Toilet floor drain water seal automatic water replenishing structure and construction method
By planning an automatic water replenishment structure at the bathroom floor drain location, laying hard polyvinyl chloride pipes and setting up water storage bends, the odor overflow problem caused by drying up of the floor drain water seal is solved, automatic water replenishment is achieved, and the phenomenon of floor drain odor is eliminated.
Patent Information
- Application Number
- CN202510317856.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-18
- Publication Date
- 2025-04-25
AI Technical Summary
The existing bathroom floor drain seal is prone to drying up, causing odor to overflow into the bathroom. The existing solutions are low in automation or require manual operation.
Design a bathroom floor drain seal automatic water replenishment structure and construction method. By planning the water replenishment structure in the bathroom layout and the direct floor drain position, laying hard polyvinyl chloride pipes to connect the bathroom equipment and the direct floor drain, and setting a water storage bend on the direct floor drain discharge pipe to ensure that the water seal is always in a water replenishment state.
It realizes that no need for users to add water regularly, and the direct floor drain is always open, completely eliminating the odor phenomenon of floor drain and solving the problem of odor overflow caused by drying water seals.
Smart Images

Figure CN119877652A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of toilet drainage, and in particular to an automatic water replenishing structure for a toilet floor drain water seal and a construction method. Background Art
[0002] In daily life, the phenomenon of bathroom floor drains smelling bad is very common. Most of the reasons are that the water seal of the straight-through floor drain or the water trap under the straight-through floor drain is damaged or dried up. To deal with this problem, the more common treatment methods are: regularly replenishing the water seal of the straight-through floor drain, or replacing the straight-through floor drain with a sealed straight-through floor drain, or using a magnetic bucket straight-through floor drain, a straight-through floor drain with a silicone drainage hose, and other so-called "odor-proof straight-through floor drains" to replace the straight-through floor drain.
[0003] However, the practice of regularly replenishing the water seal of the straight-through floor drain requires cleaning staff to add water regularly, and the automation level is too low. Although the closed straight-through floor drain does not need to be continuously replenished, it can also alleviate the odor problem, but when the floor needs to be drained, the straight-through floor drain still needs to be opened manually. If the pipe in the bathroom bursts and the straight-through floor drain is not opened, it will cause flooding. When using a magnetic tipping bucket straight-through floor drain or a straight-through floor drain with a silicone drainage hose, if hair, mud, and other debris are stuck in the flip plate of the magnetic tipping bucket straight-through floor drain or the silicone drainage outlet with a silicone drainage hose, the straight-through floor drain will still smell bad, and this straight-through floor drain needs to be cleaned frequently. Summary of the invention
[0004] The purpose of the present invention is to provide an automatic water replenishing structure for a bathroom floor drain water seal and a construction method, aiming to solve the problem that the existing bathroom floor drain water seal dries up and odor overflows into the bathroom.
[0005] To achieve the above-mentioned object, in a first aspect, the present invention provides a construction method for an automatic water replenishment structure of a bathroom floor drain water seal, comprising the following steps: Plan the installation location of the water replenishment structure based on the bathroom layout and the pre-installed straight-through floor drain position, and draw a construction sketch; Prepare bathroom equipment, pipes and construction tools based on user needs, mark the installation locations, and complete construction preparations; Based on the construction sketch, the bathroom pipes are laid, and the bathroom equipment is installed and debugged to complete the construction of the water supply structure.
[0006] The specific method of planning the installation position of the water replenishment structure based on the bathroom layout and the pre-installed straight-through floor drain position and drawing the construction sketch is as follows: Collect bathroom space data, take pictures of the bathroom environment, and obtain bathroom data; Planning the installation position of the water replenishment structure based on the bathroom data and the position of the pre-installed straight-through floor drain to obtain planning data; Modeling is performed based on the planning data and the bathroom data, and a construction sketch is drawn.
[0007] The specific method of preparing bathroom equipment, pipes and construction tools based on user needs, marking the installation location and completing the construction preparation is as follows: Prepare bathroom equipment, pipelines and construction tools based on user needs; Check whether bathroom equipment and pipes are damaged and whether the quantity is in compliance; Based on the drawing construction sketch, the bathroom is marked with drawings, the installation construction location is determined, and the construction preparation is completed.
