Quick-release hub structure of track translation trolley in tunnel

By designing a coordinated and coordinated rail translation car quick-disassembly hub structure, the problem of rapid disassembly and replacement of wheel hubs in the prior art is solved, and the effect of rapid construction and extended bearing life is achieved.

CN119795790APending Publication Date: 2025-04-11CHINA RAILWAY 18TH BUREAU GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411838627.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-13
Publication Date
2025-04-11

AI Technical Summary

Technical Problem

The existing track translation trolley cannot be quickly disassembled and replaced when the wheel hub is damaged, resulting in congestion in the transportation channel, affecting subsequent construction processes, and easily causing damage to the wheel hub.

Method used

A quick-disassembly hub structure of the rail translating trolley in the tunnel was designed. Through the coordinated cooperation of steel frame 3, steel frame 1, steel frame 2, steel frame 4, steel wheels and steel shafts, rapid disassembly and replacement are achieved. Double-row tapered roller bearings and hexagon bolts are connected to ensure the stability and reliability of the structure.

Benefits of technology

It realizes rapid disassembly and replacement of rail-translation trolley wheel hubs, reduces construction time, avoids congestion in transportation channels, extends the service life of the bearings, and improves the stability and reliability of the overall structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119795790A_ABST
    Figure CN119795790A_ABST
Patent Text Reader

Abstract

The invention relates to the field of rail translation trolleys, and discloses a quick-release hub structure of a rail translation trolley in a tunnel, which comprises a steel wheel, and a steel shaft is arranged in the middle of the steel wheel in a penetrating manner; a second steel frame is arranged outside the first steel frame, and the first steel frame and the second steel frame are connected through two fourth steel frames; the steel wheels are located in a closed space formed by the first steel frame, the second steel frame and the two fourth steel frames. The number of the third steel frames is two, the two third steel frames are installed between the first steel frame and the second steel frame correspondingly, and the two sides of the steel shaft are located between the first steel frame and the third steel frames and between the second steel frame and the third steel frames correspondingly. Through cooperation of the third steel frame, the first steel frame, the second steel frame, the fourth steel frame, the steel wheels and the steel shafts, hub quick-release type construction of the track translation trolley in the tunnel is achieved, and the construction time generated when the steel wheels of the track translation trolley are damaged and need to be maintained and replaced is shortened; the influence of a concrete tank car and a material transport vehicle on subsequent construction procedures due to the damage of steel wheels of the translation trolley is avoided, and time, manpower and material resources are saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of track translation trolleys, in particular to a quick-detachable wheel hub structure of a track translation trolley in a tunnel. Background Art

[0002] As my country's railway, highway, water pipeline and other infrastructure enters a period of equal emphasis on construction and maintenance, the number of railway tunnels, highway tunnels and water tunnels under construction has increased rapidly, and the span and depth of tunnel excavation have continued to increase. During the construction of tunnels, the transport track in the tunnel is generally a single track, and some construction sections are double tracks. When transporting concrete tankers and material transport vehicles by track, if the tankers and other material transport vehicles are not transferred in time, it will cause congestion in the transportation channel and seriously affect the subsequent transportation process. Because the wheel hub of the track translation trolley is extremely easy to be damaged when running under high pressure and high-intensity load conditions, therefore, solving the problem of rapid disassembly and replacement of the translation trolley in the tunnel is of vital importance in tunnel material transportation.

[0003] A survey of the existing domestic rail translation trolleys found that the existing rail translation trolleys are mainly optimized in terms of the width, length, area of ​​the loading panel and the load capacity of the rail translation trolley, and the problem of rapid disassembly and rapid replacement of the rail trolley wheel hub when it is damaged has not been effectively solved. Therefore, there is an urgent need for a quick-detachable wheel hub structure for the rail translation trolley in the tunnel in China. Summary of the invention

[0004] In view of the deficiencies in the prior art, the present invention provides a quick-detachable wheel hub structure for a track translation trolley in a tunnel, which solves the problem in the prior art that the problem of quick disassembly and quick replacement of the track trolley wheel hub when damaged has not been effectively solved.

