Temporary pipeline supporting device for road construction

By designing a temporary pipeline support device for road construction, the pipe alignment and fixation is achieved using lifting components and guide clamping mechanisms, the problems of long construction cycles and high costs in the prior art are solved, and a more efficient construction process is achieved.

CN119825992AActive Publication Date: 2025-04-15SICHUAN JIAOTOU CONSTR ENG CO LTD +1
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202510330288.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-20
Publication Date
2025-04-15
Estimated Expiration
2045-03-20

AI Technical Summary

Technical Problem

In road construction, the prior art requires laying a large number of concrete pads in the pipe trench to support the pipe, resulting in a long construction cycle and high cost.

Method used

A temporary support device for pipelines for road construction is designed, including a walking frame, a chassis, a lifting mechanism and a mounting seat. The pipes are aligned and fixed through the hoisting components and the guide clamping mechanism, avoiding the advance laying of concrete pads.

Benefits of technology

The device enables easy alignment and fixing of pipes without the need to lay concrete pads in advance, shortening construction cycles and reducing costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119825992A_ABST
    Figure CN119825992A_ABST
Patent Text Reader

Abstract

The invention provides a temporary pipeline supporting device for road construction, and relates to the technical field of road construction, the temporary pipeline supporting device comprises a walking frame, a bottom frame, a lifting mechanism and a mounting seat, and the walking frame is provided with a hoisting assembly; the bottom frame is vertically arranged at the bottom of the walking frame and extends into the pipe ditch, and a first attaching base and a second attaching base are arranged at the bottom of the bottom frame. The lifting mechanism comprises a supporting base fixed to the bottom frame. The bottom of the supporting base is provided with a lifting electric cylinder and a lifting assembly used for lifting the end of the pipeline in the pipe ditch upwards. A guide mechanism for a pipeline to pass through and a clamping mechanism for fixing the pipeline are arranged on the mounting seat, the guide mechanism comprises a guide seat and a guide ring, and the clamping mechanism comprises a clamping seat and a clamping ring; the first attaching base, the second attaching base, the guide ring and the clamping ring are obliquely arranged and are consistent in axis direction. According to the invention, the pipeline prepared to be put into the pipe ditch can be aligned with the installed pipeline in the pipe ditch, and a concrete cushion block does not need to be laid in the pipe ditch in advance, so that the cost is reduced while the efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of road construction, and in particular to a temporary pipeline supporting device for road construction. Background Art

[0002] Underground pipelines in road construction are an important part of urban infrastructure construction, which involves many aspects, including pipeline classification, layout principles, construction methods and precautions. When installing pipelines into pre-opened trenches on roads, they need to be temporarily supported to facilitate the docking of pipelines.

[0003] At present, when temporarily supporting pipelines, multiple concrete pads need to be placed in the trench to support the pipelines placed in the trench. Each section of the pipeline needs at least two concrete pads to support it so that the ends of two adjacent pipelines are aligned, which is convenient for connection. When the length of the trench is long, a large number of concrete pads need to be placed, which takes a long time to set up and has high construction costs. Summary of the invention

[0004] The purpose of the present invention is to provide a temporary pipe support device for road construction, which can easily align the pipe to be placed in the trench with the pipe already installed in the trench, without the need to lay concrete pads in the trench in advance, thereby shortening the construction period and reducing the construction cost.

[0005] The present invention is implemented by the following technical scheme: a temporary support device for pipelines for road construction, comprising a walking frame, a base frame, a lifting mechanism and a mounting seat, wherein the walking frame is arranged on the upper part of the pipe trench, the four corners of the bottom of the walking frame are all provided with walking wheels, and both sides of the top of the walking frame are provided with lifting assemblies; the base frame is vertically arranged at the bottom of the walking frame and extends into the pipe trench, and the two ends of the bottom of the base frame are respectively provided with a first fitting seat and a second fitting seat; The lifting mechanism comprises a support seat, the support seat is fixedly arranged on the base frame, a lifting electric cylinder is arranged at the bottom of the support seat, and a lifting assembly for lifting the end of the pipe in the trench upward is arranged on the piston rod of the lifting electric cylinder; The mounting seat is fixedly arranged at one end of the base frame, and is provided with a guide mechanism for the pipeline to pass through and a clamping mechanism for fixing the position of the pipeline, the guide mechanism includes a guide seat and a guide ring arranged at the bottom of the guide seat, and the clamping mechanism includes a clamping seat and a clamping ring arranged at the bottom of the clamping seat; the first fitting seat, the second fitting seat, the guide ring and the clamping ring are all arranged obliquely and their axial directions are consistent.

