Curtain wall force transmission system and construction method thereof

By using adjustable support and force transmission rods in the curtain wall force transmission system, the problems of unstable and complex curtain wall structure are solved, and the strengthening of force transmission and the improvement of construction quality are achieved.

CN119664017APending Publication Date: 2025-03-21CHINA MCC5 GROUP CORP LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411777217.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-05
Publication Date
2025-03-21

AI Technical Summary

Technical Problem

The existing curtain wall structure is unstable or complex, which leads to difficulty in reliable connection on the main body of the building, poses quality hazards, and is cumbersome to construction.

Method used

A curtain wall force transmission system is adopted, including reserved window holes on the main body of the building, curtain wall keels, window hole subframes, adjustable support and force transmission rods. Through the design of adjustable support and force transmission rod, the curtain wall glass, keel and wall panel force are transmitted to the main structure of the building, and the structure stability is ensured by reserved mortar for the window holes and window hole subframes.

Benefits of technology

It effectively strengthens the force transmission between the building curtain wall and the main structure, improves the structural safety and construction quality of the curtain wall, and avoids the complexity of designing the connecting structure separately.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119664017A_ABST
    Figure CN119664017A_ABST
Patent Text Reader

Abstract

The invention discloses a curtain wall force transmission system and a construction method thereof. The force transmission system comprises a building body and a reserved window opening, a curtain wall keel is fixed to the building body, a curtain wall plate is fixed to the curtain wall keel, a window opening auxiliary frame is fixed in the reserved window opening, an adjustable supporting piece is arranged between the bottom of the window opening auxiliary frame and the reserved window opening, and a force transmission rod is connected between the curtain wall keel and the window opening auxiliary frame. The construction method comprises the following steps: fixing a curtain wall keel on a building main body; an adjustable supporting piece is arranged at the bottom of the reserved window opening of the building body; a window opening auxiliary frame is temporarily positioned and installed in the reserved window opening; the adjustable supporting piece is supported between the bottom of the window opening auxiliary frame and the reserved window opening. A dowel bar is connected between the curtain wall keel and the window opening auxiliary frame; a curtain wall wallboard is installed on the curtain wall keel; a window body is installed on the inner side of the window opening auxiliary frame. The building curtain wall has the beneficial effects that force on the curtain wall glass, the curtain wall keel and the curtain wall plate is effectively transmitted to a building main body structure, and the structural safety of the building curtain wall is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of building curtain wall construction, and specifically relates to a curtain wall force transmission system and a construction method thereof. Background Art

[0002] Building curtain wall refers to the non-load-bearing exterior wall enclosure of a building, which is usually composed of panels (glass, metal plates, stone plates, ceramic plates, etc.) and the supporting structure behind (aluminum beams and columns, steel structures, glass ribs, etc.). As more and more building curtain walls are used in buildings, curtain wall structures are also differentiated into various forms or combinations of multiple forms. However, for various forms of curtain wall structures, it is not possible to reliably connect each structure to the main building, which poses certain quality risks; or each curtain wall structure is designed with a separate connection structure, which makes the curtain wall construction cumbersome. Summary of the invention

[0003] The purpose of this application is to provide a curtain wall force transmission system and a construction method thereof, which solves the problem of unstable or complex structure of existing curtain walls.

[0004] The purpose of this application is achieved through the following technical solutions:

[0005] A curtain wall force transmission system comprises a building body and reserved window openings on the building body, a curtain wall keel is fixed on the building body, a curtain wall panel is fixed on the curtain wall keel, a window hole sub-frame is fixed in the reserved window opening, an adjustable support is arranged between the bottom of the window hole sub-frame and the reserved window opening, and a force transmission rod is connected between the curtain wall keel and the window hole sub-frame.

[0006] Furthermore, the building body is a wall or beam of a reinforced concrete structure.

[0007] Furthermore, a curtain wall embedded plate is provided on the building main body, the curtain wall embedded plate is connected to the connecting rod, and the connecting rod is connected to the curtain wall keel.

