Large-area field concrete construction method based on BIM (Building Information Modeling)

By adopting BIM-based construction methods in large-area concrete construction, the problem of lack of integrated management during the construction process is solved, the quality evaluation and optimization of each pouring area is achieved, and the construction efficiency and quality are improved.

CN119885355APending Publication Date: 2025-04-25ZHENGZHOU ENG CO LTD CHINA RAILWAY SEVENTH GRP +2

Patent Information

Application Number
CN202411926773.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-25
Publication Date
2025-04-25

AI Technical Summary

Technical Problem

In the prior art, there is a lack of integrated methods of concrete pouring and material management during the construction of large-area concrete in the prior art, which is difficult to intuitively reflect the construction efficiency and quality of each pouring area.

Method used

Using BIM-based construction methods, a BIM model is established by collecting construction site data, a large-area yard is divided into multiple casting areas, and a concrete casting and material management module is established to monitor ambient temperature and humidity in real time, generate concrete curing quality index, and evaluate and optimize casting quality.

Benefits of technology

The quality evaluation and optimization of each concrete pouring area has been achieved, construction efficiency and quality have been improved, and material management has been ensured to be accurate and sufficient inventory.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119885355A_ABST
    Figure CN119885355A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of large-area field concrete construction, and discloses a large-area field concrete construction method based on BIM (Building Information Modeling), which comprises the following steps: acquiring data of a current construction site, and obtaining the required quantity of concrete and reinforcing steel bar materials required by construction according to an established BIM model and requirements in a drawing. According to the method, the environment temperature and the environment humidity in the pouring process are collected, the pouring process is regulated and controlled according to the environment temperature and the environment humidity, and after the concrete curing quality index CIi of the ith pouring area is generated at the same time, the quality states of n different pouring areas are scored; the pouring quality of each pouring area is scored, the environment temperature and humidity data of the pouring module with the highest pouring score in the pouring process and the use amount condition of each day in the pouring process are stored, and data support is provided for follow-up pouring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of large-area field concrete construction, and specifically to a large-area field concrete construction method based on BIM. Background Art

[0002] Building Information Modeling (BIM) is a three-dimensional building model based on various relevant information data of construction projects, which simulates the real information of the building through digital information simulation. It has eight characteristics: information completeness, information relevance, information consistency, visualization, coordination, simulation, optimization and mappability. The construction unit, design unit, construction unit, supervision unit and other project participants are on the same platform to share the same building information model. It is conducive to project visualization and refined construction;

[0003] The prior art CN107448022A discloses a BIM-based method for constructing a large-area, ultra-long floor in a food cold storage. The floor to be constructed is divided into several casting areas and numbered. The model is modeled using the revit2015 design software, and then the model is exported and imported into naviswork2015. Time nodes are assigned to unit engineering quantities, and a 4Dbim construction simulation animation is produced. The floor is constructed by partition casting. The odd-numbered areas are cast first, and the mold is removed when the concrete strength grade reaches more than 50% of the design strength. Then, the even-numbered areas are cast. After all the casting is completed, an integral floor structure is formed.

[0004] However, in the prior art, there is no method for integrating concrete pouring and material management during the concrete pouring process. At the same time, for large-area field concrete construction, the construction efficiency and quality of each pouring area cannot be directly reflected. Summary of the invention

[0005] 1. Technical issues to be resolved

[0006] In view of the shortcomings of the prior art, the present invention provides a large-area field concrete construction method based on BIM, which has the advantages of quality assessment of each concrete pouring area in the large-area field concrete construction, and solves the above-mentioned technical problems.

