Detachable assembly type multipurpose multifunctional PC component lifting frame body tool
By designing the removable assembled multi-purpose multi-function PC component lifting rack tool, the problems of the singularity, low efficiency and insufficient safety of existing prefabricated building lifting technologies and tools are solved, and efficient, safe and multi-functional lifting effects are achieved.
Patent Information
- Application Number
- CN202510206611.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-25
- Publication Date
- 2025-04-29
AI Technical Summary
The existing prefabricated building lifting technologies and tools have problems such as singleness, low efficiency, single lifting types, uneven distribution of sling tension and insufficient safety in bad weather.
A detachable assembled multi-purpose multi-function PC component hoisting tool is designed, including the main frame and a telescopic spreader. The main frame consists of a combined frame single and connecting parts. The telescopic spreader achieves length adjustment through the telescopic hanging long beam and pulley lifting lugs, and is equipped with a damper to deal with strong winds.
It improves lifting efficiency and adaptability to lifting types, ensures the uniform distribution of the sling tension, reduces the risk of swing in bad weather, and improves the efficiency of tool transportation and replacement.
Smart Images

Figure CN119898680A_ABST
Abstract
Description
Technical Field
[0001] The invention discloses a detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool, belonging to the field of assembled building hoisting equipment. Background Art
[0002] In recent years, prefabricated buildings have been used more and more widely as a new type of green construction method, but their lifting technology and lifting tools are not perfect.
[0003] For example, when lifting traditional composite panels, some use steel wire ropes for direct lifting, while others use simple steel poles as lifting tools; the lifting tools are not only single, but can only lift one component at a time, and the entire lifting process is not only time-consuming but also inefficient; secondly, the types of PC components that can be lifted by the lifting tools are relatively single, and some are only suitable for composite panel systems and cannot meet the lifting requirements of other types of PC components.
[0004] Moreover, the current lifting tools have a simple structure, and the tension distribution of the lifting cables is uneven during the lifting process, which can easily lead to defects such as cracks in the composite plates along the length direction during the lifting process. At the same time, when there is a sudden strong wind or a sudden change in the weather, the composite plates will suddenly shake violently during the lifting process. If there is no effective limiting device, it is very easy to cause the risk of falling off. Summary of the invention
[0005] In view of the deficiencies in the prior art, the present invention aims to provide a detachable and assembled multi-purpose and multi-functional PC component lifting frame tool.
[0006] In order to achieve the above object, the present invention is implemented through the following technical solutions: A detachable and assembled multi-purpose and multifunctional PC component lifting frame tool comprises a main frame and two sets of telescopic slings, wherein the two sets of telescopic slings are respectively arranged on both sides of the bottom of the main frame, and the main frame comprises four combined frame monomers and a plurality of connecting pieces, wherein the four combined frame monomers are connected and fixed by the plurality of connecting pieces.
[0007] Furthermore, the combined frame unit includes two short hanger beams and a long hanger beam, the two short hanger beams are arranged on the sides of the long hanger beam, the long hanger beams include a first-layer hanger long beam, a second-layer hanger long beam and a third-layer hanger long beam, the two short hanger beams are fixed on the sides of the first-layer hanger long beam, one end of the first-layer hanger long beam is sleeved with the second-layer hanger long beam, and one end of the second-layer hanger long beam is sleeved with the third-layer hanger long beam.
[0008] Furthermore, the ends of both the first-layer hanger long beam and the hanger short beam are provided with connecting bolt holes, and the ends of the four combined frame monomers are inserted into the connecting piece in groups of two. The connecting piece is provided with a plurality of connecting bolts, and the connecting bolts are locked and fixed with the connecting bolt holes.
[0009] Furthermore, a plurality of adjustment holes are provided on the first-layer hanger long beam, the second-layer hanger long beam and the third-layer hanger long beam, and the first-layer hanging ears, the second-layer hanging ears and the third-layer hanging ears are respectively connected to the adjustment holes on the first-layer hanger long beam, the second-layer hanger long beam and the third-layer hanger long beam by bolts.