[0006] Furthermore, the lifting assembly includes a lifting seat and a lifting block, a rotating groove is opened on one side of the lifting seat, the lifting block is rotatably connected in the rotating groove through a first rotating shaft and one end of the lifting block extends to the outside of the rotating groove, and the lifting block abuts against the bottom wall of the rotating groove when it is rotated to a horizontal state, and a torsion spring is connected between the first rotating shaft and the lifting seat to drive the lifting block to rotate toward a horizontal state.

[0007] Furthermore, the lifting seat is rotatably arranged on the piston rod of the lifting electric cylinder, a positioning collar is arranged on the top of the lifting seat, and a positioning pin for fixing the position of the lifting seat is arranged on the positioning collar.

[0008] Furthermore, the guide seat is fixedly arranged at the bottom of the mounting seat, and the guide seat includes a vertical seat, a tilting seat is tiltedly arranged at the bottom of the vertical seat, a hollow groove is opened in the middle of the tilting seat, and the hollow groove separates the two sides of the tilting seat into two fork arms, and the bottom of the two fork arms are hingedly arranged with rotating arms, and a straightening assembly is arranged in the hollow groove, and the straightening assembly is used to drive the two rotating arms to remain in a parallel state with the fork arms; the guide ring includes two guide half rings, and the two guide half rings are respectively arranged at the bottom of the two rotating arms.

[0009] Furthermore, the clamping seat includes an arc seat and a driving seat arranged at the bottom of the arc seat, the arc seat is rotatably arranged on the side of the mounting seat away from the base frame through a second rotating shaft, the mounting seat is provided with a rotating component for driving the arc seat to rotate, the driving seat is fixedly arranged at one end of the arc seat away from the mounting seat, the clamping ring includes two clamping half rings, and the driving seat is provided with a driving component for driving the two clamping half rings to move simultaneously in a direction of approaching or moving away from each other.

[0010] Furthermore, the straightening assembly includes a straightening electric cylinder, a driving plate is connected to the piston rod of the straightening electric cylinder, and straightening sleeves are provided on both sides of the driving plate. When the straightening sleeves are provided at the connection position between the fork arm and the rotating arm, they can prevent the rotating arm and the fork arm from rotating relative to each other.

[0011] Furthermore, a support arm for supporting the arc seat is obliquely arranged on one side of the vertical seat, a support block is arranged on the support arm, a support groove matching the shape of the arc seat is opened on the support block, a contact switch for starting the straightening electric cylinder is arranged in the support groove, and when the arc seat is rotated to fit with the support groove, the contact switch can turn on the straightening electric cylinder to drive the straightening sleeve to move to the connection position of the fork arm and the rotating arm.

[0012] Furthermore, the driving assembly includes a driving motor, a double-axis screw and two driving blocks. A driving groove is opened on a side of the driving seat facing away from the arc seat, and the double-axis screw is rotatably connected in the driving groove. The driving motor is fixedly arranged at one end of the driving seat and the output shaft of the driving motor is fixedly connected to the double-axis screw. The two driving blocks are both slidably arranged in the driving groove and are respectively threadedly connected to the two ends of the double-axis screw; the rotating assembly includes a rotating motor, a worm wheel, a worm and two mounting blocks. The worm wheel is coaxially connected to the second rotating shaft, and the two mounting blocks are fixedly arranged on the mounting seat. The worm is rotatably connected between the two mounting blocks and meshes with the worm wheel. The rotating motor is fixedly arranged on one of the mounting blocks and the output shaft of the rotating motor is coaxially connected to the worm.

[0013] Furthermore, the walking frame is provided with a through slot for the base frame to pass through, an extension frame is provided on one side of the bottom of the walking frame, a vertical seat is provided at the bottom of the mounting seat, the extension frame is provided with a through slot for the vertical seat to pass through, and the walking frame is also provided with a lifting mechanism for driving the base frame to move along the height direction of the walking frame.

