Method for installing air supply ceiling of operating room
By pre-embedding of hanging rods and setting up hanging rods and hand-pulled hoists in the operating room, pollution, safety hazards and maintenance difficulties during installation of air supply ceilings in the operating room are solved, and a safer and more efficient installation and maintenance process is achieved.
Patent Information
- Application Number
- CN202510055413.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-14
- Publication Date
- 2025-04-22
AI Technical Summary
The existing operating room air supply ceiling needs to be installed during installation, which leads to contamination in the operating room and the risk of falling from high places for installers, and is difficult to maintain and replace.
The combination of a hanging rod and a hand-rape hoist is adopted. The hanging rod and a hand-rape hoist are pre-buried in the concrete floor slab, and the hanging rod and a hand-rape hoist are set to achieve a smooth and slow lifting and fixing of the air-supporting ceiling.
It reduces construction safety hazards, simplifies the maintenance and replacement process of air supply ceilings, and improves installation efficiency and safety.
Smart Images

Figure CN119860097A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of hospital clean operating room construction, in particular to an operating room air supply ceiling installation method. Background Art
[0002] The clean operating room is an independent functional area composed of some or all of the clean operating room, clean auxiliary rooms and non-clean auxiliary rooms. The operating room has very high requirements for air cleanliness, and the core of the clean operating room construction is to use air clean technology as a guarantee to keep the ambient air at a suitable temperature, relative humidity, and cleanliness, and to meet the requirements of medical staff for fresh air, air flow speed, harmful gases, etc., so as to control hospital infections and create a suitable diagnosis and treatment environment for medical staff and patients.
[0003] The air purification system is the most effective means to ensure the cleanliness of the operating room. The air supply ceiling above the operating table is large and heavy, and the existing air supply ceiling has the following technical defects during installation: scaffolding needs to be set up in the operating room, which can easily cause pollution to the operating room, and there is a risk of falling from heights for installers. The air supply ceiling is not easy to maintain and clean after installation, and it is even more difficult to replace the entire ceiling. Summary of the invention
[0004] In view of the above problems, an embodiment of the present invention provides a method for installing an air supply ceiling in an operating room.
[0005] An embodiment of the present invention provides a method for installing an air supply ceiling in an operating room, comprising: S1. Reasonably design the position of the ventilation ceiling according to the layout of the operating room, and set the hanger on the concrete floor based on the designed position and ventilation ceiling structure; S2. According to the designed position and the structure of the air supply ceiling, a diagonal line of the air supply ceiling body is laid out on the concrete floor slab, and a hanging rod is respectively arranged at a certain distance outside the two ends of the diagonal line on the concrete floor slab; S3, fix two hand chain hoists on the set hanging rods respectively; S4. Fix a set of diagonal parts of the air supply ceiling on the lifting chains of the hand chain hoist, and pull the manual chain of the hand chain hoist slowly and synchronously to ensure that the air supply ceiling is lifted steadily and slowly; S5. When the air supply ceiling is lifted to the lower side of the suspension rod, the position of the air supply ceiling is adjusted so that the mounting hole in the air supply ceiling is aligned with the suspension rod; S6. After the air supply ceiling is lifted to the designed elevation, screw the nuts into the suspension rods to fix the air supply ceiling. After fixation, remove the hand winch. The installation of the air supply ceiling is now completed.
[0006] Compared with the prior art, the beneficial effects of the present invention are: compared with the traditional method of setting up scaffolding at the four corners of the air supply ceiling, the installation workers manually lift the air supply ceiling for installation, which reduces the safety hazards of construction. At the same time, future maintenance and cleaning of the air supply ceiling, including overall replacement, can be operated through the reserved hanging rod and hand winch.
[0007] Optionally, the hanger is in an inverted L-shape or T-shape. The process of setting the hanger on the concrete floor slab includes: After the structural reinforcement of the concrete floor is tied, the installation position of the hanger is determined based on the designed position and the ventilation ceiling structure; Tie and fix the top crossbar in the hanger to the structural reinforcement at the determined installation position; The concrete floor formwork is supported, and a through hole is reserved at the position of the hanger in the middle of the formwork so that the hanger can pass through the through hole; After the concrete floor formwork is completed, rubber sleeves are placed on the hangers and the rubber sleeves are inserted into the holes to prevent leakage, and concrete is poured to embed the hangers in the concrete floor.