[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions: a quick-detachable wheel hub structure for a track-translation trolley in a tunnel, comprising:

[0006] A steel wheel with a steel shaft passing through the middle;

[0007] Steel frame one, with steel frame two outside, the two are connected by two steel frames four; and the steel wheel is in a closed space formed by steel frame one, steel frame two and two steel frames four;

[0008] Steel frame three is provided with two, and the two steel frames three are respectively installed between steel frame one and steel frame two, and the two sides of the steel axis are respectively located between steel frame one and steel frame three and between steel frame two and steel frame three.

[0009] Preferably, the steel shaft is connected to the steel wheel using double-row tapered roller bearings, cylinders are provided on both sides of the steel shaft, and a plane is provided on the outer wall of the cylinder on one side of the steel shaft, and both sides of the steel shaft are locked by retaining springs for the steel shaft to move left and right in the bearings.

[0010] Preferably, the steel frame one and the steel frame three and the steel frame two and the steel frame three are riveted by bolts, and the bolts are hexagon socket bolts. Both sides of the two steel frames four are connected to both sides of the side surfaces close to the steel frame one and the steel frame two by double-sided submerged arc welding.

[0011] Preferably, the steel frame one, the steel frame two and the two steel frames three are all provided with threaded holes inside, and the bolts are located in the threaded holes.

[0012] Preferably, a pin is provided inside the cylinder on the other side of the steel shaft, and an oil nozzle and an oil filling hole are provided inside the pin for filling grease through the oil filling hole and the grease nozzle.

[0013] Preferably, the steel frame one and the steel frame two have the same size, and the two steel frames three and the two steel frames four have the same size.

[0014] Preferably, the top surfaces of the steel frame one and the steel frame two are both provided with mounting holes, and the mounting holes on the top surface of the steel frame two are circular, and the mounting holes on the top surface of the steel frame one are provided with flat surfaces for matching the cylinders provided on both sides of the steel shaft.

[0015] Preferably, the steel wheel, steel shaft, steel frame three, steel frame one, steel frame two and steel frame four are made of one of Q235 steel or Q345 steel.

[0016] The present invention provides a quick-detachable wheel hub structure for a track-translation trolley in a tunnel, which has the following beneficial effects:

[0017] 1. The present invention realizes the quick-disassembly construction of the wheel hub of the track translation trolley in the tunnel through the coordinated cooperation of the steel frame three, the steel frame one, the steel frame two and the steel frame four, the steel wheel and the steel shaft, thereby reducing the construction man-hours caused by the need to repair and replace the damaged steel wheel of the track translation trolley, avoiding the influence of concrete tankers and material transport vehicles on subsequent construction procedures due to the damage of the steel wheel of the translation trolley, and saving time, manpower and material resources.

[0018] 2. The present invention sets the size of steel frame 1 and steel frame 2 to be the same, and the size of two steel frames 3 and two steel frames 4 to be the same, so that the length, width, thickness, reserved installation holes and threaded hole positions of the four steel wheels, steel shafts and steel frames of the track translation trolley are all of the same size, so that the installation and subsequent maintenance of the components can be carried out quickly, accurately, efficiently and energy-savingly, reducing the construction period.

