Assembled bridge node welding equipment and method
By designing a prefabricated bridge node welding equipment including supporting chassis, splicing frame, welding mating frame and other components, the problem of rapid and prefabricated welding of prefabricated bridge node welding in the prior art is solved, and an efficient and stable welding process and high-quality welding effect are achieved.
Patent Information
- Application Number
- CN202411950338.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-27
- Publication Date
- 2025-04-08
AI Technical Summary
It is difficult for the prior art to achieve rapid and prefabricated welding treatment of prefabricated bridge nodes, and on-site building welding treatment does not meet the needs of modern prefabricated bridge construction.
A prefabricated bridge node welding equipment is designed, including support chassis, splicing frame, welding mating frame, main material transportation frame and auxiliary material transportation frame. Through the coordinated work of these components, rapid loading and transportation of steel structure bulk parts is realized, and efficient and stable welding process is achieved through the cooperation of automated welding equipment and auxiliary mechanisms.
It significantly improves production efficiency, ensures the stability and accuracy of the welding process, improves welding quality and accuracy, and promptly detects and deals with welding defects through real-time detection and spray marking functions of ultrasonic sensors.
Smart Images

Figure CN119772455A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of bridge welding processing, and in particular to assembled bridge node welding equipment and a method thereof. Background Art
[0002] With the acceleration of transportation infrastructure construction, the quality and efficiency requirements of bridge construction are getting higher and higher. Prefabricated bridges are gradually emerging as an efficient way of bridge construction. In prefabricated bridges, the welding quality of nodes is directly related to the safety and durability of the entire bridge structure. In the construction of prefabricated viaducts on urban expressways, nodes need to withstand frequent vehicle loads and complex environmental factors. If the welding quality is not up to standard, fatigue cracks may appear at the nodes, which will endanger the overall safety of the bridge. In addition, in order to complete the bridge construction as soon as possible and reduce the impact on traffic, welding equipment is required to complete the node welding work quickly and efficiently.
[0003] In conjunction with the above content, it should be noted that: Chinese patent CN2021112556066 discloses a steel structure bridge node welding device and method, which is to place and adjust two node plates in parallel, and then manually weld them, and use relevant scanning equipment to detect and adjust the welding gap;
[0004] However, the above patent content makes it difficult to realize the quick assembly process of prefabrication, rapid loading and transportation, that is, the preassembled bridge node components are welded in advance and made into prefabricated parts, and then the prefabricated parts are transported to the bridge installation area for a quick assembly process. As the bridge assembly and processing technology gradually matures, the on-site welding process expressed in the above patent content no longer meets the current needs of prefabricated bridge construction.
[0005] In view of the above technical defects, a solution is now proposed. Summary of the invention
[0006] The object of the present invention is to provide a fabricated bridge node welding device and method thereof to solve the problems raised.
[0007] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: an assembled bridge node welding device, comprising a supporting frame, a splicing frame body is arranged on the outer side of the top of the supporting frame, a plurality of limit cylinder frames are arranged on the inner wall of the bottom of the splicing frame body, a welding matching frame is slidably arranged on the top of the splicing frame body, a welding machine is arranged on the inner wall of the welding matching frame, a spraying pipe is arranged on the outer peripheral wall of the welding machine, and an auxiliary material transport frame is arranged on the inner side of the top of the supporting frame;
[0008] A main material transport rack is arranged on the outer side of the top of the auxiliary material transport rack, a lifting and matching rack is arranged on the inner wall of the bottom of the auxiliary material transport rack, an auxiliary material cylinder rack and an auxiliary material clamp are slidably arranged on the inner side of the top of the auxiliary material transport rack, and a main material cylinder beam and a main material clamp are slidably arranged on the inner wall of the main material transport rack.
[0009] Furthermore, a welding slag collecting conveyor belt is arranged on the inner wall of the bottom of the supporting frame, an external collecting container is arranged on the bottom of one end of the supporting frame, and the splicing frame and the auxiliary material transport frame are sequentially clamped on the top of the supporting frame.
[0010] Furthermore, the limiting cylinder frame has symmetrically arranged on both sides thereof a limiting movable base slidably sleeved with the inner wall of the splicing frame body, the top of the limiting cylinder frame passes through a limiting telescopic cylinder slidably sleeved therethrough, and the bottom of the limiting telescopic cylinder is provided with a limiting clamp located at the bottom of the limiting cylinder frame.