[0007] (II) Technical solution

[0008] To achieve the above object, the present invention provides the following technical solutions:

[0009] According to a first aspect of the present invention, a large-area field concrete construction method based on BIM is provided. The method comprises:

[0010] Collect data of the current construction site and build a BIM model based on the data. Then, based on the established BIM model and the requirements in the drawings, obtain the required quantity of concrete and steel materials required for construction;

[0011] Establish a concrete pouring module, divide the large area of ​​the field into n different pouring areas according to the shape and size of the field in the BIM model, and let the staff specify the pouring order and pour according to the pouring data stored in the concrete pouring module. At the same time, collect the ambient temperature and humidity during the pouring process, and regulate the pouring process according to the ambient temperature and humidity. At the same time, generate the concrete curing quality index CI of the i-th pouring area i , where i∈[1,n];

[0012] Establish a material management module to collect the current usage of concrete and steel materials when the staff are working according to the pouring sequence specified by the staff in the concrete pouring module, and then monitor the remaining and expected quantities of concrete and steel materials in the inventory through the material management module;

[0013] After pouring, the quality of concrete in n different pouring areas is evaluated, unqualified areas are marked in the BIM model, and the corresponding reasons for unqualified areas are given, and unqualified pouring areas are repaired;

[0014] After the finishing is completed, the quality status of n different pouring areas is scored, and the score of the pouring area with the highest quality score is compared with the score corresponding to the pouring data stored in the concrete pouring module; if it is higher than the score corresponding to the pouring data stored in the concrete pouring module, the data in this pouring process is replaced in the concrete pouring module.

[0015] Furthermore, the concrete curing quality index CI of the i-th pouring area is generated i ,include:

[0016] Before pouring, collect the temperature of the day. If the temperature value is higher than the limit threshold temperature, stop pouring construction on that day. If the temperature value is not higher than the limit threshold temperature, proceed with construction.

[0017] Record the ambient temperature of the i-th pouring area at the j-th moment and ambient humidity When the ambient temperature And the ambient humidity When the temperature rises, the spray equipment is started to cool the concrete;

[0018] Concrete curing quality index CI for the i-th area i Perform calculations.

[0019] Furthermore, the concrete curing quality index CI of the i-th area is i The calculation expression is as follows:

[0020]

[0021] in, represents the ambient temperature of the i-th pouring area at the j-th moment, represents the ambient humidity of the i-th pouring area at the j-th time, ω T and ω RH Represents the weighting factor of temperature and humidity, T lx Indicates the ideal curing temperature, RH lx Indicates ideal maintenance humidity. It means summing up m moments.

[0022] Further: the material management module is established, when the staff performs construction according to the pouring sequence specified by the staff in the concrete pouring module, the current usage of concrete and steel materials is collected, and then the remaining amount and expected amount of concrete and steel materials in the inventory are monitored through the material management module, including:

[0023] The amount of concrete used in the pouring process of the i-th area is HNT i and steel material consumption GJ i to collect;

[0024] Calculate the increment of concrete consumption ΔHNT and steel material consumption ΔGJ in all areas poured on the day;

[0025] If the increment of concrete consumption ΔHNT and the increment of steel material consumption ΔGJ are non-positive values, no subsequent calculations will be performed;

[0026] If the increment of the concrete consumption ΔHNT and / or the increment of the steel material consumption ΔGJ is positive, the consumption of concrete and steel material is predicted until the end of the construction period to obtain the predicted amount of concrete and the predicted amount of steel material respectively;

[0027] Determine the relationship between the remaining amount of concrete in inventory and the predicted amount of concrete to determine whether scheduling is needed;

[0028] Determine the relationship between the remaining quantity of steel bar materials in inventory and the predicted quantity of steel bar materials to determine whether scheduling is required.

[0029] Further: The expression for the increase in concrete consumption in all areas is as follows:

[0030]

[0031] Among them, ΔHNT represents the increase in the amount of concrete, HNT i represents the amount of concrete used during the pouring of the ith area, HNT i ′ represents the theoretical amount of concrete during the pouring process of the i-th area, k represents the k-th pouring area, l represents the l-th pouring area, and l-k+1 represents that l-k+1 areas were poured on that day.

