Plasma arc welding machine for high-performance material circular mechanical parts

By designing welding box components, protective components and welding components in plasma arc welding machines, and using dry ice cubes to absorb heat and compressed springs to achieve buffer protection, the problem of inability to automatically match the cooling process and lack of fault protection in the prior art is solved, and the working effect and equipment life of the welding machine are improved.

CN119857916APending Publication Date: 2025-04-22NANTONG ZHENSHUN MASCH MFG CO LTD

Patent Information

Application Number
CN202510324457.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-19
Publication Date
2025-04-22

AI Technical Summary

Technical Problem

Existing plasma arc welding machines cannot automatically match the cooling process, and lack effective protection in case of failure or offset, resulting in a decrease in working effect.

Method used

A high-performance material circular mechanical parts plasma arc welding machine is designed, using welding box components, protective components and welding components, including dry ice cubes to absorb heat, compression springs and electric push rods to achieve buffer protection and position adjustment.

Benefits of technology

Heat absorbed through dry ice cubes, avoid high temperature damage, and improve equipment life; in case of failure or offset, rapid protection is achieved, and the welding position is improved tone and working effect are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119857916A_ABST
    Figure CN119857916A_ABST
Patent Text Reader

Abstract

The invention relates to the field of plasma arc welding, in particular to a plasma arc welding machine for high-performance material circular mechanical parts. Comprising a welding box assembly, a protection assembly capable of achieving buffering protection is installed on the inner wall of one side of the welding box assembly, and a machining assembly is installed on the welding box assembly; in the high-temperature welding process, dry ice blocks are driven to be rapidly gasified to absorb heat, damage to the structure by high temperature is avoided, the service life of equipment is prolonged, when faults or deviation occurs in the welding process, a second compression spring drives a sliding baffle to move to the position under the plasma arc welding structure after feeling that pressure disappears, and the welding quality is improved. And in the moving process of the fan steel plate, the fan steel plate on the clamping structure is driven to drive a sliding plate to slide in a sliding groove to extrude a first compression spring for buffering protection, so that the convenience of the welding position is improved, and meanwhile, the working effect of the plasma arc welding machine is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of plasma arc welding, and in particular relates to a plasma arc welding machine for circular mechanical parts made of high-performance materials. Background Art

[0002] Plasma arc is a high-temperature ion flow produced by ion gas being ionized, which is ejected from the nozzle hole and compressed to form a slender arc column.

[0003] After searching, in the prior art, Chinese patent publication number: CN115194306A, publication date: 2022-10-18, discloses a plasma arc welding machine with autonomous temperature control function, including a welding table, the welding table is fixedly connected to a top plate through multiple supporting legs, a welding port is opened on the welding table, and the welding table is located on both sides of the welding port. There are also abutment mechanisms that can move toward each other to abut two plates, and the bottom of the top plate is located on both sides of the welding port. Clamping components are installed; the above embodiment can automatically perform beveling, welding, filling and cleaning processes.

[0004] But the device still has the following defects: It is impossible to automatically match the cooling process according to the high temperature generated by the plasma arc, and timely protection is not performed when encountering failures or deviations, thereby reducing the working effect of the plasma arc welding machine. Summary of the invention

[0005] In view of the above problems, the present invention provides a plasma arc welding machine for circular mechanical parts made of high-performance materials, comprising a welding box assembly, a protective assembly capable of buffering and protecting is installed on one inner wall of the welding box assembly, a processing assembly is installed on the welding box assembly, and a welding assembly capable of improving position adjustment is installed on the bottom; The welding assembly comprises a second electric slide, the output end of the second electric slide is transmission-connected with a second fixed plate, and a plasma arc welding structure is installed at the bottom center of the second fixed plate; The processing assembly includes a first connecting plate and two groups of placement boxes, one end of two groups of second compression springs are symmetrically installed on one side wall of the first connecting plate, and a second connecting plate is connected between the other ends of the two groups of second compression springs, and a number of groups of dry ice blocks that can absorb heat and avoid high-temperature damage are evenly spaced in each group of the placement boxes, a group of seventh electric push rods are installed on one side wall of each group of the placement boxes, a group of buffer cylinders are installed on the output end of each group of the seventh electric push rods, and a group of auxiliary discs are installed on the top of each group of the buffer cylinders.