[0011] Furthermore, a wire lifting frame is arranged on the top of the welding coordination frame, and adjusting beams are slidably sleeved on the inner walls at both ends of the welding coordination frame, and a sliding frame connected to the welding machine is sleeved on the surface of the adjusting beam.
[0012] Furthermore, a welding extension cylinder connected to the welding machine is arranged on the top of the sliding frame, a material pump connected to the spray pipe line is arranged on the side of the welding extension cylinder, and moving motors are arranged at the bottom of both sides of the splicing frame.
[0013] Furthermore, a slide frame slidably connected to the auxiliary material cylinder frame is arranged at the top of the inner side of the auxiliary material transport frame, a long groove one is penetrated through the top of the auxiliary material cylinder frame, and a slider one embedded in the long groove one is arranged at the bottom of the auxiliary material clamp, and a long groove four is recessed at the bottom of the inner side of the auxiliary material transport frame.
[0014] Furthermore, a second long groove is recessed on the inner wall of the main material transport rack, and two sliding blocks slidably connected to the second long groove are symmetrically arranged on both sides of the main material cylinder beam. A third long groove is penetrated through the top of the main material cylinder beam, and a third sliding block slidably connected to the third long groove is arranged at the bottom of the main material clamp.
[0015] Furthermore, four sliding blocks slidably connected to four long grooves are symmetrically arranged on both sides of the lifting and cooperating frame, a driving groove is penetrated through the top of the lifting and cooperating frame, and a driving cylinder is embedded in the driving groove, a plurality of sets of adapter plates are arranged on the top of the lifting and cooperating frame, and a lifting cylinder frame penetrating the driving groove and connected to the driving cylinder is arranged at the bottom of the adapter plate.
[0016] The present invention also provides a working method of an assembled bridge node welding device, comprising the following steps:
[0017] Anticipated transportation: After the bridge node steel structure parts are prefabricated in advance, rough parts that are not welded and fixed are obtained. The rough parts are hoisted to the main material transport rack with the cooperation of the conveying mechanism connected to the outside of the welding equipment, and other scattered components are transported to the welding equipment synchronously through the auxiliary material transport rack;
[0018] Rough welding: while waiting for the main material transport rack to transport the rough parts to the middle of the welding device with adaptive clamping; the adjusting beam slides to both sides along the inside of the welding matching rack to adjust the position, the sliding rack slides to both ends along the surface of the adjusting beam to adjust the position, and the welding extension cylinder drives the welding machine to adjust the position up and down, which is used to assist the welding machine to vertically contact the surface of the rough parts and wait for the welding area, and perform the first welding process on the rough parts to obtain rough welded parts;
[0019] Fine welding: The auxiliary material cylinder rack moves along the surface of the slide and transports the scattered components to the bottom of the rough weldment; the lifting cylinder rack is driven by the driving cylinder to approach the bottom of the scattered components, and the lifting cylinder rack drives the adapter plate to slide up, lifts the group of scattered components and moves upward, and with the cooperation of the welding machine, the scattered components are welded and fixed to the rough weldment to obtain the semi-finished weldment.
[0020] The beneficial effects of the present invention are:
[0021] 1. The present invention realizes the rapid and orderly loading and transportation of steel structure parts through the coordinated work of prefabrication, conveying mechanism, main material transport rack and auxiliary material transport rack, which significantly improves the production efficiency. At the same time, the cooperation of automated welding equipment and auxiliary mechanism makes the welding process more efficient and stable. The main material clamp and auxiliary material clamp are adaptively adjusted according to the shape and size of the parts and auxiliary materials, ensuring the stable clamping and precise positioning of the parts during welding, thereby improving the welding quality and accuracy.
[0022] 2. The present invention achieves precise welding of rough parts and scattered components by flexibly adjusting the welding matching frame, adjusting beam, sliding frame and welding extension cylinder, so that the welding machine can vertically contact and adapt to welding areas of different shapes and sizes, and realizes precise welding of rough parts and scattered components. By cooperating with the auxiliary material transport frame and the lifting matching frame, the scattered components are transported one by one and lifted to the bottom of the rough weldment for fine welding and splicing, thereby ensuring the integrity and structural strength of the final weldment.