[0032] Further: The incremental expression of the amount of steel bar material is as follows:

[0033]

[0034] Where k represents the kth pouring area, l represents the lth pouring area, l-k+1 represents that a total of l-k+1 areas were poured on that day, GJ i represents the amount of steel bars used in the pouring process of the i-th area, GJ i ′ It represents the theoretical amount of steel bars used during the pouring process of the ith area, and ΔGJ represents the increase in the amount of steel bar material used.

[0035] Further: the expressions of the predicted amount of concrete and the predicted amount of steel bar material are:

[0036]

[0037] Among them, γ HNT and γ GJ Respectively represent the predicted amount of concrete and steel material, ∑* represents the sum of the daily pouring area, Day sy Indicates the remaining days. represents the amount of concrete poured in the i-th area during the initial planning, It represents the amount of steel bars used for casting the i-th area during initial planning, ΔGJ represents the increment of steel bar material usage, and ΔHNT represents the increment of concrete usage.

[0038] Further: the specific expression for scoring the quality status of n different casting areas is as follows:

[0039]

[0040] Among them, FI i represents the score of the i-th pouring area, CI i represents the concrete curing quality index, θ i represents the average inclination angle of concrete in the i-th pouring area, Q represents the initial score, and LF i Represents the number of unqualified cracks in the i-th casting area.

[0041] According to a second aspect of the present invention, an electronic device is provided, which includes a memory and a processor, wherein a computer program is stored in the memory, and when the computer program is executed by the processor, the large-area field concrete construction method based on BIM is executed.

[0042] According to a third aspect of the present invention, a storage medium is provided, which stores a computer program that can be executed by one or more processors and can be used to implement the BIM-based large-area field concrete construction method.

[0043] Compared with the prior art, the present invention provides a large-area field concrete construction method based on BIM, which has the following beneficial effects:

[0044] 1. The present invention collects the ambient temperature and humidity during the pouring process, and regulates the pouring process according to the ambient temperature and humidity, and generates the concrete curing quality index CI of the i-th pouring area at the same time. i Finally, the quality status of n different pouring areas is scored, so as to score the pouring quality of each pouring area, and the ambient temperature and humidity data of the pouring module with the highest pouring score during the pouring process, as well as the usage of each day during the pouring process, are saved to provide data support for subsequent pouring.

[0045] 2. The present invention collects the daily concrete consumption and steel bar material consumption, and then uses the material management module to calculate the increments of the concrete consumption and steel bar material consumption of all areas poured on that day. After the calculation is completed, the two calculated increments are judged. If the increment is a non-positive value, no subsequent calculation is performed. If the increment is a positive value, it is predicted that the concrete consumption and steel bar material consumption will need to be consumed until the end of the construction period, thereby ensuring sufficient inventory. When insufficient inventory is expected, the management personnel are reminded in time. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] The above and other features, advantages and aspects of the embodiments of the present invention will become more apparent with reference to the following detailed description in conjunction with the accompanying drawings. The accompanying drawings are used to better understand the present invention and do not constitute a limitation of the present invention. In the accompanying drawings, the same or similar reference numerals represent the same or similar elements, wherein:

[0047] Figure 1 A schematic diagram of a process of a large-area field concrete construction method based on BIM according to an embodiment of the present invention is shown;

[0048] Figure 2 A block diagram of an exemplary electronic device capable of implementing embodiments of the present invention is shown. DETAILED DESCRIPTION

[0049] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0050] See also Figure 1 The present invention provides the following technical solution: A large-area field concrete construction method based on BIM, comprising the following steps:

[0051] S1. Collect data of the current construction site, and build a BIM model based on the data. Then, based on the established BIM model and the requirements in the drawings, obtain the required quantity of concrete and steel materials required for construction;

