Operation equipment special for air film dome bin and mounting and dismounting method

By designing special operating equipment for air membrane dome bins, the existing equipment has been solved for unstable operation and risks of high-altitude operations under complex ground conditions, and the equipment has achieved the function of independently completing tower lifting and falling down and adapting to different heights and radii operations, improving construction efficiency and safety.

CN119860091APending Publication Date: 2025-04-22CHINA COAL NO 68 ENG COMPANY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510090288.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-21
Publication Date
2025-04-22

AI Technical Summary

Technical Problem

The existing gas film dome ware construction equipment is unstable under complex or uneven ground conditions, which poses a risk of high altitude operation, and is difficult to adapt to the construction of gas film dome ware of different diameters and heights.

Method used

A special working equipment for air film dome bins is designed, including concrete foundation, lower slewing body and working device. The equipment realizes the expansion and rotation of the tower body through a slewing motor and a sling frame. It is equipped with a telescopic tower body assembly, a scissors and fork lifting device and a crane. It can independently complete the lifting and falling of the vertical tower body, and complete the lifting through a double oil cylinder to meet the operating needs of different heights and radii.

Benefits of technology

During the installation and disassembly process, this equipment can reduce the entry of auxiliary equipment, reduce construction risks, improve operational efficiency and safety, and is suitable for the construction of gas film dome silos of different diameters and heights.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119860091A_ABST
    Figure CN119860091A_ABST
Patent Text Reader

Abstract

The invention discloses special operation equipment for a gas film dome bin and an assembly and disassembly method. The special operation equipment comprises a concrete foundation, a lower rotary body and an operation device arranged on the lower rotary body, the concrete foundation is provided with a bolt connecting assembly; the lower rotary body comprises a rotary motor, an upper support, a rotary bearing, a lower support and a pulling stand, the lower support is connected to the bolt connecting assembly, the rotary bearing is arranged on the lower support, the upper support is arranged on the rotary bearing, the rotary motor is arranged on the upper support, and the pulling stand is connected to the side face of the lower support through a pin shaft. The whole vertical tower body can be lifted and fallen down through the device, so that the use of other auxiliary equipment in a bin is greatly reduced, and the construction risk is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of air film dome construction, and in particular to special operating equipment for an air film dome warehouse and an installation and disassembly method. Background Art

[0002] The air film dome warehouse adopts a three-center spherical vault warehouse structure, which changes the dome's vector-radius ratio from the traditional 0.5:1 to 0.35:1, thereby reducing 1 / 3 of the invalid space and greatly reducing the operating energy consumption. In addition, its dome structure has good mechanical properties, can adapt to large loads, has strong earthquake and wind resistance, and its mechanical properties are better than the shallow circular silo cone structure. It has been widely used in industrial material storage, grain storage, commercial and civil housing and other fields.

[0003] At present, a working platform is formed by a hanging basket at the end of the crane boom or a self-developed tower crane with a hanging basket. The operator cleans the inner surface of the air film, sprays polyurethane, ties steel bars, sprays concrete, and measures and lays out lines in the hanging basket. For cranes, the stability is relatively low, and the requirements for roads and sites are high. Especially when operating under complex or uneven ground conditions, it is easy to tilt or collapse, threatening the safety of operators and surrounding personnel; for the existing self-developed tower crane with a hanging basket to form a working platform, it still has not gotten rid of the shackles of the tower crane, and adopts the method of lifting from above, which increases the risk factor of high-altitude operations. The platform adopts a rigid connection and has poor stability. Therefore, it is necessary to design a special operating equipment for air film dome warehouses, which can be applied to the construction of air film dome warehouses of different diameters and heights, improve construction efficiency, and ensure construction safety. Summary of the invention

[0004] In order to solve the above technical problems, the present invention provides a special operating equipment and installation method for an air film dome warehouse.

[0005] The present invention adopts the following technical solutions:

[0006] A special operating equipment for an air-film dome warehouse, comprising a concrete foundation, a lower rotating body and an operating device arranged on the lower rotating body; the concrete foundation is provided with a bolt connection assembly; the lower rotating body comprises a rotary motor, an upper support, a rotary bearing, a lower support and a trip frame, the lower support is connected to the bolt connection assembly, the rotary bearing is arranged on the lower support, the upper support is arranged on the rotary bearing, the rotary motor is arranged on the upper support, and the trip frame is connected to the side of the lower support through a pin shaft.