[0023] 3. The present invention can detect welding defects in time and generate defect signals through the real-time detection function of the ultrasonic sensor. Through the processing of a single controller, the spray marking processing of the defective area is realized, which is convenient for subsequent screening and secondary repair to ensure the welding quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0025] Figure 1 It is a three-dimensional diagram of the overall structure of the present invention;
[0026] Figure 2 It is a structural schematic diagram of the supporting chassis of the present invention;
[0027] Figure 3 It is a structural schematic diagram of the spliced frame and the welded matching frame of the present invention;
[0028] Figure 4 It is a structural schematic diagram of the limiting cylinder frame of the present invention;
[0029] Figure 5 It is a structural schematic diagram of the welding matching frame of the present invention;
[0030] Figure 6 It is a structural schematic diagram of the welding machine of the present invention;
[0031] Figure 7 This is a schematic diagram of the structure of the main material transport rack of the present invention;
[0032] Figure 8 It is a structural schematic diagram of the auxiliary material transport rack of the present invention.
[0033] 1. Support frame; 101. Welding slag collection conveyor belt; 2. Splicing frame; 201. Limiting movable base; 202. Limiting cylinder frame; 203. Limiting clamp; 204. Limiting telescopic cylinder; 3. Welding matching frame; 301. Wire lifting frame; 302. Moving motor; 303. Adjusting beam; 304. Welding machine; 305. Sliding frame; 306. Welding extension cylinder; 307. Material pump; 308. Spraying pipe; 4. Main material transport frame; 402. Main material cylinder beam; 403. Main material clamp; 5. Auxiliary material transport frame; 501. Sliding frame; 502. Auxiliary material cylinder frame; 503. Auxiliary material clamp; 6. Lifting matching frame; 601. Adapter plate; 602. Lifting cylinder frame. DETAILED DESCRIPTION
[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0035] Example 1: Please refer to Figure 1 - Figure 8 As shown, this embodiment is an assembled bridge node welding equipment, including a supporting frame 1, a splicing frame 2 is arranged on the outer side of the top of the supporting frame 1, a plurality of sets of limiting cylinder frames 202 are arranged on the inner wall of the bottom of the splicing frame 2, a welding matching frame 3 is slidably arranged on the top of the splicing frame 2, a welding machine 304 is arranged on the inner wall of the welding matching frame 3, a spray pipe 308 is arranged on the outer peripheral wall of the welding machine 304, and an auxiliary material transport frame 5 is arranged on the inner side of the top of the supporting frame 1.
[0036] After the bridge node steel structure parts are prefabricated in advance, rough parts that are not welded and fixed are obtained. The rough parts are lifted to the main material transport rack 4 with the cooperation of the conveying mechanism connected to the outside of the welding equipment, and other scattered components are transported to the welding equipment synchronously through the auxiliary material transport rack 5. According to the loading order of the rough parts and scattered components, the operating speeds of the main material transport rack 4 and the auxiliary material transport rack 5 are controlled by external personnel to transport them to the welding equipment synchronously.
[0037] A welding slag collecting conveyor belt 101 is arranged on the inner wall at the bottom of the supporting frame 1 , an external collecting container is arranged at the bottom of one end of the supporting frame 1 , and the splicing frame 2 and the auxiliary material transport frame 5 are sequentially clamped on the top of the supporting frame 1 .
[0038] The limiting cylinder frame 202 has symmetrically arranged two sides with limiting movable bases 201 slidably sleeved with the inner wall of the splicing frame 2; the top of the limiting cylinder frame 202 is penetrated by a limiting telescopic cylinder 204 slidably sleeved; the bottom of the limiting telescopic cylinder 204 is provided with a limiting clamp 203 located at the bottom of the limiting cylinder frame 202.
[0039] A wire lifting frame 301 is set on the top of the welding coordination frame 3, and an adjusting beam 303 is slidably sleeved on the inner walls at both ends of the welding coordination frame 3, and a sliding frame 305 connected to the welding machine 304 is sleeved on the surface of the adjusting beam 303; a welding extension cylinder 306 connected to the welding machine 304 is set on the top of the sliding frame 304, and a material pump 307 connected to the spray pipe 308 pipeline is set on the side of the welding extension cylinder 306, and a moving motor 302 is set at the bottom of both sides of the splicing frame 2.
