Concrete pipe gallery side wall embedded part fixing device

By setting up bottom support components at the bottom of the side wall of the concrete pipe corridor, including side brackets, inner support pieces, support blocks and fixed columns, the uneven settlement and loosening of the embedded parts of the side wall of the pipe corridor due to land settlement is solved, and the stable support and construction convenience of the side wall of the pipe corridor is achieved.

CN119777417APending Publication Date: 2025-04-08NORTH CHINA METALLURGICAL CONSTR ENG CONSTR +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510009090.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-03
Publication Date
2025-04-08

AI Technical Summary

Technical Problem

During the construction process, the embedded parts of the side wall of the concrete pipe corridor are prone to uneven settlement due to land and soil settlement, resulting in loosening and falling off.

Method used

A concrete pipe gallery side wall embedded parts fixing device is designed, including a bottom support component at the bottom of the pipe gallery. The component consists of two side brackets, inner support pieces, support blocks and fixed columns. It is cast and connected through the inner support pieces and support shaft to form a support body, and stabilize the bottom of the pipe gallery through the fixed columns.

Benefits of technology

Effectively prevent the pipeline corridor from falling or tilting due to land settlement, resulting in loosening or falling off of embedded parts, and improve the stability of the side walls of the pipeline corridor and the convenience of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119777417A_ABST
    Figure CN119777417A_ABST
Patent Text Reader

Abstract

The invention provides a concrete pipe gallery side wall embedded part fixing device. The concrete pipe gallery side wall embedded part fixing device comprises a bottom supporting assembly arranged at the bottom of a pipe gallery. Wherein the bottom supporting assembly comprises two side supporting frames arranged on the two sides of the bottom of the pipe gallery correspondingly, an inner supporting piece is connected between the two side supporting frames, and the pipe gallery is supported on the inner supporting piece; moreover, supporting blocks are connected to the outer walls of the two side supporting frames in a sliding mode, and fixing columns are fixedly supported below the supporting blocks. By means of the concrete pipe gallery side wall embedded part fixing device, the problem that an existing concrete pipe gallery side wall embedded part is prone to loosening and falling off can be solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction, and more specifically, to a fixing device for embedded parts of a concrete pipe gallery side wall. Background Art

[0002] Concrete pipe gallery side wall embedded parts refer to metal components or other materials pre-installed or embedded on the concrete pipe gallery side wall. These components or materials are fixed inside the side wall during the concrete pouring process to support, fix or connect other components, equipment or pipelines. During the installation of concrete pipe gallery side wall embedded parts, it is necessary to determine the position and quantity of embedded parts according to the design drawings, and accurately position and fix them before concrete pouring. During the concrete pouring process, it is necessary to ensure the close combination between embedded parts and concrete to avoid hollowing or looseness.

[0003] However, during the actual construction process, the embedded parts of the concrete pipe gallery side wall will not settle evenly due to insufficient support at the bottom of the pipe gallery. This will cause uneven settlement of the concrete pipe gallery side wall, loosening and falling of the embedded parts of the concrete pipe gallery side wall.

[0004] In addition, most concrete pipe corridors are precast, and when their side walls are under construction, it is difficult to reinforce them again according to the actual usage scenario, resulting in inconvenience in the reinforcement of the side walls of concrete pipe corridors during on-site construction.

[0005] Based on this, there is an urgent need for a solution that can effectively solve the problem that the existing embedded parts on the side walls of concrete pipe corridors are prone to loosening and falling off. Summary of the invention

[0006] In view of the above problems, an object of the present invention is to provide a fixing device for embedded parts of the side walls of concrete pipe corridors, so as to solve the problem that the embedded parts of the side walls of existing concrete pipe corridors are prone to loosening and falling off.

[0007] The concrete pipe gallery side wall embedded part fixing device provided by the present invention comprises a bottom support assembly arranged at the bottom of the pipe gallery; wherein the bottom support assembly comprises two side support frames respectively arranged at both sides of the bottom of the pipe gallery, an inner support member is connected between the two side support frames, and the pipe gallery is supported on the inner support member; and

[0008] Support blocks are slidably connected to the outer walls of the two side support frames, and fixed columns are fixedly supported below the support blocks.

[0009] In addition, a preferred solution is that the inner support member includes at least one inner support unit connected between the two side support frames; wherein,

[0010] The inner support monomer comprises two bottom support frames and a support shaft connected between the two bottom support frames, and ends of the two bottom support frames away from each other are respectively fixedly connected to one of the side support frames.

