Water pile foundation integrated construction method

Through integrated construction methods, including detailed on-site investigation, optimized prefabricated pile transportation, accurate positioning system installation, automated pile foundation drilling and comprehensive inspection, the problems of low efficiency, difficult quality, increased cost and reduced safety in the existing water pile foundation construction methods are solved, and efficient, accurate and safe construction results are achieved.

CN119686311APending Publication Date: 2025-03-25ROAD & BRIDGE INT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510003471.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-02
Publication Date
2025-03-25

AI Technical Summary

Technical Problem

The existing water pile foundation construction methods have problems such as incomplete on-site investigation, lack of planning for prefabricated pile transportation, inaccurate pile foundation positioning system, lax pile driving process control and imperfect pile foundation detection methods, resulting in low construction efficiency, difficulty in ensuring quality, increased cost and reduced safety.

Method used

The integrated construction method is adopted, including detailed on-site investigation and equipment layout, optimized prefabricated pile transportation, accurate auxiliary positioning system installation, automated pile foundation drilling and comprehensive pile foundation inspection.

Benefits of technology

It improves construction efficiency and quality, reduces construction costs and safety risks, adapts to complex water areas and geological conditions, optimizes resource allocation, and improves the reliability and long-term stability of the project.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention belongs to the technical field of engineering construction, and discloses a water pile foundation integrated construction method which sequentially comprises the construction steps of site investigation and equipment arrangement, precast pile transportation, auxiliary positioning system installation, pile foundation driving and pile foundation detection. According to the method, the water pile foundation construction is efficient, accurate and safe, the construction cost is reduced, and the engineering quality and reliability are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of engineering construction, and provides an integrated construction method for pile foundations on water that improves positioning accuracy, improves construction efficiency, ensures construction quality and improves construction safety. Background Art

[0002] There are many challenges in traditional construction methods when constructing pile foundations on water. Site surveys before construction are often not comprehensive and detailed enough, making it difficult to accurately assess water and geological conditions, which may lead to many uncertainties during the construction process. The transportation of prefabricated piles also lacks reasonable planning, which can easily lead to damage to the pile body and low transportation efficiency, increasing construction costs and risks. In addition, the pile foundation positioning system is not accurate enough, affecting the quality and progress of construction; the pile driving process is not strictly controlled, which may cause damage to the pile body and construction safety hazards; the pile foundation detection methods are also limited and imperfect, making it difficult to accurately assess the performance of the pile foundation. These problems combined lead to low construction efficiency, difficulty in ensuring quality, increased costs, reduced safety, and inability to adapt to complex construction environments, limiting the optimal allocation of resources and the reliability of the project, and also hindering the development of water pile foundation construction technology.

[0003] In summary, the technical problems of existing methods of water pile foundation construction are: the on-site investigation is not comprehensive, and it is difficult for traditional methods to accurately assess the water area and geological conditions; the transportation of prefabricated piles lacks planning, which can easily lead to damage to the pile body and low transportation efficiency; the pile foundation positioning system is not accurate, affecting the construction quality and progress; the pile driving process is not strictly controlled, which may cause damage to the pile body and construction safety hazards; the pile foundation detection method is imperfect, making it difficult to accurately assess the performance of the pile foundation. Summary of the invention

[0004] In view of this, an object of the present invention is to provide an efficient, accurate, safe and integrated method for the construction of pile foundations on water.

[0005] To achieve the above object, the present invention provides the following technical solutions:

[0006] The present invention provides an integrated construction method for pile foundation on water, which comprises the following steps:

[0007] Step 1: Site investigation and equipment layout.

[0008] Set the location for pile foundation driving in the water area and arrange the construction equipment;

[0009] Step 2: Transportation of prefabricated piles.

[0010] Transport the prefabricated piles to the construction site by means of pontoons or water transport vehicles;

[0011] Step 3: Install the auxiliary positioning system.

[0012] Install positioning marks around the piling location to ensure the accuracy of pile driving;

[0013] Step 4: Pile foundation driving.

[0014] Use an automated pile driver to drive piles and monitor pile position and depth in real time;

[0015] Step five: Pile foundation inspection, using sonar or other detection technology to detect the depth and verticality of the pile foundation to ensure construction quality.