[0007] Preferably, the erecting frame includes an erecting cylinder, a channel steel beam joint, a first pin shaft assembly, a post plate, an H-shaped steel beam and a connecting ear plate; four connecting ear plates are welded to the side of the H-shaped steel beam in two groups; four channel steel beam joints are welded to the upper surface of the H-shaped steel beam in two groups; eight post plates are respectively welded to the upper and lower sides of the channel steel beam joint; the erecting cylinder is connected to the channel steel beam joint through the first pin shaft assembly.

[0008] Preferably, the slewing bearing is embedded in the upper support and connected to the upper support and the lower support by high-strength bolts.

[0009] Preferably, the operating device includes a telescopic tower body assembly, a scissors-fork lifting device, a platform lifting frame, a boom and a lifting trolley. The telescopic tower body assembly is arranged on the lower rotating body and is fixedly connected by four sets of pins; the scissors-fork lifting device is nested outside the telescopic tower body assembly, and the upper and lower ends of the scissors-fork lifting device are respectively connected to the platform lifting frame and the telescopic tower body assembly; the two booms are respectively connected to the left and right ends of the platform lifting frame; the lifting trolley is embedded in the boom and can move relative to the boom.

[0010] Preferably, the telescopic tower body assembly comprises a telescopic tower body, a vertical frame beam, a lifting cylinder A and a lifting cylinder B; the telescopic tower body is composed of five standard tower body sections; the lifting cylinder B is connected between standard section one and standard section three through a pin shaft, and the lifting cylinder A is connected between standard section three and standard section five through a pin shaft; four vertical ear plates are welded on the outside of standard section three, and the vertical frame beam is connected to the vertical ear plates through a pin shaft.

[0011] Preferably, the erected frame beam comprises an ear plate group A, an ear plate group B, a second pin shaft assembly, a cylinder seat, a bolt assembly and a frame beam half frame; the two groups of frame beam half frames are connected by a bolt assembly; and the four groups of ear plate groups A are welded to the bottom of the frame beam half frame.

[0012] A method for installing and disassembling special operating equipment for an air film dome silo, the installation method comprising the following steps:

[0013] Step 1: Pre-embed the foundation, embed the bolt connection components in the poured concrete foundation, the concrete foundation size is 4000×4000×1250mm, the ground bearing capacity is ≥0.2Mpa, the concrete foundation strength is ≥C35, and reserve a cable trough on the concrete foundation;

[0014] Step 2: Install the lower slewing body as a whole onto the concrete foundation and tighten the nuts;

[0015] Step 3: erect the telescopic tower assembly, fix the telescopic tower assembly with a pin, drive the erection cylinder until the cylinder head and the cylinder seat of the erection frame beam are at the position, and fix the erection cylinder and the cylinder seat with a second pin assembly; retract the erection cylinder, and the telescopic tower assembly starts circular motion driven by the erection cylinder until the pin hole of the standard section 1 coincides with the standard section seat hole on the upper part of the upper support, stop the retraction of the erection cylinder, and fix the connection with a pin;

[0016] Step 4: Remove the trigger frame, install the scissor fork lifting device and platform lifting frame as a whole on the top of the telescopic tower assembly, and fix them with a pin;

[0017] Step 5: On the ground, insert the lifting trolley from the head of the boom to ensure that the lifting trolley can move relative to the boom; install the boom and the lifting trolley as a whole on both sides of the platform lifting frame and fix them with pins.

[0018] Preferably, the removal method is the opposite of the installation method.

[0019] As a preferred method, the jacking method is also included:

[0020] Drive the lifting cylinder B to extend, lift the standard section 2, standard section 3, standard section 4 and standard section 5 by one end, use the pushing device to automatically push several standard section connecting pins into place, and fix the standard section 1 with the standard section 2;

[0021] Continue to drive the lifting cylinder B to extend, lift one end of the standard section 3, standard section 4 and standard section 5 until the standard section 3 is lifted to the position where it is connected with the standard section 2, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section 2 with the standard section 3;

[0022] Drive the lifting cylinder A to extend, lift the standard section four and the standard section five by one end, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section four with the standard section three;

[0023] Continue to drive the lifting cylinder A to extend, lift the standard section 5 by one end, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section 5 with the standard section 4;

[0024] At this point, all standard section lifting is completed.

