, multiple assembled steaming hoods 3 can be spliced in sequence and installed on the intelligent temperature control system base 2 to form a kiln body that seals the pier column.
[0029] like Figure 2 , 3 As shown, steel ground beams 11 are arranged at a certain interval on the pier foundation 1, and the steel ground beams 11 are connected to the embedded steel plates in the pier foundation by bolts. I-beams 12 are arranged on the steel ground beams 11, and the I-beams 12 are used to provide a stable foundation for producing piers.
[0030] Channel steels 24 are arranged around the table top of the pier foundation 1, and the intelligent temperature control system base 2 is installed in the channel steel 24. After installation, the channel steel is filled with water and sealed to seal steam and store condensed water.
[0031] The intelligent temperature control system base 2 is made of high temperature resistant rock wool sandwich color steel plate. The steam pipe 22 and the water spray pipe 23 in the spray system are both arranged in the intelligent temperature control system base. A positioning pin 21 is provided on the top of the intelligent temperature control system base 2. The positioning pin 21 is used to connect the first segment assembled steam curing cover 3 pre-buried positioning sleeve.
[0032] Preferably, an intelligent sensing temperature and humidity probe 39 is installed on the kiln body to timely feed back the kiln signal to the maintenance system host through the data line for summary and analysis so as to make contingency measures, and then issue commands to the solenoid valves in the steam pipe 22 and the water spray pipe 23 to control the water and steam supply.
[0033] like Figure 4 , 5 As shown, the kiln body of the assembled steam curing hood 3 is made of a high-strength prefabricated concrete structure. The assembled steam curing hood 3 is 2 meters long, and a high-temperature resistant ceramic coating is provided on its inner side wall.
[0034] Preferably, a sealing steel plate 33 is installed on the top of the assembled steaming hood 3 to ensure the sealing of the kiln body. The sealing steel plate 33 has a thickness of 20 mm to ensure that the kiln body maintains structural integrity and airtightness under high temperature and humidity conditions.
[0035] The pre-buried positioning sleeves 31 at four diagonal points of the assembled steaming hood 3 cooperate with the positioning pins 32 to complete the splicing of the assembled steaming hood 3.
[0036] A water pipe 34 is provided in the assembled steaming hood 3. The water pipes 34 are symmetrically arranged on the inner wall of the assembled steaming hood 3. The bottom inlet of the water pipe 34 is connected to the steam pipe 22 and the water spray pipe 23. The top of the water pipe 34 is provided with an outlet to connect with the water pipe 3 of the upper assembled steaming hood 3. After assembly, each segment of the steaming hood 3 is aligned through a preset coaxial channel, and the nozzles 40 are distributed on each water pipe 34.
[0037] By splicing the assembled steam curing hood 3, it can be applied to precast concrete columns of various pier shapes. It has modular prefabrication characteristics and can be quickly and firmly assembled into a supporting structure through special connectors. Such a modular structure provides a high degree of flexibility. The segmented steam curing hood can be assembled as the length of the pier changes. The lifting lugs 37 installed on the assembled steam curing hood 3 are connected by a hoist to carry out the rapid assembly and disassembly of the kiln body. A working window 35 is reserved at the bottom of the assembled steam curing hood 3 to facilitate the placement of test blocks under the same curing conditions and to observe the curing conditions of the piers. After the segmented steam curing hood is assembled along the length of the pier, a sealing cover is installed. After observing that its tightness meets the requirements, steam is passed to start curing.
[0038] Although the embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and cannot be understood as limiting the present invention. A person of ordinary skill in the art can change, modify, replace and modify the above embodiments within the scope of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A prefabricated pier assembly type steam curing hood, characterized in that: The invention comprises an assembled steaming curing hood and an intelligent temperature control system base, wherein the intelligent temperature control system base is installed on a prefabricated pier column base, the assembled steaming curing hood adopts an assembleable design, and a plurality of assembled steaming curing hoods are sequentially spliced according to the length of the pier column and installed on the intelligent temperature control system base to form a kiln body that seals the pier column, a steam pipe and a water spray pipe are installed on the intelligent temperature control system base, a water pipe corresponding to the steam pipe and the water spray pipe is installed in the assembled steaming curing hood, the water pipe is connected with a nozzle, a temperature and humidity probe is also installed in the assembled steaming curing hood, the temperature and humidity probe feeds back the signal in the kiln to the maintenance system host through a data line, and the maintenance system host sends a control signal to the intelligent temperature control system base to control the opening / closing of the solenoid valves in the steam pipe and the water spray pipe.
2. A prefabricated pier assembly type steam curing cover as claimed in claim 1, characterized in that: Steel ground beams are arranged at fixed intervals on the pier foundation, and the steel ground beams are connected to the embedded steel plates in the pier foundation by bolts. I-beams are densely arranged on the steel ground beams, and the I-beams are used to provide a stable foundation for producing piers.
3. A prefabricated pier assembly type steam curing cover as claimed in claim 2, characterized in that: Channel steels are arranged around the table top of the pier foundation, and the base of the intelligent temperature control system is installed in the channel steels. The channel steels are filled with water and sealed to seal steam and store condensed water.
4. A prefabricated pier assembly type steam curing cover as claimed in claim 3, characterized in that: The intelligent temperature control system base is made of high-temperature resistant rock wool sandwich colored steel plate, the steam pipe and the water spray pipe are arranged in the base, and a positioning pin is provided on the top of the intelligent temperature control system base.
5. The prefabricated pier assembly type steam curing cover according to claim 4, characterized in that: A positioning sleeve is pre-buried at a corresponding position of the bottom of the assembled steaming hood, a positioning pin is provided at the top of the assembled steaming hood, and the top of the assembled steaming hood can be completely closed by a sealing steel plate.
6. The prefabricated pier assembly type steam curing cover according to claim 5, characterized in that: The assembled steam curing hood is made of high-strength concrete, the inner side of the assembled steam curing hood is coated with a high-temperature resistant ceramic coating, and a sandwich insulation board is arranged inside the assembled steam curing hood.
7. A prefabricated pier assembly type steam curing cover as claimed in claim 6, characterized in that: The water pipes are several and symmetrically arranged on the inner wall of the assembled steam curing hood. The bottom of the water pipes is connected with the steam pipe inlet and the water spray pipe. The top of the water pipes is provided with an outlet to connect with the water pipes on the upper layer.
8. The prefabricated pier assembly type steam curing cover according to claim 7, characterized in that: The assembled steam curing hood is provided with a working window for placing sample blocks with the same curing conditions and for simultaneously observing the curing conditions of the pier columns.
9. The prefabricated pier assembly type steam curing cover according to claim 6, characterized in that: The assembled steaming hood can be customized according to the shape of the pier column to adapt to different pier column shapes.
Citation Information
Patent Citations
Equipment for insulating and curing pier column concrete in low-temperature seasons
CN106381811A
Energy-saving and environment-friendly pipe piece steam curing kiln and curing method thereof
CN117445163A
Bridge pier column maintenance system
CN220183832U
Curing apparatus and method for joint between precast concrete block with in-situ concrete
KR101245610B1
Cited By
A block assembly type pier body turnover and steam curing shed
CN120552202B
Green maintenance device for concrete members
CN121798746A
Maintenance device for road and bridge concrete prefabricated part
CN121870905A
A device for curing a road and bridge concrete precast
CN121870905B