A method for installing a separate TBM synchronous lining construction trolley
By preparing installation materials outside the tunnel and assembling them in sections inside the tunnel, the problem of long installation cycle of trolleys in traditional TBM synchronous lining construction was solved, and efficient trolley installation was achieved.
Patent Information
- Application Number
- CN202510268608.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-07
- Publication Date
- 2025-10-31
- Estimated Expiration
- 2045-03-07
AI Technical Summary
In traditional TBM synchronous lining construction, the trolley installation needs to be completed outside the tunnel before being transported inside, resulting in a long installation cycle and low efficiency.
Materials are prepared outside the tunnel and transported to the tunnel using logistics vehicles. Inside the tunnel, overhead cranes and longitudinal lifting tracks are set up. Electric flatcars and lifting equipment are used to transport and assemble the trolleys in different areas, including the simultaneous installation of the gantry pre-assembly, frame assembly, template pre-assembly, and the whole machine storage area.
This shortened the trolley installation cycle, improved installation efficiency, and eliminated the need to transport the entire trolley to the tunnel, allowing installation to be completed directly in the work area.
Smart Images

Figure CN119878236B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tunnel construction technology, and in particular to a method for installing a separate TBM synchronous lining construction trolley. Background Technology
[0002] The tunnel employs synchronous lining construction technology, with rail transport being the most common and efficient mode of transportation. Traditional TBM synchronous lining construction requires the installation of the trolleys outside the tunnel before transporting them inside. However, using a separate TBM synchronous lining construction method, the secondary synchronous lining equipment is appropriately separated from the TBM's supporting equipment and maintains a reasonable distance. The secondary synchronous lining equipment used on-site includes needle beam low sidewall trolleys, rebar trolleys, secondary lining trolleys, and curing trolleys, among other construction equipment. Multiple trolleys need to be installed inside the tunnel before construction begins.
[0003] Therefore, how to provide a reasonable installation method to speed up trolley installation, shorten the installation cycle, and improve installation efficiency is a technical problem that urgently needs to be solved in this field. Summary of the Invention
[0004] To address at least one or more of the aforementioned technical problems, the present invention provides a method for installing a separate TBM synchronous lining construction trolley, comprising:
[0005] S10. Store the installation materials required for each vehicle outside the tunnel and transport them to the installation area inside the tunnel by logistics vehicles.
[0006] S20. A crane hoisting and longitudinal lifting rail are installed above the installation area, and the lifting rail is fixed to the top anchor bolt fixing support by I-beams;
[0007] S30. Installation materials are transported by electric flatbed carts, pre-assembled on site, and completed within the installation area.
[0008] The installation area, along the direction of TBM synchronous lining construction, is divided into the following sections from back to front: gantry pre-assembly area, frame assembly area, formwork pre-assembly area, template and accessory assembly area, and sorting and whole machine storage area. The gantry pre-assembly area is used for welding and splicing the columns, horizontal and vertical beams, and related small components of each gantry system. The frame assembly area is used for welding and assembling small components into the gantry frame. The formwork pre-assembly area is used for welding and splicing the small formwork components on the pin beam invert arch gantry and the secondary lining gantry. The template and accessory assembly area is used for assembling each template module onto the gantry frame and welding and assembling accessories onto the gantry frame. The sorting and whole machine storage area is used for gantry operation testing and temporary storage.
[0009] Furthermore, the installation method of the separate TBM synchronous lining construction trolley, step S30 includes the installation of the short sidewall needle beam trolley, including:
[0010] For the outer frame assembly installation, use a longitudinal electric hoist to install the outer frame and a transverse electric hoist to install the transverse connecting frame.
[0011] Assemble the main beam and install track wheels at the bottom of both ends of the main beam;
[0012] Install hydraulic and electrical systems;
[0013] Move to the work area of the low side wall and use a folding boom crane to install the formwork system and support system.