[0010] Furthermore, the adjustment hole is also provided on the short beam of the hanger, and a stiffening rib steel plate is connected between the adjustment hole on the short beam of the hanger and the adjustment hole on the long beam of the hanger through a locking bolt, and a reinforcing angle iron is provided at the connection between the stiffening rib steel plate and the locking bolt.
[0011] Furthermore, the first-layer hanger long beam is provided with a main lifting lug, and the third-layer hanger long beam is provided with an anti-collision baffle.
[0012] Furthermore, the telescopic sling includes a first layer sling, a second layer sling and a third layer sling, the first layer sling, the second layer sling and the third layer sling are all composed of a sling long beam and two sling adjustment beams, the two sling adjustment beams are arranged on both sides of the sling long beam, and a plurality of sling adjustment holes are arranged on both the sling long beam and the sling adjustment beam, a pulley ear is connected to the sling adjustment holes on the sling long beam and the sling adjustment beam respectively through a fixing bolt, a first guide pulley is connected to the bottom of the pulley ear on the sling long beam, a lower sling is passed between the pulley ear on the sling adjustment beam and the first guide pulley, a second guide pulley is also arranged on the lower sling, and a hook is arranged at the bottom of the second guide pulley.
[0013] Furthermore, a sling upper lifting ear is respectively provided on the top of the two sling adjustment beams, and a sling connecting piece is connected to the top of the sling upper lifting ear. The sling connecting pieces on the first layer sling, the second layer sling and the third layer sling are respectively connected and fixed to the first layer lifting ear, the second layer lifting ear and the third layer lifting ear.
[0014] Furthermore, a damper is provided on the first guide pulley.
[0015] Furthermore, a flexible protective cover is provided at the end of the sling adjusting beam.
[0016] Beneficial effects of the present invention: The present invention increases the length of the sling's outspread wing through the telescopic hanger beam, improves the vertical space utilization rate, increases the single lifting capacity and lifting efficiency of the PC component hanger, reduces the lifting time, avoids the problem of lengthy outrigger arm beams, reduces the problems of large amounts of frame material and heavy weight, and can be applied to the lifting requirements of various components such as composite panels and prefabricated stairs, and has wide applicability and strong promotion potential.
[0017] The present invention changes the traditional fixing method of the end of the sling, and is equipped with a first guide pulley, a second guide pulley and a damper. When encountering strong winds, the damper can limit the rapid sliding of the sling, and the fine-tuning of the sling during the hoisting process can reduce the shaking degree of the hoisting component, thereby ensuring the safety of the hoisting process and ensuring the uniform distribution of the tension of the sling, thereby reducing the swing problem that may occur when hoisting PC components in severe weather such as strong winds.
[0018] The present invention applies the concept of assemblability and modularization, and its frame components are detachable, which improves the transportation turnover and replacement efficiency of the lifting tools when damaged, and realizes the transportation, turnover and replacement of the lifting frame tools.
[0019] The present invention uses the design of the main frame to adjust the extended length of the hanger long beam according to the difference of the PC components, so that the hoisting equipment can be adapted to different components.
[0020] The present invention adopts a design in which a plurality of combined frame monomers are spliced and connected to form a main frame, thereby facilitating assembly and transportation of the main frame and facilitating use of the main frame.
[0021] The present invention adopts the design of a telescopic sling, so that the length of the sling can be adjusted according to demand, and different numbers of slings can be used according to different PC components to be hoisted. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0023] Figure 1 It is a schematic diagram of the overall structure of a detachable and assembled multi-purpose and multi-functional PC component hoisting frame tool of the present invention; Figure 2 This is a schematic diagram of the main frame structure of a detachable and assembled multi-purpose and multi-functional PC component lifting frame tool of the present invention; Figure 3 It is a schematic diagram of the frame monomer structure of a detachable and assembled multi-purpose and multi-functional PC component hoisting frame tool of the present invention; Figure 4 It is a schematic diagram of the telescopic lifting device structure of a detachable and assembled multi-purpose and multifunctional PC component lifting frame tool of the present invention; Figure 5 It is a structural schematic diagram of a detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool of the present invention when hoisting a composite plate; Figure 6 It is a structural schematic diagram of a detachable and assembled multi-purpose and multi-functional PC component hoisting frame tool of the present invention when hoisting a prefabricated staircase.