[0052] S2. Establish a concrete pouring module. Divide the large area of ​​the field into n different pouring areas according to the shape and size of the field in the BIM model. The staff specifies the pouring sequence and pours according to the pouring data stored in the concrete pouring module. At the same time, the ambient temperature and humidity during the pouring process are collected, and the pouring process is regulated according to the ambient temperature and humidity. At the same time, the concrete curing quality index CI of the i-th pouring area is generated. i , where i∈[1,n];

[0053] Before pouring, the staff will collect the temperature of the day. If the temperature value is higher than the limit threshold temperature, the pouring construction will be stopped on that day. If the temperature value is not higher than the limit threshold temperature, the construction will be carried out.

[0054] Record the ambient temperature of the i-th pouring area at the j-th moment and ambient humidity When the ambient temperature And the ambient humidity When the temperature rises, the spray equipment is started to cool the concrete;

[0055] Concrete curing quality index CI for the i-th area i Calculate the concrete curing quality index CI of the i-th area i The calculation expression is as follows:

[0056]

[0057] in, represents the ambient temperature of the i-th pouring area at the j-th moment, represents the ambient humidity of the i-th pouring area at the j-th time, ω T and ω RHRepresents the weighting factor of temperature and humidity, T lx Indicates the ideal curing temperature, RH lx Indicates ideal maintenance humidity. It means summing up m moments.

[0058] S3. Establish a material management module. When the staff performs construction according to the pouring sequence specified by the staff in the concrete pouring module, the concrete consumption HNT in the pouring process of the i-th area is calculated. i and steel material consumption GJ i After collecting, the material management module is used to calculate the increment of concrete consumption ΔHNT and steel material consumption ΔGJ in all areas poured on that day. The specific expression is as follows:

[0059]

[0060] Among them, ΔHNT represents the increase in the amount of concrete, HNT i represents the amount of concrete used during the pouring of the ith area, HNT i ′ represents the theoretical amount of concrete used during the pouring of the i-th area, k represents the k-th pouring area, l represents the l-th pouring area, l-k+1 represents that a total of l-k+1 areas were poured on that day, and GJ i represents the amount of steel bars used in the pouring process of the i-th area, GJ i ′ It represents the theoretical amount of steel bars used in the pouring process of the i-th area, and ΔGJ represents the increment of the amount of steel bars used. After the calculation is completed, the two increments calculated are judged. If the increments ΔHNT and ΔGJ are non-positive values, no subsequent calculation is performed. If the increments are positive, it means that the amount of concrete and steel bars used on that day exceeds the normal value, and it is necessary to predict the amount of concrete and steel bars used until the end of the construction period.

[0061] The specific expressions for predicting the amount of concrete and steel materials required to be consumed by the end of the construction period are as follows:

[0062]

[0063] Among them, γ HNT and γ GJ They represent the predicted amount of concrete and steel material consumption, ∑* represents the sum of the daily pouring area, Day sy Indicates the remaining days. represents the amount of concrete poured in the i-th area during the initial planning, represents the amount of steel bars used for the i-th area during initial planning, ΔGJ represents the increment of steel bar material usage, and ΔHNT represents the increment of concrete usage

[0064] After the calculation is completed, determine the remaining amount of concrete and steel materials in the inventory KC HNT , KC GJ and the predicted amount γ HNT , γ GJ The relationship between is used to determine whether scheduling is needed. The calculation expression for determining inventory is as follows

[0065] ΔKC HNT =γ HNT -KC HNT

[0066] ΔKC GJ =γ GJ -KC GJ

[0067] Among them, ΔKC HNT and ΔKC GJ Represent the remaining values ​​of concrete and steel bars, γ HNT and γ GJ They represent the predicted amount of concrete and steel material consumption, KC HNT and KC GJ Represent the concrete and steel stocks respectively. If ΔKC HNT >AKC HNT or ΔKC GJ >AKC GJ , no scheduling is performed, AKC HNT and AKC GJ They represent the remaining thresholds of concrete and steel bars respectively, and other situations require corresponding scheduling, thus ensuring sufficient inventory. When the estimated inventory is insufficient, the management personnel are reminded in time;