[0011] In addition, a preferred solution is that at least two support blocks are provided on the outer walls of the two side support frames; and

[0012] Limiting grooves are arranged on the outer walls of the two side support frames, and each support block is slidably connected in the corresponding limiting groove.

[0013] In addition, a preferred solution is that a support plate is fixed on the top of the fixing column, and the fixing column is fixedly supported by the support plate and the support block.

[0014] In addition, a preferred solution is that a long slot adapted to the support shaft is opened inside the support frame, and one end of the support shaft is arranged in the long slot; and,

[0015] A positioning mechanism is arranged on the support frame, and one end of the support shaft is limited in the long slot by the positioning mechanism.

[0016] In addition, a preferred solution is that the limiting mechanism includes a fixing bolt and a connecting long hole opened on the top of the two side walls of the limiting groove, and one end of the fixing bolt passes through the two connecting long holes in sequence and is screwed and fixed with a fixing nut.

[0017] In addition, a preferred solution is to further include side support assemblies respectively arranged on both sides of the pipe gallery; wherein the side support assembly includes a receiving plate fixed on the side wall of the pipe gallery, a receiving frame is fixed on the outer wall of the receiving plate, a reinforcing plate is arranged in the receiving frame, and the reinforcing plate is fixedly supported by a support rod and a side support frame on the same side.

[0018] In addition, a preferred solution is that at least two receiving frames are provided on the outer wall of the receiving plate; and,

[0019] The receiving frames are distributed at equal intervals on the outer wall of the receiving plate.

[0020] In addition, a preferred solution is that a support groove is opened at the top of the side support frame, and the lower end of the support rod is supported in the support groove.

[0021] In addition, a preferred solution is that a connecting strip is provided on the inside of the receiving plate, and a reserved groove adapted to the connecting strip is opened on the side wall of the pipe gallery, and the receiving plate is fixed to the side wall of the pipe gallery through the connecting strip and the reserved groove.

[0022] Compared with the prior art, the above-mentioned concrete pipe gallery side wall embedded part fixing device according to the present invention has the following beneficial effects:

[0023] The concrete pipe gallery side wall embedded part fixing device provided by the present invention is provided with two side support frames, and inner support parts are provided on the inner walls of the two side support frames, and the inner support parts are cast and connected through support shafts, so that a supporting body is formed between the two side support frames, and the bottom of the pipe gallery is stably supported in cooperation with the fixed columns, so as to prevent the pipe gallery from falling and tilting due to land settlement after installation, thereby preventing damage.

[0024] In order to achieve the above and related purposes, one or more aspects of the present invention include features that will be described in detail later and are particularly pointed out in the claims. The following description and the accompanying drawings describe some exemplary aspects of the present invention in detail. However, these aspects indicate only some of the various ways in which the principles of the present invention can be used. In addition, the present invention is intended to include all of these aspects and their equivalents. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] By referring to the following description in conjunction with the accompanying drawings, and with a more comprehensive understanding of the present invention, other objects and results of the present invention will become more apparent and easy to understand. In the accompanying drawings:

[0026] Figure 1 A three-dimensional structural diagram of a concrete pipe gallery side wall embedded component fixing device provided by an embodiment of the present invention is shown;

[0027] Figure 2 A schematic structural diagram of a bottom support member of a fixing device for embedded members of a concrete pipe gallery side wall provided by an embodiment of the present invention is shown;

[0028] Figure 3 A schematic structural diagram of a bottom support frame of a fixing device for embedded parts of a concrete pipe gallery side wall provided by an embodiment of the present invention is shown;

[0029] Figure 4 A schematic structural diagram of a side support frame of a fixing device for embedded parts of a concrete pipe gallery side wall provided by an embodiment of the present invention is shown;

[0030] Figure 5 A first structural schematic diagram of a side support assembly of a fixing device for embedded parts of a concrete pipe gallery side wall provided by an embodiment of the present invention is shown;

[0031] Figure 6 A second structural schematic diagram of the side support assembly of the concrete pipe gallery side wall embedded component fixing device provided by an embodiment of the present invention is shown;

[0032] Figure 7 It shows a structural schematic diagram of a single support frame member of a fixing device for embedded parts of a concrete pipe gallery side wall provided by an embodiment of the present invention;

[0033] Figure 8 A schematic structural diagram showing a plurality of bracket members of a fixing device for embedded members of a concrete pipe gallery side wall provided by an embodiment of the present invention;

[0034] Fig. 9 The embodiment of the present invention shows the concrete pipe gallery side wall embedded part fixing device Figure 6 A magnified view of the structure at position A in the middle;

[0035] Figure numerals: pipe gallery 1, receiving frame 2, support rod 3, side support frame 4, support block 5, limit groove 6, support plate 7, fixing column 8, bottom support frame 9, reinforcing plate 10, connecting block 11, supporting shaft 12, fixing bolt 13, supporting groove 14, fixing nut 16, connecting long hole 17, second reinforcing rib 18, receiving plate 20, reserved groove 21, connecting strip 22, first reinforcing rib 23.