[0025] Compared with the prior art, the present invention has the following advantages: During the installation and disassembly process, the air film dome warehouse special operation equipment of the present invention can complete the lifting and lowering of the entire vertical tower body by itself, greatly reducing the use of other auxiliary equipment entering the warehouse and reducing construction risks. At the same time, the five-section telescopic tower body is lifted by double cylinders to meet the needs of operations at different heights. The head of the boom can be infinitely retracted by the cylinder to meet the needs of operations at different construction radiuses, greatly improving construction efficiency and ensuring construction safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 This is a schematic diagram of the extended state of the special operating equipment for the air film dome warehouse.

[0027] Figure 2 This is a schematic diagram of the indented state of the special operating equipment for the air film dome warehouse.

[0028] Figure 3 Schematic diagram of the concrete foundation structure.

[0029] Figure 4It is a schematic diagram of the structure of the lower rotating body.

[0030] Figure 5 It is a top view of the lower rotating body.

[0031] Figure 6 It is a structural schematic diagram of the stand.

[0032] Figure 7 for Figure 6 AA section view.

[0033] Figure 8 It is a structural schematic diagram of the telescopic tower assembly.

[0034] Fig. 9 This is a structural diagram of the erected frame beam.

[0035] Fig.10 This is a side view of the erected frame beam.

[0036] Fig.11 This is a top view of the erected frame beam.

[0037] Fig.12 This is a schematic diagram of the initial state of the special operating equipment for the air film dome warehouse.

[0038] Fig.13 This is a schematic diagram of the intermediate state of the special operating equipment for the air film dome warehouse.

[0039] Fig.14 This is a schematic diagram of the completed erection status of the special operating equipment for the air-film dome warehouse.

[0040] In the figure, concrete foundation 1, bolt connection assembly 1-1, lower rotating body 2, rotating motor 2-1, upper support 2-2, slewing bearing 2-3, lower support 2-4, erecting frame 2-5, erecting cylinder 2-5-1, channel beam joint 2-5-2, first pin assembly 2-5-3, pasting plate 2-5-4, H-shaped steel beam 2-5-5, connecting ear plate 2-5-6, telescopic tower body assembly 3, telescopic tower body 3-1, erecting frame beam 3-2, ear plate group A3-2-1, ear plate group B3-2-2, second pin assembly 3-2-3, cylinder seat 3-2-4, bolt assembly 3-2-5, frame beam half frame 3-2-6, lifting cylinder A3-3, lifting cylinder B3-4, scissors fork lifting device 4, platform lifting frame 5, boom 6, lifting trolley 7. DETAILED DESCRIPTION

[0041] In order to facilitate the understanding of the technical solution of the present invention, a detailed description is given below in conjunction with the accompanying drawings and specific embodiments.

[0042] Example 1

[0043] like Figure 1-4As shown, a special operating equipment for an air-film dome silo includes a concrete foundation 1, a lower rotating body 2 and an operating device arranged on the lower rotating body 2; the concrete foundation 1 is provided with a bolt connection assembly 1-1; the lower rotating body 2 includes a rotary motor 2-1, an upper support 2-2, a rotary bearing 2-3, a lower support 2-4 and a tripod frame 2-5, the lower support 2-4 is connected to the bolt connection assembly 1-1, the rotary bearing 2-3 is arranged on the lower support 2-4, the upper support 2-2 is arranged on the rotary bearing 2-3, the rotary motor 2-1 is arranged on the upper support 2-2, and the tripod frame 2-5 is connected to the side of the lower support 2-4 through a pin shaft.

[0044] like Figure 5-7 As shown, the erecting frame 2-5 includes an erecting cylinder 2-5-1, a channel steel beam joint 2-5-2, a first pin shaft assembly 2-5-3, a plate 2-5-4, an H-shaped steel beam 2-5-5 and a connecting ear plate 2-5-6; four connecting ear plates 2-5-6 are welded to the side of the H-shaped steel beam 2-5-5 in two groups; four channel steel beam joints 2-5-2 are welded to the upper surface of the H-shaped steel beam 2-5-5 in two groups; eight plates 2-5-4 are respectively welded to the upper and lower sides of the channel steel beam joint 2-5-2 to improve the overall strength; the erecting cylinder 2-5-1 is connected to the channel steel beam joint 2-5-2 through the first pin shaft assembly 2-5-3.