[0019] 3. The present invention connects the steel shaft and the steel wheel by adopting double-row tapered roller bearings, and the steel frame one and the steel frame three are riveted with hexagon socket bolts, the steel frame two and the steel frame three are riveted with hexagon socket bolts, and the steel frame four is welded to the ends of the steel frame one and the steel frame two by double-sided submerged arc welding. Among them, the double-row tapered roller bearings have a large load-bearing capacity, can stably operate under heavy loads and impact loads for a long time, and can automatically adjust the axis deviation to make the bearing force uniform, greatly reduce the wear and fatigue of the bearing, and extend the service life of the bearing. The hexagon socket bolts are tightly and reliably connected and not easy to fall off, and the installation process is simple and the disassembly is strong. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a structural schematic diagram of the present invention;

[0021] Figure 2 A front view of a steel frame of the present invention;

[0022] Figure 3 A side view of the steel frame of the present invention;

[0023] Figure 4 A top view of the steel frame of the present invention;

[0024] Figure 5 It is a second front view of the steel frame of the present invention;

[0025] Figure 6 It is a side view of the steel frame of the present invention;

[0026] Figure 7 It is a second top view of the steel frame of the present invention;

[0027] Figure 8 It is three front views of the steel frame of the present invention;

[0028] Fig. 9 It is three side views of the steel frame of the present invention;

[0029] Fig.10 It is a three-dimensional top view of the steel frame of the present invention;

[0030] Fig.11 It is four front views of the steel frame of the present invention;

[0031] Fig.12 Four side views of the steel frame of the present invention;

[0032] Fig.13 Four top views of the steel frame of the present invention;

[0033] Fig.14 It is a front view of the pin shaft of the present invention;

[0034] Fig.15 It is a side view of the pin shaft of the present invention;

[0035] Fig.16 A top view of the pin of the present invention;

[0036] Fig.17 It is a front view of the steel shaft and the steel wheel of the present invention;

[0037] Fig.18 A side view of a steel shaft and a steel wheel of the present invention;

[0038] Fig.19 It is a top view of the steel shaft and steel wheel of the present invention.

[0039] Among them, 1. steel wheel; 2. steel shaft; 3. steel frame three; 4. steel frame one; 5. steel frame two; 6. steel frame four; 7. bolt; 8. mounting hole; 9. threaded hole; 10. pin shaft; 11. oil nozzle; 12. oil filling hole. DETAILED DESCRIPTION

[0040] The following will be combined with the drawings in the specification of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0041] In order to better understand the present invention, the above contents are described in detail below in conjunction with specific embodiments.

[0042] Please see attached Figure 1-Figure 19 The embodiment of the present invention provides a quick-detachable wheel hub structure of a track translation trolley in a tunnel, comprising: a steel wheel 1, a steel shaft 2 is passed through the middle of the steel wheel 1; a steel frame 1 4, a steel frame 2 5 is provided on the outside of the steel wheel 1, and the two are connected by two steel frames 4 6; and the steel wheel 1 is in a closed space formed by the steel frame 1 4, the steel frame 2 5 and the two steel frames 4 6; a steel frame 3 3 is provided with two steel frames 3, and the two steel frames 3 3 are respectively installed between the steel frame 1 4 and the steel frame 2 5, and the two sides of the steel shaft 2 are respectively between the steel frame 1 4 and the steel frame 3 3 and between the steel frame 2 5 and the steel frame 3 3.

[0043] In the present invention, the steel wheel 1 is supported by the steel shaft 2, and the steel shaft 2 is connected to the steel wheel 1 through a double-row tapered roller bearing, which ensures the smooth rotation of the steel wheel 1 on the shaft. The steel frame 1 4 and the steel frame 2 5 are respectively arranged on both sides of the steel wheel 1, and are connected through two steel frames 4 6 to form a closed structural space, fixing the steel wheel 1 in the middle, and providing sufficient supporting force. The two steel frames 3 3 are respectively installed between the steel frame 1 4 and the steel frame 2 5, which play a role in reinforcing and stabilizing the entire structure. The two sides of the steel shaft 2 are respectively between the steel frame 1 4 and the steel frame 3 3 and between the steel frame 2 5 and the steel frame 3 3, ensuring the stable operation of the steel wheel 1 and sharing the load.

[0044] The steel shaft 2 is connected to the steel wheel 1 using double-row tapered roller bearings. Cylinders are provided on both sides of the steel shaft 2, and a plane is provided on the outer wall of the cylinder on one side of the steel shaft 2. Both sides of the steel shaft 2 are locked by retaining springs to enable the steel shaft 2 to move left and right in the bearings.

