Project implementation progress risk assessment method and system

By constructing a risk knowledge base for the progress of investment projects and setting factor weights, the high workload and inefficient assessment problems caused by the dependence of artificial experience in the existing technology are solved, and a more accurate and efficient risk assessment is achieved.

CN119809331APending Publication Date: 2025-04-11THINVENT DIGITAL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411860838.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-17
Publication Date
2025-04-11

AI Technical Summary

Technical Problem

In the existing technology, the risk assessment of the progress of investment projects is based on manual experience, which has a large workload and low evaluation efficiency.

Method used

By constructing a risk knowledge base for the implementation of investment projects, using the main category and factor names in the previous project progress abnormality analysis report, setting factor weights, and risk scoring is performed based on the information of the project to be evaluated.

Benefits of technology

It improves the accuracy of risk assessment, reduces workload, improves the efficiency and quality of assessment, and realizes the intelligent transformation from manual experience to data-driven.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119809331A_ABST
    Figure CN119809331A_ABST
Patent Text Reader

Abstract

The invention provides a project implementation progress risk assessment method and system, and the method comprises the steps: obtaining a plurality of main categories and a plurality of factor names associated with the main categories through a previous project progress abnormality analysis report, and setting factor weights for the factor names; determining a project category of the to-be-evaluated investment project information, selecting a target category from the plurality of main categories, and selecting a plurality of factor names corresponding to the target category as screening names; obtaining result information corresponding to the screening name; and performing assignment processing on the screening name based on the result information to obtain an assignment result corresponding to the screening name, determining a risk score of the to-be-assessed investment project information through the factor weight and the assignment result, and completing risk assessment based on the risk score. Through the above mode, intelligent conversion of investment project implementation progress supervision from manual experience to data driving is realized, the workload is reduced, and the evaluation efficiency and quality are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of data evaluation, and in particular to a project implementation schedule risk evaluation method and system. Background Art

[0002] In recent years, with the rapid economic development, the number of investment projects has shown a rapid growth trend. Investment projects are the carriers of investment. Ensuring that investment projects are smoothly constructed as planned is an important means to ensure the implementation of investment.

[0003] The risk assessment of the implementation schedule of investment projects is the main means to ensure the smooth construction of investment projects. It means that after risk identification, the overall risk level of the implementation schedule of investment projects is determined through full, systematic and comprehensive consideration of the risk factors of the project, and the construction plan is adjusted according to the assessment results.

[0004] At present, the implementation progress risk assessment of investment projects mainly relies on manual experience and judgment. Experts review relevant information on various investment projects and combine experience to give an assessment result of the overall risk. However, this method has a large workload and low assessment efficiency. Summary of the invention

[0005] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a project implementation schedule risk assessment method and system, aiming to solve the technical problems of relying on manual experience to conduct investment project implementation schedule risk assessment in the prior art, which has a large workload and low assessment efficiency.

[0006] In order to achieve the above objectives, in a first aspect, an embodiment of the present application provides a project implementation schedule risk assessment method, comprising the following steps:

[0007] Building an investment project implementation progress risk knowledge base through a number of past project progress anomaly analysis reports, wherein the investment project implementation progress risk knowledge base includes a number of main categories and a number of factor names associated with the main categories, and setting factor weights for the factor names;

[0008] Determine the project category of the investment project information to be evaluated, compare the project category with the plurality of main categories respectively, select a target category from the plurality of main categories, and select the plurality of factor names corresponding to the target category as screening names;

[0009] Obtaining result information corresponding to the screening name from the information of the investment project to be evaluated, wherein the result information includes pass and fail;

[0010] Based on the result information, the screening name is assigned a value to obtain an assignment result corresponding to the screening name, the risk score of the investment project information to be evaluated is determined through the factor weight and the assignment result, and the risk assessment is completed based on the risk score.

[0011] Compared with the prior art, the beneficial effects of the present invention are: constructing the risk knowledge base based on the abnormal analysis reports of the previous project progress, distinguishing the different main categories, and then distinguishing the factor weights of the same factor name in different main categories, thereby improving the accuracy of risk assessment; by obtaining the result information, determining the risk score of the investment project information to be assessed based on the result information and the factor weight, realizing the intelligent transformation of the supervision of the implementation progress of the investment project from relying mainly on manual experience to data-driven, reducing the workload, and improving the efficiency and quality of the assessment.