[0014] Furthermore, the installation method of the separate TBM synchronous lining construction trolley, step S30 also includes the installation of the rebar lifting trolley, including:
[0015] Install the first traveling system onto the first bottom longitudinal beam and hoist it onto the track;
[0016] Assemble the first gantry frame and connect it to the first bottom longitudinal beam after hoisting;
[0017] Install the first upper longitudinal beam and other connecting parts;
[0018] Install the first lower-level work platform and other accessories;
[0019] Install a steel bar lifting crane;
[0020] Install the first duct protective cover and the first upper working platform;
[0021] The entire machine was moved to the sorting and storage area for testing.
[0022] Furthermore, the installation method of the separate TBM synchronous lining construction trolley, step S30 also includes the installation of the rebar trolley, including:
[0023] Install the second travel system onto the second bottom longitudinal beam and hoist it onto the track;
[0024] Assemble the second gantry frame and connect it to the second bottom longitudinal beam after hoisting.
[0025] Install the second upper longitudinal beam and other connecting parts;
[0026] Install the second lower working platform, the first middle working platform, the first lower ladder, and other accessories;
[0027] Install upper-level columns, curved tracks, and a lifting platform;
[0028] Install the second duct protective cover, the second upper working platform, the first upper ladder and other accessories;
[0029] The entire steel bar trolley was moved to the sorting and storage area for testing.
[0030] Furthermore, the installation method of the separate TBM synchronous lining construction trolley, step S30 also includes the installation of the lining trolley, including:
[0031] Install the third travel system onto the third bottom longitudinal beam and hoist it onto the track;
[0032] Assemble the third gantry frame and connect it to the third bottom longitudinal beam after hoisting;
[0033] Install the third upper longitudinal beam and other connecting parts; install the third lower working platform, the second middle working platform, the second lower ladder and other accessories.
[0034] Install the third duct protective cover, upper lining frame, third upper working platform, second upper ladder and other accessories, hydraulic system, and electrical system;
[0035] Add left and right translation fixtures to the front and rear working platforms, place the top mold flat on the ground, use left and right electric hoists to lift the top mold onto the translation fixtures on the front and rear working platforms, move it left or right to the hoisting position, and use electric hoists to hoist the top mold to the installation position.
[0036] Install guide frames on the left and right sides, use a folding boom crane to lift the side mold and place it on the guide frames, move the trolley body to the side mold placement position, and use a manual hoist to lift the side mold to the installation position.
[0037] Place the corner mold at the bottom and use a manual hoist to lift the corner mold to the installation position;
[0038] The lining trolley was moved to the sorting and storage area for debugging.
[0039] Furthermore, the installation method of the split TBM synchronous lining construction trolley, step S30 also includes the installation of the support trolley, including:
[0040] Install the fourth travel system onto the fourth bottom longitudinal beam and hoist it onto the track;
[0041] Assemble the fourth gantry frame and connect it to the fourth bottom longitudinal beam after hoisting;
[0042] Install the fourth upper longitudinal beam and other connecting parts;
[0043] Install the fourth lower-level work platform and other accessories;
[0044] Install a fourth duct protective cover;
[0045] The support trolley was moved to the sorting and storage area for debugging.
[0046] Furthermore, the installation method of the separate TBM synchronous lining construction trolley, step S30 further includes the installation of the curing trolley, including:
[0047] Install the fifth travel system onto the fifth bottom longitudinal beam and hoist it onto the track;
[0048] Assemble the fifth gantry frame and connect it to the fifth bottom longitudinal beam after hoisting;
[0049] Install the fifth upper longitudinal beam and other connecting parts;
[0050] Install the fifth lower working platform, the third middle working platform, the third lower ladder, and other accessories;
[0051] Install the fifth duct protective cover, upper frame, sprinkler pipe, fourth upper work platform, third upper ladder and other accessories;
[0052] Install electrical systems;
[0053] The entire maintenance trolley was moved to the sorting and storage area for testing.
[0054] In this embodiment, an installation method for the separate TBM synchronous lining construction trolley is provided. First, the installation materials required for each trolley are stored outside the tunnel to prepare for the installation, saving time and improving efficiency during installation inside the tunnel. Then, a logistics vehicle transports the materials to the installation area inside the tunnel. A crane and longitudinal lifting rails are installed above the installation area. These lifting rails are fixed to the top anchor supports by I-beams. Lifting equipment is then installed on the lifting rails above the installation area. For example, there are two lifting rails, one on each side, with two electric hoists on each side, for a total of four electric hoists, preparing for the subsequent movement and installation of various trolley components. Finally, an electric flatcar transports the installation materials for on-site pre-assembly, completing the separate TBM synchronous lining construction trolley installation within the installation area.
