Modularized steel structure house and assembly process

Through the design of modular steel structure houses, using nodes I and node II for horizontal and vertical assembly, the construction difficulty and accuracy of existing modular houses is solved, and flexible changes in buildings and large-scale applications are achieved.

CN119900344AInactive Publication Date: 2025-04-29HEFEI ROYALSTAR ELECTRONIC APPLIANCE GROUP CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411903534.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-23
Publication Date
2025-04-29
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Due to the complex structure of the connecting nodes, the cumbersome construction process, and the assembly accuracy of the steel structure skeleton is affected by the construction accuracy, the difficulty of on-site construction has increased and limited the large-scale application of modular houses.

Method used

The design of a modular steel structure house is adopted, including modules A, module B, module C, and module D for horizontal and vertical assembly through nodes I and node II. The modular design allows the building to flexibly change according to needs and adapt to different spatial needs and functional requirements.

Benefits of technology

Through modular design and standardized connection methods, the construction process is simplified, the assembly speed and efficiency are improved, the risks and complexity of on-site construction are reduced, and it is suitable for a variety of space requirements and functional requirements, achieving large-scale applications.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119900344A_ABST
    Figure CN119900344A_ABST
Patent Text Reader

Abstract

The modular steel structure house comprises a plurality of modules A, a plurality of modules B, a plurality of modules C and a plurality of modules D. The upper, lower, left and right adjacent modules A are assembled through a node I and a node II, and the modules B are assembled with the modules A through the node I and the node II. The module C is assembled with the module A and the module B through the node I and the node II, the module D is assembled with the module C through the node I and the node II, the module A, the module B, the module C and the module D are single use spaces, and the module A, the module B, the module C and the module D are horizontally and vertically assembled or independently used; the whole building is split into a plurality of modules A, B, C and D according to different functions, the building is allowed to be flexibly changed according to use requirements and can be freely combined horizontally and vertically, more design choices are provided, diversified building forms are met, and the building assembly efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steel structure assembly buildings, in particular to a modular steel structure house and an assembly process. Background Art

[0002] Traditional concrete structure house construction requires a lot of on-site pouring and long-term high-altitude work. Compared with concrete, steel structure has better tensile and earthquake resistance and short construction period. Modular prefabricated building system has great potential for factory and mechanization.

[0003] In the related technology, modular steel structure smart house is a movable and reusable building product, also known as modular house or container house. Steel structure modular smart house refers to the house body adopting steel frame structure system. The steel frame structure system is composed of frame beams and columns to resist vertical and horizontal loads. By dividing the components of the house into different functional modules, modular, standardized and universal production is used to achieve factory manufacturing. The house can be assembled on site anytime and anywhere, and the whole assembly process is more convenient and quick. With the advancement of technology and the increase in people's demand for modular houses, modular houses themselves are also developing, and modular houses with various functional designs have appeared on the market.

[0004] The existing modular houses have complex connection node structures and cumbersome construction procedures. In addition, the assembly accuracy of the steel structure skeleton is affected by the construction accuracy at the assembly site, which increases the difficulty of on-site construction and limits the large-scale application of modular houses. Therefore, most of the existing modular houses are single structures. The design of modular houses is generally a single room or only one floor. This type of modular house is difficult to accommodate a large number of people, so it also limits the development and application scenarios of modular houses. Summary of the invention

[0005] The object of the present invention is to provide a modular steel structure house and an assembly process to solve the problems raised in the above background technology.

[0006] To achieve the above object, the present invention provides the following technical solution: a modular steel structure house, comprising a plurality of modules A, wherein the modules A are arranged in a plurality of numbers, and the upper, lower, left and right adjacent modules A are assembled through nodes I and II;

[0007] Module B, wherein the module B is assembled with the module A via nodes I and II;

[0008] Module C, wherein the module C is assembled with the module A and the module B via the node I and the node II;

[0009] Module D, wherein the module D is assembled with the module C via nodes I and II;

[0010] The modules A, B, C and D are monomer frames of modular steel structure houses. The modules A, B, C and D are assembled horizontally and vertically based on nodes I and II to form modular steel structure houses, or the modules A, B, C and D are used separately. The modules are flexible and convenient to use and can meet different building requirements.

[0011] Furthermore, the modules A, B, C, and D are all assembled from a plurality of first steel components and second steel components. The steel has good plasticity and toughness and can absorb a large amount of energy, so that the modules A, B, C, and D exhibit good seismic performance. The steel structure has high strength and light weight, is easy to transport and install, and is suitable for large-span, high-height, and heavy-load-bearing structural buildings.

[0012] Furthermore, the module A is optionally equipped with a fence, and whether to use the fence can be determined based on demand. If the top space of the module A needs to be utilized, it is safer to stand on the module A.

[0013] Furthermore, a ladder frame is fixedly connected inside the module B. When the modules A, B, C and D are assembled into a multi-story building, the built-in ladder frame can be used to go upstairs without building stairs, and the building assembly speed is fast.