[0012] Further, the step of constructing an investment project implementation progress risk knowledge base through a number of past project progress anomaly analysis reports, wherein the investment project implementation progress risk knowledge base includes a number of main categories and a number of factor names associated with the main categories includes:

[0013] Obtaining subject names of the plurality of past project progress anomaly analysis reports, obtaining initial categories from the subject names, performing deduplication processing on the plurality of initial categories to obtain a plurality of main categories, and separating the plurality of past project progress anomaly analysis reports into a plurality of report sets based on the main categories;

[0014] The report set is segmented to obtain a number of words, the occurrence frequencies of the words are obtained, and factor names are selected from the words based on the occurrence frequencies.

[0015] Furthermore, the step of setting factor weights for the factor names includes:

[0016] Obtaining a single negative evaluation result and a single positive evaluation result corresponding to the factor name from the report set, and obtaining the total negative evaluation results and the total positive evaluation results of the report set;

[0017] Based on the number of the report sets, obtaining a first number corresponding to the single negative evaluation result, a second number corresponding to the single positive evaluation result, a third number corresponding to the total negative evaluation results, and a fourth number corresponding to the total positive evaluation results;

[0018] A first weight component is determined by the first quantity and the third quantity, and a second weight component is determined by the second quantity and the fourth quantity, and a factor weight is obtained based on the first weight component and the second weight component.

[0019] Furthermore, the calculation formula of the factor weight is:

[0020] ω si =0.5ω gre +0.5ω terr ,

[0021] Among them, ω si represents the factor weight corresponding to the i-th factor name, ω terr represents the first weight component, ω gre Represents the second weight component.

[0022] Furthermore, the step of obtaining result information corresponding to the screening name from the information of the investment project to be evaluated includes:

[0023] Using the screening name as a keyword, selecting a screening statement from the information of the investment project to be evaluated;

[0024] The screening sentence is segmented to obtain screening words, and the screening words are compared with preset words to obtain result information.

[0025] Furthermore, the assignment result is 0 or 1, and the step of performing assignment processing on the screening name based on the result information to obtain the assignment result corresponding to the screening name includes:

[0026] If the result information is passed, determining the assignment result to be 0, and associating the assignment result to the screening name;

[0027] If the result information is failed, the assignment result is determined to be 1, and the assignment result is associated with the screening name.

[0028] Furthermore, the steps of completing the risk assessment based on the risk score are specifically:

[0029] The risk score is compared with a scoring threshold. If the risk score is greater than the scoring threshold, it is determined that the investment project information to be evaluated has risks. If the risk score is less than the scoring threshold, it is determined that the investment project information to be evaluated does not have risks.

[0030] In a second aspect, an embodiment of the present application provides a project implementation schedule risk assessment system, which is applied to the project implementation schedule risk assessment method as described in the first aspect above, and the system includes:

[0031] A construction module, used to construct an investment project implementation progress risk knowledge base through a number of past project progress anomaly analysis reports, wherein the investment project implementation progress risk knowledge base includes a number of main categories and a number of factor names associated with the main categories, and factor weights are set for the factor names;

[0032] A selection module, for determining the project category of the investment project information to be evaluated, comparing the project category with the plurality of main categories respectively, so as to select a target category from the plurality of main categories, and selecting the plurality of factor names corresponding to the target category as screening names;

[0033] An analysis module, used for obtaining result information corresponding to the screening name from the information of the investment project to be evaluated, wherein the result information includes pass and fail;

[0034] An execution module is used to assign a value to the screening name based on the result information to obtain an assignment result corresponding to the screening name, determine the risk score of the investment project information to be evaluated through the factor weight and the assignment result, and complete the risk evaluation based on the risk score.

[0035] In a third aspect, an embodiment of the present application provides a computer, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the computer program, the project implementation schedule risk assessment method as described in the first aspect above is implemented.

[0036] In a fourth aspect, an embodiment of the present application provides a storage medium having a computer program stored thereon, which, when executed by a processor, implements the project implementation schedule risk assessment method as described in the first aspect above. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 It is a flowchart of the project implementation progress risk assessment method in the first embodiment of the present invention;

[0038] Figure 2 It is a structural block diagram of a project implementation schedule risk assessment system in a second embodiment of the present invention;

[0039] The following specific implementation manner will further illustrate the present invention in conjunction with the above-mentioned drawings. DETAILED DESCRIPTION

[0040] In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings. Several embodiments of the present invention are given in the drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thorough and comprehensive.

[0041] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.

[0042] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.