[0014] Furthermore, the lifting mechanism includes a lifting motor, a driving screw and a driving beam, the driving screw is rotatably connected to the traveling frame along the height direction of the traveling frame, the lifting motor is fixedly arranged on the top of the traveling frame and the output shaft of the lifting motor is fixedly connected to the driving screw, one end of the driving beam is threadedly connected to the driving screw, and the other end is fixedly connected to the base frame, a guide beam is also arranged on the base frame, a guide rod is arranged on the traveling frame and on the side opposite to the driving screw, a guide hole is opened on the guide beam and is sleeved on the guide rod.

[0015] The technical solution of the present invention has at least the following advantages and beneficial effects: 1. The present invention hoists the pipe in the trench to fit with the first fitting seat and the second fitting seat through the hoisting assembly, and fixes the pipe outside the trench to be placed in the trench through the guiding mechanism and the clamping mechanism; because the first fitting seat, the second fitting seat, the guide ring and the clamping ring are all inclined and have the same axial direction, the pipe to be placed in the trench can be easily aligned with the pipe installed in the trench, and there is no need to lay concrete pads in the trench in advance, which shortens the construction period and reduces the construction cost.

[0016] 2. The present invention uses a lifting cylinder and a lifting assembly to lift the end of the pipeline upward, so that the lifting belt of the lifting assembly can be installed on the pipeline, which is convenient for the subsequent lifting process; the lifting assembly is rotatably installed on the piston rod of the lifting cylinder, so that after the lifting belt is installed on the pipeline, the lifting assembly can be moved to the outside of the pipeline, and then the lifting cylinder drives the lifting assembly to move upward as a whole so that the lifting assembly is located above the pipeline, so as to avoid obstruction to the subsequent pipeline docking operation.

[0017] 3. The present invention installs the base frame on the traveling frame by sliding along the height direction of the traveling frame, and drives the base frame to move through the lifting mechanism, so that when the pipeline docking operation is required, the first fitting seat, the second fitting seat, the guide mechanism and the clamping mechanism are driven by the base frame to move into the pipe trench at the same time, and after the operation is completed, the first fitting seat, the second fitting seat, the guide mechanism and the clamping mechanism are driven by the base frame to move out of the pipe trench at the same time. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the use state of the present invention; Figure 2 It is a front view of the present invention; Figure 3 It is a structural schematic diagram of the hoisting assembly of the present invention; Figure 4 It is a structural schematic diagram of the lifting mechanism of the present invention; Figure 5 It is a structural schematic diagram of the lifting assembly of the present invention; Figure 6 It is a schematic diagram of the installation structure of the guide mechanism and the clamping mechanism of the present invention on the installation seat; Figure 7 It is a structural schematic diagram of the guide mechanism and the clamping mechanism of the present invention; Figure 8 It is a structural schematic diagram of the guide mechanism of the present invention; Fig. 9 It is a schematic diagram of the structure of the guide seat and the rotating assembly on the mounting seat of the present invention; 1-travel frame, 11-travel wheel, 12-lifting assembly, 121-winch, 1211-hook, 122-lifting belt, 1221-hanging ring, 1222-connecting bolt, 1223-connecting nut, 13-extension frame, 14-lifting mechanism, 141-lifting motor, 142-driving screw, 143-guide rod, 2-base frame, 21-first fitting seat, 22-second fitting seat, 23-driving beam, 24-guide beam, 3-lifting mechanism, 31-support seat, 32-lifting electric cylinder, 33-lifting assembly, 331-lifting seat, 3311-rotating groove, 332-lifting block, 333-first rotating shaft, 334-torsion spring, 335-positioning collar, 3351-positioning pin, 4-mounting seat, 41-rotating assembly, 411-rotating electric Machine, 412-worm wheel, 413-worm, 414-mounting block, 42-vertical seat, 5-guide mechanism, 51-guide seat, 511-vertical seat, 512-tilted seat, 5121-hollow groove, 5122-fork arm, 513-rotating arm, 52-guide ring, 521-guide semi-ring, 53-straightening assembly, 531-straightening electric cylinder, 532-drive plate, 533-straightening sleeve, 54-support arm, 541-support block, 5411-support groove, 542-contact switch, 6-clamping mechanism, 61-clamping seat, 611-arc seat, 612-drive seat, 6121-drive groove, 613-second rotating shaft, 62-clamping ring, 621-clamping semi-ring, 63-drive assembly, 631-drive motor, 632-dual-axis lead screw, 633-drive block. DETAILED DESCRIPTION