[0055] The installation area can be divided into a gantry pre-assembly area, a frame assembly area, a template pre-assembly area, a template and accessory assembly area, and a sorting and storage area for the entire machine. The separate TBM synchronous lining construction trolley can be installed in multiple areas, and the installation of various trolleys can be carried out simultaneously. Moreover, there is no need to transport the whole machine into the tunnel. The installation can be completed directly in the work area, which can effectively shorten the installation cycle and improve the installation efficiency. Attached Figure Description
[0056] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the description of the embodiments or the prior art are briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on the structures shown in these drawings without creative effort. In the drawings, the same parts use the same reference numerals. The drawings are not drawn to scale.
[0057] Figure 1 This is a schematic diagram of an embodiment of the installation method of the split TBM synchronous lining construction trolley of the present invention in the construction area.
[0058] Figure 2 This is a schematic diagram of an embodiment of the installation of the short side wall needle beam trolley portion of the installation method of the split TBM synchronous lining construction trolley of the present invention.
[0059] Figure 3 This is a schematic diagram of an embodiment of the installation method of the split TBM synchronous lining construction trolley of the present invention, showing the full installation of the low side wall needle beam trolley.
[0060] Figure 4 This is a schematic diagram of an embodiment of the installation of the steel bar lifting trolley portion of the installation method of the split TBM synchronous lining construction trolley of the present invention.
[0061] Figure 5 A schematic diagram of an embodiment of the installation method of the split TBM synchronous lining construction trolley of the present invention, showing the full installation of the steel bar lifting trolley;
[0062] Figure 6 This is a schematic diagram of a partial installation of the steel reinforcement trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention.
[0063] Figure 7 This is a schematic diagram of a complete installation embodiment of the steel reinforcement trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention.
[0064] Figure 8 Left view of an embodiment of the installation of the steel reinforcement trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention;
[0065] Figure 9 This is a schematic diagram of an embodiment of the installation of the lining trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention.
[0066] Figure 10 Left view of another embodiment of the installation of a lining trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention;
[0067] Figure 11 This is a schematic diagram of an embodiment of the installation of the side formwork of the lining trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention.
[0068] Figure 12 This is a schematic diagram of an embodiment of the installation of the side formwork of the lining trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention.
[0069] Figure 13 This is a schematic diagram of an embodiment of the installation of the top formwork, side formwork, and corner formwork of the lining trolley in the installation method of the separable TBM synchronous lining construction trolley of the present invention.
[0070] Figure 14 This is a schematic diagram of an embodiment of the installation of a support trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention.
[0071] Figure 15 Left view of an embodiment of the installation of the support trolley for the installation method of the split TBM synchronous lining construction trolley of the present invention;
[0072] Figure 16 This is a schematic diagram of a partial installation of the curing trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention.
[0073] Figure 17 Left view of an embodiment of the installation of the maintenance trolley in the installation method of the split TBM synchronous lining construction trolley of the present invention. Detailed Implementation
[0074] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the scope of protection of the present invention.
[0075] It should be noted that when a component is referred to as "fixed to" or "set on" another component, it can be directly on the other component or there may be an intervening component present. When a component is referred to as "connected to" another component, it can be directly connected to the other component or there may be an intervening component present.
[0076] It should also be noted that if the embodiments of the present invention involve directional indications, such as up, down, left, right, front, back, etc., these directional indications are only used to explain the relative positional relationship and movement of the components in a specific posture. If the specific posture changes, the directional indications will also change accordingly. Furthermore, if the embodiments of the present invention involve descriptions such as "first," "second," "S1," "S2," "step one," "step two," etc., these descriptions are for descriptive purposes only and should not be construed as indicating or implying their relative importance, or implicitly indicating the number of technical features indicated or the order of method execution. Those skilled in the art will understand that anything that does not violate the inventive concept and does not contradict the inventive points should be included within the scope of protection of the present invention.
