Prefabricated wall mounting hanging formwork and construction method thereof

By adopting prefabricated wall installation hanging molds and construction methods, the problems of large labor consumption, poor construction quality and poor grouting quality in the prior art are solved, and the convenience and efficiency of construction are achieved, ensuring the improvement of construction quality and grouting quality.

CN119843865AActive Publication Date: 2025-04-18THE SECOND CONSTR OF CHINA CONSTR EIGHTH ENG DIV
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202510095798.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-22
Publication Date
2025-04-18
Estimated Expiration
2045-01-22

AI Technical Summary

Technical Problem

In the existing prefabricated wall construction technology, the construction of seat slurry is very labor-consuming, the construction quality is poor, and it is difficult to effectively prevent the grouting pressure from shattering the mortar in the silo, resulting in poor grouting quality.

Method used

A prefabricated wall installation hanging mold and a construction method thereof are adopted, including a hanging mold mold plate and installation components. The hanging mold plate consists of a panel, a frame, reinforced steel ribs and level bubbles. The panel is equipped with installation holes in the position of prefabricated wall steel bars. The installation components include threaded barrels, mounting sleeves, limit thread holes and limit bolts. These components are used to fix the prefabricated wall steel bars on the hanging mold plate to ensure their level and fixation.

Benefits of technology

The convenience and efficiency of prefabricated wall seat slurry construction is achieved, manual consumption is reduced, construction quality is improved, grouting pressure is used to damage the mortar in the enclosure silo, and grouting quality is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119843865A_ABST
    Figure CN119843865A_ABST
Patent Text Reader

Abstract

The invention provides a prefabricated wall mounting hanging formwork and a construction method thereof, and belongs to the field of building construction. According to the technical scheme, the formwork hanging device comprises a formwork hanging plate and an installation assembly matched with the formwork hanging plate, the formwork hanging plate comprises a panel, a frame is arranged at the edge of the panel, reinforcing steel ribs are arranged on the inner side of the frame, a level bubble is arranged in the center of the panel, and a plurality of through installation holes are formed in the position, corresponding to prefabricated wall steel bars, of the panel. The device has the beneficial effects that the structure is simple, installation is convenient and fast, and the problems that the labor consumption of prefabricated wall base slurry construction is large, the construction quality is poor, and the grouting quality is poor due to the fact that mortar in a surrounding bin is difficult to be effectively prevented from being damaged by grouting pressure during surrounding bin are effectively solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of building construction, and in particular to a prefabricated wall installation hanging formwork and a construction method thereof. Background Art

[0002] The existing prefabricated wall construction process is to hoist the wall on the floor slab after pouring, and use gaskets under the wall to control the elevation (the floor slab is uneven). After the wall panel is placed, the gap (3-5cm) between the wall panel and the floor slab needs to be sealed with seat slurry (sealing warehouse process). There is also a method of separating each grouting port with seat slurry before the prefabricated wall is placed (separating warehouse process). After the above-mentioned sealing warehouse or dividing warehouse construction is completed, the grouting port is grouting construction. The existing seat slurry construction requires workers to bend down and squat for a long time, which consumes a lot of physical strength. At the same time, it is difficult to control the quality during operation. In the later stage of grouting, grouting material often leaks and cannot be filled. After grouting, the seat slurry needs to be removed, resulting in waste. Summary of the invention

[0003] The purpose of the present invention is to provide a prefabricated wall installation hanging formwork and a construction method thereof which has a simple structure and is easy to install, and which effectively solves the problems of high labor consumption in the construction of prefabricated wall base slurry, poor construction quality, and difficulty in effectively preventing the grouting pressure from damaging the enclosure mortar during enclosure, resulting in poor grouting quality.

[0004] The present invention is achieved by the following measures: A prefabricated wall installation hanging formwork, characterized in that it comprises a hanging formwork mold plate and an installation component that cooperates with the hanging formwork mold plate; The hanging mold plate comprises a panel, a frame is arranged at the edge of the panel, a reinforcing steel rib is arranged inside the frame, and a level bubble is arranged at the center of the panel; The panel is provided with a plurality of through-holes corresponding to the positions of the prefabricated wall reinforcements; The installation assembly includes a plurality of threaded barrels arranged on the panel and connected to the installation holes in a one-to-one correspondence, a mounting sleeve is arranged on the periphery of the threaded barrel, the prefabricated wall reinforcement passes through the mounting sleeve and the threaded barrel, a through-limiting threaded hole is opened on the side wall of the mounting sleeve, a limiting bolt is arranged in the limiting threaded hole, and the end of the limiting bolt passes through the limiting threaded hole and abuts against the prefabricated wall reinforcement; The number of mounting hole positions is determined based on the number of prefabricated wall reinforcement positions; A mold reinforcement steel rib is arranged on the back side of the hanging mold plate (the side not in contact with concrete), and the reinforcement steel rib is used to enhance the rigidity of the hanging mold plate and reduce deformation.