[0019] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0020] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0021] Example The following reference Figure 1-Figure 9 As shown, combined with a specific embodiment, this embodiment further illustrates that a temporary pipe support device for road construction is provided. Figure 1 , Figure 2As shown, it includes a traveling frame 1, a base frame 2, a lifting mechanism 3 and a mounting seat 4. The traveling frame 1 is arranged at the upper part of the pipe trench. The four corners of the bottom of the traveling frame 1 are provided with traveling wheels 11 to facilitate pushing the traveling frame 1 to move above the pipe trench along the length direction of the pipe trench. Both sides of the top of the traveling frame 1 are provided with lifting components 12. The lifting components 12 include a winch 121 and a lifting belt 122 hung at the bottom of the winch 121; the base frame 2 is vertically arranged at the bottom of the traveling frame 1 and extends into the pipe trench. The first fitting seat 21 and the second fitting seat 22 are respectively arranged at both ends of the bottom of the base frame 2; the lifting mechanism 3 is arranged at one end of the base frame 2 and is used to lift the end of the pipe in the pipe trench upwards. Push the walking frame 1 along the length direction of the trench to above the end of the installed pipe in the trench, lift the end of the pipe in the trench upward through the lifting mechanism 3, and then install the lifting belts 122 at the bottom of the two sets of lifting components 12 to the specified position of the pipe in the trench, and lift the pipe in the trench through the winch 121 until the pipe is in a fitting state with the first fitting seat 21 and the second fitting seat 22, that is, the direction of the end of the pipe in the trench can be guaranteed, and the two pipes can be conveniently connected by making the direction of the pipe outside the trench consistent with that of the pipe in the trench.

[0022] Reference Figure 1 , Figure 2 As shown, the mounting seat 4 is welded to one end of the base frame 2, and the mounting seat 4 is provided with a guide mechanism 5 for the pipeline to pass through and a clamping mechanism 6 for fixing the position of the pipeline, the guide mechanism 5 includes a guide seat 51 and a guide ring 52 arranged at the bottom of the guide seat 51, and the clamping mechanism 6 includes a clamping seat 61 and a clamping ring 62 arranged at the bottom of the clamping seat 61; the first fitting seat 21, the second fitting seat 22, the guide ring 52 and the clamping ring 62 are all arranged obliquely and in the same axial direction. Lift one end of the pipeline in the trench upward and fit it with the first fitting seat 21 and the second fitting seat 22, then insert the pipeline outside the trench into the guide ring 52 and clamp it through the clamping ring 62, that is, the pipeline in the trench can be in a coaxial state with the pipeline outside the trench, so that the docking operation can be conveniently performed. For pipes of different materials and types, the docking operation may be carried out by welding, hot-melt connection and socket connection. Since the present application limits the position direction of the pipe outside the trench by the guide mechanism 5 and fixes the adjusted position of the pipe by the clamping mechanism 6, after the adjustment is completed, the pipe outside the trench and the pipe inside the trench always have the same axial direction, so it can adapt to the operation process of the above-mentioned multiple connection methods.

[0023] Reference Figure 2 , Figure 3As shown, the winch 121 is fixedly installed on the top of the traveling frame 1, the steel rope of the winch 121 is provided with a hook 1211, and the lifting belt 122 is provided with a hanging ring 1221 for hanging the hook 1211. The two ends of the lifting belt 122 are detachably connected by connecting bolts 1222 and connecting nuts 1223. First, one end of the pipeline is lifted upward by the lifting mechanism 3 to facilitate the lifting belt 122 to be put on the pipeline, and then the connecting bolts 1222 are sequentially passed through the through holes pre-opened at both ends of the lifting belt 122, and then the connecting nuts 1223 are screwed into the connecting bolts 1222, so that the state of the lifting belt 122 can be maintained, so that the lifting belt 122 forms a closed loop to facilitate the lifting operation of the pipeline.