[0077] This invention provides an installation method for a separate TBM synchronous lining construction trolley, referencing... Figure 1 Its features include:
[0078] S10. Store the installation materials required for each vehicle outside the tunnel and transport them to the installation area inside the tunnel by logistics vehicles.
[0079] S20. A crane hoisting and longitudinal lifting rail are installed above the installation area, and the lifting rail is fixed to the top anchor bolt fixing support by I-beams;
[0080] S30. Installation materials are transported by electric flatbed carts, pre-assembled on site, and completed within the installation area.
[0081] The installation area, along the direction of TBM synchronous lining construction, is divided into the following sections from back to front: gantry pre-assembly area 100, frame assembly area 200, template pre-assembly area 300, template and accessory assembly area 400, and sorting and whole-machine storage area 500. The gantry pre-assembly area 100 is used for welding and splicing the columns, horizontal and vertical beams, and related small components of each gantry system. The frame assembly area 200 is used for welding and assembling small components into the gantry frame. The template pre-assembly area 300 is used for welding and splicing small template components on the pin beam inverted arch gantry and the secondary lining gantry. The template and accessory assembly area 400 is used for assembling each template module onto the gantry frame and welding and assembling accessories onto the gantry frame. The sorting and whole-machine storage area 500 is used for gantry operation testing and temporary storage.
[0082] In this embodiment, the present invention provides an installation method for a separate TBM synchronous lining construction trolley. First, the installation materials required for each trolley are stored outside the tunnel to prepare for the installation of the separate TBM synchronous lining construction trolley, saving time and improving installation efficiency inside the tunnel. Then, a logistics vehicle transports the materials to the installation area inside the tunnel. A crane and longitudinal lifting rails are installed above the installation area. The lifting rails are fixed to the top anchor support by I-beams. Lifting equipment is then installed on the lifting rails above the installation area. For example, there are two lifting rails, left and right, with two electric hoists on each side, for a total of four electric hoists, preparing for the subsequent movement and installation of various trolley components. Finally, an electric flatcar transports the installation materials for on-site pre-assembly, completing the separate TBM synchronous lining construction trolley installation within the installation area.
[0083] Specifically, the installation area can be divided into a gantry pre-assembly area, a frame assembly area, a template pre-assembly area, a template and accessory assembly area, and a sorting and whole machine storage area. The separate TBM synchronous lining construction trolley is installed in multiple areas, and the installation of various trolleys can be carried out simultaneously. Moreover, there is no need to transport the whole machine into the tunnel. The installation can be completed directly in the work area, which can effectively shorten the installation cycle and improve the installation efficiency.
[0084] Preferred, Reference Figure 2 and Figure 3 The installation method of the split TBM synchronous lining construction trolley, step S30 includes the installation of the short side wall needle beam trolley, including:
[0085] The outer frame assembly 112 is installed, the outer frame is installed using a longitudinal electric hoist 110, and the transverse connecting frame is installed using a transverse electric hoist 110.
[0086] Assemble the main beam 111 and install track-mounted wheels 113 at the bottom of both ends of the main beam 111;
[0087] Install hydraulic and electrical systems;
[0088] Move to the work area of the low side wall and use a folding boom crane to install the formwork system and support system.
[0089] This embodiment presents an installation method for a low-profile wall pin beam trolley. First, the outer frame assembly is installed using a longitudinal electric hoist, and the transverse connecting frame is installed using a transverse electric hoist. Utilizing both longitudinal and transverse electric hoists to complete the outer frame assembly installation significantly improves installation efficiency. Next, track wheels are installed at the bottom of both ends of the main beam to facilitate the movement of the low-profile wall pin beam trolley. The hydraulic and electrical systems of the low-profile wall pin beam trolley are then installed. Finally, the low-profile wall pin beam trolley is moved to the low-profile wall working area, where a folding arm installation system and support system are used to directly install the low-profile wall pin beam trolley within the working area, greatly saving installation time.