[0016] In the above scheme, further:

[0017] The specific process of the on-site investigation described in step 1 above is as follows:

[0018] Hydrological surveys to measure water depth, flow velocity, tidal changes and water temperature, and assess the construction environment in the water area;

[0019] Geological exploration, using drilling and sampling methods to obtain soil conditions, including soil type, clay layer thickness, and groundwater level, in order to determine the bearing capacity of the pile foundation and the appropriate pile type;

[0020] On-site surveying: Use total station or GPS equipment to survey the construction area, obtain the precise coordinates of the pile positions, and provide data support for equipment layout;

[0021] Environmental assessment: inspect the ecological environment of the construction area, assess the impact on surrounding aquatic organisms and ecology, and ensure that the construction meets environmental protection requirements;

[0022] The specific process of equipment arrangement described in the above step 1 is as follows:

[0023] Equipment preparation,

[0024] Pile striking equipment, such as hydraulic pile drivers and vibratory pile drivers, is determined according to the pile type and geological conditions;

[0025] Transportation equipment, such as pontoons and boats, are used to transport precast piles to the construction site;

[0026] Construction platform: build a stable water construction platform to ensure the safe placement of equipment and the operating space for construction personnel;

[0027] Positioning and monitoring equipment, including pile positioning system and depth monitoring equipment, to ensure the accuracy of pile driving;

[0028] The construction platform should be built in an area with stable waters and moderate flow rate to facilitate the operation of construction equipment;

[0029] Transport channel: design a reasonable transport channel to ensure the smooth transportation and placement of precast piles;

[0030] Equipment layout: Arrange heavy equipment on the platform to ensure its stability and safety, while leaving necessary space and passages for other facilities;

[0031] Safety protection measures include setting up warning signs and safety railings in the construction area to ensure the safety of construction workers and people in the surrounding waters.

[0032] In the above scheme, further:

[0033] The specific process of transporting the prefabricated piles described in step 2 above is as follows:

[0034] S1. Transportation preparation,

[0035] Formulate transportation plan, reasonably plan transportation time and route, and determine transportation equipment and personnel arrangements according to construction progress requirements and pile foundation design plan;

[0036] Prefabricated pile inspection: quality inspection of prefabricated piles before leaving the factory to ensure that their strength, size and surface quality meet the construction requirements, and mark the pile numbers and special transportation marks;

[0037] Prepare transportation tools and select appropriate transportation tools according to the size of the pile and the transportation distance;

[0038] S2. Transportation method selection,

[0039] Water transportation, using special transport ships or barges to transport on the water, is suitable for long-distance transportation and reaching remote construction areas. It is necessary to consider the navigation capacity, load limit and water conditions of the ship;

[0040] Land transportation: if the construction area is close to the shore, the piles can be transported to the waterside by truck or trailer, and then transferred to the construction platform by buoys or other tools;

[0041] S3. Loading and bundling of precast piles,

[0042] Loading method: During the loading process, forklifts or cranes should be used to load the prefabricated piles safely and securely onto the transport vehicle, ensuring that there is sufficient support and cushioning between the pile bodies to prevent collisions;

[0043] Binding and fixing: Use appropriate binding materials to firmly bind the prefabricated piles to prevent them from moving or tilting during transportation;

[0044] S4. Transportation process management

[0045] Real-time monitoring: During transportation, use GPS or other positioning systems to monitor the transportation progress in real time to ensure that it arrives at the construction site on time;

[0046] Safety inspection: regularly inspect the transportation tools and loading conditions to ensure there is no looseness, wear or damage, and to ensure transportation safety;

[0047] S5. On-site unloading and transshipment

[0048] Safe unloading: After arriving at the construction site, use a crane or other mechanical equipment to unload the piles to ensure that the piles land smoothly and avoid damage;

[0049] Temporary storage: If precast piles need to be temporarily stored on site, a flat area should be selected and a safety fence should be set up to ensure the safety of the piles and construction workers.

[0050] In the above scheme, further: the specific process of installing the auxiliary positioning system described in the above step 3 is as follows:

[0051] System composition,

[0052] Positioning equipment, including laser locators, total stations, and GPS locators, for real-time measurement and recording of pile positions;

[0053] A data processing unit, a computer or a dedicated controller, is used to receive positioning data and process and analyze it;

[0054] Display interface, visual interface, real-time display of pile position information and installation progress, convenient for operators to make adjustments and judgments;

[0055] The installation steps are as follows:

[0056] S1. Site preparation,

[0057] Before construction, the exact location and direction of each pile is determined based on the survey data and marked;

[0058] Clean the construction area to ensure that the positioning equipment has a clear measurement view;

[0059] S2, positioning equipment settings,

[0060] According to the pile position requirements, place the laser or total station at a fixed location to ensure its level and stability;

[0061] Calibrate equipment to ensure measurement accuracy;

[0062] S3, data collection and processing,

[0063] Start the positioning device and start collecting pile position data in real time;

[0064] The data is transmitted to the data processing unit via wireless or wired connection for real-time analysis and calculation;

[0065] S4. Adjustment and supervision,

[0066] The operator monitors the pile position in real time based on the data provided in the display interface;

[0067] According to the information fed back by the positioning system, the installation angles of the equipment and piles are adjusted in real time to ensure that the design requirements are met;

[0068] S5, positioning accuracy,

[0069] When designing the system, factors that affect positioning accuracy should be considered, including water surface interference, wind speed, and equipment accuracy. Through comprehensive analysis of multi-channel factors, the accuracy of positioning can be maximized;

[0070] Regularly calibrate and maintain the equipment to ensure stability and accuracy during long-term use.