[0006] Furthermore, the welding box assembly includes a welding box body, and two groups of first cavities are symmetrically opened on one side wall of the welding box body, a group of first electric push rods are installed in each group of the first cavities, and a heat insulation plate is installed between the output ends of the two groups of the first electric push rods.

[0007] Furthermore, a collecting plate is installed on one side wall of the heat insulation board, the bottom of the collecting plate is slidably connected to the bottom inner wall of the welding box body, and a first pressure sensor is installed on one side wall of the welding box body.

[0008] Furthermore, a second cavity is opened on the top of the welding box body, a second electric push rod is installed in the second cavity, and a top plate is installed on the output end of the second electric push rod.

[0009] Furthermore, the protection component includes a first electric slide, which is installed on the inner wall of the welding box body. The output end of the first electric slide is transmission-connected with a first fixed block, a first fixed plate is installed on one side wall of the first fixed block, and a slide groove is opened on the bottom of the first fixed plate.

[0010] Furthermore, a second fixed block is installed on the bottom edge of the first fixed plate, one end of a first compression spring is installed on a side wall of the second fixed block, a sliding plate is installed on the other end of the first compression spring, the sliding plate is slidably connected in the sliding groove, and a clamping structure is installed on the bottom of the sliding plate.

[0011] Furthermore, the top of the second electric slide is installed on the bottom of the top plate, and two groups of third fixed blocks are symmetrically installed on the bottom edge of the second fixed plate. A group of third electric push rods are installed on one side wall of each group of the third fixed blocks, and a group of protective fan rings are installed on the output end of each group of the third electric push rods.

[0012] Furthermore, one end of the first connecting plate is mounted on a side wall of the heat insulation plate, and the bottom of the second connecting plate is slidably connected to the top of the aggregate plate.

[0013] Furthermore, a fourth electric push rod is installed on the outer wall of the first connecting plate, a first electromagnetic block is installed on the output end of the fourth electric push rod, a second electromagnetic block is installed on the outer wall of the second connecting plate, and the first electromagnetic block is magnetically connected to the second electromagnetic block.

[0014] Furthermore, two groups of fifth electric push rods are symmetrically installed on the top edge of the second connecting plate, a group of fourth fixed blocks are installed on the output end of each group of the fifth electric push rods, a group of sixth electric push rods are installed on the bottom of each group of the fourth fixed blocks, a group of clamping blocks are installed on the output end of each group of the sixth electric push rods, a group of sliding baffles are slidably connected between the tops of the two groups of clamping blocks, and one end of each group of the placement boxes is installed on a side wall of the clamping block.

[0015] The beneficial effects of the present invention are: 1. During high-temperature welding, the dry ice is driven to vaporize quickly to absorb heat, avoiding damage to the structure caused by high temperature and prolonging the service life of the equipment. When a fault or deviation occurs during welding, the second compression spring senses that the pressure disappears and drives the sliding baffle to move directly below the plasma arc welding structure. In the process of moving the fan steel plate, the fan steel plate on the clamping structure drives the sliding plate to slide in the slide groove to squeeze the first compression spring for buffering protection, thereby improving the adjustability of the welding position and the working effect of the plasma arc welding machine.

[0016] 2. When welding, the auxiliary disc is located below the welding point to provide auxiliary support and stability for the fan steel plate. As the welding point moves, the seventh electric push rod can be started for auxiliary adjustment. In the subsequent heat dissipation work, the first electric push rod can be started to push the insulation board to move for heat dissipation. In order to improve the maintenance effect of the structure, the second electric push rod is started to drive the top plate to rise, thereby improving the convenience of device maintenance.

[0017] 3. Before the plasma arc welding machine starts working, first place one group of fan steel plates that need to be welded on the clamping structure for limit clamping, then start the first electric slide to adjust the height, then place the other group of fan steel plates between the two groups of clamping blocks, then start the fifth electric push rod to push the fourth fixed block to move toward each other, so that the two groups of clamping blocks clamp and limit the fan steel plates, and then start the sixth electric push rod to adjust the height, which improves the steel plate alignment effect while improving the device clamping compatibility effect.

