110 kilovolt power transmission line equipment mounting and conveying device and construction method

By designing the 110 kV transmission line equipment installation and transmission device, the wire assembly and winding assembly are used to achieve rapid lifting of the equipment, and through the design of wire wheels and wire pulling, the equipment and mounting frames are avoided, which solves the problems of inefficiency in traditional lifting methods and equipment damage, and achieves safe and efficient equipment installation.

CN119797193APending Publication Date: 2025-04-11郑州祥和集团有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510064403.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-15
Publication Date
2025-04-11

AI Technical Summary

Technical Problem

During the installation and construction of power transmission and transformation line equipment, the maintenance and replacement of transformers require manual transmission. The traditional hand-crank hoist lifting method is inefficient and is prone to collision with the tower rod, damaging the equipment, and increasing construction costs.

Method used

A 110 kV transmission line equipment installation and transmission device is designed, including a pole, a wire assembly and a winding assembly. By setting up a wire and a winding assembly, the equipment can be quickly lifted by pulling wires and motors, and through the design of wire wheels and pulling wires, the equipment can be avoided from collision with the mounting frame.

Benefits of technology

It realizes rapid and safe lifting of the equipment, avoids collision between the equipment and the mounting frame, extends the service life of the equipment, and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119797193A_ABST
    Figure CN119797193A_ABST
Patent Text Reader

Abstract

The invention discloses a 110 kilovolt power transmission line equipment mounting and conveying device and a construction method, the equipment mounting and conveying device comprises a wire rod and two groups of wire assemblies, the upper part of the wire rod is provided with an equipment mounting rack, and the wire assemblies are arranged on the wire rod; the two wire guide assemblies are located on the wire rod above the equipment mounting rack and the wire rod below the equipment mounting rack respectively, the top of the wire rod is connected with a buckle cover through a bolt, the top of the buckle cover is provided with a top wire guide wheel, a second pull wire is arranged between the top wire guide wheel and the two ends of the wire guide assembly, and one end of the second pull wire is connected with the equipment. And the other end of the second stay wire is connected with the winding assembly. The first stay wire is arranged between the inserting rod and the ground, the situation that equipment collides with the mounting frame or a wire rod is avoided, the service life of the equipment is prolonged, the winding assembly is arranged, the equipment can be rapidly hoisted to the mounting position, the hoisting safety and stability are guaranteed, and the hoisting device is convenient to use, easy to operate and easy to popularize.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a transformer hoisting mechanism, in particular to a 110 kV transmission line equipment installation and transmission device and a construction method, belonging to the technical field of equipment hoisting. Background Art

[0002] During the installation and construction of power transmission and transformation line equipment, the inspection and replacement of transformers are common in construction. Since heavy machinery and equipment cannot reach some areas, the equipment can only be transported by manpower. The traditional transportation method is: using a hand-cranked hoist to hoist the transformer, but the hand-cranked hoist can only hoist the equipment in the vertical direction. Later, the staff is required to move the equipment from the bottom of the mounting frame to the upper position of the mounting frame (installation position). This method is time-consuming, labor-intensive, and inefficient. In addition, during the transportation process, the transformer will collide with the tower, causing the transformer to be damaged, which not only increases the construction cost but also shortens the service life of the item. Summary of the invention

[0003] The technical problem to be solved by the present invention is: to overcome the shortcomings of the prior art and provide a 110 kV transmission line equipment installation and conveying device and construction method, which can quickly hoist the equipment above the installation frame and avoid the safety hazard of collision between the equipment and the installation frame.

[0004] The technical solution adopted by the present invention to solve the technical problem is: A 110 kV transmission line equipment installation and transmission device comprises a pole and a conductor assembly, wherein an equipment mounting frame is arranged on the upper portion of the pole, and a conductor assembly is arranged on the pole, wherein the conductor assembly comprises two groups, which are respectively located on the pole above the equipment mounting frame and on the pole below the equipment mounting frame, wherein a buckle cover is connected to the top of the pole by bolts, a top conductor wheel is arranged on the top of the buckle cover, a second pull wire is arranged between the top conductor wheel and both ends of the conductor assembly, one end of the second pull wire is connected to the equipment, and the other end of the second pull wire is connected to the winding assembly.