[0045] In the present invention, the steel shaft 2 is connected to the steel wheel 1 through a double-row tapered roller bearing, so it can provide a larger load-bearing capacity, ensure stable operation under heavy loads and impact loads, and can automatically adjust the axis deviation to make the bearing force uniform and reduce wear and fatigue. Cylinders are provided on both sides of the steel shaft 2 to cooperate with the inside of the bearing to enhance stability. The outer wall of the cylinder on one side of the steel shaft 2 is provided with a plane design, which helps to dock and fix with other components, ensuring the accuracy and reliability of assembly. At the same time, both sides of the steel shaft 2 are locked by retaining springs to prevent the steel shaft 2 from moving left and right in the bearing, ensuring a stable connection between the steel shaft 2 and the steel wheel 1, and improving the stability and durability of the entire structure.

[0046] The steel frame 1 4 and the steel frame 3 3 as well as the steel frame 2 5 and the steel frame 3 3 are riveted by bolts 7, and the bolts 7 are hexagon socket bolts. Both sides of the two steel frames 4 6 are connected to the two sides of the side surfaces close to the steel frame 1 4 and the steel frame 2 5 by double-sided submerged arc welding.

[0047] In the present invention, the steel frame 1 4 and the steel frame 3 3, as well as the steel frame 2 5 and the steel frame 3 3 are riveted by bolts 7, and the bolts 7 are hexagon socket bolts. This connection method can provide high-strength and reliable fixation, ensuring that they will not loosen or fall off under heavy-load working environments. The use of hexagon socket bolts simplifies the installation process, while providing sufficient tightening force to facilitate rapid disassembly and maintenance of the equipment. In order to further enhance the stability of the connection, the two sides of the two steel frames 4 6 are firmly connected to the adjacent sides of the steel frame 1 4 and the steel frame 2 5 by double-sided submerged arc welding. Double-sided submerged arc welding has strong welding strength and durability, and can maintain the stability of the structure under high load conditions, ensuring that the entire hub structure will not deform or loosen during long-term use.

[0048] The steel frame 1 4 , the steel frame 2 5 and the two steel frames 3 are all provided with threaded holes 9 inside, and the bolts 7 are located in the threaded holes 9 .

[0049] In the present invention, the steel frame 1 4, the steel frame 2 5 and the two steel frames 3 are all provided with threaded holes 9 inside, and the bolts 7 are installed therein through the threaded holes 9. It is ensured that the bolts 7 can be accurately fixed at the predetermined position, and a more stable connection method is provided. The existence of the threaded holes 9 not only improves the reliability of the connection, but also facilitates subsequent maintenance and replacement operations. Through this structure, the bolts 7 can effectively withstand the force under high load conditions, and ensure the tightness between the connecting parts to avoid loosening or deformation. It also simplifies the overall assembly and disassembly process, improves the manufacturing and maintenance efficiency, and ensures the long-term stable operation of the hub structure.

[0050] A pin shaft 10 is provided inside the cylinder on the other side of the steel shaft 2 , and an oil nozzle 11 and an oil filling hole 12 are provided inside the pin shaft 10 for filling grease through the oil filling hole 12 and the grease nozzle 11 .

[0051] In the present invention, a pin shaft 10 is provided inside the cylinder on the other side of the steel shaft 2, and an oil nozzle 11 and an oil filling hole 12 are provided inside the pin shaft 10. This structure is used to add butter through the oil filling hole 12 and the butter nozzle 11 to ensure the lubrication of the double-row tapered roller bearing between the steel shaft 2 and the steel wheel 1 under high load and long-term operation. Through the oil nozzle 11 and the oil filling hole 12, lubricating oil can be easily injected into the bearing part to reduce friction and wear, thereby extending the service life of the bearing and improving the working efficiency and reliability of the overall structure. It effectively solves the problem of difficult lubrication, reduces the occurrence of mechanical failures, and is also convenient for daily maintenance and maintenance, further improving the operating stability of the track translation trolley in the tunnel.