[0024] Reference Figure 4 , Figure 5 As shown, the lifting mechanism 3 includes a support seat 31, which is welded to the base frame 2. A lifting electric cylinder 32 is installed at the bottom of the support seat 31, and a lifting assembly 33 is arranged on the piston rod of the lifting electric cylinder 32; the lifting assembly 33 includes a lifting seat 331 and a lifting block 332, and a rotating groove 3311 is opened on one side of the lifting seat 331, and the lifting block 332 is rotatably connected in the rotating groove 3311 through a first rotating shaft 333, and one end of the lifting block 332 extends to the outside of the rotating groove 3311, and when the lifting block 332 rotates to a horizontal state, it abuts against the bottom wall of the rotating groove 3311, and a torsion spring 334 is connected between the first rotating shaft 333 and the lifting seat 331 for driving the lifting block 332 to rotate toward a horizontal state. Start the lifting cylinder 32 and move the piston rod of the lifting cylinder 32 out of the cylinder barrel, which can drive the lifting assembly 33 to move into the trench. When the lifting block 332 moves to contact the pipe, it can rotate upward from a horizontal state to a vertical state to pass through the pipe wall of the pipe. When the lifting assembly 33 is driven upward by the lifting cylinder 32, the lifting block 332 will not rotate due to the abutment of the bottom wall of the rotating groove 3311, so that the pipe can be lifted upward, so that the bottom of the pipe is separated from the bottom wall of the trench, so as to facilitate the installation of the lifting belt 122 on the pipe.

[0025] Reference Figure 5 As shown, the lifting seat 331 is rotatably mounted on the piston rod of the lifting electric cylinder 32, and a positioning collar 335 is provided on the top of the lifting seat 331, and a positioning pin 3351 is provided on the positioning collar 335 for fixing the position of the lifting seat 331. After the lifting belt 122 is installed on the pipeline, the pipeline is further lifted upward by two winches 121, so that the lifting assembly 33 can be separated from the pipe wall of the pipeline, the positioning pin 3351 is taken out and the lifting seat 331 is rotated 90°, so that the lifting block 332 can be moved to the outside of the pipeline, and then the lifting electric cylinder 32 drives the lifting assembly 33 to move upward as a whole, so that the lifting assembly 33 can be located above the pipeline, so as not to affect the subsequent pipeline docking operation.

[0026] Reference Figure 1 , Figure 2 As shown, the traveling frame 1 is provided with a through slot for the base frame 2 to pass through, and the traveling frame 1 is also provided with a lifting mechanism 14 for driving the base frame 2 to move along the height direction of the traveling frame 1. After the pipeline construction is completed, the base frame 2 is driven to move upward as a whole by the lifting mechanism 14, that is, the first fitting seat 21, the second fitting seat 22, the guide mechanism 5 and the clamping mechanism 6 can all move upward to the outside of the pipe trench. As shown in reference 6, an extension frame 13 is welded to one side of the bottom of the traveling frame 1, and a vertical seat 42 is provided at the bottom of the mounting seat 4. The extension frame 13 is provided with a through slot for the vertical seat 42 to pass through, so as to improve the stability of the mounting seat 4.

[0027] Reference Figure 1 As shown, the lifting mechanism 14 includes a lifting motor 141, a driving screw 142 and a driving beam 23. The driving screw 142 is connected to the traveling frame 1 by rotation along the height direction of the traveling frame 1. The lifting motor 141 is fixedly arranged at the top of the traveling frame 1 and the output shaft of the lifting motor 141 is fixedly connected to the driving screw 142. One end of the driving beam 23 is threadedly connected to the driving screw 142 and the other end is fixedly connected to the base frame 2. The base frame 2 is also provided with a guide beam 24. A guide rod 143 is provided on the traveling frame 1 and is located on the side opposite to the driving screw 142. A guide hole is provided on the guide beam 24 and is sleeved on the guide rod 143. When the lifting motor 141 is started to drive the driving screw 142 to rotate, the base frame 2 can be driven as a whole by the driving beam 23. Under the guidance of the guide rod 143 and the guide beam 24, the base frame 2 can be moved into or out of the pipe trench in the vertical direction.

[0028] Reference Figure 6 , Figure 8As shown, the guide seat 51 is fixedly arranged at the bottom of the mounting seat 4, and the guide seat 51 includes a vertical seat 511, and an inclined seat 512 is inclinedly arranged at the bottom of the vertical seat 511. A hollow groove 5121 is opened in the middle of the inclined seat 512, and the hollow groove 5121 separates the two sides of the inclined seat 512 into two fork arms 5122. The bottoms of the two fork arms 5122 are both hingedly arranged with rotating arms 513, and a straightening assembly 53 is arranged in the hollow groove 5121. The straightening assembly 53 is used to drive the two rotating arms 513 to remain in a parallel state with the fork arms 5122; the guide ring 52 includes two guide half rings 521, and the two guide half rings 521 are respectively arranged at the bottoms of the two rotating arms 513. When it is necessary to place the pipe outside the trench into the guide mechanism 5 and guide it, the two rotating arms 513 are kept parallel to the fork arm 5122 through the straightening assembly 53. At this time, the two guiding half rings 521 are in a closed state and form a guiding ring 52. The inner wall of the guiding ring 52 can fit the outer wall of the pipe and guide the pipe. After the pipe outside the trench is docked with the pipe inside the trench, the straightening assembly 53 is detached from the connection between the rotating arm 513 and the fork arm 5122. The two rotating arms 513 are not restricted by the straightening assembly 53 and can drive the guiding half rings 521 to rotate in a direction away from each other and detach from the pipe, thereby conveniently realizing the separation process of the guiding mechanism 5 and the pipe.