[0024] In the figure, 1, main lifting lug; 101, first layer lifting device; 102, second layer lifting device; 103, third layer lifting device; 100, first layer lifting lug; 200, second layer lifting lug; 300, third layer lifting lug; 2, main frame; 3, frame monomer; 4, telescopic lifting device; 5, stiffening rib steel plate; 6, anti-collision baffle; 7, hanger long beam; 701, first layer hanger long beam; 702, second layer hanger long beam; 703, third layer hanger long beam; 8, hanger short beam ; 9. Lifting lug on sling; 10. Lifting lug on pulley; 11. Reinforcement angle iron; 12. Lower sling; 13. Connecting piece; 14. Connecting piece of sling; 15. Adjustment hole of sling; 16. Adjustment hole; 17. Connecting bolt; 18. Prefabricated stairs; 19. Flexible protective cover; 20. Hook; 21. First guide pulley; 22. Second guide pulley; 23. Damper; 24. Long beam of sling; 25. Adjustment beam of sling; 26. Fixing bolt; 27. Composite plate. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0026] See also Figure 1-Figure 6 The present invention provides a technical solution for a detachable and assembled multi-purpose and multifunctional PC component lifting frame tool, comprising a main frame 2 and two groups of telescopic hangers 4, the two groups of telescopic hangers 4 are respectively arranged on both sides of the bottom of the main frame 2, the main frame 2 comprises four combined frame monomers 3 and a plurality of connecting members 13, and the four combined frame monomers 3 are connected and fixed by a plurality of connecting members 13; the present invention increases the length of the hanger's outspread wing through a telescopic hanger long beam, improves the vertical space utilization rate, increases the single lifting capacity of the PC component hanger, avoids the problem of the length of the outrigger arm beam, and reduces the problems of the frame using a lot of materials and heavy weight.
[0027] See also Figure 2-Figure 3The combined frame monomer 3 includes two hanger short beams 8 and a hanger long beam 7. The two hanger short beams 8 are arranged on the side of the hanger long beam 7. The hanger long beam 7 includes a first-layer hanger long beam 701, a second-layer hanger long beam 702 and a third-layer hanger long beam 703. The two hanger short beams 8 are fixed on the side of the first-layer hanger long beam 701. One end of the first-layer hanger long beam 701 is sleeved with the second-layer hanger long beam 702, and one end of the second-layer hanger long beam 702 is sleeved with the third-layer hanger long beam 703. The ends of the first-layer hanger long beam 701 and the hanger short beam 8 are both provided with connecting bolt holes. The ends of the four combined frame monomers 3 are inserted into the connecting piece 13 in groups of two. The connecting piece 13 is provided with a plurality of connecting bolts 17, and the connecting bolts 17 are locked and fixed with the connecting bolt holes. A plurality of adjustment holes 16 are provided on the first-layer hanger long beam 701, the second-layer hanger long beam 702 and the third-layer hanger long beam 703, and the adjustment holes 16 are used to adjust the extension length of the hanger long beam and the fixation between the hanger long beam and the telescopic hanger 4. The first-layer hanger long beam 701, the second-layer hanger long beam 702 and the third-layer hanger long beam 703 are respectively connected with the first-layer lifting ear 100, the second-layer lifting ear 200 and the third-layer lifting ear 300 by bolts in the adjustment holes 16. The present invention can adjust the extension length of the hanger long beam 7 according to the different PC components through the design of the main frame 2, so that the lifting equipment can be adapted to different components. At the same time, the design of the main frame 2 is formed by splicing and connecting a plurality of combined frame monomers 3, so that the main frame 2 can be easily assembled and transported, and the main frame 2 can be used for convenience.