[0008] Optionally, when the air supply ceiling needs to be maintained or replaced, a hand winch is fixed on the set hanging rod, and the lifting chain of the hand winch is fixed on a set of diagonals of the air supply ceiling. The nuts on the hanging rod are slowly loosened in a diagonal manner so that the lifting chain gradually bears the weight. After the nuts on the hanging rod are completely removed, the manual chain of the hand winch is synchronously and slowly pulled to lower the air supply ceiling smoothly and slowly to the ground.
[0009] Optionally, the suspension rod is an expansion bolt, or a U-shaped ring embedded in the concrete floor. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] The drawings described herein are used to provide a further understanding of the present invention, constitute a part of the present application, and do not constitute a limitation of the present invention. In the drawings: Figure 1 A schematic diagram of a flow chart of a method for installing an operating room air supply ceiling provided by an embodiment of the present invention; Figure 2 A schematic diagram of a suspended state of an air supply ceiling in an operating room provided by an embodiment of the present invention; Figure 3 A schematic diagram of an operating room air supply ceiling hoisted in place according to an embodiment of the present invention.
[0011] Among them, 1. Air supply ceiling; 2. Concrete floor; 3. Hanging rod; 4. Hand winch. DETAILED DESCRIPTION
[0012] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments and the accompanying drawings. Here, the illustrative embodiments of the present invention and their descriptions are used to explain the present invention, but are not intended to limit the present invention.
[0013] See also Figure 1 , an embodiment of the present invention provides an operating room air supply ceiling installation method, comprising: S1. Reasonably design the position of the air supply ceiling 1 according to the layout of the operating room, and set the hanger 3 on the concrete floor 2 based on the designed position and the structure of the air supply ceiling 1.
[0014] In practice, the hanger 3 is in an inverted L-shape or a T-shape, and the process of setting the hanger 3 on the concrete floor 2 includes: After the structural reinforcement of the concrete floor 2 is tied, the installation position of the hanger 3 is determined based on the designed position and the structure of the air supply ceiling 1; Tie and fix the top cross bar in the hanger 3 to the structural reinforcement at the determined installation position; The concrete floor slab 2 is supported by a formwork, and a through hole is reserved at the position of the hanger 3 in the middle of the formwork so that the hanger can pass through the through hole; After the concrete floor 2 is formed, a rubber sleeve is placed on the hanger 3 and the rubber sleeve is inserted into the hole to prevent leakage, and concrete is poured to embed the hanger 3 in the concrete floor 2.
[0015] In this implementation, the hanger rod 3 is connected to the structural steel bars in the concrete floor slab 2 as a whole and is pre-embedded in the concrete floor slab 2, which greatly improves the installation strength of the hanger rod 3.
[0016] S2. According to the designed position and structure of the air supply ceiling 1, a diagonal line of the air supply ceiling 1 is laid out on the concrete floor slab, and a hanging rod is respectively arranged on the concrete floor slab 2 at a certain distance outside the two ends of the diagonal line.
[0017] S3. Fix two hand hoists 4 on the provided hanging rods respectively.
[0018] During implementation, the suspension rod can be fixed with expansion bolts. When the expansion bolts are fixed on the concrete floor, a hanging ring can be tied to the expansion bolts with wire, and the hanging ring can be pressed against the concrete floor 2 with the nut on the expansion bolt to ensure a firm connection, and the hand winch 4 is hung on the hanging ring.
[0019] The hanging rod can also be made of a U-shaped ring, which is also fixed in the concrete floor by pre-embedded means. When fixing, the U-shaped ring is tied and fixed to the structural steel bars of the concrete floor. When the concrete floor is supported by formwork, a long hole is reserved at the position of the U-shaped ring. After the U-shaped ring passes through the long hole, a rubber plug of a suitable shape is used to seal the long hole, and concrete is poured after sealing.