[0090] Preferred, Reference Figure 4 and Figure 5 The installation method of the split TBM synchronous lining construction trolley, step S30 also includes the installation of the rebar lifting trolley, including:
[0091] Install the first walking system 122 onto the first bottom longitudinal beam 121 and hoist it onto the track 600;
[0092] Assemble the first gantry frame 123, and after hoisting, connect it to the first bottom longitudinal beam 121;
[0093] Install the first upper longitudinal beam 124 and other connecting parts;
[0094] Install the first lower working platform 125 and other accessories;
[0095] 126 steel bar hoisting cranes were installed.
[0096] Install the first duct protective cover 127 and the first upper working platform 128;
[0097] The entire machine was moved to the sorting and storage area 500 for debugging.
[0098] This embodiment provides an installation method for a rebar lifting trolley. First, the first traveling system is installed on the first bottom longitudinal beam and hoisted onto the track, allowing the rebar lifting trolley to move freely on the track. It is understood that the first traveling system can be other rail-type traveling wheels. Then, the first upper longitudinal beam and other connecting parts, the first lower working platform and other accessories, the rebar lifting crane, the first air duct protective cover, and the first upper working platform are installed sequentially. Finally, the entire rebar lifting trolley is moved to the sorting and storage area for debugging. The entire rebar lifting trolley is generally installed sequentially from bottom to top. Debugging the rebar lifting trolley in the sorting and storage area avoids occupying the track for extended periods, freeing up space for the installation and operation of other trolleys, greatly improving installation efficiency and saving construction time.
[0099] Preferred, Reference Figure 6-8The installation method of the split TBM synchronous lining construction trolley, step S30 also includes the installation of the rebar trolley, including:
[0100] Install the second travel system 132 onto the second bottom longitudinal beam 131 and hoist it onto the track;
[0101] Assemble the second gantry frame 133, and after hoisting, connect it to the second bottom longitudinal beam 131;
[0102] Install the second upper longitudinal beam 134 and other connecting parts;
[0103] Install the second lower working platform 135a, the first middle working platform 135b, the first lower ladder 136, and other accessories;
[0104] Install the upper column 137, the arc track 138, and the lifting platform 139d;
[0105] Install the second duct protective cover 139a, the second upper working platform 139b, the first upper ladder 139c and other accessories;
[0106] The entire rebar trolley was moved to the sorting and storage area 500 for testing.
[0107] In this embodiment, a method for installing a rebar trolley is provided. The second traveling system is installed on the second bottom longitudinal beam and hoisted onto the track, allowing the rebar lifting trolley to move freely on the track and improving its applicability. The second gantry is then assembled, hoisted using an electric hoist, and connected to the second bottom longitudinal beam. The second upper longitudinal beam and other connecting parts are then installed, completing the basic frame installation of the rebar trolley. Next, the second upper longitudinal beam and other connecting parts, the second lower working platform, the first middle working platform and the first lower ladder and other accessories, the upper column, the curved track, the lifting platform, the second duct protective cover, the second upper working platform, the first upper ladder, and other accessories are installed sequentially. The first lower... The ladders and the first upper ladder facilitate the movement of operators up and down the rebar trolley. The second lower working platform, the first middle working platform, and the second upper working platform of the rebar trolley are mainly used for stacking and tying rebars. The second bottom longitudinal beam, the second upper longitudinal beam, and the upper column, along with their various accessories and connectors, constitute the main body of the rebar trolley, serving as its structural framework and providing support. The second duct protective cover protects the ducts that pass through the rebar trolley. The curved track and lifting platform are used for moving the rebars up and down. Finally, the entire rebar trolley is moved to the sorting and storage area for debugging, which avoids occupying the track for a long time, freeing up space for the installation and operation of other trolleys, greatly improving installation efficiency and saving construction time.