[0071] In the above scheme, further:

[0072] The specific process of driving the pile foundation described in step 4 above is as follows:

[0073] S1. Selection of piling equipment,

[0074] Type of pile driver: choose the appropriate pile driver according to the project scale and construction conditions, including hydraulic pile driver, steam pile driver or vibratory pile driver;

[0075] Equipment capacity, ensuring that the selected pile driver has sufficient pile driving capacity to meet the construction requirements of different pile types and soil layers;

[0076] Auxiliary equipment, equipped with necessary auxiliary equipment such as cranes, grab buckets and conveyor belts to support the piling operation;

[0077] S2. Preparation before piling,

[0078] Pile position review: Before formal piling, the pile position is reviewed based on the data provided by the installation auxiliary positioning system to ensure accurate positioning;

[0079] Construction environment inspection, check the water area and surrounding environment to ensure there are no obstacles, and ensure the operating space and safety of the pile driver;

[0080] Equipment inspection: conduct a comprehensive inspection of the pile driver, including oil, parts and safety devices, to ensure that the equipment is in good condition;

[0081] S3, piling operation process,

[0082] Initial piling: Use a pile driver to drive the pile into the soil to ensure good contact between the pile and the soil;

[0083] Pile driving speed control: adjust the piling speed and frequency according to the soil conditions to avoid damage to the pile body or disturbance of the poor soil layer caused by excessive speed;

[0084] Real-time monitoring: sensors monitor the depth, vibration and other key parameters of pile driving in real time to ensure the quality of pile driving;

[0085] S4, subsequent processing,

[0086] Confirm the depth of pile driving. After the pile driving is completed, use positioning equipment to confirm the final depth and verticality of the pile foundation to ensure that it meets the design requirements;

[0087] Pile body inspection: inspect the driven prefabricated piles to check the integrity and stability of the pile body to ensure there are no cracks or damage;

[0088] S5. Safety measures,

[0089] Construction personnel training: Provide professional training to personnel involved in piling operations to ensure they understand equipment operation and safety precautions;

[0090] Establish a safety zone, set up safety signs and guardrails around the construction area to prevent non-relevant personnel from entering the construction site;

[0091] Emergency Plan: Develop detailed safety emergency plans to ensure that you can respond quickly to emergencies such as equipment failure or weather changes.

[0092] In the above scheme, further:

[0093] The specific process of pile foundation testing described in step 5 above:

[0094] Detection methods,

[0095] Static load test applies vertical load to the pile foundation to test its bearing capacity and settlement performance. Commonly used methods are:

[0096] Single pile static load test, loading a single pile and recording the settlement;

[0097] The pile group static load test is to load a group of piles simultaneously, which is suitable for the evaluation of the bearing capacity of pile group foundations;

[0098] Dynamic load test, by applying dynamic load, using pile hammer or exciter equipment to test the dynamic response of the pile and evaluate its bearing capacity and dynamic characteristics;

[0099] Sonic testing uses ultrasonic or reflected wave technology to evaluate the integrity of the pile through the speed of sound wave propagation and reflected waves. It is suitable for detecting internal defects and quality of piles.

[0100] Core drilling testing, by drilling pile core samples for on-site or laboratory testing, can directly evaluate the actual strength of the pile and the quality of concrete;

[0101] Detection steps,

[0102] S1. Develop a testing plan. According to design requirements and construction conditions, select appropriate testing methods, develop a detailed testing plan, and specify the testing frequency and scope;

[0103] S2. Equipment preparation and calibration: prepare and calibrate the testing equipment to ensure its accuracy and reliability, check the measuring instruments in time and keep them in good condition;

[0104] S3. Implement testing and conduct testing according to the plan. Operators must strictly follow standard operating procedures to ensure the accuracy and reliability of data;

[0105] S4, data recording and analysis, real-time recording of test data, use of professional software to analyze data results, and generate test reports;

[0106] Data evaluation and reporting,

[0107] Qualification standards: evaluate the test results in combination with design requirements and specification standards to determine whether the bearing capacity and quality of the pile foundation meet the requirements;

[0108] Report preparation: After the test is completed, write a detailed test report, including the test method, result analysis, charts and suggestions, clearly expressing the status of the pile foundation and the evaluation conclusion;

[0109] Subsequent processing,

[0110] Defect treatment: formulate corresponding remedial measures for pile foundation defects found during inspection, including reinforcement, replacement or other repair plans;

[0111] Continuous monitoring: In the later stages of the project, the completed pile foundations are regularly monitored to ensure their long-term stability and safety;

[0112] Safety and Compliance,

[0113] Comply with the regulations and strictly follow the relevant national and local testing standards and regulations to ensure the standardization and legality of the testing process;

[0114] Personnel qualifications: ensure that testing personnel have relevant qualifications and experience, and are proficient in the operation of various testing techniques and equipment.