[0018] 4. After the two sets of clamping blocks clamp the fan steel plate in place, start the fourth electric push rod to push the first electromagnetic block and the second electromagnetic block to establish a magnetic connection. Then, drive the fourth electric push rod to drive the second connecting plate to move toward the first connecting plate, start the plasma arc welding structure for welding, and in order to increase the welding range, start the second electric slide to drive the plasma arc welding structure for translational welding. Then, in order to improve the protection effect of plasma arc welding, start the third electric push rod to push the protective fan ring to the designated position to block the high temperature. After the subsequent work is completed, the two sets of protective fan rings can be started to align for wrapping protection, thereby improving the protection effect of the device.

[0019] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures pointed out in the description, claims and drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0021] Figure 1 A schematic structural diagram of a plasma arc welding machine according to an embodiment of the present invention is shown; Figure 2 It shows a schematic structural diagram of a welding box assembly according to an embodiment of the present invention; Figure 3 A schematic diagram of the structure of a protection component according to an embodiment of the present invention is shown; Figure 4 A schematic structural diagram of a welding assembly according to an embodiment of the present invention is shown; Figure 5 A schematic diagram of the structure of a processing assembly according to an embodiment of the present invention is shown; Figure 6 A schematic diagram of the placement box structure according to an embodiment of the present invention is shown.

[0022] In the figure: 1. welding box assembly; 101. welding box body; 102. first cavity; 103. first electric push rod; 104. heat insulation board; 105. collecting plate; 106. first pressure sensor; 107. second cavity; 108. second electric push rod; 109. top plate; 2. protection assembly; 201. first electric slide; 202. first fixed block; 203. first fixed plate; 204. slide groove; 205. second fixed block; 206. sliding plate; 207. first compression spring; 208. clamping structure; 3. welding assembly; 301. second electric slide; 302. second fixed plate ; 303, third fixed block; 304, third electric push rod; 305, protective fan ring; 306, plasma arc welding structure; 4, processing assembly; 401, first connecting plate; 402, second compression spring; 403, second connecting plate; 404, fourth electric push rod; 405, first electromagnetic block; 406, second electromagnetic block; 407, fifth electric push rod; 408, fourth fixed block; 409, sixth electric push rod; 410, clamping block; 411, sliding baffle; 412, placement box; 413, dry ice block; 414, seventh electric push rod; 415, buffer cylinder; 416, auxiliary disc. DETAILED DESCRIPTION

[0023] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0024] The embodiment of the present invention provides a plasma arc welding machine for high-performance material circular mechanical parts. It includes a welding box assembly 1, exemplarily, such as Figure 1 As shown, a protection component 2 is installed on one inner wall of the welding box component 1, a processing component 4 is installed on the welding box component 1, and a welding component 3 is installed on the bottom.

[0025] For example, Figure 2As shown, the welding box assembly 1 includes a welding box body 101, and two groups of first cavities 102 are symmetrically opened on one side wall of the welding box body 101, and a group of first electric push rods 103 are installed in each group of the first cavities 102, and a heat insulation board 104 is installed between the output ends of the two groups of the first electric push rods 103, and a collecting plate 105 is installed on one side wall of the heat insulation board 104, and the bottom of the collecting plate 105 is slidably connected to the bottom inner wall of the welding box body 101, and a first pressure sensor 106 is installed on one side wall of the welding box body 101, and a second cavity 107 is opened on the top of the welding box body 101, and a second electric push rod 108 is installed in the second cavity 107, and a top plate 109 is installed on the output end of the second electric push rod 108, and the top plate 109 is located directly above the welding box body 101.

[0026] For example, Figure 3 As shown, the protective component 2 includes a first electric slide 201, which is installed on the inner wall of the welding box body 101, and a first fixed block 202 is transmission-connected on the output end of the first electric slide 201, a first fixed plate 203 is installed on one side wall of the first fixed block 202, a slide groove 204 is provided on the bottom of the first fixed plate 203, a second fixed block 205 is installed on the bottom edge of the first fixed plate 203, one end of a first compression spring 207 is installed on one side wall of the second fixed block 205, a sliding plate 206 is installed on the other end of the first compression spring 207, the sliding plate 206 is slidably connected in the slide groove 204, and a clamping structure 208 is installed on the bottom of the sliding plate 206.