[0045] In order to reduce the impact of adverse factors such as dust and rain on the slewing bearing 2-3, the slewing bearing 2-3 is embedded in the upper support 2-2 and connected to the upper support 2-2 and the lower support 2-4 by high-strength bolts. The slewing motor 2-1 is installed on the internal plate of the upper support 2-2 by bolts, and drives the slewing bearing 2-3 to rotate by internal engagement; the upper support 2-2 and the lower support 2-4 are mainly welded by plate.

[0046] The operating device includes a telescopic tower body assembly 3, a scissor fork lifting device 4, a platform lifting frame 5, a boom 6 and a lifting trolley 7. The telescopic tower body assembly 3 is arranged on the lower rotating body 2 and is fixedly connected by four sets of pins; the scissor fork lifting device 4 is nested outside the telescopic tower body assembly 3, and the upper and lower ends of the scissor fork lifting device 4 are respectively connected to the platform lifting frame 5 and the telescopic tower body assembly 3; the two booms 6 are respectively connected to the left and right ends of the platform lifting frame 5; the lifting trolley 7 is embedded on the boom 6 and can move relative to the boom 6 to cover a wider construction area.

[0047] like Figure 8As shown, the telescopic tower body assembly 3 includes a telescopic tower body 3-1, a vertical frame beam 3-2, a lifting cylinder A3-3 and a lifting cylinder B3-4; the telescopic tower body 3-1 is composed of five standard tower body sections, namely standard section one, standard section two, standard section three, standard section four and standard section five, among which standard section one is located at the innermost side and standard section five is located at the outermost side. Except for the innermost standard section one, which is made of square steel pipe as the main material, the main materials of the other standard tower body sections are angle steels, and friction blocks are designed on the inner side of the angle steels to prevent damage caused by friction between the main materials when the standard tower body sections are vertically lifted; the lifting cylinder B3-4 is connected between the standard section one and the standard section three by a pin shaft, the lifting cylinder A3-3 is connected between the standard section three and the standard section five by a pin shaft, and the lifting cylinder B3-4 and the lifting cylinder A3-3 are staggered to avoid interference; four vertical ear plates are welded on the outer side of the standard section three, and the vertical frame beam 3-2 is connected to the vertical ear plates by a pin shaft.

[0048] like Figure 9-11 As shown, the erected frame beam 3-2 includes an ear plate group A3-2-1, an ear plate group B3-2-2, a second pin shaft assembly 3-2-3, a cylinder seat 3-2-4, a bolt assembly 3-2-5 and a frame beam half frame 3-2-6; two groups of frame beam half frames 3-2-6 are connected by the bolt assembly 3-2-5; four groups of ear plate groups A3-2-1 are welded to the bottom of the frame beam half frame 3-2-6.

[0049] like Figure 12-14 As shown, a method for installing and disassembling a special operation equipment for an air film dome silo, the installation method comprises the following steps:

[0050] Step 1: Embed the foundation. Embed the bolt connection assembly 1-1 in the poured concrete foundation. The concrete foundation has a size of 4000×4000×1250mm, a ground bearing capacity of ≥0.2Mpa, and a concrete foundation strength of ≥C35. Reserve a cable trough on the concrete foundation.

[0051] Step 2: Install the lower slewing body 2, install the lower slewing body 2 as a whole on the concrete foundation, and tighten the nuts;

[0052] Step 3: erect the telescopic tower assembly 3, fix the telescopic tower assembly 3 with a pin, drive the erection cylinder 2-5-1 until the cylinder head and the cylinder seat 3-2-4 of the erection frame beam 3-2, and fix the erection cylinder 2-5-1 and the cylinder seat 3-2-4 with the second pin assembly 3-2-3; retract the erection cylinder 2-5-1, and the telescopic tower assembly 3 starts circular motion driven by the erection cylinder 2-5-1 until the pin hole of the standard section 1 coincides with the standard section seat hole on the upper support 2-2, stop the retraction action of the erection cylinder 2-5-1, and fix the connection with a pin;

[0053] Step 4: Remove the trigger frame 2-5, install the scissor fork lifting device 4 and the platform lifting frame 5 as a whole on the top of the telescopic tower assembly 3, and fix them with a pin;

[0054] Step 5: On the ground, insert the lifting trolley 7 from the head of the boom 6 to ensure that the lifting trolley 7 can move relative to the boom 6; install the boom 6 and the lifting trolley 7 as a whole on both sides of the platform lifting frame 5, and fix them with pins; in order to meet the construction of different heights, the extension and retraction of the jacking cylinder in the telescopic tower assembly 3, the cylinder in the scissor fork lifting device 4 and the cylinder in the lifting trolley 7 can be met;

[0055] Step 6: The removal method is opposite to the installation method, and the stand 2-5 can be installed in advance.