[0029] Reference Figure 8 As shown, the straightening assembly 53 includes a straightening electric cylinder 531, a driving plate 532 is connected to the piston rod of the straightening electric cylinder 531, and straightening sleeves 533 are arranged on both sides of the driving plate 532. When the straightening sleeves 533 are sleeved on the connecting part of the fork arm 5122 and the rotating arm 513, they can prevent the rotating arm 513 and the fork arm 5122 from rotating relative to each other, so that the two guide semi-rings 521 are in a state of being close to each other; when the driving plate 532 is driven to move upward by the straightening electric cylinder 531, the driving plate 532 drives the straightening sleeves 533 to move synchronously and move to the side of the fork arm 5122 away from the rotating arm 513, so that the position of the rotating arm 513 is no longer restricted. After the pipeline is connected, when it is lowered by the lifting assembly 12, the two guide semi-rings 521 can rotate freely so that the pipeline can be moved out of the guide mechanism 5.

[0030] Reference Figure 6 , Figure 7As shown, the clamping seat 61 includes an arc seat 611 and a driving seat 612 arranged at the bottom of the arc seat 611. The arc seat 611 is rotatably arranged on the side of the mounting seat 4 away from the base frame 2 through the second rotating shaft 613. The mounting seat 4 is provided with a rotating assembly 41 for driving the arc seat 611 to rotate. The driving seat 612 is fixedly arranged at one end of the arc seat 611 away from the mounting seat 4. The clamping ring 62 includes two clamping half rings 621. The driving seat 612 is provided with a driving assembly 63 for driving the two clamping half rings 621 to move in a direction close to or away from each other at the same time. When it is necessary to dock the pipeline outside the trench with the pipeline inside the trench, the arc seat 611 is driven to rotate into the trench through the rotating assembly 41, and then one end of the pipeline is inserted into the guide mechanism 5. After adjusting the position, the driving assembly 63 drives the two clamping half rings 621 to clamp the pipeline to achieve positioning, so as to facilitate the subsequent docking operation of the two pipelines.

[0031] Reference Figure 7 , Figure 8 As shown, a support arm 54 for supporting the arc seat 611 is obliquely arranged on one side of the vertical seat 511, a support block 541 is arranged on the support arm 54, a support groove 5411 adapted to the shape of the arc seat 611 is opened on the support block 541, a contact switch 542 for starting the straightening electric cylinder 531 is arranged in the support groove 5411, when the arc seat 611 is rotated to fit with the support groove 5411, the contact switch 542 can turn on the straightening electric cylinder 531 to drive the straightening sleeve 533 to move to the connection position between the fork arm 5122 and the rotating arm 513. When the arc seat 611 is driven to rotate to a specified position in the pipe trench by the rotating component 41, the arc seat 611 is abutted against the support groove 5411 and the contact switch 542 is started to turn on the straightening cylinder 531. The piston rod of the straightening cylinder 531 drives the straightening sleeve 533 to move through the driving plate 532 and fixes the relative position of the rotating arm 513 and the fork arm 5122, so that the two guide half rings 521 are close to each other to form a guide ring 52, so as to guide the pipeline.