[0068] S4. After pouring, evaluate the quality of concrete in n different pouring areas, including the number of concrete cracks and flatness. Mark the unqualified areas in the BIM model and give the corresponding reasons for the unqualified areas. At the same time, repair the unqualified pouring areas. The unqualified areas specifically refer to the unqualified crack width, that is, the crack width is greater than 0.3mm. If there are special needs, the staff will limit it by themselves;

[0069] S5. After finishing in step S4, the quality status of n different casting areas is scored. The specific expression for scoring each casting area is as follows:

[0070]

[0071] Among them, FIi represents the score of the i-th pouring area, CI i represents the concrete curing quality index, θ i represents the average inclination angle of concrete in the i-th pouring area, Q represents the initial score, and LF i represents the number of unqualified cracks in the i-th pouring area, and compares the score of the pouring area with the highest quality, max{FI}, with the score corresponding to the pouring data stored in the concrete pouring module. If it is higher than the score corresponding to the pouring data stored in the concrete pouring module, max{FI}>CC FI , where CC FI Indicates the score corresponding to the pouring data stored in the concrete pouring module. The data in the pouring process is replaced into the concrete pouring module. If max{FI}≤CC FI , no processing is done, so as to score the pouring quality of each pouring area, and save the ambient temperature and humidity data of the pouring module with the highest pouring score during the pouring process, as well as the daily usage during the pouring process, to provide data support for subsequent pouring.

[0072] According to an embodiment of the present invention, the present invention also provides an electronic device and a readable storage medium.

[0073] Figure 2 A schematic block diagram of an electronic device that can be used to implement an embodiment of the present invention is shown. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices, and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.

[0074] The electronic device includes a computing unit 201, which can perform various appropriate actions and processes according to a computer program stored in ROM 202 or a computer program loaded from a storage unit 208 into RAM 203. In RAM 203, various programs and data required for the operation of the electronic device can also be stored. The computing unit 201, ROM 202, and RAM 203 are connected to each other via a bus 204. An I / O interface 205 is also connected to the bus 204.

[0075] A number of components in the electronic device are connected to the I / O interface 205, including: an input unit 206, such as a keyboard, a mouse, etc.; an output unit 207, such as various types of displays, speakers, etc.; a storage unit 208, such as a disk, an optical disk, etc.; and a communication unit 209, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 209 allows the electronic device to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.

[0076] The computing unit 201 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the computing unit 201 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various dedicated artificial intelligence (AI) computing chips, various computing units running machine learning model algorithms, digital signal processors (DSPs), and any appropriate processors, controllers, microcontrollers, etc. The computing unit 201 performs the various methods and processes described above. For example, in some embodiments, the large-area field concrete construction method based on BIM may be implemented as a computer software program, which is tangibly contained in a machine-readable medium, such as a storage unit 208. In some embodiments, part or all of the computer program may be loaded and / or installed on an electronic device via ROM 202 and / or a communication unit 209. When the computer program is loaded into RAM 203 and executed by the computing unit 201, one or more steps of the large-area field concrete construction method based on BIM described above may be performed. Alternatively, in other embodiments, the computing unit 201 may be configured to perform the large-area field concrete construction method based on BIM in any other appropriate manner (e.g., by means of firmware).

[0077] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations may include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.

[0078] The program code for implementing the method of the present invention can be written in any combination of one or more programming languages. These program codes can be provided to a processor or controller of a general-purpose computer, a special-purpose computer or other programmable data processing device, so that the program code, when executed by the processor or controller, enables the functions / operations specified in the flow chart and / or block diagram to be implemented. The program code can be executed entirely on the machine, partially on the machine, partially on the machine as a stand-alone software package and partially on a remote machine, or entirely on a remote machine or server.