[0115] The beneficial effects of the present invention compared with the prior art are:

[0116] 1. Improve construction efficiency by optimizing each construction step, reducing the waiting and adjustment time during construction, making the entire construction process more compact and efficient.

[0117] 2. Ensure construction quality through precise on-site investigation, accurate positioning system, strict piling control and comprehensive pile foundation testing to ensure that the quality indicators such as the pile foundation's bearing capacity, verticality, and pile body integrity meet the design requirements.

[0118] 3. Reduce construction costs, reasonable equipment layout and selection, effective transportation planning, reduce pile damage and construction errors, and reduce material, equipment and labor costs.

[0119] 4. Enhance construction safety. Strict safety measures and standardized operating procedures reduce safety risks during the construction process and ensure the safety of construction workers and the surrounding environment.

[0120] 5. It can adapt to complex environments and cope with different water conditions, geological conditions and construction requirements, thus improving the versatility and adaptability of construction methods.

[0121] 6. Optimal resource allocation, precise positioning and reasonable construction arrangements reduce material waste and achieve optimal utilization of resources.

[0122] 7. Improve project reliability. Complete testing and subsequent treatment measures ensure the long-term stability and reliability of the pile foundation, thereby improving the quality and service life of the entire project.

[0123] 8. Promote technological development. The application and promotion of this integrated construction method has promoted the continuous innovation and progress of water pile foundation construction technology.

[0124] In summary, the method of the present invention makes the construction of pile foundation on water efficient, accurate and safe, reduces the construction cost, and improves the quality and reliability of the project. DETAILED DESCRIPTION

[0125] The present invention will be further described below in conjunction with specific implementation modes.

[0126] The present invention provides an integrated construction method for pile foundation on water, which comprises the following steps:

[0127] Step 1: Site investigation and equipment layout.

[0128] Set the location for pile foundation driving in the water area and arrange the construction equipment;

[0129] Step 2: Transportation of prefabricated piles.

[0130] Transport the prefabricated piles to the construction site by means of pontoons or water transport vehicles;

[0131] Step 3: Install the auxiliary positioning system.

[0132] Install positioning marks around the piling location to ensure the accuracy of pile driving;

[0133] Step 4: Pile foundation driving.

[0134] Use an automated pile driver to drive piles and monitor pile position and depth in real time;

[0135] Step five: Pile foundation inspection, using sonar or other detection technology to detect the depth and verticality of the pile foundation to ensure construction quality.

[0136] In the above embodiments, preferably:

[0137] The specific process of the on-site investigation described in step 1 above is as follows:

[0138] Hydrological surveys to measure water depth, flow velocity, tidal changes and water temperature, and assess the construction environment in the water area;

[0139] Geological exploration, using drilling and sampling methods to obtain soil conditions, including soil type, clay layer thickness, and groundwater level, in order to determine the bearing capacity of the pile foundation and the appropriate pile type;

[0140] On-site surveying: Use total station or GPS equipment to survey the construction area, obtain the precise coordinates of the pile positions, and provide data support for equipment layout;

[0141] Environmental assessment: inspect the ecological environment of the construction area, assess the impact on surrounding aquatic organisms and ecology, and ensure that the construction meets environmental protection requirements;

[0142] The specific process of equipment arrangement described in the above step 1 is as follows:

[0143] Equipment preparation,

[0144] Pile striking equipment, such as hydraulic pile drivers and vibratory pile drivers, is determined according to the pile type and geological conditions;

[0145] Transportation equipment, such as pontoons and boats, are used to transport precast piles to the construction site;

[0146] Construction platform: build a stable water construction platform to ensure the safe placement of equipment and the operating space for construction personnel;

[0147] Positioning and monitoring equipment, including pile positioning system and depth monitoring equipment, to ensure the accuracy of pile driving;

[0148] The construction platform should be built in an area with stable waters and moderate flow rate to facilitate the operation of construction equipment;

[0149] Transport channel: design a reasonable transport channel to ensure the smooth transportation and placement of precast piles;

[0150] Equipment layout: Arrange heavy equipment on the platform to ensure its stability and safety, while leaving necessary space and passages for other facilities;

[0151] Safety protection measures include setting up warning signs and safety railings in the construction area to ensure the safety of construction workers and people in the surrounding waters.