[0108] Preferred, Reference Figures 9 to 13The installation method of the split TBM synchronous lining construction trolley, step S30 also includes the installation of the lining trolley, including:
[0109] Install the third travel system 142 onto the third bottom longitudinal beam 141 and hoist it onto the track 600;
[0110] Assemble the third gantry frame 143, and after hoisting, connect it to the third bottom longitudinal beam 141;
[0111] Install the third upper longitudinal beam 144 and other connecting parts, install the third lower working platform 145a, the second middle working platform 145b, the second lower ladder 146 and other accessories;
[0112] Install the third duct protective cover 147, the upper lining platform 148, the third upper working platform 149a, the second upper ladder 149b and other accessories, hydraulic system, and electrical system;
[0113] Add left and right translation fixtures 149c to the front and rear two-layer working platforms 145c, place the top mold 149d flat on the ground, use left and right electric hoists 110 to lift the top mold 149d onto the translation fixtures 149c on the front and rear two-layer working platforms 145c, and move it to the left or right to the hoisting position, and use electric hoists 110 to hoist the top mold 149d to the installation position;
[0114] Install guide frames 149e on the left and right sides, use a folding boom crane to lift the side mold 149f and place it on the guide frame 149e, move the trolley body to the side mold 149f placement position, and use a manual hoist to lift the side mold 149f to the installation position.
[0115] Place the corner mold 149g at the bottom and use a manual hoist to lift the corner mold 149g to the installation position;
[0116] The lining trolley was moved to the sorting and storage area 500 for debugging.
[0117] This embodiment presents a method for installing a secondary lining trolley. During installation, electric and manual hoists are used multiple times to ensure the safe and stable lifting of heavy components, reducing the risks associated with manual operation and improving operational safety. Simultaneously, the left-right sliding fixture and stable lifting system ensure accurate positioning of components such as the top and side forms, reducing installation deviations that may occur during manual operation and improving installation accuracy. The design of the left-right sliding fixture and guide frame makes efficient use of space, avoiding excessive space occupation during the lifting of large equipment and improving operational efficiency on the construction site. The entire installation process considers the convenience of later debugging. With the assistance of a third travel system, the trolley is moved as a whole to a designated area for debugging, facilitating the identification and correction of problems and ensuring the normal operation of the equipment. The installation of a third duct protective cover is primarily for protecting the ducts during construction. The installation of a second upper ladder and a second lower ladder facilitates easy movement for operators on the lining trolley, improving its usability. The third bottom longitudinal beam, third gantry, third upper longitudinal beam, and other connecting components form the basic framework of the lining trolley, connecting and supporting the top formwork, side formwork, and corner formwork. The hydraulic and electrical systems described are conventional and will not be elaborated upon further.
[0118] Preferred, Reference Figure 14 and 15 The installation method of the split TBM synchronous lining construction trolley, step S30 also includes the installation of the support trolley, including:
[0119] Install the fourth travel system 152 onto the fourth bottom longitudinal beam 151 and hoist it onto the track;
[0120] Assemble the fourth gantry frame 153, and after hoisting, connect it to the fourth bottom longitudinal beam 151;
[0121] Install the fourth upper longitudinal beam 154 and other connecting parts;
[0122] Install the fourth lower-level work platform 155 and other accessories;
[0123] Install the fourth duct protective cover 156;
[0124] The support trolley was moved to the sorting and storage area 500 for debugging.
[0125] This embodiment presents a method for installing a support trolley. A fourth traveling system is installed on the support trolley as the foundation for its movement, enabling precise and stable movement along tracks or other designated paths. Specifically, the fourth traveling system includes a drive unit, a transmission unit, and track wheels to ensure precise and stable movement of the equipment. In this installation method, the fourth traveling system, the fourth bottom longitudinal beam, the fourth gantry, the fourth upper longitudinal beam, and the connecting components are installed using a modular or prefabricated design, reducing on-site installation workload and significantly improving installation efficiency. Simultaneously, this installation method reduces vibration, noise, and wear caused by improper installation, improving the operating efficiency and lifespan of the support trolley. Installing the fourth traveling system onto the fourth bottom longitudinal beam, and then hoisting the fourth gantry to connect with the fourth bottom longitudinal beam, ensures the connection accuracy between components and the stability of the overall structure. Moving the support trolley to a designated storage area for debugging allows for concentrated resources for comprehensive performance testing and functional verification, resulting in a more rational installation layout.