[0036] The same reference numerals throughout the drawings indicate similar or corresponding features or functions. DETAILED DESCRIPTION

[0037] In the following description, for the purpose of illustration, in order to provide a comprehensive understanding of one or more embodiments, many specific details are set forth. However, it is apparent that these embodiments may also be implemented without these specific details. In other examples, for ease of describing one or more embodiments, known structures and devices are shown in the form of block diagrams.

[0038] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as limiting the present invention; the terms "first", "second", and "third" are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance; in addition, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0039] Figure 1 The three-dimensional structure of the concrete pipe gallery side wall embedded component fixing device provided by an embodiment of the present invention is shown. Figure 2The structure of the bottom support member of the concrete pipe gallery side wall embedded member fixing device provided by an embodiment of the present invention is shown. Figure 3 The structure of the bottom support frame of the concrete pipe gallery side wall embedded component fixing device provided by an embodiment of the present invention is shown. Figure 4 The structure of the side support frame of the concrete pipe gallery side wall embedded part fixing device provided by the embodiment of the present invention is shown. Figure 5 The first structure of the side support assembly of the concrete pipe gallery side wall embedded component fixing device provided by an embodiment of the present invention is shown. Figure 6 The second structure of the side support assembly of the concrete pipe gallery side wall embedded part fixing device provided by the embodiment of the present invention is shown. Figure 7 The structure of a single frame member of the concrete pipe gallery side wall embedded member fixing device provided by an embodiment of the present invention is shown. Figure 8 The structure of the concrete pipe gallery side wall embedded component fixing device provided by the embodiment of the present invention supports multiple frame components. Fig. 9 The embodiment of the present invention shows the concrete pipe gallery side wall embedded part fixing device Figure 6 The enlarged structure at position A in the middle.

[0040] Combination Figures 1 to 9 It can be known that the concrete pipe gallery 1 side wall embedded part fixing device provided by the present invention includes a bottom support assembly arranged at the bottom of the pipe gallery 1, and the bottom support assembly serves as the main support member of the pipe gallery 1; specifically, the bottom support assembly includes two side support frames 4 respectively arranged on both sides of the bottom of the pipe gallery 1 (one side support frame 4 is arranged on each side), and an inner support member is connected between the two side support frames 4, and the pipe gallery 1 is supported on the inner support member; and, in order to achieve stable support for the two side support frames 4, support blocks 5 are slidably connected to the outer walls of the two side support frames 4, and fixed columns 8 are fixedly supported below the support blocks 5.

[0041] The invention provides a fixing device for embedded parts of the side walls of a concrete pipe gallery 1, which is provided with two side support frames 4, and inner support members are provided on the inner walls of the two side support frames 4, and the inner support members are cast and connected through a support shaft 12, so that a supporting body is formed between the two side support frames 4, and the bottom of the pipe gallery 1 is stably supported in cooperation with the fixed columns 8, so as to prevent the pipe gallery 1 from falling and tilting due to land settlement after installation, thereby causing damage.

[0042] In a specific embodiment of the present invention, in order to achieve stable support of the entire pipe corridor 1 by the internal support components, the internal support components may include an internal support unit connected between two side support frames 4, and multiple (at least one) internal support units may be provided. Then, the pipe corridor 1 is erected on multiple internal support units. By providing multiple internal support units, the support stability of the internal support components is ensured.

[0043] Furthermore, in order to realize the production of the internal support unit, the internal support unit may include two bottom support frames 9 and a support shaft 12 connected between the two bottom support frames 9, and the ends of the two bottom support frames 9 that are away from each other are respectively fixedly connected to the side support frames 4 on the corresponding sides, and the pipeline corridor 1 is erected on multiple internal support units composed of two bottom support frames 9 and one support shaft 12.