[0014] Furthermore, the node I includes a T-shaped plate, a first upper vertical plate, and a first lower vertical plate, and the first upper vertical plate and the first lower vertical plate are respectively fixedly connected to the upper and lower surfaces of the T-shaped plate, and the surfaces of the T-shaped plate, the first upper vertical plate, and the first lower vertical plate are all provided with a first elliptical bolt hole.

[0015] The node II includes a cross plate, a second upper vertical plate, and a second lower vertical plate, and the second upper vertical plate and the second lower vertical plate are respectively fixedly connected to the upper and lower surfaces of the cross plate, and the surfaces of the cross plate, the second upper vertical plate, and the second lower vertical plate are all provided with second elliptical bolt holes.

[0016] A first reinforcing rib is fixedly connected between the first upper vertical plate and the first lower vertical plate and the T-shaped plate, and a second reinforcing rib is fixedly connected between the second upper vertical plate and the second lower vertical plate and the cross plate;

[0017] By fixedly connecting the first upper vertical plate and the first lower vertical plate to the T-shaped plate, and fixedly connecting the second upper vertical plate and the second lower vertical plate to the cross plate, the stability of the node and the rigidity of the overall structure are enhanced. The provision of the first reinforcing rib and the second reinforcing rib can significantly improve the bearing capacity of the node, especially when subjected to shear force and bending moment. The design of the first elliptical bolt hole and the second elliptical bolt hole allows the bolt to adjust its position within a certain range, which helps to align the hole position during installation and improve the reliability and flexibility of the connection. The provision of the reinforcing rib helps to disperse stress and reduce local stress concentration, thereby improving the durability and service life of the steel structure house.

[0018] An assembly process for a modular steel structure house comprises the following steps:

[0019] Step 1, planning drawings: prepare the first steel member, second steel member, node I and node II that meet the requirements;

[0020] Step 2: prefabrication: select a number of first steel members, second steel members, nodes I and II and prefabricate them into a number of modules A, modules B, modules C and modules D;

[0021] Step 3, transportation: transport the spare first steel member, the second steel member, node I, node II, module A, module B, module C, and module D to the assembly site;

[0022] Step 4: Foundation treatment: Place modules A, B, C and D on a solid and level foundation and level them;

[0023] Step 5: Assembly: Based on step 1, several modules A, B, C, and D are assembled horizontally and vertically into a building.

[0024] When prefabricating module A, module B, module C, and module D based on the planning drawings, the bottom surface of module A or module C or module D assembled above module B is an open structure; the fence is fixedly connected to the surface of prefabricated module A based on the needs;

[0025] Prefabricated modules can be manufactured in advance in a factory environment, reducing on-site construction time and improving construction efficiency. Since most of the work is completed in the factory, the workload on site is reduced, thereby reducing the risk and complexity of on-site construction.

[0026] Compared with the prior art, the present invention has the following beneficial effects:

[0027] (1) The building is divided into several modules A, B, C, and D according to different functions, allowing the building to change flexibly according to usage needs and adapt to different spatial needs and functional requirements.

[0028] (2) Modules A, B, C, and D can be freely combined horizontally and vertically, providing more design options, meeting diverse architectural forms, and flexibly adapting to a variety of space requirements.

[0029] (3) Assembling the building based on module A, module B, module C, and module D reduces the number of single components, can reduce material costs and manufacturing costs, and improve the efficiency of building assembly. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a structural schematic diagram of module A of the present invention;

[0031] Figure 2 It is a structural schematic diagram of module B of the present invention;

[0032] Figure 3 It is a structural schematic diagram of module C of the present invention;

[0033] Figure 4 It is a structural schematic diagram of module D of the present invention;

[0034] Figure 5 It is a structural schematic diagram of node I of the present invention;

[0035] Figure 6 It is a structural schematic diagram of node II of the present invention;

[0036] Figure 7 It is a schematic diagram of the overall structure of the building of the present invention.

[0037] In the figure: 1. first upper vertical plate; 2. first elliptical bolt hole; 3. T-shaped plate; 4. first reinforcing rib; 5. first lower vertical plate; 6. second elliptical bolt hole; 7. second upper vertical plate; 8. second reinforcing rib; 9. cross plate; 10. second lower vertical plate; 12. first steel member; 13. second steel member; 100. module A; 101. fence; 200. module B; 201. ladder frame; 300. module C; 400. module D; 500. overall building; 600. node I; 700. node II. DETAILED DESCRIPTION

[0038] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0039] Example:

[0040] See also Figure 1-7 The present invention provides a technical solution: a modular steel structure house, including a module A100, wherein a plurality of modules A100 are provided, and the upper, lower, left, and right adjacent modules A100 are assembled through nodes I600 and II700, and the modules A100 can be used as a single building or connected to each other to meet the living requirements and storage needs of different numbers of people;

[0041] Module B200, the module B200 is assembled with module A100 through node I 600 and node II 700, and a ladder frame 201 is fixedly connected inside the module B200. When the whole building has more than two floors, the ladder frame 201 of the module B200 can be used to go up to the second floor. The modular ladder frame 201 reduces the workload of on-site construction because the ladder frame 201 as a part of the module B200 has been prefabricated in the factory, which speeds up the completion of the whole building;

[0042] Module C300, the module C300 is assembled with module A100 and module B200 via node I 600 and node II 700;

[0043] Module D400, the module D400 is assembled with module C300 via node I 600 and node II 700;

[0044] The modules A100, B200, C300 and D400 are monomer frames of modular steel structure houses. The modules A100, B200, C300 and D400 are assembled horizontally and vertically into modular steel structure houses based on nodes I600 and II700, or the modules A100, B200, C300 and D400 are used independently. The independent use is for single rooms, which is convenient for single use of the space inside the modules A100, B200, C300 and D400.