[0079] In the context of the present invention, a readable storage medium may be a tangible medium that may contain or store a program for use by or in conjunction with an instruction execution system, device, or equipment. A readable storage medium may be a machine-readable signal medium or a machine-readable storage medium. A readable storage medium may include, but is not limited to, an electronic, magnetic, optical, electromagnetic, infrared, or semiconductor system, device, or equipment, or any suitable combination of the foregoing. More specific examples of readable storage media may include electrical connections based on one or more lines, portable computer disks, hard disks, random access memories (RAM), read-only memories (ROM), erasable programmable read-only memories (EPROM or flash memory), optical fibers, portable compact disk read-only memories (CD-ROM), optical storage devices, magnetic storage devices, or any suitable combination of the foregoing.

[0080] To provide interaction with a user, the systems and techniques described herein can be implemented on a computer having: a display device for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the computer. Other types of devices can also be used to provide interaction with the user; for example, the feedback provided to the user can be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user can be received in any form (including acoustic input, voice input, or tactile input).

[0081] The systems and techniques described herein may be implemented in a computing system that includes back-end components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes front-end components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such back-end components, middleware components, or front-end components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communications network). Examples of communications networks include: a local area network (LAN), a wide area network (WAN), and the Internet.

[0082] A computer system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The relationship of client and server is generated by computer programs running on respective computers and having a client-server relationship with each other. The server may be a cloud server, a server of a distributed system, or a server combined with a blockchain.

[0083] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A large-area field concrete construction method based on BIM, characterized in that: include: Collect data of the current construction site and build a BIM model based on the data. Then, based on the established BIM model and the requirements in the drawings, obtain the required quantity of concrete and steel materials required for construction; Establish a concrete pouring module, divide the large area of ​​the field into n different pouring areas according to the shape and size of the field in the BIM model, and let the staff specify the pouring order and pour according to the pouring data stored in the concrete pouring module. At the same time, collect the ambient temperature and humidity during the pouring process, and regulate the pouring process according to the ambient temperature and humidity. At the same time, generate the concrete curing quality index CI of the i-th pouring area i , where i∈[1,n]; Establish a material management module to collect the current usage of concrete and steel materials when the staff are working according to the pouring sequence specified by the staff in the concrete pouring module, and then monitor the remaining and expected quantities of concrete and steel materials in the inventory through the material management module; After pouring, the quality of concrete in n different pouring areas is evaluated, unqualified areas are marked in the BIM model, and the corresponding reasons for unqualified areas are given, and unqualified pouring areas are repaired; After the finishing is completed, the quality status of n different pouring areas is scored, and the score of the pouring area with the highest quality score is compared with the score corresponding to the pouring data stored in the concrete pouring module; if it is higher than the score corresponding to the pouring data stored in the concrete pouring module, the data in this pouring process is replaced in the concrete pouring module.

2. A large-area field concrete construction method based on BIM according to claim 1, characterized in that: The concrete curing quality index CI of the i-th pouring area is generated i ,include: Before pouring, collect the temperature of the day. If the temperature value is higher than the limit threshold temperature, stop pouring construction on that day. If the temperature value is not higher than the limit threshold temperature, proceed with construction. Record the ambient temperature of the i-th pouring area at the j-th moment and ambient humidity When the ambient temperature And the ambient humidity When the temperature rises, the spray equipment is started to cool the concrete; Concrete curing quality index CI for the i-th area i Perform calculations.

3. A large-area field concrete construction method based on BIM according to claim 2, characterized in that: The concrete curing quality index CI of the i-th area i The calculation expression is as follows: in, represents the ambient temperature of the i-th pouring area at the j-th moment, represents the ambient humidity of the i-th pouring area at the j-th time, ω T and ω RH Represents the weighting factor of temperature and humidity, T lx Indicates the ideal curing temperature, RH lx Indicates ideal maintenance humidity. It means summing up m moments.