[0032] Reference Figure 7 As shown, the driving assembly 63 includes a driving motor 631, a double-axis lead screw 632 and two driving blocks 633. A driving groove 6121 is provided on one side of the driving seat 612 away from the arc seat 611. The double-axis lead screw 632 is rotatably connected in the driving groove 6121. The driving motor 631 is fixedly arranged at one end of the driving seat 612 and the output shaft of the driving motor 631 is fixedly connected to the double-axis lead screw 632. The two driving blocks 633 are both slidably arranged in the driving groove 6121 and are respectively threadedly connected to the two ends of the double-axis lead screw 632. When the driving motor 631 is started to drive the bidirectional lead screw to rotate, the two clamping half rings 621 can be driven to move towards each other through the two driving blocks 633, and the pipeline can be clamped to achieve the positioning effect. Fig. 9As shown, the rotating assembly 41 includes a rotating motor 411, a worm wheel 412, a worm 413 and two mounting blocks 414. The worm wheel 412 is coaxially connected to the second rotating shaft 613. The two mounting blocks 414 are welded to the mounting seat 4. The worm 413 is rotatably connected between the two mounting blocks 414 and meshes with the worm wheel 412. The rotating motor 411 is fixedly arranged on one of the mounting blocks 414 and the output shaft of the rotating motor 411 is coaxially connected to the worm 413. The rotating motor 411 drives the worm 413 to rotate, that is, the arc seat 611 can be driven to rotate through the worm wheel 412, and the position stability can be maintained after the rotation.

[0033] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A temporary pipe support device for road construction, characterized in that: The invention comprises a walking frame (1), a base frame (2), a lifting mechanism (3) and a mounting seat (4); a lifting assembly (12) is arranged on the top of the walking frame (1); the base frame (2) is arranged on the bottom of the walking frame (1); a first fitting seat (21) and a second fitting seat (22) are arranged at both ends of the bottom of the base frame (2); The lifting mechanism (3) comprises a support seat (31), the support seat (31) is fixed on the base frame (2), a lifting electric cylinder (32) is provided at the bottom of the support seat (31), and a lifting component (33) is provided on the piston rod of the lifting electric cylinder (32); The mounting seat (4) is fixed to one end of the base frame (2); a guide mechanism (5) for the pipeline to pass through and a clamping mechanism (6) for fixing the pipeline are arranged on the mounting seat (4); the guide mechanism (5) comprises a guide seat (51) and a guide ring (52) arranged at the bottom of the guide seat (51); the clamping mechanism (6) comprises a clamping seat (61) and a clamping ring (62) arranged at the bottom of the clamping seat (61); the first fitting seat (21), the second fitting seat (22), the guide ring (52) and the clamping ring (62) are all arranged obliquely and have the same axial direction.

2. The temporary support device for pipelines for road construction according to claim 1, characterized in that: The lifting assembly (33) includes a lifting seat (331) and a lifting block (332), a rotating groove (3311) is provided on one side of the lifting seat (331), the lifting block (332) is rotatably connected in the rotating groove (3311) through a first rotating shaft (333), and one end of the lifting block (332) extends to the outside of the rotating groove (3311), and when the lifting block (332) is rotated to a horizontal state, it abuts against the bottom wall of the rotating groove (3311), and a torsion spring (334) is connected between the first rotating shaft (333) and the lifting seat (331) for driving the lifting block (332) to rotate toward a horizontal state.

3. The temporary support device for pipelines for road construction according to claim 2, characterized in that: The lifting seat (331) is rotatably arranged on the piston rod of the lifting electric cylinder (32), a positioning ring (335) is arranged on the top of the lifting seat (331), and a positioning pin (3351) for fixing the position of the lifting seat (331) is arranged on the positioning ring (335).

4. The temporary support device for pipelines for road construction according to claim 1, characterized in that: The guide seat (51) is fixedly arranged at the bottom of the mounting seat (4), and the guide seat (51) comprises a vertical seat (511). An inclined seat (512) is obliquely arranged at the bottom of the vertical seat (511). A hollow groove (5121) is opened in the middle of the inclined seat (512), and the hollow groove (5121) separates the two sides of the inclined seat (512) into two fork arms (5122). The bottoms of the two fork arms (5122) are both hingedly provided with rotating arms (513). A straightening assembly (53) is arranged in the hollow groove (5121), and the straightening assembly (53) is used to drive the two rotating arms (513) to remain in a state of being parallel to the fork arms (5122); the guide ring (52) comprises two guide half rings (521), and the two guide half rings (521) are respectively arranged at the bottoms of the two rotating arms (513).