[0043] See also Figure 1 The project implementation schedule risk assessment method provided by the first embodiment of the present invention comprises the following steps:

[0044] S10: constructing an investment project implementation progress risk knowledge base through a number of past project progress anomaly analysis reports, wherein the investment project implementation progress risk knowledge base includes a number of main categories and a number of factor names associated with the main categories, and setting factor weights for the factor names;

[0045] The step S10 comprises:

[0046] S110: Obtain subject names of several past project progress anomaly analysis reports, obtain initial categories from the subject names, perform duplicate elimination processing on several initial categories to obtain several main categories, and separate several past project progress anomaly analysis reports into several report sets based on the main categories;

[0047] The subject names of the abnormal progress analysis reports of past projects are generally: abnormal analysis report of XX highway construction project, abnormal analysis report of XX building construction project, and the initial category can be determined by extracting the subject names, which are highway construction, building construction, etc. After the main category is clarified, the abnormal progress analysis reports of past projects corresponding to the same main category can be associated with the main category.

[0048] S120: performing word segmentation processing on the report set to obtain a plurality of words, obtaining the occurrence frequencies of the words, and selecting factor names from the plurality of words based on the occurrence frequencies;

[0049] The word segmentation processing method is now widely used and will not be described here. After obtaining the word, the number of occurrences of the word is obtained, and the frequency of occurrence is obtained based on the number of occurrences and the total number of the word, and the words are sorted according to the frequency of occurrence, and the word with a higher frequency of occurrence is selected as the factor name. In some embodiments, after obtaining the factor name, the factor name can be determined through expert review. Taking highway construction as the main category as an example, the factor name is land expropriation, environmental assessment, and land approval;

[0050] S130: Obtaining a single negative evaluation result and a single positive evaluation result corresponding to the factor name from the report set, and obtaining a total negative evaluation result and a total positive evaluation result of the report set;

[0051] Select the report set corresponding to a certain main category, and extract the previous project progress abnormality analysis report therein, and extract the result data of the previous project progress abnormality analysis report together, that is, whether there is a risk or not. It can be understood that the existence of a risk is the total negative evaluation result, and the absence of a risk is the total positive evaluation result. Furthermore, if the factor name is land expropriation, environmental assessment, and land approval, then passing and failing are the single positive evaluation result and the single negative evaluation result.

[0052] S140: Based on the number of the report set, obtaining a first number corresponding to the single negative evaluation result, a second number corresponding to the single positive evaluation result, a third number corresponding to the total negative evaluation results, and a fourth number corresponding to the total positive evaluation results;

[0053] S150: determining a first weight component by using the first quantity and the third quantity, determining a second weight component by using the second quantity and the fourth quantity, and obtaining a factor weight based on the first weight component and the second weight component;

[0054] The first weight component=the first quantity / the third quantity, and the second weight component=the second quantity / the fourth quantity.

[0055] The calculation formula of the factor weight is:

[0056] ω si =0.5ω gre +0.5ω terr ,

[0057] Among them, ω si represents the factor weight corresponding to the i-th factor name, ω terr represents the first weight component, ω gre Represents the second weight component.

[0058] S20: determining the project category of the investment project information to be evaluated, comparing the project category with the plurality of main categories respectively, selecting a target category from the plurality of main categories, and selecting the plurality of factor names corresponding to the target category as screening names;

[0059] In this embodiment, the project category is obtained by the subject name of the investment project information to be evaluated, which is consistent with the acquisition method of the main category. The project category is compared with the main category to determine the factor name affecting the investment project information to be evaluated, that is, the screening name.

[0060] S30: Obtaining result information corresponding to the screening name from the information of the investment project to be evaluated, wherein the result information includes pass and fail;

[0061] The step S30 comprises:

[0062] S310: Using the screening name as a keyword, selecting a screening statement from the information of the investment project to be evaluated;

[0063] The information of the investment project to be evaluated is subjected to keyword screening based on the screening name to extract the screening statement containing the screening name.

[0064] S320: performing word segmentation processing on the screening sentence to obtain screening words, and comparing the screening words with preset words to obtain result information;

[0065] The preset words also include passed and failed.

[0066] S40: performing assignment processing for the screening name based on the result information to obtain an assignment result corresponding to the screening name, determining a risk score of the investment project information to be evaluated through the factor weight and the assignment result, and completing risk evaluation based on the risk score;

[0067] The assignment result is 0 or 1.

[0068] The step S40 comprises:

[0069] S410: If the result information is passed, determine that the assignment result is 0, and associate the assignment result with the screening name;

[0070] S420: If the result information is failed, determine that the assignment result is 1, and associate the assignment result with the screening name;

[0071] The risk score is obtained by:

[0072]

[0073] Among them, P j represents the risk score of the jth investment project information to be evaluated, Indicates the result of assigning the i-th screening name corresponding to the j-th investment project information to be evaluated, represents the factor weight of the i-th screening name corresponding to the j-th investment project information to be evaluated, and n represents the number of screening names corresponding to the j-th investment project information to be evaluated.