[0028] See also Figure 2-Figure 3 The adjustment hole 16 is also provided on the short beam 8 of the hanger. The adjustment hole 16 on the short beam 8 of the hanger and the adjustment hole 16 on the long beam 7 of the hanger are connected with a stiffening rib steel plate 5 through a locking bolt. The stiffening rib steel plate 5 can improve the overall rigidity and stability of the frame when lifting heavy objects. A reinforcing angle iron 11 is provided at the connection between the stiffening rib steel plate 5 and the locking bolt. The setting of the reinforcing angle iron 11 can prevent damage to the long beam of the hanger due to stress concentration deformation.
[0029] See also Figure 2-Figure 3 The first-layer hanger beam 701 is provided with a main lifting ear 1, and a lifting wire rope is connected to the main lifting ear 1. The third-layer hanger beam 703 is provided with an anti-collision baffle 6. The setting of the anti-collision baffle 6 can prevent collision and play a limiting role when the third-layer hanger beam 703 is retracted.
[0030] See also Figure 4The telescopic sling 4 includes a first-layer sling 101, a second-layer sling 102 and a third-layer sling 103. The first-layer sling 101, the second-layer sling 102 and the third-layer sling 103 are all composed of a sling long beam 24 and two sling adjustment beams 25. The two sling adjustment beams 25 are arranged on both sides of the sling long beam 24. The ends of the sling adjustment beams 25 are provided with flexible protective covers 19. Both the sling long beam 24 and the sling adjustment beams 25 are provided with a plurality of sling adjustment holes 15. The sling adjustment holes 15 on the sling long beam 24 and the sling adjustment beams 25 are respectively connected with a pulley ear 10 through a fixing bolt 26. The bottom of the pulley ear 10 on the sling long beam 24 is connected with a first guide pulley 21. The first guide pulley 21 is provided with A damper 23, a lower sling 12 is passed through between the pulley lifting ear 10 on the sling adjusting beam 25 and the first guide pulley 21, and a second guide pulley 22 is also provided on the lower sling 12, and a hook 20 is provided at the bottom of the second guide pulley 22, and the top of the two sling adjusting beams 25 is respectively provided with a sling upper lifting ear 9, and the top of the sling upper lifting ear 9 is connected with a sling connector 14, and the sling connectors 14 on the first layer sling 101, the second layer sling 102 and the third layer sling 103 are respectively connected and fixed to the first layer lifting ear 100, the second layer lifting ear 200 and the third layer lifting ear 300; through the design of the telescopic sling 4, the length of the sling can be adjusted according to needs, and at the same time, different numbers of slings can be used according to different hoisting PC components.
[0031] When in use, according to the different PC components to be hoisted, the number of the three-layer hanger long beams in the hanger long beam 7 can be selected. When hoisting a prefabricated wall, it is only necessary to connect the hook 20 on the first layer of the hanger 101 with the hoist ring on the prefabricated wall to carry out the hoisting work; when hoisting a prefabricated staircase 18, such as Figure 6 As shown, the hooks 20 on the first-layer sling 101 and the second-layer sling 102 are connected to the rings on the prefabricated stairs 18 to carry out the lifting work; when the composite plate 27 is lifted, as shown in FIG. Figure 5 As shown, the hooks 20 on the first layer of slings 101, the second layer of slings 102 and the third layer of slings 103 are connected to the rings on the composite plate 27 to carry out the lifting work.
[0032] Although this specification is described according to implementation modes, not every implementation mode includes only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool, characterized in that: The invention comprises a main frame (2) and two groups of telescopic slings (4), wherein the two groups of telescopic slings (4) are respectively arranged on both sides of the bottom of the main frame (2), and the main frame (2) comprises four combined frame monomers (3) and a plurality of connecting members (13), and the four combined frame monomers (3) are connected and fixed by the plurality of connecting members (13).