[0008] Furthermore, mortar is filled between the reserved window hole and the window hole sub-frame.

[0009] Furthermore, a window main frame is arranged inside the window hole sub-frame, and glass is arranged inside the window main frame.

[0010] Furthermore, the adjustable support member includes a pre-embedded threaded sleeve and a supporting threaded rod. The pre-embedded threaded sleeve is embedded in the main body of the building. The pre-embedded threaded sleeve and the supporting threaded rod are threadedly matched, and the supporting threaded rod supports the window hole sub-frame.

[0011] Furthermore, the force transmission rod includes a force transmission horizontal rod, a force transmission vertical rod and a force transmission diagonal rod. The force transmission horizontal rod is connected to the window opening sub-frame, the force transmission horizontal rod is connected to the force transmission vertical rod, the force transmission vertical rod is connected to the curtain wall keel, and a force transmission diagonal rod is connected between the force transmission horizontal rod and the force transmission vertical rod.

[0012] A construction method for a curtain wall force transmission system comprises the following steps:

[0013] The first step is to fix the curtain wall keel on the main body of the building;

[0014] The second step is to place adjustable supports at the bottom of the reserved window openings of the building body;

[0015] The third step is to temporarily locate and install the window hole sub-frame in the reserved window hole;

[0016] The fourth step is to operate the adjustable support member so that the adjustable support member is supported between the bottom of the window hole sub-frame and the reserved window hole;

[0017] Step 5: Connect the force transmission rod between the curtain wall keel and the window opening sub-frame;

[0018] The sixth step is to install the curtain wall panels on the curtain wall keels; fill and seal the space between the outer side of the window opening sub-frame and the reserved window opening, and install the window body on the inner side of the window opening sub-frame.

[0019] Furthermore, in the first step, a curtain wall embedded plate is installed on the main building, the curtain wall embedded plate is fixed to the main building by expansion bolts, and then the inner end of the connecting rod is welded to the curtain wall embedded plate, and the outer end of the connecting rod is welded to the curtain wall keel.

[0020] Furthermore, a pre-embedded threaded sleeve of an adjustable support is embedded in the main body of the building in advance. In the second step, the support threaded rod 102 is screwed into the pre-embedded threaded sleeve 101. In the fourth step, the support threaded rod is rotated to tighten the window hole sub-frame through the thread cooperation between the pre-embedded threaded sleeve and the support threaded rod.

[0021] Furthermore, in the fifth step, the force transmission rod includes a force transmission horizontal rod, a force transmission vertical rod and a force transmission diagonal rod. The force transmission horizontal rod is first welded to the force transmission vertical rod, and the force transmission diagonal rod is welded between the force transmission horizontal rod and the force transmission vertical rod. Then, the force transmission horizontal rod is welded to the window opening sub-frame, and the force transmission vertical rod is welded to the curtain wall keel.

[0022] Furthermore, in the sixth step, the curtain wall panels are fixed to the curtain wall keels by screws; mortar is filled between the outer side of the window hole sub-frame and the reserved window hole, and the outer surface of the mortar is flush with the outer surface of the window hole sub-frame; the window main frame is installed on the inner side of the window hole sub-frame, the window main frame is fixed to the window hole sub-frame by screws, glass is placed in the window main frame, and glue is applied to seal the window main frame and the glass.

[0023] Beneficial effects of this application:

[0024] (1) Strengthen the force conduction between the building curtain wall and the main structure, effectively transfer the force on the curtain wall glass, curtain wall keel, and curtain wall panel to the main structure of the building, and improve the structural safety of the building curtain wall.

[0025] (2) By positioning and supporting the window opening sub-frame through adjustable supports, the flatness of the window opening sub-frame can be adjusted, thereby ensuring the level of the curtain wall glass and improving the structural quality of the building curtain wall.

[0026] The aforementioned main scheme of the present application and its further options can be freely combined to form multiple schemes, all of which are schemes that can be adopted and claimed for protection in the present application; and in the present application, (non-conflicting options) can also be freely combined with each other and with other options. After understanding the scheme of the present application, those skilled in the art can understand that there are many combinations based on the prior art and common knowledge, all of which are technical schemes to be protected by the present application, and they are not exhaustively listed here. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the structure of this application.