[0040] While waiting for the main material transport rack 4 to adaptively clamp and transport the rough parts to the middle of the welding device, the welding coordination rack 3 is actively driven by multiple sets of mobile motors 302. The output end of the mobile motor 302 is provided with a roller that is slidably connected to the outer side of the top of the supporting base frame 1. Based on this, the welding coordination rack 3 is driven to move and adjust its position along the supporting base frame 1 for preliminary welding processing of the rough parts.
[0041] An inner push cylinder 1 connected to the adjustment beam 303 is arranged on the inner walls at both ends of the welding matching frame 3. The inner push cylinder 1 drives the adjustment beam 303 to slide to both sides along the inside of the welding matching frame 3 to adjust the position, and an inner push cylinder 2 is arranged on the inner walls on both sides of the adjustment beam 303. The inner push cylinder 2 drives the sliding frame 305 to slide to both ends along the surface of the adjustment beam 303 to adjust the position, and the welding extension cylinder 306 drives the welding machine 304 to adjust the position up and down, which is used to assist the welding machine 304 to vertically contact the surface of the rough parts waiting for the welding area, and perform the first welding process on the rough parts to obtain rough weldments.
[0042] Embodiment 2: This embodiment is an assembled bridge node welding equipment, which also includes a main material transport rack 4 arranged on the top outer side of the auxiliary material transport rack 5, a lifting and matching rack 6 arranged on the bottom inner wall of the auxiliary material transport rack 5, an auxiliary material cylinder rack 502 and an auxiliary material clamp 503 are slidably arranged on the inner side of the top of the auxiliary material transport rack 5, and a main material cylinder beam 402 and a main material clamp 403 are slidably arranged on the inner wall of the main material transport rack 4.
[0043] A slide 501 is provided on the top of the inner side of the auxiliary material transport rack 5, which is slidably connected with the auxiliary material cylinder rack 502. A long groove 1 is provided on the top of the auxiliary material cylinder rack 502, and a slider 1 embedded in the long groove 1 is provided at the bottom of the auxiliary material clamp 503. A long groove 4 is provided in a concave manner at the bottom of the inner side of the auxiliary material transport rack 5. The scattered components are hoisted to the auxiliary material transport rack one by one. The auxiliary material clamps on the auxiliary material transport rack are adjusted in advance according to each auxiliary material and replaced with suitable auxiliary material clamps. The number of auxiliary material cylinder racks 502 in a single area is adjusted according to the need to lift the auxiliary materials. Accessories and driving parts are provided at both ends of the auxiliary material cylinder rack 502.
[0044] The accessories are used to cooperate with the sliding connection between the slide 501 and the auxiliary material cylinder frame 502, and the driving member is used to drive the auxiliary material cylinder frame 502 to move along the surface of the slide 501. Accordingly, the auxiliary material transport frame 5 transports the scattered components to the bottom of the rough weldment.
[0045] A long groove II is recessed on the inner wall of the main material transport rack 4, and sliding blocks II slidably connected to the long groove II are symmetrically arranged on both sides of the main material cylinder beam 402. A long groove III is penetrated through the top of the main material cylinder beam 402, and a sliding block III slidably connected to the long groove III is arranged at the bottom of the main material clamp 403. The main material clamp 403 on the main material transport rack 4 is replaced according to the rough loose parts, waiting for external equipment to lift the rough loose parts to one end of the main material transport rack 4, and put them above multiple groups of main material clamps 403. The main material clamps 403 are adjusted in advance by external personnel according to the shape of the rough loose parts, and the number between multiple groups of main material cylinder beams 402 in a single area, so as to adaptively lift and clamp the rough loose parts.
[0046] Slide blocks four are symmetrically arranged on both sides of the lifting and matching frame 6, which are slidably sleeved with the long slots four. A driving slot is penetrated through the top of the lifting and matching frame 6, and a driving cylinder is embedded inside the driving slot. Multiple groups of adapter plates 601 are arranged on the top of the lifting and matching frame 6, and a lifting cylinder frame 602 that penetrates the driving slot and is connected to the driving cylinder is arranged at the bottom of the adapter plate 601. It should be noted that micro motors are arranged inside the multiple groups of sliders for driving the multiple groups of sliders to move inside the corresponding long slots.