2. A detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool according to claim 1, characterized in that: The combined frame monomer (3) comprises two short hanger beams (8) and a long hanger beam (7), the two short hanger beams (8) being arranged on the sides of the long hanger beam (7), the long hanger beam (7) comprising a first-layer long hanger beam (701), a second-layer long hanger beam (702) and a third-layer long hanger beam (703), the two short hanger beams (8) being fixed on the sides of the first-layer long hanger beam (701), one end of the first-layer long hanger beam (701) being sleeved with the second-layer long hanger beam (702), and one end of the second-layer long hanger beam (702) being sleeved with the third-layer long hanger beam (703).
3. The detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool according to claim 2, characterized in that: The ends of the first-layer hanger long beam (701) and the hanger short beam (8) are both provided with connecting bolt holes, and the ends of the four combined frame monomers (3) are inserted into the connecting piece (13) in groups of two, and the connecting piece (13) is provided with a plurality of connecting bolts (17), and the connecting bolts (17) are locked and fixed with the connecting bolt holes.
4. The detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool according to claim 2, characterized in that: A plurality of adjustment holes (16) are provided on the first-layer hanger long beam (701), the second-layer hanger long beam (702) and the third-layer hanger long beam (703), and a first-layer lifting ear (100), a second-layer lifting ear (200) and a third-layer lifting ear (300) are respectively connected to the adjustment holes (16) on the first-layer hanger long beam (701), the second-layer hanger long beam (702) and the third-layer hanger long beam (703) by bolts.
5. The detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool according to claim 4, characterized in that: The adjustment hole (16) is also provided on the hanger short beam (8), and a stiffening rib steel plate (5) is connected between the adjustment hole (16) on the hanger short beam (8) and the adjustment hole (16) on the hanger long beam (7) via a locking bolt, and a reinforcing angle iron (11) is provided at the connection between the stiffening rib steel plate (5) and the locking bolt.
6. The detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool according to claim 2, characterized in that: The first-layer hanger long beam (701) is provided with a main lifting lug (1), and the third-layer hanger long beam (703) is provided with an anti-collision baffle (6).
7. The detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool according to claim 4, characterized in that: The telescopic sling (4) comprises a first-layer sling (101), a second-layer sling (102) and a third-layer sling (103); the first-layer sling (101), the second-layer sling (102) and the third-layer sling (103) are all composed of a sling long beam (24) and two sling adjustment beams (25); the two sling adjustment beams (25) are arranged on both sides of the sling long beam (24); a plurality of sling adjustment holes (15) are arranged on both the sling long beam (24) and the sling adjustment beam (25); the sling long beam (24) and the sling adjustment beam (25) are each provided with a plurality of sling adjustment holes (1 ... 4) and the sling adjustment hole (15) on the sling adjustment beam (25) are respectively connected to a pulley eye (10) through a fixing bolt (26); the bottom of the pulley eye (10) on the sling long beam (24) is connected to a first guide pulley (21); a lower sling (12) is passed between the pulley eye (10) on the sling adjustment beam (25) and the first guide pulley (21); a second guide pulley (22) is also provided on the lower sling (12); and a hook (20) is provided at the bottom of the second guide pulley (22).
8. The detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool according to claim 7, characterized in that: A sling upper lifting ear (9) is respectively provided at the top of the two sling adjustment beams (25), and a sling connecting piece (14) is connected to the top of each sling upper lifting ear (9); the sling connecting pieces (14) on the first layer sling (101), the second layer sling (102) and the third layer sling (103) are respectively connected and fixed to the first layer lifting ear (100), the second layer lifting ear (200) and the third layer lifting ear (300).
9. The detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool according to claim 7, characterized in that: A damper (23) is provided on the first guide pulley (21).
10. The detachable and assembled multi-purpose and multifunctional PC component hoisting frame tool according to claim 7, characterized in that: A flexible protective cover (19) is provided at the end of the sling adjusting beam (25).