[0152] In the above embodiments, preferably:

[0153] The specific process of transporting the prefabricated piles described in step 2 above is as follows:

[0154] S1. Transportation preparation,

[0155] Formulate transportation plan, reasonably plan transportation time and route, and determine transportation equipment and personnel arrangements according to construction progress requirements and pile foundation design plan;

[0156] Prefabricated pile inspection: quality inspection of prefabricated piles before leaving the factory to ensure that their strength, size and surface quality meet the construction requirements, and mark the pile numbers and special transportation marks;

[0157] Prepare transportation tools and select appropriate transportation tools according to the size of the pile and the transportation distance;

[0158] S2. Transportation method selection,

[0159] Water transportation, using special transport ships or barges to transport on the water, is suitable for long-distance transportation and reaching remote construction areas. It is necessary to consider the navigation capacity, load limit and water conditions of the ship;

[0160] Land transportation: if the construction area is close to the shore, the piles can be transported to the waterside by truck or trailer, and then transferred to the construction platform by buoys or other tools;

[0161] S3. Loading and bundling of precast piles,

[0162] Loading method: During the loading process, forklifts or cranes should be used to load the prefabricated piles safely and securely onto the transport vehicle, ensuring that there is sufficient support and cushioning between the pile bodies to prevent collisions;

[0163] Binding and fixing: Use appropriate binding materials to firmly bind the prefabricated piles to prevent them from moving or tilting during transportation;

[0164] S4. Transportation process management

[0165] Real-time monitoring: During transportation, use GPS or other positioning systems to monitor the transportation progress in real time to ensure that it arrives at the construction site on time;

[0166] Safety inspection: regularly inspect the transportation tools and loading conditions to ensure there is no looseness, wear or damage, and to ensure transportation safety;

[0167] S5. On-site unloading and transshipment

[0168] Safe unloading: After arriving at the construction site, use a crane or other mechanical equipment to unload the piles to ensure that the piles land smoothly and avoid damage;

[0169] Temporary storage: If precast piles need to be temporarily stored on site, a flat area should be selected and a safety fence should be set up to ensure the safety of the piles and construction workers.

[0170] In the above embodiment, preferably: the specific process of installing the auxiliary positioning system in the above step 3 is as follows:

[0171] System composition,

[0172] Positioning equipment, including laser locators, total stations, and GPS locators, for real-time measurement and recording of pile positions;

[0173] A data processing unit, a computer or a dedicated controller, is used to receive positioning data and process and analyze it;

[0174] Display interface, visual interface, real-time display of pile position information and installation progress, convenient for operators to make adjustments and judgments;

[0175] The installation steps are as follows:

[0176] S1. Site preparation,

[0177] Before construction, the exact location and direction of each pile is determined based on the survey data and marked;

[0178] Clean the construction area to ensure that the positioning equipment has a clear measurement view;

[0179] S2, positioning equipment settings,

[0180] According to the pile position requirements, place the laser or total station at a fixed location to ensure its level and stability;

[0181] Calibrate equipment to ensure measurement accuracy;

[0182] S3, data collection and processing,

[0183] Start the positioning device and start collecting pile position data in real time;

[0184] The data is transmitted to the data processing unit via wireless or wired connection for real-time analysis and calculation;

[0185] S4. Adjustment and supervision,

[0186] The operator monitors the pile position in real time based on the data provided in the display interface;

[0187] According to the information fed back by the positioning system, the installation angles of the equipment and piles are adjusted in real time to ensure that the design requirements are met;

[0188] S5, positioning accuracy,

[0189] When designing the system, factors that affect positioning accuracy should be considered, including water surface interference, wind speed, and equipment accuracy. Through comprehensive analysis of multi-channel factors, the accuracy of positioning can be maximized;

[0190] Regularly calibrate and maintain the equipment to ensure stability and accuracy during long-term use.

[0191] In the above embodiments, preferably:

[0192] The specific process of driving the pile foundation described in step 4 above is as follows:

[0193] S1. Selection of piling equipment,

[0194] Type of pile driver: choose the appropriate pile driver according to the project scale and construction conditions, including hydraulic pile driver, steam pile driver or vibratory pile driver;

[0195] Equipment capacity, ensuring that the selected pile driver has sufficient pile driving capacity to meet the construction requirements of different pile types and soil layers;

[0196] Auxiliary equipment, equipped with necessary auxiliary equipment such as cranes, grab buckets and conveyor belts to support the piling operation;

[0197] S2. Preparation before piling,

[0198] Pile position review: Before formal piling, the pile position is reviewed based on the data provided by the installation auxiliary positioning system to ensure accurate positioning;

[0199] Construction environment inspection, check the water area and surrounding environment to ensure there are no obstacles, and ensure the operating space and safety of the pile driver;

[0200] Equipment inspection: conduct a comprehensive inspection of the pile driver, including oil, parts and safety devices, to ensure that the equipment is in good condition;