[0027] During the high-temperature welding process, the dry ice block 413 will be driven to vaporize quickly to absorb heat, thereby avoiding damage to the structure due to high temperature and increasing the service life of the equipment. When a fault or deviation occurs during the welding process, the magnetic connection between the first electromagnetic block 405 and the second electromagnetic block 406 will be detached. After the second compression spring 402 senses the disappearance of pressure, it begins to drive the second connecting plate 403 to move away from the first connecting plate 401. During the movement, the sliding baffle 411 is driven to move to the bottom of the plasma arc welding structure 306. During the movement of the fan steel plate, the fan steel plate on the clamping structure 208 drives the sliding plate 206 to slide in the slide groove 204 to squeeze the first compression spring 207 for buffering protection, thereby improving the adjustability of the welding position and the working effect of the plasma arc welding machine.

[0028] For example, Figure 4As shown, the welding assembly 3 includes a second electric slide 301, the top of the second electric slide 301 is installed on the bottom of the top plate 109, the output end of the second electric slide 301 is transmission-connected with a second fixed plate 302, a plasma arc welding structure 306 is installed at the bottom center of the second fixed plate 302, two groups of third fixed blocks 303 are symmetrically installed at the bottom edge of the second fixed plate 302, a group of third electric push rods 304 are installed on one side wall of each group of the third fixed blocks 303, and a group of protective fan rings 305 are installed on the output end, and the two groups of protective fan rings 305 are movably connected.

[0029] When welding, the auxiliary disc 416 is located below the welding point, which provides auxiliary support and stability for the fan steel plate. As the welding point moves, the seventh electric push rod 414 can be started for auxiliary adjustment. In subsequent heat dissipation work, the first electric push rod 103 can be started to push the insulation board 104 to move for heat dissipation. In order to improve the maintenance effect of the structure, the second electric push rod 108 is started to drive the top plate 109 to rise, thereby improving the convenience of device maintenance.

[0030] For example, Figure 5 and Figure 6As shown, the processing assembly 4 includes a first connecting plate 401, one end of the first connecting plate 401 is installed on a side wall of the heat insulation plate 104, one end of two groups of second compression springs 402 are symmetrically installed on one side wall of the first connecting plate 401, a second connecting plate 403 is connected between the other ends of the two groups of second compression springs 402, the bottom of the second connecting plate 403 is slidably connected to the top of the collecting plate 105, a fourth electric push rod 404 is installed on the outer wall of the first connecting plate 401, a first electromagnetic block 405 is installed on the output end of the fourth electric push rod 404, a second electromagnetic block 406 is installed on the outer wall of the second connecting plate 403, the first electromagnetic block 405 is magnetically connected to the second electromagnetic block 406, and two groups of fifth electric push rods are symmetrically installed at the top edge of the second connecting plate 403. Push rod 407, a group of fourth fixing blocks 408 are installed on the output end of each group of the fifth electric push rod 407, a group of sixth electric push rod 409 is installed on the bottom of each group of the fourth fixing blocks 408, a group of clamping blocks 410 are installed on the output end of each group of the sixth electric push rod 409, a group of sliding baffles 411 are slidably connected between the tops of the two groups of the clamping blocks 410, a group of placement boxes 412 are installed on one side wall of each group of the clamping blocks 410, and a number of groups of dry ice blocks 413 are evenly spaced in each group of the placement boxes 412, a group of seventh electric push rod 414 is installed on one side wall of each group of the placement boxes 412, a group of buffer cylinders 415 are installed on the output end of each group of the seventh electric push rod 414, and a group of auxiliary discs 416 are installed on the top of each group of the buffer cylinders 415.

[0031] Before the plasma arc welding machine starts working, one group of fan steel plates that need to be welded is first placed on the clamping structure 208 for limit clamping, and then the first electric slide 201 is started for height adjustment, and then the other group of fan steel plates is placed between the two groups of clamping blocks 410, and then the fifth electric push rod 407 is started to push the fourth fixed block 408 to move toward each other, so that the two groups of clamping blocks 410 clamp and limit the fan steel plates, and then the sixth electric push rod 409 is started for height adjustment, which improves the steel plate alignment effect while improving the device clamping compatibility effect.