[0028] Figure 2 It is a structural schematic diagram of the adjustable support member of the present application.

[0029] In the figure: 1-building body, 2-reserved window opening, 3-embedded curtain wall plate, 4-connecting rod, 5-curtain wall keel, 6-curtain wall panel, 7-window opening sub-frame, 8-window main frame, 9-mortar, 10-adjustable support, 11-force transmission rod, 12-glass; 101-embedded threaded sleeve, 102-supporting threaded rod, 111-force transmission horizontal rod, 112-force transmission vertical rod, 113-force transmission diagonal rod. DETAILED DESCRIPTION

[0030] The following non-limiting examples are provided to illustrate the present application.

[0031] Example 1

[0032] refer to Figure 1 and Figure 2 As shown, a curtain wall force transmission system includes a building body 1, a reserved window opening 2, a curtain wall embedded plate 3, a connecting rod 4, a curtain wall keel 5, a curtain wall panel 6, a window opening sub-frame 7, a window main frame 8, mortar 9, an adjustable support 10, a force transmission rod 11 and a glass 12.

[0033] The main building 1 is a wall or beam of a reinforced concrete structure, and the entire curtain wall is constructed on the main building 1. A number of reserved window openings 2 are formed on the main building 1, and the reserved window openings 2 are used for the subsequent placement of curtain wall glass. Curtain wall keels 5 are fixed on the main building 1, and a number of curtain wall keels 5 are arranged horizontally. The curtain wall keels 5 are square tubes or rectangular tubes. The loads of other curtain wall structures are gathered on the curtain wall keels 5, and then act on the main building 1 through the curtain wall keels 5.

[0034] A plurality of embedded curtain wall panels 3 are provided on the building body 1. The embedded curtain wall panels 3 are made of steel plates and are fixed to the building body 1 by expansion bolts. The embedded curtain wall panels 3 are welded to the inner ends of the connecting rods 4. The outer ends of the connecting rods 4 are welded to the curtain wall keels 5. The connecting rods 4 also adopt square tubes or rectangular tubes to realize the connection transition between the embedded curtain wall panels 3 and the curtain wall keels 5.

[0035] A plurality of curtain wall embedded panels 3 fix a curtain wall keel 5, so as to realize reliable fixation of the curtain wall keel 5 on the building main body 1. A curtain wall panel 6 is fixed on the curtain wall keel 5, and the curtain wall panel 6 is located on the outside for decorative protection. A plurality of curtain wall panels 6 are directly arranged horizontally on the keel by screws.

[0036] A window hole sub-frame 7 is fixed in the reserved window hole 2, and the window hole sub-frame 7 is preferably made of metal. The reserved window hole 2 and the window hole sub-frame 7 are both rectangular, but the size of the window hole sub-frame 7 is slightly smaller than the reserved window hole 2. Mortar 9 is filled between the reserved window hole 2 and the window hole sub-frame 7 to seal the gap between the two to achieve waterproof and windproof.

[0037] An adjustable support member 10 is provided between the bottom of the window hole sub-frame 7 and the reserved window hole 2. The window hole sub-frame 7 can be supported by the adjustable support member 10. At the same time, the adjustable support member 10 can also adjust the support height to adjust the flatness of the window hole sub-frame 7 to ensure the construction quality of the subsequent curtain wall glass.

[0038] The window hole auxiliary frame 7 transmits force to the concrete building main structure through the adjustable support member 10 and the filling mortar. Because it is difficult to ensure the flatness of the structural surface during concrete pouring, the adjustable support member 10 is placed during concrete pouring to support the weight of the auxiliary frame and the glass upwards.

[0039] The adjustable support member 10 includes a pre-embedded threaded sleeve 101 and a supporting threaded rod 102. The pre-embedded threaded sleeve 101 is pre-embedded inside the building body 1, and the pre-embedded threaded sleeve 101 is threadedly matched with the lower end of the supporting threaded rod 102, and the upper end of the supporting threaded rod 102 supports the window hole sub-frame 7, and the height adjustment can be achieved by rotating the supporting threaded rod 102.