5. The temporary support device for pipelines for road construction according to claim 4, characterized in that: The clamping seat (61) comprises an arc seat (611) and a driving seat (612) arranged at the bottom of the arc seat (611); the arc seat (611) is rotatably arranged on a side of the mounting seat (4) away from the base frame (2) via a second rotating shaft (613); a rotating assembly (41) for driving the arc seat (611) to rotate is arranged on the mounting seat (4); the driving seat (612) is fixedly arranged at one end of the arc seat (611) away from the mounting seat (4); the clamping ring (62) comprises two clamping half rings (621); and a driving assembly (63) for driving the two clamping half rings (621) to move simultaneously in a direction of approaching or moving away from each other is arranged on the driving seat (612).

6. The temporary support device for pipelines for road construction according to claim 5, characterized in that: The straightening assembly (53) comprises a straightening electric cylinder (531), a piston rod of the straightening electric cylinder (531) being connected to a driving plate (532), straightening sleeves (533) being arranged on both sides of the driving plate (532), and the straightening sleeves (533) being arranged on the connection portion between the fork arm (5122) and the rotating arm (513) to prevent the rotating arm (513) and the fork arm (5122) from rotating relative to each other.

7. The temporary support device for pipelines for road construction according to claim 6, characterized in that: A support arm (54) for supporting the arc seat (611) is obliquely arranged on one side of the vertical seat (511); a support block (541) is arranged on the support arm (54); a support groove (5411) matching the shape of the arc seat (611) is opened on the support block (541); a contact switch (542) for starting the straightening electric cylinder (531) is arranged in the support groove (5411); when the arc seat (611) rotates to fit with the support groove (5411), the contact switch (542) can open the straightening electric cylinder (531) to drive the straightening sleeve (533) to move to the connection position between the fork arm (5122) and the rotating arm (513).

8. The temporary support device for pipelines for road construction according to claim 5, characterized in that: The driving assembly (63) comprises a driving motor (631), a double-axis lead screw (632) and two driving blocks (633); a driving groove (6121) is provided on a side of the driving seat (612) facing away from the arc-shaped seat (611); the double-axis lead screw (632) is rotatably connected in the driving groove (6121); the driving motor (631) is fixedly arranged at one end of the driving seat (612) and the output shaft of the driving motor (631) is fixedly connected to the double-axis lead screw (632); the two driving blocks (633) are both slidably arranged in the driving groove (6121) and are respectively threadedly connected to the double-axis lead screw (6121). 32); the rotating assembly (41) comprises a rotating motor (411), a worm wheel (412), a worm (413) and two mounting blocks (414); the worm wheel (412) is coaxially connected to the second rotating shaft (613); the two mounting blocks (414) are fixedly arranged on the mounting seat (4); the worm (413) is rotatably connected between the two mounting blocks (414) and meshes with the worm wheel (412); the rotating motor (411) is fixedly arranged on one of the mounting blocks (414); and the output shaft of the rotating motor (411) is coaxially connected to the worm (413).

9. The temporary support device for pipelines for road construction according to claim 5, characterized in that: The walking frame (1) is provided with a through slot for the base frame (2) to pass through, an extension frame (13) is provided on one side of the bottom of the walking frame (1), a vertical seat (42) is provided at the bottom of the mounting seat (4), the extension frame (13) is provided with a through slot for the vertical seat (42) to pass through, and the walking frame (1) is also provided with a lifting mechanism (14) for driving the base frame (2) to move along the height direction of the walking frame (1).

10. The temporary pipe support device for road construction according to claim 9, characterized in that: The lifting mechanism (14) comprises a lifting motor (141), a driving screw (142) and a driving beam (23); the driving screw (142) is connected to the walking frame (1) in a rotational manner along the height direction of the walking frame (1); the lifting motor (141) is fixedly arranged on the top of the walking frame (1) and the output shaft of the lifting motor (141) is fixedly connected to the driving screw (142); one end of the driving beam (23) is threadedly connected to the driving screw (142) and the other end is fixedly connected to the base frame (2); a guide beam (24) is also arranged on the base frame (2); a guide rod (143) is arranged on the walking frame (1) and on a side opposite to the driving screw (142); a guide hole is opened on the guide beam (24) and is sleeved on the guide rod (143).

Citation Information

Patent Citations

  • Auxiliary installation device for buried pipeline

    CN117249301A

  • Municipal pipeline connecting device

    CN214789402U

  • Municipal engineering pipeline construction device

    CN217921108U

  • Machining tool for connecting groove in air inlet pipe in air heater connecting pipe

    CN219853375U

  • Well lid opening device

    CN221420634U