[0005] The specific features of the present invention also include: The outer wall of the threaded barrel and the inner wall of the mounting sleeve are provided with threads that match each other.

[0006] Adjustable horizontal steel bars are arranged under the panel, and the adjustable horizontal steel bars are tied or welded to the reserved steel bars of the prefabricated wall.

[0007] The construction method includes the following steps: S1. During construction, first install the adjustable horizontal steel bars according to the predetermined position, then pass the prefabricated wall steel bars through the corresponding mounting holes and the threaded tubes on the panel, and place the hanging formwork mold plate on the adjustable horizontal steel bars; S2, passing the installation sleeve through the reserved wall steel bar and installing it on the threaded tube, finely adjusting the horizontality of the hanging formwork mold plate by using a bubble level, and tightening the limit bolts to fix the hanging formwork mold plate; S3. After pouring the slab concrete, remove the hanging formwork mold plate. The hanging formwork mold plate is placed on the floor slab surface to form a hanging formwork groove. Pour the pre-laid grouting material into the groove. After the prefabricated wall is installed at the designated position, the pre-laid grouting material is squeezed out from the bottom of the prefabricated wall to close the gap between the groove and the prefabricated wall, and then proceed to the next step of prefabricated wall construction.

[0008] The beneficial effects of the present invention are: simple structure, convenient installation, and effective solution to the problems of high labor consumption and poor construction quality in the construction of prefabricated wall base slurry, and difficulty in effectively preventing the grouting pressure from damaging the enclosure mortar during enclosure, resulting in poor grouting quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0009] Figure 1 It is a structural schematic diagram of the present invention in use state.

[0010] Figure 2 It is a structural schematic diagram of the hanging mold plate in the present invention.

[0011] Figure 3 It is a structural schematic diagram of the hanging mold plate in the present invention.

[0012] Among them, the figure markings are: 1. prefabricated wall; 2. hanging formwork mold plate; 201. panel; 202. frame; 203. mounting hole; 204. reinforcing steel rib; 205. level bubble; 3. prefabricated wall steel bar; 4. adjusting horizontal steel bar; 5. threaded tube; 6. mounting sleeve; 601. limiting threaded hole; 7. limiting bolt. DETAILED DESCRIPTION

[0013] In order to clearly illustrate the technical features of this solution, this solution is described below through a specific implementation method.

[0014] See also Figure 1-3 , a prefabricated wall installation hanging formwork, comprising a hanging formwork mold plate 2 and an installation component that matches the hanging formwork mold plate 2; The hanging mold plate 2 includes a panel 201, a frame 202 is arranged at the edge of the panel 201, a reinforcing steel rib 204 is arranged inside the frame 202, and a level bubble 205 is arranged at the center of the panel 201; A plurality of through-holes 203 are provided on the panel 201 corresponding to the positions of the reinforcement bars 3 of the prefabricated wall 1; The installation assembly includes a plurality of threaded barrels 5 arranged on the panel 201 and connected to the installation holes 203 in a one-to-one correspondence. The outer periphery of the threaded barrel 5 is provided with a mounting sleeve 6. The prefabricated wall 1 steel bar 3 passes through the mounting sleeve 6 and the threaded barrel 5. A through-limiting threaded hole 601 is provided on the side wall of the mounting sleeve 6. A limiting bolt 7 is arranged in the limiting threaded hole 601. The end of the limiting bolt 7 passes through the limiting threaded hole 601 and abuts against the prefabricated wall 1 steel bar 3. The number of the positions of the mounting holes 203 is determined according to the number of the positions of the steel bars 3 of the prefabricated wall 1; A mold reinforcement steel rib 204 is arranged on the back side of the hanging mold plate 2 (the side not in contact with concrete), and the reinforcement steel rib 204 is used to enhance the rigidity of the hanging mold plate 2 and reduce deformation.