[0005] The wire assembly consists of an upper clamp, a lower clamp, a first extension rod, a second extension rod and an end wire pulley. The first extension rod is arranged on one side of the upper clamp, and the second extension rod is arranged on the other side of the upper clamp. The ends of the first extension rod and the second extension rod are respectively provided with end wire pulleys. A through hole is arranged at the bottom of the right end of the first extension rod, and an inserted rod is threadedly connected to the through hole. A first pull wire is arranged between the inserted rod and the ground.

[0006] The upper end of the first pull wire is fixedly connected to the insertion rod, and the lower end of the first pull wire is provided with a ring, and the ring is fixedly connected to the ground through a positioning rod, and the first pull wire is in a tensioned state.

[0007] Reinforcement rods are respectively arranged between the lower clamp and the first extension rod, and between the lower clamp and the second extension rod.

[0008] The winding assembly consists of a base frame, a winding frame and a motor. The base frame is provided with a winding frame, the rotating shaft of the winding frame is fixedly connected with the rotating shaft of the motor, and the winding frame is provided with a second pull wire.

[0009] The size of the buckle cover matches the size of the top of the pole.

[0010] The plunger is located at the rear of the end guide wheel.

[0011] The insertion rod is located at an outer position of the equipment mounting frame.

[0012] The construction method of installing a transmission device for a 110 kV power transmission line equipment comprises the following steps: S1. Install the buckle cover on the top of the wire pole, install the wire assembly above and below the equipment mounting frame, and adjust the direction of the end wire wheel and the top wire wheel; S2. According to the distance between the insertion rod and the ground, select the first pull wire of matching length, tie the first pull wire to the insertion rods on the two sets of wire assemblies, and use the positioning rod to fix the ring on the ground, so that the first pull wire is in a taut state; S3, adjusting the position of the first pull wire on the wire assembly below the equipment mounting frame so that the position of the first pull wire there is located inside the first pull wire in the wire assembly above; S4, placing the winding assembly on one side of the wire rod and fixing the winding assembly on the ground with a positioning rod, then pulling out the second pull wire on the winding frame and winding it around the end wire wheel on the left side of the wire assembly, the top wire wheel, and the end wire wheel on the right side of the wire assembly in sequence; S5. Fix the right end of the second pull wire to the equipment to be hoisted, start the motor, and slowly hoist the equipment to the equipment mounting frame.

[0013] The positive beneficial effects of the present invention are: 1. The present invention sets a first pull wire between the insertion rod and the ground, and the insertion rod is located behind the end wire wheel. During the equipment hoisting process, the equipment is prevented from colliding with the mounting frame or the wire pole, thereby extending the service life of the equipment and ensuring the safety of the construction.

[0014] 2. The present invention can quickly hoist the equipment to the installation position by setting up a winding assembly. By setting up the end wire pulley and the top wire pulley, it is beneficial to the smooth hoisting of the equipment. At the same time, it also provides a running track for the pulling wire to avoid the equipment from shaking drastically during the hoisting process, which is beneficial to the smooth installation of the equipment, easy to use and simple to operate. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a structural schematic diagram of the present invention; Figure 2 It is a structural schematic diagram of the wire assembly of the present invention; Figure 3 It is a structural schematic diagram of the winding assembly of the present invention; Figure 4 It is a schematic diagram of the structure of the upper clamp and the lower clamp of the present invention; Among them: 1-wire pole, 2-equipment mounting frame, 3-buckle cover, 4-top wire pulley, 5-upper clamp, 6-lower clamp, 7-first extension rod, 8-second extension rod, 9-end wire pulley, 10-reinforcement rod, 11-perforation, 12-insertion rod, 13-first pull wire, 14-ring, 15-positioning rod, 16-base, 17-winding frame, 18-motor, 19-second pull wire. DETAILED DESCRIPTION

[0016] The present invention will be further explained and illustrated below in conjunction with the accompanying drawings: Example 1, see Figure 1-Figure 4 A 110 kV transmission line equipment installation and transmission device comprises a pole 1 and a conductor assembly, an equipment mounting frame 2 is arranged on the upper part of the pole 1, a conductor assembly is arranged on the pole 1, the conductor assembly is divided into two groups, which are respectively located on the pole 1 above the equipment mounting frame 2 and on the pole 1 below the equipment mounting frame 2, a buckle cover 3 is connected to the top of the pole 1 by bolts, a top conductor wheel 4 is arranged on the top of the buckle cover 3, a second pull wire 19 is arranged between the top conductor wheel 4 and the two ends of the conductor assembly, one end of the second pull wire 19 is connected to the equipment, and the other end of the second pull wire 19 is connected to the winding assembly.