[0201] S3, piling operation process,

[0202] Initial piling: Use a pile driver to drive the pile into the soil to ensure good contact between the pile and the soil;

[0203] Pile driving speed control: adjust the piling speed and frequency according to the soil conditions to avoid damage to the pile body or disturbance of the poor soil layer caused by excessive speed;

[0204] Real-time monitoring: sensors monitor the depth, vibration and other key parameters of pile driving in real time to ensure the quality of pile driving;

[0205] S4, subsequent processing,

[0206] Confirm the depth of pile driving. After the pile driving is completed, use positioning equipment to confirm the final depth and verticality of the pile foundation to ensure that it meets the design requirements;

[0207] Pile body inspection: inspect the driven prefabricated piles to check the integrity and stability of the pile body to ensure there are no cracks or damage;

[0208] S5. Safety measures,

[0209] Construction personnel training: Provide professional training to personnel involved in piling operations to ensure they understand equipment operation and safety precautions;

[0210] Establish a safety zone, set up safety signs and guardrails around the construction area to prevent non-relevant personnel from entering the construction site;

[0211] Emergency Plan: Develop detailed safety emergency plans to ensure that you can respond quickly to emergencies such as equipment failure or weather changes.

[0212] In the above embodiments, preferably:

[0213] The specific process of pile foundation testing described in step 5 above:

[0214] Detection methods,

[0215] Static load test applies vertical load to the pile foundation to test its bearing capacity and settlement performance. Commonly used methods are:

[0216] Single pile static load test, loading a single pile and recording the settlement;

[0217] The pile group static load test is to load a group of piles simultaneously, which is suitable for the evaluation of the bearing capacity of pile group foundations;

[0218] Dynamic load test, by applying dynamic load, using pile hammer or exciter equipment to test the dynamic response of the pile and evaluate its bearing capacity and dynamic characteristics;

[0219] Sonic testing uses ultrasonic or reflected wave technology to evaluate the integrity of the pile through the speed of sound wave propagation and reflected waves. It is suitable for detecting internal defects and quality of piles.

[0220] Core drilling testing, by drilling pile core samples for on-site or laboratory testing, can directly evaluate the actual strength of the pile and the quality of concrete;

[0221] Detection steps,

[0222] S1. Develop a testing plan. According to design requirements and construction conditions, select appropriate testing methods, develop a detailed testing plan, and specify the testing frequency and scope;

[0223] S2. Equipment preparation and calibration: prepare and calibrate the testing equipment to ensure its accuracy and reliability, check the measuring instruments in time and keep them in good condition;

[0224] S3. Implement testing and conduct testing according to the plan. Operators must strictly follow standard operating procedures to ensure the accuracy and reliability of data;

[0225] S4, data recording and analysis, real-time recording of test data, use of professional software to analyze data results, and generate test reports;

[0226] Data evaluation and reporting,

[0227] Qualification standards: evaluate the test results in combination with design requirements and specification standards to determine whether the bearing capacity and quality of the pile foundation meet the requirements;

[0228] Report preparation: After the test is completed, write a detailed test report, including the test method, result analysis, charts and suggestions, clearly expressing the status of the pile foundation and the evaluation conclusion;

[0229] Subsequent processing,

[0230] Defect treatment: formulate corresponding remedial measures for pile foundation defects found during inspection, including reinforcement, replacement or other repair plans;

[0231] Continuous monitoring: In the later stages of the project, the completed pile foundations are regularly monitored to ensure their long-term stability and safety;

[0232] Safety and Compliance,

[0233] Comply with the regulations and strictly follow the relevant national and local testing standards and regulations to ensure the standardization and legality of the testing process;

[0234] Personnel qualifications: ensure that testing personnel have relevant qualifications and experience, and are proficient in the operation of various testing techniques and equipment.

[0235] The specific construction equipment in all the above embodiments are conventional market products, and the specific construction techniques in all the above embodiments are existing conventional techniques. The invention is to achieve efficient, accurate and safe construction by optimizing the steps of on-site investigation, prefabricated pile transportation, positioning system installation, pile foundation driving and testing, and reduce construction costs, and improve engineering quality and reliability.

[0236] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution, which should be included in the scope of the claims of the present invention.

Claims

1. An integrated construction method for pile foundation on water, characterized in that: The steps include: Step 1: Site investigation and equipment layout. Set the location for pile foundation driving in the water area and arrange the construction equipment; Step 2: Transportation of prefabricated piles. Transport the prefabricated piles to the construction site by means of pontoons or water transport vehicles; Step 3: Install the auxiliary positioning system. Install positioning marks around the piling location to ensure the accuracy of pile driving; Step 4: Pile foundation driving. Use an automated pile driver to drive piles and monitor pile position and depth in real time; Step five: Pile foundation inspection, using sonar or other detection technology to detect the depth and verticality of the pile foundation to ensure construction quality.