[0047] The lifting and matching frame 6 is started, and the lifting cylinder frame 602 is driven by the driving cylinder to slide axially along the driving groove, thereby driving the adapter plate 601 to approach the bottom of the scattered components. The lifting cylinder frame 602 drives the adapter plate 601 to slide upward, lifting the group of scattered components and moving them upward. With the cooperation of the welding machine 304, the scattered components are welded and fixed to the rough weldments. Based on this, the auxiliary material transport frame 5 transports the subsequent scattered components one by one until the required scattered components are assembled and the semi-finished weldments are obtained.
[0048] Embodiment 3: This embodiment is a prefabricated bridge node welding device, wherein a downward ultrasonic sensor is provided at the bottom of the sliding frame 305, and the ultrasonic sensor is used to collect defect data of the welding area of the rough parts, and send the defect data to the database of the main control room in real time, and retrieve the preset welding comparison data from the database for comparison with the defect data:
[0049] If the defect data is greater than the preset welding comparison data, it is determined that there is a defect in the welding of the area, and a defect signal is generated. The database sends the welding signal to the single controller of the welding equipment through the main control room. After receiving the defect signal, the single controller immediately generates a text message in the style of "weld sequence 0383 / weld point abnormality / spray color mark / data record" and displays it on the display screen of the single controller, and emits a "beep beep" alarm sound for 5 seconds to alert the control personnel;
[0050] After receiving the defect signal, the single controller immediately controls the operation of the material pump 307. The material pump 307 is connected to the external pigment container pipeline through a pipeline, and extracts a certain amount of pigment and transports it to the spray pipe 308. A marking rotary cylinder part is provided on the top of the spray pipe 308 and is sleeved on the rod body of the outer wall of the top of the welding machine 304. The marking rotary cylinder part drives the spray pipe 308 to rotate, and the welding area that generates the defect signal is sprayed and marked accordingly, so that the semi-finished weldment can enter the subsequent steps for screening and secondary repair by relevant personnel.
[0051] In combination with Example 1, Example 2 and Example 3, it can be known that the present invention realizes the rapid and orderly loading and transportation of steel structure parts through the coordination of prefabrication processing, conveying mechanism and main and auxiliary material transport frame 5, significantly improves production efficiency, and the coordination of automated welding equipment and adaptive fixtures ensures the stability and accuracy of the welding process. At the same time, the flexible adjustment of components such as the welding coordination frame 3 and the adjustment beam 303 enables the welding machine 304 to accurately weld parts of different shapes and sizes.
[0052] The cooperation between the auxiliary material transport rack 5 and the lifting and matching rack 6 ensures the integrity and structural strength of the weldment; in addition, the real-time detection of the ultrasonic sensor and the processing of the single controller can timely detect welding defects and spray mark them, which is convenient for subsequent screening and repair, ensuring the welding quality.
[0053] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. An assembled bridge node welding device, comprising a supporting frame (1), characterized in that: A splicing frame (2) is arranged on the outer side of the top of the supporting base frame (1); a plurality of groups of limiting cylinder frames (202) are arranged on the inner wall of the bottom of the splicing frame (2); a welding matching frame (3) is slidably arranged on the top of the splicing frame (2); a welding machine (304) is arranged on the inner wall of the welding matching frame (3); a spraying pipe (308) is arranged on the outer peripheral wall of the welding machine (304); and an auxiliary material transport frame (5) is arranged on the inner side of the top of the supporting base frame (1); A main material transport frame (4) is arranged on the outer side of the top of the auxiliary material transport frame (5), a lifting and matching frame (6) is arranged on the inner wall of the bottom of the auxiliary material transport frame (5), an auxiliary material cylinder frame (502) and an auxiliary material clamp (503) are slidably arranged on the inner side of the top of the auxiliary material transport frame (5), and a main material cylinder beam (402) and a main material clamp (403) are slidably arranged on the inner wall of the main material transport frame (4).