[0040] A plurality of force transmission rods 11 are connected between the curtain wall keel 5 and the window hole sub-frame 7. The force transmission rods 11 transmit the load of the curtain wall glass to the curtain wall keel 5, avoiding the safety hazard of the curtain wall glass not being provided with a connection structure, and also avoiding the complicated process of adding an additional connection structure. The plurality of force transmission rods 11 are evenly arranged on the window hole sub-frame 7 to ensure uniform load action.

[0041] The main weight of the building curtain wall comes from the weight of the curtain wall panels and the weight of the glass. This weight is mainly transferred to the curtain wall keel and the window opening sub-frame. The curtain wall keel transfers the force to the structural wall or beam surface through the curtain wall embedded plate. The curtain wall keel and the sub-frame are welded to form a whole using force transfer rods. The keel and the sub-frame jointly transfer the force to the main structure through the embedded plate and supporting components.

[0042] The force transmission rod 11 includes a force transmission horizontal rod 111, a force transmission vertical rod 112 and a force transmission diagonal rod 113, all of which are square tubes or rectangular tubes. The inner end of the force transmission horizontal rod 111 is welded to the window opening sub-frame 7, the outer end of the force transmission horizontal rod 111 is connected to the upper end of the force transmission vertical rod 112, and the lower end of the force transmission vertical rod 112 is connected to the curtain wall keel 5, so as to realize load transmission while satisfying the right-angle structure at the window opening. A force transmission diagonal rod 113 is welded between the force transmission horizontal rod 111 and the force transmission vertical rod 112 to strengthen the structures of both.

[0043] A main window frame 8 is arranged inside the window hole sub-frame 7. The main window frame 8 is also rectangular. The outer contour of the main window frame 8 just matches the inner contour of the window hole sub-frame 7. The main window frame 8 is fixed to the window hole sub-frame 7 by screws. Glass 12 is arranged inside the main window frame 8. Glue is applied between the main window frame 8 and the glass 12 to seal.

[0044] This force transmission volume can strengthen the force conduction between the building curtain wall and the main structure, effectively transfer the force on the curtain wall glass, curtain wall keel and curtain wall panel to the main structure of the building, and improve the structural safety of the building curtain wall.

[0045] Example 2

[0046] A construction method of a curtain wall force transmission system is based on a building main body 1 that has been cast and completed to obtain a curtain wall force transmission system of Example 1. When the building main body 1 is cast, a pre-embedded threaded sleeve 101 with an inner thread is pre-embedded in the concrete component near the window in advance to facilitate the subsequent installation of a supporting threaded rod 102 on the sleeve.

[0047] The construction method comprises the following steps: the first step is to fix several layers of horizontally arranged curtain wall keels 5 on the building body 1, and the loads of other curtain wall structures are gathered on the curtain wall keels 5, and then act on the building body 1 through the curtain wall keels 5.

[0048] Several layers of embedded curtain wall panels 3 are installed on the main building 1. Each layer of embedded curtain wall panels 3 includes several horizontally arranged panels. The embedded curtain wall panels 3 are fixed to the main building 1 by expansion bolts. Then the inner ends of the connecting rods 4 are welded to the embedded curtain wall panels 3, and the outer ends of the connecting rods 4 are welded to the curtain wall keels 5, so that the curtain wall keels 5 are fixed to the main building 1 in a horizontal state.

[0049] The second step is to place an adjustable support member 10 at the bottom of the reserved window opening 2 of the building body 1. The adjustable support member 10 can support the window opening sub-frame 7, and the adjustable support member 10 can also adjust the support height to adjust the flatness of the window opening sub-frame 7 to ensure the construction quality of the subsequent curtain wall glass.

[0050] Since a plurality of embedded threaded sleeves 101 of the adjustable support members 10 are arranged in advance at the bottom of the reserved window openings 2 of the building main body 1 , in the second step, the support threaded rods 102 are screwed into the embedded threaded sleeves 101 .