[0015] The outer wall of the threaded barrel 5 and the inner wall of the mounting sleeve 6 are provided with threads that match each other.

[0016] Adjustable horizontal steel bars 4 are arranged below the panel 201 , and the adjustable horizontal steel bars 4 are tied or welded to the reserved steel bars 3 of the prefabricated wall 1 .

[0017] The construction method includes the following steps: S1. During construction, firstly, the horizontal steel bars 4 are installed and adjusted according to the predetermined position, then the steel bars 3 of the prefabricated wall 1 are passed through the corresponding installation holes 203 and the threaded tube 5 on the panel 201, and the hanging mold plate 2 is placed on the adjusted horizontal steel bars 4; S2, install the installation sleeve 6 through the reserved wall reinforcement 3 on the threaded tube 5, finely adjust the horizontality of the hanging mold plate 2 by the bubble level, tighten the limit bolt 7 to fix the hanging mold plate 2; S3. After pouring the slab concrete, remove the hanging formwork mold plate 2, which is located on the floor slab surface to form a hanging formwork groove, pour pre-laid grouting material into the groove, and after the prefabricated wall 1 is installed at the designated position, the pre-laid grouting material is squeezed out from the bottom of the prefabricated wall 1 to close the gap between the groove and the prefabricated wall 1, and then the next step of construction of the prefabricated wall 1 is carried out.

[0018] Technical features not described in the present invention can be achieved through or by adopting existing technologies and will not be described in detail here. Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by ordinary technicians in this technical field within the essential scope of the present invention should also fall within the scope of protection of the present invention.

Claims

1. A prefabricated wall installation hanging formwork, characterized in that: It includes a hanging mold plate and a mounting assembly that matches the hanging mold plate; The hanging mold plate comprises a panel, a frame is arranged at the edge of the panel, a reinforcing steel rib is arranged inside the frame, and a level bubble is arranged at the center of the panel; The panel is provided with a plurality of through-holes corresponding to the positions of the prefabricated wall reinforcements; The installation assembly includes a plurality of threaded tubes arranged on the panel and connected to the installation holes in a one-to-one correspondence. A mounting sleeve is arranged on the periphery of the threaded tube. The prefabricated wall reinforcement passes through the mounting sleeve and the threaded tube. A penetrating limiting threaded hole is opened on the side wall of the mounting sleeve. A limiting bolt is arranged in the limiting threaded hole. The end of the limiting bolt passes through the limiting threaded hole and rests on the prefabricated wall reinforcement.

2. The prefabricated wall installation hanging formwork according to claim 1, characterized in that: The outer wall of the threaded barrel and the inner wall of the mounting sleeve are provided with threads that match each other.

3. The prefabricated wall installation hanging formwork according to claim 2, characterized in that: Adjustable horizontal steel bars are arranged under the panel, and the adjustable horizontal steel bars are tied or welded to the reserved steel bars of the prefabricated wall.

4. The prefabricated wall installation hanging formwork according to claim 3, characterized in that: The construction method includes the following steps: S1. During construction, first install the adjustable horizontal steel bars according to the predetermined position, then pass the prefabricated wall steel bars through the corresponding mounting holes and the threaded tubes on the panel, and place the hanging formwork mold plate on the adjustable horizontal steel bars; S2, passing the installation sleeve through the reserved wall steel bar and installing it on the threaded tube, finely adjusting the horizontality of the hanging formwork mold plate by using a bubble level, and tightening the limit bolts to fix the hanging formwork mold plate; S3. After pouring the slab concrete, remove the hanging formwork mold plate. The hanging formwork mold plate is placed on the floor slab surface to form a hanging formwork groove. Pour the pre-laid grouting material into the groove. After the prefabricated wall is installed at the designated position, the pre-laid grouting material is squeezed out from the bottom of the prefabricated wall to close the gap between the groove and the prefabricated wall, and then proceed to the next step of prefabricated wall construction.

Citation Information

Patent Citations

  • Same-floor grouting method for installing prefabricated shear wall of fabricated type building

    CN112211319A

  • Connecting structure and connecting method for cast-in-place concrete wall and PC component wall

    CN114718218A

  • Formwork lower opening gap plugging method

    CN115772956A

  • Construction method for joint of vertical component and cast-in-place structure of fabricated stair

    CN117145228A

  • Typical forms is used in PC prefab external wall board grout

    CN206737417U