[0008] Among them, the specific method of laying pipes in the bathroom based on the construction sketch, installing and debugging bathroom equipment, and completing the construction of the water replenishment structure is: Laying pipes for the bathroom based on the construction sketch and the construction location; Install the corresponding bathroom equipment and straight-through floor drain to the construction location, and check whether the installation is secure; Connect the pipes to the bathroom equipment and the straight-through floor drain, and seal the joints to preliminarily complete the installation of the water replenishment structure; Turn on the bathroom equipment and water source, check whether the water seal of the direct floor drain can be replenished in time, whether the pipeline is leaking, debug the defective position, and complete the construction of the water replenishment structure.
[0009] Among them, when laying pipes in the bathroom, the pipes are made of hard polyvinyl chloride pipes, using socket connections, and PVC glue is evenly applied to the interfaces. After insertion, they are rotated and fixed, and left to stand for 30 minutes. The minimum slope of the pipe is 0.026.
[0010] Among them, a water trap is provided on the straight floor drain discharge pipe, and the connection between the water trap and the pipe needs to be additionally reinforced. Pipe clamps are set every 1 meter for horizontally laid pipes, and pipe clamps are set every 1.5 meters for vertically laid pipes, and additional fixed points are required at the bends of the pipes.
[0011] In a second aspect, the present invention further provides an automatic water replenishing structure for a floor drain water seal in a bathroom, which is applied to the construction method of the automatic water replenishing structure for a floor drain water seal in a bathroom as described in the first aspect above.
[0012] It includes bathroom equipment, pipelines, a water trap and a straight floor drain. The pipelines are connected to the bathroom equipment and the straight floor drain respectively and are located between the bathroom equipment and the straight floor drain. The water trap is connected to the straight floor drain and is located at the bottom of the straight floor drain.
[0013] The invention discloses a construction method for an automatic water replenishment structure of a floor drain water seal in a bathroom. The method comprises the following steps: planning the installation position of the water replenishment structure based on the bathroom layout and the position of a pre-installed straight-through floor drain, and drawing a construction sketch; preparing bathroom sanitary equipment, pipelines and construction tools based on user needs, and marking the installation position to complete the construction preparation; laying pipelines in the bathroom based on the construction sketch, installing and debugging the bathroom equipment, and completing the construction of the water replenishment structure. In the method, drainage of bathroom equipment (wash basin, urinal or mop pool, etc.) is connected to the straight-through floor drain drainage pipe through a pipeline, and water can be continuously replenished to the straight-through floor drain water seal when the bathroom equipment in the bathroom is used normally, thereby saving water resources and not requiring users to add water regularly. The straight-through floor drain is always in an open state, and does not need to be turned over to open the sealed straight-through floor drain, so that the phenomenon of odor from the straight-through floor drain is completely eliminated, and the problem of drying up the water seal of the existing bathroom floor drain and odor overflowing into the bathroom is solved. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0015] Figure 1 The present invention provides a flow chart of a construction method of an automatic water replenishment structure for a bathroom floor drain water seal.
[0016] Figure 2 It is a flowchart of the specific method of planning the installation position of the water replenishment structure based on the bathroom layout and the pre-installed straight-through floor drain position, and drawing a construction sketch.
[0017] Figure 3 It is a flowchart of the specific method of preparing bathroom sanitary equipment, pipes and construction tools based on user needs, marking the installation location, and completing construction preparation.
[0018] Figure 4 It is a flowchart of the specific method of laying pipes in the bathroom, installing and debugging bathroom equipment, and completing the construction of the water replenishment structure based on the construction sketch.
[0019] Figure 5 It is an assembly schematic diagram of an automatic water replenishing structure for a bathroom floor drain water seal provided by the present invention (one pipeline).
[0020] Figure 6 It is an assembly schematic diagram of an automatic water replenishing structure for a bathroom floor drain water seal provided by the present invention (two pipelines).
[0021] In the picture: 1-bathroom equipment, 2-pipes, 3-trap, 4-straight floor drain. DETAILED DESCRIPTION
[0022] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.