[0074] S430: Compare the risk score with a scoring threshold. If the risk score is greater than the scoring threshold, determine that the investment project information to be evaluated has risks. If the risk score is less than the scoring threshold, determine that the investment project information to be evaluated has no risks.

[0075] The risk knowledge base is constructed based on the abnormal analysis reports of the previous project progress, and the different main categories are distinguished, and then the factor weights of the same factor name in different main categories are distinguished, thereby improving the accuracy of risk assessment; by obtaining the result information, the risk score of the investment project information to be assessed is determined based on the result information and the factor weight, thereby realizing the intelligent transformation of the supervision of the implementation progress of investment projects from relying mainly on manual experience to data-driven, reducing the workload and improving the efficiency and quality of the assessment.

[0076] See also Figure 2 The second embodiment of the present invention provides a project implementation schedule risk assessment system, which is applied to the project implementation schedule risk assessment method described in the above embodiment, and will not be repeated here. As used below, the terms "module", "unit", "subunit", etc. can be a combination of software and / or hardware that implements a predetermined function. Although the device described in the following embodiments is preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.

[0077] The system comprises:

[0078] A construction module 10 is used to construct an investment project implementation progress risk knowledge base through a number of past project progress abnormality analysis reports, wherein the investment project implementation progress risk knowledge base includes a number of main categories and a number of factor names associated with the main categories, and factor weights are set for the factor names;

[0079] The building block 10 comprises:

[0080] The first unit is used to obtain the subject names of the past project progress anomaly analysis reports, obtain initial categories from the subject names, remove duplicates from the initial categories to obtain a number of main categories, and separate the past project progress anomaly analysis reports into a number of report sets based on the main categories;

[0081] The second unit is used for performing word segmentation processing on the report set to obtain a plurality of words, obtain the occurrence frequency of the words, and select factor names from the plurality of words based on the occurrence frequency;

[0082] The third unit is used to obtain a single negative evaluation result and a single positive evaluation result corresponding to the factor name from the report set, and obtain the total negative evaluation results and the total positive evaluation results of the report set;

[0083] A fourth unit is used to obtain, based on the number of the report set, a first number corresponding to the single negative evaluation result, a second number corresponding to the single positive evaluation result, a third number corresponding to the total negative evaluation results, and a fourth number corresponding to the total positive evaluation results;

[0084] A fifth unit, configured to determine a first weight component by using the first quantity and the third quantity, determine a second weight component by using the second quantity and the fourth quantity, and obtain a factor weight based on the first weight component and the second weight component;

[0085] A selection module 20 is used to determine the project category of the investment project information to be evaluated, compare the project category with the plurality of main categories respectively, select a target category from the plurality of main categories, and select the plurality of factor names corresponding to the target category as screening names;

[0086] An analysis module 30 is used to obtain result information corresponding to the screening name from the information of the investment project to be evaluated, wherein the result information includes pass and fail;

[0087] The analysis module 30 includes:

[0088] The sixth unit is used to select a screening statement from the information of the investment project to be evaluated by using the screening name as a keyword;

[0089] The seventh unit is used to perform word segmentation processing on the screening sentence to obtain screening words, and compare the screening words with preset words to obtain result information;

[0090] An execution module 40 is used to perform a value assignment process on the screening name based on the result information to obtain a value assignment result corresponding to the screening name, determine a risk score of the investment project information to be evaluated through the factor weight and the value assignment result, and complete risk evaluation based on the risk score;

[0091] The execution module 40 includes:

[0092] An eighth unit, for determining the assignment result to be 0 if the result information is passed, and associating the assignment result to the screening name;

[0093] A ninth unit, for determining the assignment result to be 1 if the result information is failure, and associating the assignment result to the screening name;

[0094] The tenth unit is used to compare the risk score with a scoring threshold. If the risk score is greater than the scoring threshold, it is determined that the investment project information to be evaluated has risks; if the risk score is less than the scoring threshold, it is determined that the investment project information to be evaluated does not have risks.

[0095] The present invention also provides a computer, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the computer program, the project implementation schedule risk assessment method as described in the above technical solution is implemented.

[0096] The present invention also provides a storage medium on which a computer program is stored. When the computer program is executed by a processor, the project implementation schedule risk assessment method as described in the above technical solution is implemented.