[0056] It also includes the lifting method of the special operating equipment of the air film dome warehouse:

[0057] From inside to outside, the standard sections are standard section one, standard section two, standard section three, standard section four and standard section five.

[0058] Drive the lifting cylinder B3-4 to extend, lift the standard section 2, standard section 3, standard section 4 and standard section 5 by one end, and use the pushing device to automatically push several standard section connecting pins into place, replacing the traditional manual knocking, to fix the standard section 1 with the standard section 2;

[0059] Continue to drive the lifting cylinder B3-4 to extend, lift one end of the standard section three, standard section four and standard section five until the standard section three is lifted to the position where it is connected with the standard section two, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section two with the standard section three;

[0060] Drive the lifting cylinder A3-3 to extend, lift the standard section four and the standard section five by one end, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section four with the standard section three;

[0061] Continue to drive the lifting cylinder A3-3 to extend, lift the standard section 5 by one end, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section 5 with the standard section 4;

[0062] At this point, all standard section lifting is completed.

[0063] In this way, spraying operations at different heights in the vertical direction can be achieved; at the same time, the rotary motor 2-1 can be driven to rotate the part above the lower rotary body at different rotation angles to meet the needs of operations at different rotation angles; when the existing working range cannot meet the needs of construction, the detachable platform at the head of the boom 6 can be infinitely adjusted to extend it outward by a certain distance to meet the needs of operations within a small range.

[0064] The above are only preferred embodiments of the present invention. The protection scope of the present invention shall be based on the scope defined by the claims. Several improvements and modifications made by those skilled in the art without departing from the spirit and scope of the present invention should also be regarded as the protection scope of the present invention.

Claims

1. A special operating equipment for air film dome silo, characterized in that: The invention comprises a concrete foundation (1), a lower rotating body (2) and an operating device arranged on the lower rotating body (2); the concrete foundation (1) is provided with a bolt connection assembly (1-1); the lower rotating body (2) comprises a rotating motor (2-1), an upper support (2-2), a rotating bearing (2-3), a lower support (2-4) and a tripping frame (2-5); the lower support (2-4) is connected to the bolt connection assembly (1-1), the rotating bearing (2-3) is arranged on the lower support (2-4), the upper support (2-2) is arranged on the rotating bearing (2-3), the rotating motor (2-1) is arranged on the upper support (2-2), and the tripping frame (2-5) is connected to the side of the lower support (2-4) through a pin shaft.

2. The air film dome silo special operation equipment according to claim 1 is characterized in that: The erection frame (2-5) comprises an erection cylinder (2-5-1), a channel steel beam joint (2-5-2), a first pin shaft assembly (2-5-3), a plate (2-5-4), an H-shaped steel beam (2-5-5) and a connecting ear plate (2-5-6); four connecting ear plates (2-5-6) are welded to the side of the H-shaped steel beam (2-5-5) in two groups; four channel steel beam joints (2-5-2) are welded to the upper surface of the H-shaped steel beam (2-5-5) in two groups; eight plates (2-5-4) are respectively welded to the upper and lower sides of the channel steel beam joint (2-5-2); and the erection cylinder (2-5-1) is connected to the channel steel beam joint (2-5-2) through the first pin shaft assembly (2-5-3).

3. The air film dome silo special operation equipment according to claim 2 is characterized in that: The slewing bearing (2-3) is embedded in the upper support (2-2) and connected to the upper support (2-2) and the lower support (2-4) via high-strength bolts.