2. The integrated construction method of pile foundation on water according to claim 1, characterized in that: The specific process of the on-site investigation described in step 1 above is as follows: Hydrological surveys to measure water depth, flow velocity, tidal changes and water temperature, and assess the construction environment in the water area; Geological exploration, using drilling and sampling methods to obtain soil conditions, including soil type, clay layer thickness, and groundwater level, in order to determine the bearing capacity of the pile foundation and the appropriate pile type; On-site surveying: Use total station or GPS equipment to survey the construction area, obtain the precise coordinates of the pile positions, and provide data support for equipment layout; Environmental assessment: inspect the ecological environment of the construction area, assess the impact on surrounding aquatic organisms and ecology, and ensure that the construction meets environmental protection requirements; The specific process of equipment arrangement described in the above step 1 is as follows: Equipment preparation, Pile striking equipment, such as hydraulic pile drivers and vibratory pile drivers, is determined according to the pile type and geological conditions; Transportation equipment, such as pontoons and boats, are used to transport precast piles to the construction site; Construction platform: build a stable water construction platform to ensure the safe placement of equipment and the operating space for construction personnel; Positioning and monitoring equipment, including pile positioning system and depth monitoring equipment, to ensure the accuracy of pile driving; The construction platform should be built in an area with stable waters and moderate flow rate to facilitate the operation of construction equipment; Transport channel: design a reasonable transport channel to ensure the smooth transportation and placement of precast piles; Equipment layout: Arrange heavy equipment on the platform to ensure its stability and safety, while leaving necessary space and passages for other facilities; Safety protection measures include setting up warning signs and safety railings in the construction area to ensure the safety of construction workers and people in the surrounding waters.

3. The integrated construction method of pile foundation on water according to claim 1, characterized in that: The specific process of transporting the prefabricated piles described in step 2 above is as follows: S1. Transportation preparation, Formulate transportation plan, reasonably plan transportation time and route, and determine transportation equipment and personnel arrangements according to construction progress requirements and pile foundation design plan; Prefabricated pile inspection: quality inspection of prefabricated piles before leaving the factory to ensure that their strength, size and surface quality meet the construction requirements, and mark the pile numbers and special transportation marks; Prepare transportation tools and select appropriate transportation tools according to the size of the pile and the transportation distance; S2. Transportation method selection, Water transportation, using special transport ships or barges to transport on the water, is suitable for long-distance transportation and reaching remote construction areas. It is necessary to consider the navigation capacity, load limit and water conditions of the ship; Land transportation: if the construction area is close to the shore, the piles can be transported to the waterside by truck or trailer, and then transferred to the construction platform by buoys or other tools; S3. Loading and bundling of precast piles, Loading method: During the loading process, forklifts or cranes should be used to load the prefabricated piles safely and securely onto the transport vehicle, ensuring that there is sufficient support and cushioning between the pile bodies to prevent collisions; Binding and fixing: Use appropriate binding materials to firmly bind the prefabricated piles to prevent them from moving or tilting during transportation; S4. Transportation process management Real-time monitoring: During transportation, use GPS or other positioning systems to monitor the transportation progress in real time to ensure that it arrives at the construction site on time; Safety inspection: regularly inspect the transportation tools and loading conditions to ensure there is no looseness, wear or damage, and to ensure transportation safety; S5. On-site unloading and transshipment Safe unloading: After arriving at the construction site, use a crane or other mechanical equipment to unload the piles to ensure that the piles land smoothly and avoid damage; Temporary storage: If precast piles need to be temporarily stored on site, a flat area should be selected and a safety fence should be set up to ensure the safety of the piles and construction workers.

4. The integrated construction method of pile foundation on water according to claim 1, characterized in that: The specific process of installing the auxiliary positioning system described in step 3 above is as follows: System composition, Positioning equipment, including laser locators, total stations, and GPS locators, for real-time measurement and recording of pile positions; A data processing unit, a computer or a dedicated controller, is used to receive positioning data and process and analyze it; Display interface, visual interface, real-time display of pile position information and installation progress, convenient for operators to make adjustments and judgments; The installation steps are as follows: S1. Site preparation, Before construction, the exact location and direction of each pile is determined based on the survey data and marked; Clean the construction area to ensure that the positioning equipment has a clear measurement view; S2, positioning equipment settings, According to the pile position requirements, place the laser or total station at a fixed location to ensure its level and stability; Calibrate equipment to ensure measurement accuracy; S3, data collection and processing, Start the positioning device and start collecting pile position data in real time; The data is transmitted to the data processing unit via wireless or wired connection for real-time analysis and calculation; S4. Adjustment and supervision, The operator monitors the pile position in real time based on the data provided in the display interface; According to the information fed back by the positioning system, the installation angles of the equipment and piles are adjusted in real time to ensure that the design requirements are met; S5, positioning accuracy, When designing the system, factors that affect positioning accuracy should be considered, including water surface interference, wind speed, and equipment accuracy. Through comprehensive analysis of multi-channel factors, the accuracy of positioning can be maximized; Regularly calibrate and maintain the equipment to ensure stability and accuracy during long-term use.