[0052] The steel frame 1 4 has the same size as the steel frame 2 5 , and the two steel frames 3 3 and the two steel frames 4 6 have the same size.

[0053] In the present invention, the size of steel frame 1 4 is the same as that of steel frame 2 5, and the size of two steel frames 3 3 and two steel frames 4 6 is the same. This design ensures the dimensional consistency of the components of the track translation trolley in the tunnel, so that the components can be standardized and unified during installation and later maintenance, thereby improving assembly accuracy and work efficiency. Through unified dimensions, manufacturing errors and mismatch problems are reduced, and the fit between components is tighter, ensuring the stability and reliability of the structure. In addition, the standardized design simplifies the production process, facilitates rapid disassembly and assembly during mass production and component replacement, improves the maintenance efficiency of the entire device, and reduces maintenance costs. This enables the equipment to operate stably for a long time, while improving interchangeability and ease of maintenance during use.

[0054] The top surfaces of steel frame 1 4 and steel frame 2 5 are both provided with mounting holes 8 , and the mounting holes 8 on the top surface of steel frame 2 5 are circular, and the mounting holes 8 on the top surface of steel frame 1 4 are provided with flat surfaces for matching the cylinders provided on both sides of the steel shaft 2 .

[0055] In the present invention, the top surface of steel frame 1 4 and the top surface of steel frame 2 5 are both provided with mounting holes 8, and the mounting holes 8 on the top surface of steel frame 2 5 are circular, and the mounting holes 8 on the top surface of steel frame 1 4 are provided with planes for matching the cylinders provided on both sides of the steel shaft 2. Through this design, the shape and position of the mounting holes accurately match the cylinders on both sides of the steel shaft 2, ensuring the accurate positioning and stable support of the steel shaft 2 between steel frame 1 4 and steel frame 2 5. The circular mounting holes 8 on the top surface of steel frame 2 5 are tightly matched with the cylinders of the steel shaft 2, which can effectively prevent the deviation or instability of the steel shaft 2, thereby improving the working performance and bearing capacity of the steel shaft and the steel wheel. At the same time, the matching of the plane mounting holes 8 on the top surface of steel frame 1 4 with the cylinders enhances the installation accuracy, ensures the tightness and stability of the entire structure, and avoids the deviation or looseness caused by installation errors. Not only does it optimize the assembly process, but it also improves the overall stability and service life of the trolley.

[0056] The steel wheel 1, the steel shaft 2, the steel frame three 3, the steel frame one 4, the steel frame two 5 and the steel frame four 6 are made of materials including one of Q235 steel or Q345 steel.

[0057] In the present invention, Q235 steel has good plasticity and welding properties, and is suitable for manufacturing structural components that bear lighter loads, while Q345 steel has higher strength and wear resistance, and is suitable for components that bear larger mechanical loads. Selecting these two types of steel as the main materials can not only meet the strength and durability required by the steel wheel 1, steel shaft 1 and various steel frame components in the track translation trolley in the tunnel, but also effectively ensure the bearing capacity and long-term stable operation of the entire structure. The use of Q235 or Q345 steel can ensure the stability of the components under high-strength and long-term working conditions, and also has good processing performance, which helps to improve efficiency during production and installation. Choosing one of these two materials can make an appropriate choice based on actual load requirements and cost considerations, thereby providing excellent performance in different working environments.