2. The assembled bridge node welding equipment according to claim 1 is characterized in that: A welding slag collecting conveyor belt (101) is provided on the inner wall of the bottom of the supporting base frame (1), an external collecting container is provided at the bottom of one end of the supporting base frame (1), and the splicing frame body (2) and the auxiliary material transport frame (5) are sequentially clamped on the top of the supporting base frame (1).
3. The assembled bridge node welding equipment according to claim 1 is characterized in that: The limiting cylinder frame (202) is symmetrically provided with limiting movable bases (201) slidably sleeved with the inner wall of the spliced frame (2) on both sides, the limiting cylinder frame (202) has a limiting telescopic cylinder (204) slidably sleeved through the top, and the limiting telescopic cylinder (204) is provided with a limiting clamp (203) located at the bottom of the limiting cylinder frame (202) at the bottom.
4. The assembled bridge node welding equipment according to claim 1 is characterized in that: A wire lifting frame (301) is arranged on the top of the welding coordination frame (3), and adjusting beams (303) are slidably sleeved on the inner walls at both ends of the welding coordination frame (3), and a sliding frame (305) connected to the welding machine (304) is sleeved on the surface of the adjusting beam (303).
5. The assembled bridge node welding equipment according to claim 4 is characterized in that: A welding extension cylinder (306) connected to the welding machine (304) is arranged on the top of the sliding frame (304), a material pump (307) connected to the spray pipe (308) pipeline is arranged on the side of the welding extension cylinder (306), and moving motors (302) are arranged at the bottom of both sides of the splicing frame (2).
6. The assembled bridge node welding equipment according to claim 1, characterized in that: The top of the inner side of the auxiliary material transport frame (5) is provided with a slide frame (501) which is slidably connected with the auxiliary material cylinder frame (502); the top of the auxiliary material cylinder frame (502) is provided with a long groove one, and the bottom of the auxiliary material clamp (503) is provided with a slide block one embedded in the long groove one; the bottom of the inner side of the auxiliary material transport frame (5) is recessed with a long groove four.
7. The assembled bridge node welding equipment according to claim 1 is characterized in that: The inner wall of the main material transport frame (4) is recessed with a second long groove, and two sliding blocks slidably connected to the second long groove are symmetrically arranged on both sides of the main material cylinder beam (402). A third long groove is penetrated through the top of the main material cylinder beam (402), and a third sliding block slidably connected to the third long groove is arranged at the bottom of the main material clamp (403).
8. The assembled bridge node welding equipment according to claim 6 is characterized in that: The lifting and matching frame (6) is symmetrically provided with four sliding blocks slidably sleeved with the four long grooves on both sides, the top of the lifting and matching frame (6) is provided with a driving groove penetrating therethrough, and a driving cylinder is embedded in the driving groove, the top of the lifting and matching frame (6) is provided with a plurality of sets of adapter plates (601), and the bottom of the adapter plate (601) is provided with a lifting cylinder frame (602) penetrating the driving groove and connected to the driving cylinder.
9. A working method of a prefabricated bridge node welding device, used for a prefabricated bridge node welding device as claimed in any one of claims 1 to 8, characterized in that: The following steps are involved: Anticipated transportation: After the bridge node steel structure parts are prefabricated in advance, rough parts that have not been welded and fixed are obtained. The rough parts are hoisted to the main material transport rack (4) with the cooperation of the conveying mechanism connected to the outside of the welding equipment, and other scattered components are transported to the welding equipment simultaneously through the auxiliary material transport rack (5); Rough welding: while waiting for the main material transport rack (4) to transport the rough parts to the middle of the welding device by adaptive clamping; the adjusting beam (303), the sliding rack (305) and the welding extension cylinder (306) jointly drive the welding machine (304) to adjust the position of the multi-axis, so as to assist the welding machine (304) to vertically contact the surface of the rough parts to wait for the welding area, and perform the first welding process on the rough parts to obtain rough welded parts; Fine welding: the auxiliary material cylinder rack (502) moves along the surface of the slide (501) and transports the scattered components to the bottom of the rough weldment; the group of scattered components is lifted and moved upward, and with the cooperation of the welding machine (304), the scattered components are welded and fixed to the rough weldment to obtain a semi-finished weldment.