[0032] After the two groups of clamping blocks 410 clamp the fan steel plate in place, the fourth electric push rod 404 is started to push the first electromagnetic block 405 and the second electromagnetic block 406 to be magnetically connected, and then the fourth electric push rod 404 drives the second connecting plate 403 to move toward the direction close to the first connecting plate 401, and the plasma arc welding structure is started for welding. In order to increase the welding range, the second electric slide 301 is started to drive the plasma arc welding structure 306 to perform translational welding. Subsequently, in order to improve the protection effect of plasma arc welding, the third electric push rod 304 can be started to push the protective fan ring 305 to the designated position to block and protect against high temperature. After the subsequent work is completed, the two groups of protective fan rings can be started to align for wrapping protection, thereby improving the protection effect of the device.

[0033] During high-temperature welding, the dry ice block 413 is driven to vaporize quickly to absorb heat, thereby avoiding damage to the structure caused by high temperature and increasing the service life of the equipment. When a fault or deviation occurs during welding, the second compression spring 402 senses that the pressure disappears and drives the sliding baffle 411 to move to the bottom of the plasma arc welding structure 306. During the movement of the fan steel plate, the fan steel plate on the clamping structure 208 drives the sliding plate 206 to slide in the slide groove 204 and squeeze the first compression spring 207 for buffering protection, thereby improving the adjustability of the welding position and improving the working effect of the plasma arc welding machine.

[0034] When welding, the auxiliary disc 416 is located below the welding point, which provides auxiliary support and stability for the fan steel plate. As the welding point moves, the seventh electric push rod 414 can be started for auxiliary adjustment. In subsequent heat dissipation work, the first electric push rod 103 can be started to push the insulation board 104 to move for heat dissipation. In order to improve the maintenance effect of the structure, the second electric push rod 108 is started to drive the top plate 109 to rise, thereby improving the convenience of device maintenance.

[0035] Before the plasma arc welding machine starts working, one group of fan steel plates that need to be welded is first placed on the clamping structure 208 for limit clamping, and then the first electric slide 201 is started for height adjustment, and then the other group of fan steel plates is placed between the two groups of clamping blocks 410, and then the fifth electric push rod 407 is started to push the fourth fixed block 408 to move toward each other, so that the two groups of clamping blocks 410 clamp and limit the fan steel plates, and then the sixth electric push rod 409 is started for height adjustment, which improves the steel plate alignment effect while improving the device clamping compatibility effect.

[0036] After the two groups of clamping blocks 410 clamp the fan steel plate in place, the fourth electric push rod 404 is started to push the first electromagnetic block 405 and the second electromagnetic block 406 to be magnetically connected, and then the fourth electric push rod 404 drives the second connecting plate 403 to move toward the direction close to the first connecting plate 401, and the plasma arc welding structure is started for welding. In order to increase the welding range, the second electric slide 301 is started to drive the plasma arc welding structure 306 to perform translational welding. Subsequently, in order to improve the protection effect of plasma arc welding, the third electric push rod 304 can be started to push the protective fan ring 305 to the designated position to block and protect against high temperature. After the subsequent work is completed, the two groups of protective fan rings can be started to align for wrapping protection, thereby improving the protection effect of the device.

[0037] Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent substitutions for some of the technical features therein; and these modifications or substitutions do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A plasma arc welding machine for circular mechanical parts made of high-performance materials, comprising a welding box assembly, characterized in that: A protective component capable of buffering and protecting is installed on one inner wall of the welding box component, a processing component is installed on the welding box component, and a welding component capable of improving position adjustment is installed on the bottom; The welding assembly comprises a second electric slide, the output end of the second electric slide is transmission-connected with a second fixed plate, and a plasma arc welding structure is installed at the bottom center of the second fixed plate; The processing assembly includes a first connecting plate and two groups of placement boxes, one end of two groups of second compression springs are symmetrically installed on one side wall of the first connecting plate, and a second connecting plate is connected between the other ends of the two groups of second compression springs, and a number of groups of dry ice blocks that can absorb heat and avoid high-temperature damage are evenly spaced in each group of the placement boxes, a group of seventh electric push rods are installed on one side wall of each group of the placement boxes, a group of buffer cylinders are installed on the output end of each group of the seventh electric push rods, and a group of auxiliary discs are installed on the top of each group of the buffer cylinders.