[0044] In the actual manufacturing process, multiple support blocks 5 can be slidably arranged on the side support frame 4, and limiting grooves 6 are provided on the outer walls of the two side support frames 4, and each support block 5 is slidably connected in the corresponding limiting groove 6; in the actual construction process, the position of the support block 5 on the side support frame 4 is adjusted by sliding the support block 5 in the corresponding limiting groove 6, so that the fixed column 8 under the support block 5 can be supported in a relatively stable bottom surface, thereby effectively improving the support stability of the bottom support assembly to the pipe gallery 1. Furthermore, in order to achieve stable support between the support block 5 and the fixed column 8, a support plate 7 is fixed on the top of the fixed column 8, and the fixed column 8 is fixedly supported by the support plate 7 and the support block 5.

[0045] In addition, based on the different widths of the pipe gallery 1, different lengths of internal support units can be set for support; in order to achieve the length adjustment of the internal support unit, a long groove adapted to the support shaft 12 is opened inside the support frame, and one end of the support shaft 12 is set in the long groove and can be adjusted in the front and rear position; and a positioning mechanism is provided on the support frame. When one end of the support shaft 12 is adjusted to a preset position in the long groove, one end of the support shaft 12 is limited in the long groove by the positioning mechanism (mainly limiting the vertical direction of the support shaft 12), so as to achieve the length adjustment of the entire internal support unit. After the length of the internal support unit is adjusted to the preset value, the bottom support frame 9 and the support shaft 12 are cast and fixed by pouring concrete.

[0046] Furthermore, in order to achieve position limiting of the support shaft 12 by the limiting mechanism, the limiting mechanism may include a fixing bolt 13 and a connecting long hole 17 opened at the top of the two side walls of the limiting groove 6. One end of the fixing bolt 13 passes through the two connecting long holes 17 in sequence and is screwed and fixed with the fixing nut 16 to achieve position limiting of the support shaft 12 by the limiting mechanism.

[0047] In another preferred embodiment of the present invention, the concrete pipe gallery 1 side wall embedded part fixing device provided by the present invention may also include side support components respectively arranged on both sides of the pipe gallery 1, and the side support components are used to stably support both sides of the pipe gallery 1.

[0048] Specifically, the side support assembly may include a receiving plate 20 fixed on the side wall of the pipe gallery 1, a receiving frame 2 is fixed on the outer wall of the receiving plate 20 (the side away from the side wall of the pipe gallery 1), a reinforcing plate 10 is arranged inside the receiving frame 2, and the reinforcing plate 10 is fixedly supported by the side support frame 4 on the same side through the support rod 3, so as to support the side wall of the pipe gallery 1. It should be noted that the side support assembly provided by the present invention is also supported on the bottom support assembly as the supporting body, and there is no need to set a separate force point for the side support assembly, so that the force of the entire concrete pipe gallery 1 side wall embedded part fixing device is concentrated.

[0049] In order to achieve fixed support of the reinforcing plate 10 and the side support frame 4 on the same side through the support rod 3, a plurality of connecting blocks 11 can be fixedly arranged at equal distances on the outer wall of the reinforcing plate 10, and supported between the side support frame 4 and the connecting blocks 11 at corresponding positions by using support rods 3 of different lengths.

[0050] Furthermore, in order to enhance the supporting stability of the side support assembly on the side wall of the pipe gallery 1, a plurality of (at least two) receiving frames 2 are arranged on the outer wall of the receiving plate 20; and the receiving frames 2 are evenly spaced on the outer wall of the receiving plate 20 to ensure that the side support assembly is evenly stressed on the side wall of the pipe gallery 1.

[0051] In addition, in order to prevent the lower end of the support rod 3 from sliding on the side support frame 4, a support groove 14 can be opened on the top of the side support frame 4, and the lower end of the support rod 3 is limitedly supported in the support groove 14 to achieve the lower end limit of the support rod 3.

[0052] In addition, in order to achieve a stable connection between the receiving plate 20 and the side wall of the pipe gallery 1, a connecting strip 22 can be arranged on the inside of the receiving plate 20, and a reserved groove 21 adapted to the connecting strip 22 can be opened on the side wall of the pipe gallery 1. The connecting strip 22 can be limited in the reserved groove 21, and the receiving plate 20 is fixed to the side wall of the pipe gallery 1 through the connecting strip 22 and the reserved groove 21.