[0051] The third step is to temporarily position and install the window hole sub-frame 7 in the reserved window hole 2. The sub-frame is fixed to the concrete structure beside the window through a fixing piece, and an adjustable support member 10 is provided below the sub-frame.

[0052] The fourth step is to operate the adjustable support member 10 to support the adjustable support member 10 between the bottom of the window hole sub-frame 7 and the reserved window hole 2. Through the threaded cooperation between the embedded threaded sleeve 101 and the support threaded rod 102, the support threaded rod 102 is rotated to tighten the window hole sub-frame 7, so that the adjustable support member 10 is completely fitted with the metal sub-frame, and can effectively support the sub-frame.

[0053] In the fifth step, a force transmission rod 11 is connected between the curtain wall keel 5 and the window opening sub-frame 7, and the force transmission rod 11 transmits the load of the curtain wall glass to the curtain wall keel 5.

[0054] The force transmission rod 11 includes a force transmission horizontal rod 111, a force transmission vertical rod 112 and a force transmission diagonal rod 113, all of which are square tubes or rectangular tubes. The outer end of the force transmission horizontal rod 111 is first welded to the upper end of the force transmission vertical rod 112 to form an L-shaped rectangular tube structure, and the force transmission diagonal rod 113 is welded between the force transmission horizontal rod 111 and the force transmission vertical rod 112 to strengthen the structure. Then, the inner end of the force transmission horizontal rod 111 is welded to the window hole sub-frame 7, and the lower end of the force transmission vertical rod 112 is welded to the curtain wall keel 5.

[0055] In the sixth step, a plurality of curtain wall panels 6 are installed on the curtain wall keels 5 , and the curtain wall panels 6 are fixed on the curtain wall keels 5 by screws.

[0056] The outer side of the window hole sub-frame 7 and the reserved window hole 2 are filled and blocked, and mortar 9 is filled between the outer side of the window hole sub-frame 7 and the reserved window hole 2, and the outer surface of the mortar 9 is flush with the outer surface of the window hole sub-frame 7.

[0057] The window body is installed inside the window hole sub-frame 7, and the window body includes a window main frame 8 and glass 12. The window main frame 8 is installed inside the window hole sub-frame 7, and the window main frame 8 is fixed on the window hole sub-frame 7 by screws. The glass 12 is placed in the window main frame 8, and the window main frame 8 and the glass 12 are sealed with glue.

[0058] The aforementioned basic examples and their further selected examples can be freely combined to form multiple embodiments, all of which are embodiments that can be adopted and claimed for protection in this application. In the scheme of this application, each selected example can be arbitrarily combined with any other basic examples and selected examples.

[0059] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A curtain wall force transmission system, comprising a building body (1) and a reserved window opening (2) on the building body (1), characterized in that: A curtain wall keel (5) is fixed on the building body (1), a curtain wall panel (6) is fixed on the curtain wall keel (5), a window hole sub-frame (7) is fixed in the reserved window hole (2), an adjustable support member (10) is provided between the bottom of the window hole sub-frame (7) and the reserved window hole (2), and a force transmission rod (11) is connected between the curtain wall keel (5) and the window hole sub-frame (7).

2. The curtain wall force transmission system according to claim 1, characterized in that: The building main body (1) is provided with a curtain wall embedded plate (3), the curtain wall embedded plate (3) is connected to a connecting rod (4), and the connecting rod (4) is connected to a curtain wall keel (5).

3. The curtain wall force transmission system according to claim 1 or 2, characterized in that: The reserved window hole (2) and the window hole sub-frame (7) are filled with mortar (9); a window main frame (8) is arranged inside the window hole sub-frame (7), and glass (12) is arranged inside the window main frame (8).

4. The curtain wall force transmission system according to claim 1, characterized in that: The adjustable support member (10) comprises a pre-embedded threaded sleeve (101) and a supporting threaded rod (102); the pre-embedded threaded sleeve (101) is embedded in the building body (1); the pre-embedded threaded sleeve (101) and the supporting threaded rod (102) are threadably matched; the supporting threaded rod (102) supports the window hole sub-frame (7).