5. The integrated construction method of pile foundation on water according to claim 1, characterized in that: The specific process of driving the pile foundation described in step 4 above is as follows: S1. Selection of piling equipment, Type of pile driver: choose the appropriate pile driver according to the project scale and construction conditions, including hydraulic pile driver, steam pile driver or vibratory pile driver; Equipment capacity, ensuring that the selected pile driver has sufficient pile driving capacity to meet the construction requirements of different pile types and soil layers; Auxiliary equipment, equipped with necessary auxiliary equipment such as cranes, grab buckets and conveyor belts to support the piling operation; S2. Preparation before piling, Pile position review: Before formal piling, the pile position is reviewed based on the data provided by the installation auxiliary positioning system to ensure accurate positioning; Construction environment inspection, check the water area and surrounding environment to ensure there are no obstacles, and ensure the operating space and safety of the pile driver; Equipment inspection: conduct a comprehensive inspection of the pile driver, including oil, parts and safety devices, to ensure that the equipment is in good condition; S3, piling operation process, Initial piling: Use a pile driver to drive the pile into the soil to ensure good contact between the pile and the soil; Pile driving speed control: adjust the piling speed and frequency according to the soil conditions to avoid damage to the pile body or disturbance of the poor soil layer caused by excessive speed; Real-time monitoring: sensors monitor the depth, vibration and other key parameters of pile driving in real time to ensure the quality of pile driving; S4, subsequent processing, Confirm the depth of pile driving. After the pile driving is completed, use positioning equipment to confirm the final depth and verticality of the pile foundation to ensure that it meets the design requirements; Pile body inspection: inspect the driven prefabricated piles to check the integrity and stability of the pile body to ensure there are no cracks or damage; S5. Safety measures, Construction personnel training: Provide professional training to personnel involved in piling operations to ensure they understand equipment operation and safety precautions; Establish a safety zone, set up safety signs and guardrails around the construction area to prevent non-relevant personnel from entering the construction site; Emergency Plan: Develop detailed safety emergency plans to ensure that you can respond quickly to emergencies such as equipment failure or weather changes.

6. The integrated construction method of pile foundation on water according to claim 1, characterized in that: The specific process of pile foundation testing described in step 5 above: Detection methods, Static load test applies vertical load to the pile foundation to test its bearing capacity and settlement performance. Commonly used methods are: Single pile static load test, loading a single pile and recording the settlement; The pile group static load test is to load a group of piles simultaneously, which is suitable for the evaluation of the bearing capacity of pile group foundations; Dynamic load test, by applying dynamic load, using pile hammer or exciter equipment to test the dynamic response of the pile and evaluate its bearing capacity and dynamic characteristics; Sonic testing uses ultrasonic or reflected wave technology to evaluate the integrity of the pile through the speed of sound wave propagation and reflected waves. It is suitable for detecting internal defects and quality of piles. Core drilling testing, by drilling pile core samples for on-site or laboratory testing, can directly evaluate the actual strength of the pile and the quality of concrete; Detection steps, S1. Develop a testing plan. According to design requirements and construction conditions, select appropriate testing methods, develop a detailed testing plan, and specify the testing frequency and scope; S2. Equipment preparation and calibration: prepare and calibrate the testing equipment to ensure its accuracy and reliability, check the measuring instruments in time and keep them in good condition; S3. Implement testing and conduct testing according to the plan. Operators must strictly follow standard operating procedures to ensure the accuracy and reliability of data; S4, data recording and analysis, real-time recording of test data, use of professional software to analyze data results, and generate test reports; Data evaluation and reporting, Qualification standards: evaluate the test results in combination with design requirements and specification standards to determine whether the bearing capacity and quality of the pile foundation meet the requirements; Report preparation: After the test is completed, write a detailed test report, including the test method, result analysis, charts and suggestions, clearly expressing the status of the pile foundation and the evaluation conclusion; Subsequent processing, Defect treatment: formulate corresponding remedial measures for pile foundation defects found during inspection, including reinforcement, replacement or other repair plans; Continuous monitoring: In the later stages of the project, the completed pile foundations are regularly monitored to ensure their long-term stability and safety; Safety and Compliance, Comply with the regulations and strictly follow the relevant national and local testing standards and regulations to ensure the standardization and legality of the testing process; Personnel qualifications: ensure that testing personnel have relevant qualifications and experience, and are proficient in the operation of various testing techniques and equipment.