[0126] Preferred, Reference Figure 16 and Figure 17 The installation method of the split TBM synchronous lining construction trolley, step S30 also includes the installation of the curing trolley, including:
[0127] Install the fifth travel system 162 onto the fifth bottom longitudinal beam 161 and hoist it onto the track 600;
[0128] Assemble the fifth gantry frame 163, and after hoisting, connect it to the fifth bottom longitudinal beam 161;
[0129] Install the fifth upper longitudinal beam 164 and other connecting parts;
[0130] Install the fifth lower working platform 165a, the third middle working platform 165b, the third lower ladder 166 and other accessories;
[0131] Install the fifth duct protective cover 167, the upper platform 168, the sprinkler pipe 169a, the fourth upper working platform 169b, the third upper ladder 169c and other accessories;
[0132] Install electrical systems;
[0133] The entire maintenance trolley was moved to the sorting and storage area 500 for testing.
[0134] This embodiment provides an installation method for a maintenance trolley. The fifth traveling system serves as the foundation for the trolley's movement, ensuring smooth and accurate movement on the track. The installation of the fifth traveling system, the fifth bottom longitudinal beam, the fifth gantry, the upper platform, the fifth upper longitudinal beam, and connecting components all employ modular or prefabricated designs, reducing on-site installation workload and significantly improving installation efficiency. The third upper ladder, the third lower ladder, and other accessories provide operators with vertical movement channels, facilitating easier movement between the various work platforms. The electrical system, specifically including motors, controllers, and sensors, controls the trolley's movement, the lifting and lowering of each work platform, and the switching of the spray pipes, achieving automated and intelligent control of the trolley. It is noteworthy that this embodiment provides an installation method for the maintenance trolley, enabling its specific installation. The specific control flow, action time, and travel path for the movement, lifting, and operation of each module of the electrical system can be implemented using programmable logic devices such as PLCs, and will not be elaborated further here. Sprinkler pipes are used for regular curing of hardened concrete to prevent excessive evaporation of moisture and subsequent shrinkage cracks. For example, at room temperature, concrete should be watered with sprinklers within 4-6 hours after pouring, 4-6 times a day for the first three days, and then 2-3 times a day thereafter, with a curing period of no less than 14 days. The fifth lower working platform, the third middle working platform, and the fourth upper working platform provide additional working space for the curing trolley, increasing its versatility. The entire curing trolley is installed modularly from bottom to top, resulting in high installation efficiency. After installation, it is moved to the sorting and storage area for testing, ensuring the stability and functionality of the overall structure. The rational layout of the entire curing trolley installation process improves installation efficiency.
[0135] The embodiments described above are merely examples of several implementations of the present invention, and are described in a relatively specific and detailed manner. The combinations of their technical effects and features will not be repeated here, but should not be construed as limiting the scope of the invention patent. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of the present invention, and these all fall within the protection scope of the present invention.
Claims
1. A method for installing a separate TBM synchronous lining construction trolley, characterized in that, include: S10. Store the installation materials required for each vehicle outside the tunnel and transport them to the installation area inside the tunnel by logistics vehicles. S20. A crane hoisting and longitudinal lifting rail are installed above the installation area, and the lifting rail is fixed to the top anchor bolt fixing support by I-beams; S30. Installation materials are transported by electric flatbed carts, pre-assembled on site, and completed within the installation area. The installation area, along the direction of TBM synchronous lining construction, is divided into the following sections from back to front: gantry pre-assembly area, frame assembly area, formwork pre-assembly area, formwork and accessory assembly area, and sorting and whole-machine storage area. The gantry pre-assembly area is used for welding and splicing the columns, horizontal and vertical beams, and related small components of each gantry system. The frame assembly area is used for welding and assembling small components into the gantry frame. The formwork pre-assembly area is used for welding and splicing the small formwork components on the pin beam invert arch gantry and the secondary lining gantry. The formwork and accessory assembly area is used for assembling each formwork module onto the gantry frame and welding and assembling accessories onto the gantry frame. The sorting and whole-machine storage area is used for gantry operation testing and temporary storage. Step S30 includes the installation of the pin beam trolley for the low sidewall, including: For the outer frame assembly installation, use a longitudinal electric hoist to install the outer frame and a transverse electric hoist to install the transverse connecting frame. Assemble the main beam and install track-mounted wheels at the bottom of both ends of the main beam; Install hydraulic and electrical systems; Move to the work area of the low side wall and use a folding boom crane to install the formwork system and support system; Step S30 also includes the installation of the rebar lifting trolley, including: Install the first traveling system onto the first bottom longitudinal beam and hoist it onto the track; Assemble the first gantry frame and connect it to the first bottom longitudinal beam after hoisting; Install the first upper longitudinal beam and other connecting parts; Install the first lower-level work platform and other accessories; Install a steel bar lifting crane; Install the first duct protective cover and the first upper working platform; The entire machine was moved to the sorting and storage area for testing.