[0023] See also Figures 1 to 6 , the present invention provides a construction method of a bathroom floor drain water seal automatic water replenishment structure, comprising the following steps; S1 plans the installation position of the water replenishment structure based on the bathroom layout and the 4 pre-installed straight-through floor drains, and draws a construction sketch; Specific method: S11 collects bathroom space data and takes pictures of the bathroom environment to obtain bathroom data; In an embodiment of the present invention, a worker uses a roll of material or other measuring tools to measure the bathroom, obtains the length, width, and height of the bathroom, obtains space data, and uses a camera to take pictures of the bathroom environment, thereby determining the lighting and layout of the bathroom.
[0024] S12 plans the installation position of the water replenishment structure based on the bathroom data and the position planning of the pre-installed straight-through floor drain 4 to obtain planning data; In the embodiment of the present invention, design planning is performed based on the layout of the bathroom and the bathroom data to obtain the installation positions of the bathroom equipment 1 and the straight floor drain 4.
[0025] S13 performs modeling based on the planning data and the bathroom data, and draws a construction sketch.
[0026] In an embodiment of the present invention, three-dimensional software is used to model the planning data and the bathroom data, and the model is exported to draw a two-dimensional sketch, and the two-dimensional sketch is analyzed to determine whether the sketch conforms to the space and installation basis.
[0027] S2 prepares bathroom equipment 1, pipes 2 and construction tools based on user needs, marks the installation location, and completes construction preparation; Specific method: S21 prepares bathroom equipment 1, pipelines 2 and construction tools based on user needs; S22 checks whether the bathroom equipment 1 and pipe 2 are damaged and whether the quantity is in compliance; S23: marking the bathroom based on the drawing construction sketch, determining the installation construction location, and completing the construction preparation.
[0028] In the embodiment of the present invention, the purpose of drawing and marking is to confirm the installation position of the bathroom equipment 1 and the straight floor drain 4 with the construction personnel and to carry out the construction with the workers.
[0029] S3: based on the construction sketch, the pipes 2 are laid in the bathroom, and the bathroom equipment 1 is installed and debugged to complete the construction of the water replenishment structure.
[0030] Specific method: S31 Laying pipes 2 for the bathroom based on the construction sketch and the construction location; In the embodiment of the present invention, when laying the pipeline 2 in the bathroom, the pipeline 2 adopts a hard polyvinyl chloride pipe, uses a socket connection, and evenly applies PVC glue to the interface. After insertion, it is rotated and fixed, and left to stand for 30 minutes. The minimum slope of the pipeline is 0.026.
[0031] S32: installing the corresponding bathroom equipment 1 and the straight floor drain 4 to the construction location, and checking whether the installation is secure; S33 connects the pipe 2 to the bathroom equipment 1 and the straight-through floor drain 4, and seals the connection, thus preliminarily completing the installation of the water supply structure; In the embodiment of the present invention, a water trap 3 is provided on the discharge pipe of the straight floor drain 4, and the connection between the water trap 3 and the pipeline needs to be additionally reinforced. Pipe clamps are set every 1 meter for horizontally laid pipelines, and pipe clamps are set every 1.5 meters for vertically laid pipelines, and additional fixing points are required at the bends of the pipelines.
[0032] S34 opens the bathroom equipment 1 and the water source, checks whether the water seal of the direct floor drain 4 can be replenished in time, whether the pipeline 2 is leaking, and debugs the defective position to complete the construction of the water replenishment structure.
[0033] In the embodiment of the present invention, the bathroom equipment 1 and the water source are turned on for debugging to check whether they can work normally and whether the water seal of the direct floor drain 4 can be replenished in time. At the same time, observe whether there is leakage at the pipe connection, and if there is leakage, handle it in time.
[0034] In a second aspect, the present invention further provides a bathroom floor drain 4 water seal automatic water replenishment structure, which is applied to the bathroom floor drain 4 water seal automatic water replenishment structure construction method as described in the first aspect above.