4. The air film dome silo special operation equipment according to claim 1 is characterized in that: The operating device comprises a telescopic tower assembly (3), a scissor-fork lifting device (4), a platform lifting frame (5), a boom (6) and a lifting trolley (7); the telescopic tower assembly (3) is arranged on the lower rotating body (2) and is fixedly connected via four sets of pins; the scissor-fork lifting device (4) is nested outside the telescopic tower assembly (3); the upper and lower ends of the scissor-fork lifting device (4) are respectively connected to the platform lifting frame (5) and the telescopic tower assembly (3); the two booms (6) are respectively connected to the left and right ends of the platform lifting frame (5); and the lifting trolley (7) is externally embedded on the boom (6) and can move relative to the boom (6).

5. The air film dome silo special operation equipment according to claim 4 is characterized in that: The telescopic tower assembly (3) comprises a telescopic tower (3-1), a vertical frame beam (3-2), a lifting cylinder A (3-3) and a lifting cylinder B (3-4); the telescopic tower (3-1) is composed of five standard tower sections; the lifting cylinder B (3-4) is connected between the first standard section and the third standard section via a pin shaft, and the lifting cylinder A (3-3) is connected between the third standard section and the fifth standard section via a pin shaft; four vertical ear plates are welded on the outer side of the third standard section, and the vertical frame beam (3-2) is connected to the vertical ear plate via a pin shaft.

6. The air film dome silo special operation equipment according to claim 5 is characterized in that: The erecting frame beam (3-2) comprises an ear plate group A (3-2-1), an ear plate group B (3-2-2), a second pin shaft assembly (3-2-3), a cylinder seat (3-2-4), a bolt assembly (3-2-5) and a frame beam half frame (3-2-6); two groups of frame beam half frames (3-2-6) are connected by the bolt assembly (3-2-5); and four groups of ear plate groups A (3-2-1) are welded to the bottom of the frame beam half frame (3-2-6).

7. A method for installing and disassembling special equipment for air film dome silo, characterized in that: The installation method includes the following steps: Step 1: Pre-embed the foundation, embed the bolt connection assembly (1-1) in the poured concrete foundation, the concrete foundation size is 4000×4000×1250mm, the ground bearing capacity is ≥0.2Mpa, the concrete foundation strength is ≥C35, and a cable trough is reserved on the concrete foundation; Step 2: Install the lower rotating body (2), install the lower rotating body (2) as a whole on the concrete foundation, and tighten the nuts; Step 3: erect the telescopic tower assembly (3), fix the five standard tower sections of the telescopic tower assembly (3) with a pin shaft, drive the erection cylinder (2-5-1) until the cylinder head and the cylinder seat (3-2-4) of the erection frame beam (3-2), and fix the erection cylinder (2-5-1) and the cylinder seat (3-2-4) with a second pin shaft assembly (3-2-3); retract the erection cylinder (2-5-1), and the telescopic tower assembly (3) starts circular motion driven by the erection cylinder (2-5-1) until the pin shaft hole of the standard section one coincides with the standard section seat hole on the upper support (2-2), stop the retraction action of the erection cylinder (2-5-1), and fix the connection with a pin shaft; Step 4: Remove the pull stand (2-5), install the scissor fork lifting device (4) and the platform lifting frame (5) as a whole on the top of the telescopic tower assembly (3), and fix them with a pin; Step 5: On the ground, insert the lifting trolley (7) from the head of the boom (6) to ensure that the lifting trolley (7) can move relative to the boom (6); install the boom (6) and the lifting trolley (7) as a whole on both sides of the platform lifting frame (5), and fix them with pins.

8. The installation and disassembly method of the air film dome silo special operation equipment according to claim 7 is characterized in that: The removal method is the opposite of the installation method.

9. The installation and disassembly method of the air film dome silo special operation equipment according to claim 7, characterized in that: Also includes jacking methods: Drive the lifting cylinder B (3-4) to extend, lift the standard section 2, standard section 3, standard section 4 and standard section 5 by one end, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section 1 with the standard section 2; Continue to drive the lifting cylinder B (3-4) to extend, lift the standard section 3, standard section 4 and standard section 5 by one end until the standard section 3 is lifted to the position where it is connected with the standard section 2, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section 2 with the standard section 3; Drive the lifting cylinder A (3-3) to extend, lift the standard section four and the standard section five by one end, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section four and the standard section three; Continue to drive the lifting cylinder A (3-3) to extend, lift the standard section 5 by one end, and use the pushing device to automatically push several standard section connecting pins into place, so as to fix the standard section 5 with the standard section 4; At this point, all standard section lifting is completed.