[0053] Of course, in order to further improve the supporting stability of the side wall embedded part fixing device of the concrete pipe gallery 1 provided by the present invention, reinforcing ribs can also be arranged in the specific supporting parts. For example, the first reinforcing rib 23 (multiple reinforcing ribs can be arranged) can be cast inside the connecting strip 22, and the second reinforcing rib 18 (multiple reinforcing ribs can be arranged) can be cast inside the bottom support frame 9, etc.

[0054] The concrete pipe gallery 1 side wall embedded part fixing device provided by the present invention can quickly engage and connect the receiving plate 20 during the actual construction process by arranging side support components on both sides of the side wall of the pipe gallery 1, and then cast and fix the receiving plate 20 with concrete, so that the two receiving plates 20 can firmly and firmly support the two side walls of the pipe gallery 1. At the same time, the first reinforcing ribs 23 and the reinforcing plates 10 are fixedly connected to the inner and outer walls of the receiving plates 20, respectively, so that the overall support of the receiving plates 20 is more stable, thereby facilitating the reinforcement and use of the side wall structure of the pipe gallery 1 and the installation and fixation of the embedded parts.

[0055] As above Figures 1 to 9 The concrete pipe gallery side wall embedded component fixing device provided by the present invention is described by way of example. However, those skilled in the art should understand that various improvements can be made to the concrete pipe gallery side wall embedded component fixing device proposed by the present invention without departing from the content of the present invention. Therefore, the protection scope of the present invention should be determined by the content of the attached claims.

Claims

1. A fixing device for embedded parts of concrete pipe gallery side wall, characterized in that: It comprises a bottom support assembly arranged at the bottom of the pipe gallery; wherein the bottom support assembly comprises two side support frames respectively arranged at two sides of the bottom of the pipe gallery, an inner support member is connected between the two side support frames, and the pipe gallery is supported on the inner support member; and Support blocks are slidably connected to the outer walls of the two side support frames, and fixed columns are fixedly supported below the support blocks.

2. The concrete pipe gallery side wall embedded part fixing device according to claim 1, characterized in that: The inner support member includes at least one inner support unit connected between the two side support frames; wherein, The inner support unit comprises two bottom support frames and a support shaft connected between the two bottom support frames, and ends of the two bottom support frames away from each other are respectively fixedly connected to the side support frames on the corresponding sides.

3. The concrete pipe gallery side wall embedded part fixing device according to claim 2, characterized in that: At least two support blocks are provided on the outer walls of the two side support frames; and Limiting grooves are provided on the outer walls of the two side support frames, and each support block is slidably connected in the corresponding limiting groove.

4. The concrete pipe gallery side wall embedded part fixing device according to claim 3, characterized in that: A support plate is fixed on the top of the fixed column, and the fixed column is fixedly supported by the support plate and the support block.

5. The concrete pipe gallery side wall embedded part fixing device according to claim 4, characterized in that: A long slot adapted to the support shaft is provided inside the support frame, and one end of the support shaft is arranged in the long slot; and A positioning mechanism is arranged on the support frame, and one end of the support shaft is limited in the long slot by the positioning mechanism.

6. The concrete pipe gallery side wall embedded part fixing device according to claim 5, characterized in that: The limiting mechanism comprises a fixing bolt and a connecting long hole provided at the top of the two side walls of the limiting groove, and one end of the fixing bolt passes through the two connecting long holes in sequence and is screwed and fixed with a fixing nut.

7. The concrete pipe gallery side wall embedded part fixing device according to any one of claims 1 to 6, characterized in that: It also includes side support components respectively arranged on both sides of the pipe gallery; wherein, The side support assembly includes a receiving plate fixed on the side wall of the pipe gallery, a receiving frame fixed on the outer wall of the receiving plate, a reinforcing plate arranged in the receiving frame, and the reinforcing plate is fixedly supported by the side support frame on the same side through a support rod.

8. The concrete pipe gallery side wall embedded part fixing device according to claim 7, characterized in that: At least two receiving frames are provided on the outer wall of the receiving plate; and The receiving frames are distributed at equal intervals on the outer wall of the receiving plate.

9. The concrete pipe gallery side wall embedded part fixing device according to claim 8, characterized in that: A support groove is provided on the top of the side support frame, and the lower end of the support rod is supported in the support groove.

10. The concrete pipe gallery side wall embedded part fixing device according to claim 9, characterized in that: A connecting strip is arranged inside the receiving plate, and a reserved groove matched with the connecting strip is opened on the side wall of the pipe gallery. The receiving plate is fixed to the side wall of the pipe gallery through the connecting strip and the reserved groove.