[0020] S4, fix a set of diagonal parts of the air supply ceiling 1 to the lifting chain of the hand chain hoist 4, such as Figure 2 As shown, the manual chain of the hand chain hoist 4 is pulled synchronously and slowly to ensure that the air supply ceiling 1 is lifted smoothly and slowly.
[0021] During the actual hoisting process, workers can hold a push rod against one side of the air supply ceiling 1 to improve the hoisting stability.
[0022] S5, when the air supply ceiling 1 is lifted to the lower side of the suspension rod 3, the position of the air supply ceiling 1 is adjusted so that the mounting hole in the air supply ceiling 1 is aligned with the suspension rod 3; S6. After the air supply ceiling 1 is raised to the designed elevation, Figure 3 As shown, a nut is screwed into the suspension rod 3 to fix the air supply ceiling 1. After the fixing is completed, the hand chain hoist 4 is removed. At this point, the installation of the air supply ceiling 1 is completed.
[0023] During implementation, when the air supply ceiling 1 needs to be maintained or replaced, the hand winch 4 is fixed on the set hanging rod, and the lifting chain of the hand winch 4 is fixed to a set of diagonals of the air supply ceiling 1. The nuts on the suspension rod 3 are slowly loosened in a diagonal manner so that the lifting chain gradually bears the weight. After the nuts on the suspension rod 3 are completely removed, the manual chain of the hand winch 4 is slowly pulled synchronously to lower the air supply ceiling 1 smoothly and slowly to the ground.
[0024] The above description is only a preferred embodiment of the present invention and is not intended to limit the protection scope of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention are included in the protection scope of the present invention.
Claims
1. A method for installing an air supply ceiling in an operating room, characterized in that: include: S1. Reasonably design the position of the ventilation ceiling according to the layout of the operating room, and set the hanger on the concrete floor based on the designed position and ventilation ceiling structure; S2. According to the designed position and the air supply ceiling structure, a diagonal line of the air supply ceiling body is laid out on the concrete floor slab, and a hanging rod is respectively arranged at a certain distance outside the two ends of the diagonal line on the concrete floor slab; S3, fix two hand chain hoists on the set hanging rods respectively; S4. Fix a set of diagonal parts of the air supply ceiling on the lifting chains of the hand chain hoist, and pull the manual chain of the hand chain hoist slowly and synchronously to ensure that the air supply ceiling is lifted steadily and slowly; S5. When the air supply ceiling is lifted to the lower side of the suspension rod, the position of the air supply ceiling is adjusted so that the mounting hole in the air supply ceiling is aligned with the suspension rod; S6. After the air supply ceiling is lifted to the designed elevation, screw the nuts into the suspension rods to fix the air supply ceiling. After fixation, remove the hand winch. The installation of the air supply ceiling is now completed.
2. The method for installing an operating room air supply ceiling according to claim 1, characterized in that: The hanger is in an inverted L-shape or T-shape. The process of setting the hanger on the concrete floor includes: After the structural reinforcement of the concrete floor is tied, the installation position of the hanger is determined based on the designed position and the ventilation ceiling structure; Tie and fix the top crossbar in the hanger to the structural reinforcement at the determined installation position; The concrete floor formwork is supported, and a through hole is reserved at the position of the hanger in the middle of the formwork so that the hanger can pass through the through hole; After the concrete floor formwork is completed, rubber sleeves are placed on the hangers and the rubber sleeves are inserted into the holes to prevent leakage, and concrete is poured to embed the hangers in the concrete floor.
3. The method for installing an operating room air supply ceiling according to claim 1, characterized in that: It also includes fixing a hand chain hoist on a set hanging rod when the air supply ceiling needs to be maintained or replaced, fixing the lifting chain of the hand chain hoist on a set of diagonals of the air supply ceiling, and slowly loosening the nuts on the hanging rod in a diagonal manner so that the lifting chain gradually bears the weight. After the nuts on the hanging rod are completely removed, the manual chain of the hand chain hoist is slowly and synchronously pulled to lower the air supply ceiling smoothly and slowly to the ground.
4. The method for installing an operating room air supply ceiling according to claim 1, characterized in that: The hanging rod is an expansion bolt or a U-shaped ring embedded in the concrete floor.