[0097] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0098] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. A project implementation schedule risk assessment method, characterized in that: The following steps are involved: Building an investment project implementation progress risk knowledge base through a number of past project progress anomaly analysis reports, wherein the investment project implementation progress risk knowledge base includes a number of main categories and a number of factor names associated with the main categories, and setting factor weights for the factor names; Determine the project category of the investment project information to be evaluated, compare the project category with the plurality of main categories respectively, select a target category from the plurality of main categories, and select the plurality of factor names corresponding to the target category as screening names; Obtaining result information corresponding to the screening name from the information of the investment project to be evaluated, wherein the result information includes pass and fail; Based on the result information, the screening name is assigned a value to obtain an assignment result corresponding to the screening name, the risk score of the investment project information to be evaluated is determined through the factor weight and the assignment result, and the risk assessment is completed based on the risk score.

2. The project implementation schedule risk assessment method according to claim 1, characterized in that: The step of constructing an investment project implementation progress risk knowledge base through a number of past project progress abnormality analysis reports, wherein the investment project implementation progress risk knowledge base includes a number of main categories and a number of factor names associated with the main categories includes: Obtaining subject names of the plurality of past project progress anomaly analysis reports, obtaining initial categories from the subject names, performing deduplication processing on the plurality of initial categories to obtain a plurality of main categories, and separating the plurality of past project progress anomaly analysis reports into a plurality of report sets based on the main categories; The report set is segmented to obtain a number of words, the occurrence frequencies of the words are obtained, and factor names are selected from the words based on the occurrence frequencies.

3. The project implementation schedule risk assessment method according to claim 2 is characterized in that: The step of setting the factor weight for the factor name comprises: Obtaining a single negative evaluation result and a single positive evaluation result corresponding to the factor name from the report set, and obtaining the total negative evaluation results and the total positive evaluation results of the report set; Based on the number of the report sets, obtaining a first number corresponding to the single negative evaluation result, a second number corresponding to the single positive evaluation result, a third number corresponding to the total negative evaluation results, and a fourth number corresponding to the total positive evaluation results; A first weight component is determined by the first quantity and the third quantity, and a second weight component is determined by the second quantity and the fourth quantity, and a factor weight is obtained based on the first weight component and the second weight component.

4. The project implementation schedule risk assessment method according to claim 3 is characterized in that: The calculation formula of the factor weight is: oh si =0.5h gre +0.5h terr , Among them, ω si represents the factor weight corresponding to the i-th factor name, ω terr represents the first weight component, ω gre Represents the second weight component.

5. The project implementation schedule risk assessment method according to claim 1 is characterized in that: The step of obtaining result information corresponding to the screening name from the information of the investment project to be evaluated comprises: Using the screening name as a keyword, selecting a screening statement from the information of the investment project to be evaluated; The screening sentence is segmented to obtain screening words, and the screening words are compared with preset words to obtain result information.

6. The project implementation schedule risk assessment method according to claim 1 is characterized in that: The assignment result is 0 or 1, and the step of performing assignment processing on the screening name based on the result information to obtain the assignment result corresponding to the screening name includes: If the result information is passed, determining the assignment result to be 0, and associating the assignment result to the screening name; If the result information is failed, the assignment result is determined to be 1, and the assignment result is associated with the screening name.

7. The project implementation schedule risk assessment method according to claim 1 is characterized in that: The steps of completing the risk assessment based on the risk score are specifically: The risk score is compared with a scoring threshold. If the risk score is greater than the scoring threshold, it is determined that the investment project information to be evaluated has risks. If the risk score is less than the scoring threshold, it is determined that the investment project information to be evaluated does not have risks.

8. A project implementation schedule risk assessment system, applied to the project implementation schedule risk assessment method according to any one of claims 1 to 7, characterized in that: The system comprises: A construction module, used to construct an investment project implementation progress risk knowledge base through a number of past project progress anomaly analysis reports, wherein the investment project implementation progress risk knowledge base includes a number of main categories and a number of factor names associated with the main categories, and factor weights are set for the factor names; A selection module, for determining the project category of the investment project information to be evaluated, comparing the project category with the plurality of main categories respectively, so as to select a target category from the plurality of main categories, and selecting the plurality of factor names corresponding to the target category as screening names; An analysis module, used for obtaining result information corresponding to the screening name from the information of the investment project to be evaluated, wherein the result information includes pass and fail; An execution module is used to assign a value to the screening name based on the result information to obtain an assignment result corresponding to the screening name, determine the risk score of the investment project information to be evaluated through the factor weight and the assignment result, and complete the risk evaluation based on the risk score.

9. A computer comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the project implementation schedule risk assessment method according to any one of claims 1 to 7 is implemented.

10. A storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the project implementation schedule risk assessment method as described in any one of claims 1 to 7 is implemented.