4. A large-area field concrete construction method based on BIM according to claim 3, characterized in that: The material management module is established to collect the current usage of concrete and steel materials when the staff performs construction according to the pouring sequence specified by the staff in the concrete pouring module, and then monitor the remaining amount and expected amount of concrete and steel materials in the inventory through the material management module, including: The amount of concrete used in the pouring process of the i-th area is HNT i and steel material consumption GJ i to collect; Calculate the increment of concrete consumption ΔHNT and steel material consumption ΔGJ in all areas poured on the day; If the increment of concrete consumption ΔHNT and the increment of steel material consumption ΔGJ are non-positive values, no subsequent calculations will be performed; If the increment of the concrete consumption ΔHNT and / or the increment of the steel material consumption ΔGJ is positive, the consumption of concrete and steel material is predicted until the end of the construction period to obtain the predicted amount of concrete and the predicted amount of steel material respectively; Determine the relationship between the remaining amount of concrete in inventory and the predicted amount of concrete to determine whether scheduling is needed; Determine the relationship between the remaining quantity of steel bar materials in inventory and the predicted quantity of steel bar materials to determine whether scheduling is required.

5. A large-area field concrete construction method based on BIM according to claim 4, characterized in that: The expression for the increment of concrete consumption in all areas is as follows: Among them, ΔHNT represents the increase in the amount of concrete, HNT i represents the amount of concrete used during the pouring of the ith area, HNT i ′ represents the theoretical amount of concrete during the pouring process of the i-th area, k represents the k-th pouring area, l represents the l-th pouring area, and l-k+1 represents that l-k+1 areas were poured on that day.

6. A large-area field concrete construction method based on BIM according to claim 5, characterized in that: The incremental expression of the steel bar material consumption is as follows: Where k represents the kth pouring area, l represents the lth pouring area, l-k+1 represents that a total of l-k+1 areas were poured on that day, GJ i represents the amount of steel bars used in the pouring process of the i-th area, GJ i ′ It represents the theoretical amount of steel bars used during the pouring process of the ith area, and ΔGJ represents the increase in the amount of steel bar material used.

7. A large-area field concrete construction method based on BIM according to claim 6, characterized in that: The expressions for the predicted amount of concrete and the predicted amount of steel bars are: Among them, γ HNT and γ GJ Respectively represent the predicted amount of concrete and steel material, ∑* represents the sum of the daily pouring area, Day sy Indicates the remaining days. represents the amount of concrete poured in the i-th area during the initial planning, It represents the amount of steel bars used for casting the i-th area during initial planning, ΔGJ represents the increment of steel bar material usage, and ΔHNT represents the increment of concrete usage.

8. A large-area field concrete construction method based on BIM according to claim 7, characterized in that: The specific expression for scoring the quality status of n different casting areas is as follows: Among them, FI i represents the score of the i-th pouring area, CI i represents the concrete curing quality index, θ i represents the average inclination angle of concrete in the i-th pouring area, Q represents the initial score, and LF i Represents the number of unqualified cracks in the i-th casting area.

9. An electronic device, characterized in that: It includes a memory and a processor, wherein a computer program is stored in the memory, and when the computer program is executed by the processor, the large-area field concrete construction method based on BIM as described in any one of claims 1 to 8 is executed.

10. A storage medium, characterized in that: The computer program stored in the storage medium can be executed by one or more processors and can be used to implement the BIM-based large-area field concrete construction method as described in any one of claims 1 to 8.

Citation Information

Patent Citations

  • Large-area and super-long food refrigeration house terrace construction method based on BIM (building information model)

    CN107448022A

Cited By

  • Method and system for optimizing standard mix proportion of concrete

    CN120877990A

  • Nanometer embedding tonic wine stabilization method

    CN121506291A

  • Nano-encapsulation method for stabilizing wine

    CN121506291B