[0017] The wire assembly consists of an upper clamp 5, a lower clamp 6, a first extension rod 7, a second extension rod 8 and an end wire pulley 9. The first extension rod 7 is arranged on one side of the upper clamp 5, and the second extension rod 8 is arranged on the other side of the upper clamp 5. End wire pulleys 9 are respectively arranged at the ends of the first extension rod 7 and the second extension rod 8. A through hole 11 is arranged at the bottom of the right end of the first extension rod 7, and an inserted rod 12 is connected to the through hole 11 by a thread, and a first pull wire 13 is arranged between the inserted rod 12 and the ground.

[0018] The upper end of the first pull wire 13 is fixedly connected to the insertion rod 12, and a collar 14 is provided at the lower end of the first pull wire 13. The collar 14 is fixedly connected to the ground through a positioning pin 15, and the first pull wire 13 is in a tensioned state.

[0019] A reinforcing rod 10 is provided between the lower clamp 6 and the first extension rod 7 and between the lower clamp 6 and the second extension rod 8 respectively.

[0020] The winding assembly consists of a base frame 16 , a winding frame 17 and a motor 18 . The winding frame 17 is arranged on the base frame 16 . The rotating shaft of the winding frame 17 is fixedly connected with the rotating shaft of the motor 18 . The second pull wire 19 is arranged on the winding frame 17 .

[0021] The size of the buckle cover 3 matches the size of the top of the wire rod 1 .

[0022] The plunger 12 is located at the rear of the end guide wheel 9 .

[0023] The insertion rod 12 is located at an outer position of the equipment mounting frame 2 .

[0024] In the above description, the length of the upper plugging rod of the upper conductor assembly is twice the length of the upper plugging rod of the lower conductor assembly, so the four first pull wires are distributed in a row.

[0025] In the above description, the upper clamp and the lower clamp are respectively composed of two semicircular arc plates, and are fixedly connected to the wire rod by bolts.

[0026] In the above description, the first epitaxial plate, half of the upper clamp and half of the lower clamp are an integrated structure, and the second epitaxial plate, half of the upper clamp and half of the lower clamp are an integrated structure.

[0027] In the above description, the insertion rod is located outside the equipment mounting frame, so that during the hoisting process, the first pull wire is located outside the equipment mounting frame, which can avoid collision between the equipment and the mounting frame.

[0028] In the above description, bolts are provided on the outer wall of the buckle cover.

[0029] Embodiment 2, the above-mentioned construction method for installing a transmission device for a 110 kV power transmission line equipment comprises the following steps: S1, install the buckle cover 3 on the top of the wire rod 1, install the wire assembly above and below the equipment mounting frame 2, and adjust the direction of the end wire wheel 9 and the top wire wheel 4; S2. According to the distance between the insertion rod 12 and the ground, select the first pull wire 13 of matching length, tie the first pull wire 13 to the insertion rod 12 on the two sets of wire assemblies, and use the positioning rod 15 to fix the ring 14 on the ground, so that the first pull wire 13 is in a tensioned state; S3, adjusting the position of the first pull wire 13 on the wire assembly below the equipment mounting frame 2 so that the position of the first pull wire 13 there is located inside the first pull wire 13 in the upper wire assembly; S4, placing the winding assembly on one side of the wire rod 1, and fixing the winding assembly on the ground with a positioning rod 15, then pulling out the second pull wire 19 on the winding frame 17, and winding it around the end wire wheel 9 on the left side of the wire assembly, the top wire wheel 4, and the end wire wheel 9 on the right side of the wire assembly in sequence; S5, fix the right end of the second pull wire 19 to the equipment to be hoisted, start the motor 18, and slowly hoist the equipment to the equipment mounting frame 2.

[0030] During construction, a first guy wire is set between the upper and lower adjacent extension plates to form a safety protection line outside the equipment mounting frame to avoid collision between the transformer and the equipment mounting frame during equipment lifting. By setting a top wire pulley and an end wire pulley, the displacement trajectory of the second guy wire is limited to avoid large-scale shaking of the second guy wire, thereby ensuring the safety and stability of lifting. The system is easy to use, simple to operate, and easy to promote.