2. The plasma arc welding machine for circular mechanical parts made of high-performance materials according to claim 1, characterized in that: The welding box assembly comprises a welding box body, and two groups of first cavities are symmetrically opened on one side wall of the welding box body. A group of first electric push rods are installed in each group of the first cavities, and a heat insulation board is installed between the output ends of the two groups of the first electric push rods.

3. The plasma arc welding machine for circular mechanical parts made of high-performance materials according to claim 2, characterized in that: A material collecting plate is installed on one side wall of the heat insulation board, the bottom of the material collecting plate is slidably connected to the bottom inner wall of the welding box body, and a first pressure sensor is installed on one side wall of the welding box body.

4. The plasma arc welding machine for circular mechanical parts made of high-performance materials according to claim 2, characterized in that: A second cavity is opened on the top of the welding box body, a second electric push rod is installed in the second cavity, and a top plate is installed on the output end of the second electric push rod.

5. The plasma arc welding machine for circular mechanical parts made of high-performance materials according to claim 1, characterized in that: The protection component includes a first electric slide, which is installed on the inner wall of the welding box body. The output end of the first electric slide is transmission-connected with a first fixed block, a first fixed plate is installed on a side wall of the first fixed block, and a slide groove is opened on the bottom of the first fixed plate.

6. The plasma arc welding machine for circular mechanical parts made of high-performance materials according to claim 5, characterized in that: A second fixed block is installed on the bottom edge of the first fixed plate, one end of a first compression spring is installed on a side wall of the second fixed block, a sliding plate is installed on the other end of the first compression spring, the sliding plate is slidably connected in the sliding groove, and a clamping structure is installed on the bottom of the sliding plate.

7. The plasma arc welding machine for circular mechanical parts made of high-performance materials according to claim 1, characterized in that: The top of the second electric slide is installed on the bottom of the top plate, and two groups of third fixed blocks are symmetrically installed on the bottom edge of the second fixed plate. A group of third electric push rods are installed on one side wall of each group of the third fixed blocks, and a group of protective fan rings are installed on the output end of each group of the third electric push rods.

8. The plasma arc welding machine for circular mechanical parts made of high-performance materials according to claim 1, characterized in that: One end of the first connecting plate is mounted on a side wall of the heat insulation plate, and the bottom of the second connecting plate is slidably connected to the top of the collecting plate.

9. The plasma arc welding machine for circular mechanical parts made of high-performance materials according to claim 8, characterized in that: A fourth electric push rod is installed on the outer wall of the first connecting plate, a first electromagnetic block is installed on the output end of the fourth electric push rod, a second electromagnetic block is installed on the outer wall of the second connecting plate, and the first electromagnetic block is magnetically connected to the second electromagnetic block.

10. The plasma arc welding machine for circular mechanical parts made of high-performance materials according to claim 8, characterized in that: Two groups of fifth electric push rods are symmetrically installed on the top edge of the second connecting plate, a group of fourth fixed blocks are installed on the output end of each group of the fifth electric push rods, a group of sixth electric push rods are installed on the bottom of each group of the fourth fixed blocks, a group of clamping blocks are installed on the output end of each group of the sixth electric push rods, a group of sliding baffles are slidably connected between the tops of the two groups of clamping blocks, and one end of each group of the placement boxes is installed on a side wall of the clamping block.

Citation Information

Patent Citations

  • Plasma arc welding machine with automatic temperature control function

    CN115194306A

  • Multi-angle adjustable laser cutting machine

    CN119077170A

  • Protective electrical equipment cabinet for intelligent mobile power supply

    CN119093176A

  • Continuous cutting-off device for production of self-correcting type saw blade type milling cutter

    CN119328587A

  • Automatic welding equipment

    WO2023019711A1

Cited By

  • Intelligent positioning welding device for automatic welding

    CN120533240A

  • Intelligent positioning welding device for automatic welding

    CN120533240B

  • Plastic product recovery pretreatment device

    CN120886395A

  • Automatic disc welding machine tool for pet cage production

    CN120941054A