2. The installation method of the separate TBM synchronous lining construction trolley according to claim 1, characterized in that, Step S30 also includes the installation of the rebar trolley, including: Install the second travel system onto the second bottom longitudinal beam and hoist it onto the track; Assemble the second gantry frame and connect it to the second bottom longitudinal beam after hoisting. Install the second upper longitudinal beam and other connecting parts; Install the second lower working platform, the first middle working platform, the first lower ladder, and other accessories; Install upper-level columns, curved tracks, and a lifting platform; Install the second duct protective cover, the second upper working platform, the first upper ladder and other accessories; The entire steel bar trolley was moved to the sorting and storage area for testing.
3. The installation method of the separate TBM synchronous lining construction trolley according to claim 1, characterized in that, Step S30 also includes the installation of the lining trolley, including: Install the third travel system onto the third bottom longitudinal beam and hoist it onto the track; Assemble the third gantry frame and connect it to the third bottom longitudinal beam after hoisting; Install the third upper longitudinal beam and other connecting parts; install the third lower working platform, the second middle working platform, the second lower ladder and other accessories. Install the third duct protective cover, upper lining frame, third upper working platform, second upper ladder and other accessories, hydraulic system, and electrical system; Add left and right translation fixtures to the front and rear working platforms, place the top mold flat on the ground, use left and right electric hoists to lift the top mold onto the translation fixtures on the front and rear working platforms, move it left or right to the hoisting position, and use electric hoists to hoist the top mold to the installation position. Install guide frames on the left and right sides, use a folding boom crane to lift the side mold and place it on the guide frames, move the trolley body to the side mold placement position, and use a manual hoist to lift the side mold to the installation position; Place the corner mold at the bottom and use a manual hoist to lift the corner mold to the installation position; The lining trolley was moved to the sorting and storage area for debugging.
4. The installation method of the separate TBM synchronous lining construction trolley according to claim 1, characterized in that, Step S30 also includes installing the support trolley, including: Install the fourth travel system onto the fourth bottom longitudinal beam and hoist it onto the track; Assemble the fourth gantry frame and connect it to the fourth bottom longitudinal beam after hoisting; Install the fourth upper longitudinal beam and other connecting parts; Install the fourth lower-level work platform and other accessories; Install a fourth duct protective cover; The support trolley was moved to the sorting and storage area for debugging.
5. The installation method of the separate TBM synchronous lining construction trolley according to any one of claims 1 to 4, characterized in that, Step S30 also includes the installation of the maintenance trolley, including: Install the fifth travel system onto the fifth bottom longitudinal beam and hoist it onto the track; Assemble the fifth gantry frame and connect it to the fifth bottom longitudinal beam after hoisting; Install the fifth upper longitudinal beam and other connecting parts; Install the fifth lower working platform, the third middle working platform, the third lower ladder, and other accessories; Install the fifth duct protective cover, upper frame, sprinkler pipe, fourth upper work platform, third upper ladder and other accessories; Install electrical systems; The entire maintenance trolley was moved to the sorting and storage area for testing.
Citation Information
Patent Citations
Tunnel construction method based on inverted arch and inverted arch filling layer replaced steel and concrete combined structure
CN110318776A
Longitudinal needle beam slip form trolley for tunnel bottom plate
CN119177867A