[0058] Working principle: When in use, the double-row tapered roller bearings can make the steel wheel 1 and the steel shaft 2 rotate with each other, thereby realizing the movement of the rail trolley in the tunnel. When the trolley steel wheel 1 is damaged and needs to be removed and replaced with a new steel wheel 1, first use the hydraulic jack to lift the entire translation trolley to a certain height, then remove the hexagon socket bolts 7 riveted between the steel frame 1 4 and the steel frame 3 3, remove the hexagon socket bolts 7 riveted between the steel frame 2 5 and the steel frame 3 3, remove the damaged steel shaft 2 and steel wheel 1 again, replace the new steel shaft 2 and wheel hub steel wheel 1, finally tighten the hexagon socket bolts 7 riveted between the steel frame 1 4 and the steel frame 3 3, tighten the hexagon socket bolts 7 riveted between the steel frame 2 5 and the steel frame 3 3, and remove the hydraulic jack. Then the steel wheel 1 can be quickly loaded and unloaded.

[0059] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A quick-detachable wheel hub structure for a track-translating trolley in a tunnel, characterized in that: include: A steel wheel (1) having a steel shaft (2) passing through the middle thereof; A steel frame 1 (4) is provided with a steel frame 2 (5) outside thereof, and the two are connected by two steel frames 4 (6); and the steel wheel (1) is located in a closed space formed by the steel frame 1 (4), the steel frame 2 (5) and the two steel frames 4 (6); The steel frame three (3) is provided with two, and the two steel frames three (3) are respectively installed between the steel frame one (4) and the steel frame two (5), and the two sides of the steel shaft (2) are respectively located between the steel frame one (4) and the steel frame three (3) and between the steel frame two (5) and the steel frame three (3).

2. The quick-detachable wheel hub structure of the track translation trolley in a tunnel according to claim 1, characterized in that: The steel shaft (2) and the steel wheel (1) are connected by double-row tapered roller bearings. Cylinders are provided on both sides of the steel shaft (2), and a plane is provided on the outer wall of the cylinder on one side of the steel shaft (2). Both sides of the steel shaft (2) are locked by retaining springs to enable the steel shaft (2) to move left and right in the bearings.

3. The quick-detachable wheel hub structure of the track translation trolley in a tunnel according to claim 2, characterized in that: The steel frame one (4) and the steel frame three (3) as well as the steel frame two (5) and the steel frame three (3) are riveted by bolts (7), and the bolts (7) are hexagon socket bolts. Both sides of the two steel frames four (6) are connected to both sides of the side surfaces of the steel frame one (4) and the steel frame two (5) by double-sided submerged arc welding.

4. The quick-detachable wheel hub structure of the track-translation trolley in a tunnel according to claim 3, characterized in that: The steel frame one (4), the steel frame two (5) and the two steel frames three (3) are all provided with threaded holes (9) inside, and the bolts (7) are located in the threaded holes (9).

5. The quick-detachable wheel hub structure of the track-translation trolley in a tunnel according to claim 3 is characterized in that: A pin shaft (10) is arranged inside the cylinder on the other side of the steel shaft (2), and an oil nozzle (11) and an oil filling hole (12) are arranged inside the pin shaft (10) for filling grease through the oil filling hole (12) and the grease nozzle (11).

6. The quick-detachable wheel hub structure of the track-translation trolley in a tunnel according to claim 2, characterized in that: The steel frame one (4) and the steel frame two (5) have the same size, and the two steel frames three (3) and the two steel frames four (6) have the same size.

7. The quick-detachable wheel hub structure of the track-translation trolley in a tunnel according to claim 6, characterized in that: The top surfaces of the steel frame one (4) and the steel frame two (5) are both provided with mounting holes (8), and the mounting holes (8) on the top surface of the steel frame two (5) are circular, and the mounting holes (8) on the top surface of the steel frame one (4) are provided with flat surfaces for matching the cylinders provided on both sides of the steel shaft (2).

8. The quick-detachable wheel hub structure of the track-translation trolley in a tunnel according to claim 1, characterized in that: The steel wheel (1), the steel shaft (2), the third steel frame (3), the first steel frame (4), the second steel frame (5) and the fourth steel frame (6) are made of one of Q235 steel and Q345 steel.