Claims

1. A 110 kV transmission line equipment installation and transmission device, comprising a wire pole (1) and a conductor assembly, wherein an equipment installation frame (2) is arranged on the upper part of the wire pole (1), characterized in that: The utility pole (1) is provided with a conductor assembly. The conductor assembly comprises two groups, one group being located on the utility pole (1) above the equipment mounting frame (2) and the other group being located on the utility pole (1) below the equipment mounting frame (2). The top of the utility pole (1) is connected with a buckle cover (3) by bolts. The top of the buckle cover (3) is provided with a top conductor wheel (4). A second pull wire (19) is provided between the top conductor wheel (4) and two ends of the conductor assembly. One end of the second pull wire (19) is connected to the equipment, and the other end of the second pull wire (19) is connected to the winding assembly.

2. A 110 kV transmission line equipment installation and transmission device according to claim 1, characterized in that: The wire assembly is composed of an upper clamp (5), a lower clamp (6), a first extension rod (7), a second extension rod (8) and an end wire pulley (9); the first extension rod (7) is arranged on one side of the upper clamp (5), the second extension rod (8) is arranged on the other side of the upper clamp (5), the end of the first extension rod (7) and the end of the second extension rod (8) are respectively provided with an end wire pulley (9); a through hole (11) is arranged at the bottom of the right end of the first extension rod (7), an insertion rod (12) is connected to the through hole (11) by means of a thread, and a first pull wire (13) is arranged between the insertion rod (12) and the ground.

3. A 110 kV transmission line equipment installation and transmission device according to claim 2, characterized in that: The upper end of the first pull wire (13) is fixedly connected to the insertion rod (12), and the lower end of the first pull wire (13) is provided with a ring (14), and the ring (14) is fixedly connected to the ground through a positioning rod (15), and the first pull wire (13) is in a tensioned state.

4. A 110 kV transmission line equipment installation and transmission device according to claim 2, characterized in that: A reinforcing rod (10) is provided between the lower clamp (6) and the first extension rod (7), and between the lower clamp (6) and the second extension rod (8), respectively.

5. The 110 kV transmission line equipment installation and transmission device according to claim 1, characterized in that: The winding assembly is composed of a base frame (16), a winding frame (17) and a motor (18); the base frame (16) is provided with a winding frame (17); a rotating shaft of the winding frame (17) is fixedly connected to a rotating shaft of the motor (18); and a second pull wire (19) is provided on the winding frame (17).

6. A 110 kV transmission line equipment installation and transmission device according to claim 1, characterized in that: The size of the buckle cover (3) matches the size of the top of the wire rod (1).

7. A 110 kV transmission line equipment installation and transmission device according to claim 2, characterized in that: The insertion rod (12) is located at the rear of the end wire wheel (9).

8. The 110 kV transmission line equipment installation and transmission device according to claim 1, characterized in that: The insertion rod (12) is located at an outer position of the equipment mounting frame (2).

9. A construction method for installing a transmission device for 110 kV power transmission line equipment according to any one of claims 1 to 8, characterized in that: The steps include: S1. Install a buckle cover (3) on the top of the line pole (1), install the conductor assembly above and below the equipment mounting frame (2), and adjust the orientation of the end conductor wheel (9) and the top conductor wheel (4); S2, according to the distance between the insertion rod (12) and the ground, select a first pull wire (13) of matching length, tie the first pull wire (13) to the insertion rod (12) on the two sets of wire assemblies, and use a positioning rod (15) to fix the ring (14) on the ground, so that the first pull wire (13) is in a tensioned state; S3, adjusting the position of the first pull wire (13) on the conductor assembly below the equipment mounting frame (2) so that the position of the first pull wire (13) there is located on the inner side of the first pull wire (13) in the upper conductor assembly; S4, placing a winding assembly on one side of the wire rod (1), and fixing the winding assembly to the ground using a positioning rod (15), then pulling out the second pull wire (19) on the winding frame (17), and winding it around the end wire wheel (9) on the left side of the wire assembly, the top wire wheel (4), and the end wire wheel (9) on the right side of the wire assembly in sequence; S5. Fix the right end of the second pull wire (19) to the equipment to be hoisted, start the motor (18), and slowly hoist the equipment to the equipment mounting frame (2).