5. The curtain wall force transmission system according to claim 1 or 4, characterized in that: The force transmission rod (11) comprises a force transmission cross rod (111), a force transmission vertical rod (112) and a force transmission diagonal rod (113); the force transmission cross rod (111) is connected to the window hole sub-frame (7); the force transmission cross rod (111) is connected to the force transmission vertical rod (112); the force transmission vertical rod (112) is connected to the curtain wall keel (5); and the force transmission diagonal rod (113) is connected between the force transmission cross rod (111) and the force transmission vertical rod (112).

6. A construction method for a curtain wall force transmission system, characterized in that: The steps include: The first step is to fix the curtain wall keel (5) on the building body (1); The second step is to place an adjustable support member (10) at the bottom of the reserved window opening (2) of the building body (1); The third step is to temporarily position and install the window hole sub-frame (7) in the reserved window hole (2); The fourth step is to operate the adjustable support member (10) so that the adjustable support member (10) is supported between the bottom of the window hole sub-frame (7) and the reserved window hole (2); Step 5: Connect the force transmission rod (11) between the curtain wall keel (5) and the window opening sub-frame (7); The sixth step is to install the curtain wall panel (6) on the curtain wall keel (5); fill and seal the space between the outer side of the window hole sub-frame (7) and the reserved window hole (2), and install the window body on the inner side of the window hole sub-frame (7).

7. The construction method of the curtain wall force transmission system according to claim 6, characterized in that: In the first step, a curtain wall embedded plate (3) is installed on the building body (1), and the curtain wall embedded plate (3) is fixed to the building body (1) by expansion bolts, and then the inner end of the connecting rod (4) is welded to the curtain wall embedded plate (3), and the outer end of the connecting rod (4) is welded to the curtain wall keel (5).

8. The construction method of the curtain wall force transmission system according to claim 6 or 7, characterized in that: The embedded threaded sleeve (101) of the adjustable support member (10) is embedded in the building body (1) in advance. In the second step, the support threaded rod 102 is screwed into the embedded threaded sleeve 101. In the fourth step, the threaded engagement between the embedded threaded sleeve (101) and the support threaded rod (102) is used to rotate the support threaded rod (102) to tighten the window hole sub-frame (7).

9. The construction method of the curtain wall force transmission system according to claim 6, characterized in that: In the fifth step, the force transmission rod (11) comprises a force transmission horizontal rod (111), a force transmission vertical rod (112) and a force transmission diagonal rod (113). The force transmission horizontal rod (111) and the force transmission vertical rod (112) are firstly welded and connected, and the force transmission diagonal rod (113) is welded between the force transmission horizontal rod (111) and the force transmission vertical rod (112). Then, the force transmission horizontal rod (111) is welded to the window hole sub-frame (7), and the force transmission vertical rod (112) is welded to the curtain wall keel (5).

10. The construction method of the curtain wall force transmission system according to claim 6 or 9, characterized in that: In the sixth step, the curtain wall panel (6) is fixed to the curtain wall keel (5) by screws; mortar (9) is filled between the outer side of the window hole sub-frame (7) and the reserved window hole (2), and the outer surface of the mortar (9) is flush with the outer surface of the window hole sub-frame (7); the window main frame (8) is installed on the inner side of the window hole sub-frame (7), the window main frame (8) is fixed to the window hole sub-frame (7) by screws, glass (12) is placed in the window main frame (8), and glue is applied to seal between the window main frame (8) and the glass (12).

Citation Information

Patent Citations

  • Door-window achieving nail-free installation

    CN104727696A

  • Aluminum alloy window sleeve unit body for installing stone curtain wall and installation method

    CN111173172A

  • Window sleeve connecting system of stone curtain wall

    CN111691587A

  • Mounting structure of environment-friendly decorative plate

    CN213174591U

  • Base-layer-free dry-hanging design structure of assembly type finished wood plaque

    CN215167518U