[0035] It includes bathroom equipment 1, pipeline 2, water trap 3 and straight floor drain 4, the pipeline 2 is connected to the bathroom equipment 1 and the straight floor drain 4 respectively, and is located between the bathroom equipment 1 and the straight floor drain 4, the water trap 3 is connected to the straight floor drain 4, and is located at the bottom of the straight floor drain 4.
[0036] The above disclosure is only a preferred embodiment of the automatic water replenishment structure and construction method of a bathroom floor drain water seal of the present invention. Of course, this cannot be used to limit the scope of rights of the present invention. Ordinary technicians in this field can understand that all or part of the processes of the above embodiments and equivalent changes made according to the claims of the present invention still fall within the scope of the invention.
Claims
1. A construction method for an automatic water replenishment structure for a bathroom floor drain seal, characterized in that: The steps include: Plan the installation location of the water replenishment structure based on the bathroom layout and the pre-installed straight-through floor drain position, and draw a construction sketch; Prepare bathroom equipment, pipes and construction tools based on user needs, mark the installation locations, and complete construction preparations; Based on the construction sketch, the bathroom pipes are laid, and the bathroom equipment is installed and debugged to complete the construction of the water supply structure.
2. The construction method of the automatic water replenishment structure of the bathroom floor drain water seal as claimed in claim 1, It is characterized by: The specific method of planning the installation position of the water replenishment structure based on the bathroom layout and the pre-installed straight-through floor drain position and drawing the construction sketch is as follows: Collect bathroom space data, take pictures of the bathroom environment, and obtain bathroom data; Planning the installation position of the water replenishment structure based on the bathroom data and the position of the pre-installed straight-through floor drain to obtain planning data; Modeling is performed based on the planning data and the bathroom data, and a construction sketch is drawn.
3. The construction method of the automatic water replenishment structure of the bathroom floor drain water seal as claimed in claim 1, characterized in that ; The specific method of preparing bathroom equipment, pipes and construction tools based on user needs, marking the installation location, and completing construction preparation is as follows: Prepare bathroom equipment, pipelines and construction tools based on user needs; Check whether bathroom equipment and pipes are damaged and whether the quantity is in compliance; Based on the drawing construction sketch, the bathroom is marked with drawings, the installation construction location is determined, and the construction preparation is completed.
4. The construction method of the automatic water replenishment structure of the bathroom floor drain water seal as claimed in claim 1, It is characterized by: The specific method of laying the pipeline in the bathroom based on the construction sketch, installing and debugging the bathroom equipment, and completing the construction of the water replenishment structure is: Laying pipes for the bathroom based on the construction sketch and the construction location; Install the corresponding bathroom equipment and straight-through floor drain to the construction location, and check whether the installation is secure; Connect the pipes to the bathroom equipment and the straight-through floor drain, and seal the joints to preliminarily complete the installation of the water replenishment structure; Turn on the bathroom equipment and water source, check whether the water seal of the direct floor drain can be replenished in time, whether the pipeline is leaking, debug the defective position, and complete the construction of the water replenishment structure.
5. The construction method of the automatic water replenishment structure of the bathroom floor drain water seal as claimed in claim 1, characterized in that; When laying pipes in the bathroom, hard polyvinyl chloride pipes are used, and socket connections are used. PVC glue is evenly applied to the joints. After insertion, they are rotated and fixed, and left to stand for 30 minutes. The minimum slope of the pipe is 0.
026.
6. The construction method of the automatic water replenishment structure of the bathroom floor drain water seal as claimed in claim 1, characterized in that ; The straight floor drain discharge pipe is provided with a water trap, and the connection between the water trap and the pipe needs to be additionally reinforced. Pipe clamps are set every 1 meter for horizontally laid pipes, and pipe clamps are set every 1.5 meters for vertically laid pipes, and additional fixing points are required at the bends of the pipes.
7. An automatic water replenishment structure for a floor drain seal in a bathroom, applied to the construction method for the automatic water replenishment structure for a floor drain seal in a bathroom as claimed in any one of claims 1 to 6; It includes bathroom equipment, pipelines, a water trap and a straight floor drain. The pipelines are connected to the bathroom equipment and the straight floor drain respectively and are located between the bathroom equipment and the straight floor drain. The water trap is connected to the straight floor drain and is located at the bottom of the straight floor drain.