[0045] Using unified nodes Ⅰ600 and Ⅱ700 to connect modules can ensure the stability and consistency of the entire structure. The modular and standardized connection method simplifies the construction process and speeds up assembly. The modular structure design can better disperse vibration forces and improve the seismic performance of the building. The components of the modular structure can be more easily recycled and reused, which improves the utilization rate of steel.

[0046] In this embodiment, if Figures 1 to 6 As shown, the module A100, module B200, module C300, and module D400 are all assembled from a plurality of first steel components 12 and second steel components 13, and the first steel components 12 and the second steel components 13 are obtained by cutting, and fasteners and welding technology are used to form the stable modules A100, module B200, module C300, and module D400, which are safer to live in and have a high bearing capacity.

[0047] In this embodiment, if Figure 1 As shown, the module A100 is optionally equipped with a fence 101. When there is no obstruction above the module A100, the fence 101 can be fixed to the module A100 as needed. When standing on the module A100, it is safer and will not fall off the module A100.

[0048] In this embodiment, if Figure 5 As shown, the node Ⅰ600 includes a T-shaped plate 3, a first upper vertical plate 1, and a first lower vertical plate 5, and the first upper vertical plate 1 and the first lower vertical plate 5 are fixedly connected to the upper and lower surfaces of the T-shaped plate 3 respectively. The surfaces of the T-shaped plate 3, the first upper vertical plate 1, and the first lower vertical plate 5 are all provided with a first elliptical bolt hole 2. Fasteners are used to cooperate with the first elliptical bolt hole 2 to form the first steel member 12 and the second steel member 13 and the module A100, module B200, module C300, and module D400. The modules A100, module B200, module C300, and module D400 can also be assembled together.

[0049] In this embodiment, if Figure 6 As shown, the node II 700 includes a cross plate 9, a second upper vertical plate 7, and a second lower vertical plate 10, and the second upper vertical plate 7 and the second lower vertical plate 10 are respectively fixedly connected to the upper and lower surfaces of the cross plate 9, and the surfaces of the cross plate 9, the second upper vertical plate 7, and the second lower vertical plate 10 are all provided with second elliptical bolt holes 6. The functions of the node II 700 and the node I 600 are similar. The node II 700 can connect the first steel members 12 and the second steel members 13 in six directions, and is suitable for use in the middle position of the building as a whole 500.

[0050] In this embodiment, if Figure 5 and Figure 6 As shown, the first reinforcing rib 4 is fixedly connected between the first upper vertical plate 1 and the first lower vertical plate 5 and the T-shaped plate 3, and the second reinforcing rib 8 is fixedly connected between the second upper vertical plate 7 and the second lower vertical plate 10 and the cross plate 9, so as to improve the structural strength of the node II 700 and the node I 600. Not only the structural strength of the module A 100, the module B 200, the module C 300 and the module D 400 is stable, but also the whole building 500 is stable.

[0051] An assembly process for a modular steel structure house comprises the following steps:

[0052] Step 1, planning drawings: prepare the first steel member 12, the second steel member 13, the node I 600, and the node II 700 that meet the requirements;

[0053] Step 2, prefabrication: select a number of first steel members 12, second steel members 13, nodes I 600, and nodes II 700 to prefabricate into a number of modules A 100, modules B 200, modules C 300, and modules D 400;

[0054] Step 3, transportation: transport the spare first steel member 12, the second steel member 13, the node I 600, the node II 700, the module A 100, the module B 200, the module C 300, and the module D 400 to the assembly site;

[0055] Step 4: Foundation treatment: Place module A100, module B200, module C300, and module D400 on a solid and level foundation and level them;

[0056] Step five, assembly: based on step one, several modules A100, module B200, module C300, and module D400 are assembled horizontally and vertically into a building 500.

[0057] When prefabricating module A100, module B200, module C300, and module D400 based on the planning drawings, the bottom surface of module A100 or module C300 or module D400 assembled above module B200 is an open structure; the fence 101 is fixedly connected to the surface of the prefabricated module A100 based on demand.

[0058] Step 1: Planning drawings

[0059] Design Review: Ensures all design drawings comply with building codes and safety standards.

[0060] Material selection: Choose the right steel and other materials to ensure they meet strength and durability requirements.

[0061] Component design: Detailed design of the structure and dimensions of the first steel component 12, the second steel component 13, node I600, node II700, and module A100, module B200, module C300, and module D400.

[0062] Module function planning: According to the use requirements of the building, plan the functions of each module. For example, module A100 may be a living space, module B200 may be a staircase, module C300 may be a storage space, module D400 may be a bathroom, etc., without any restrictions.

[0063] Step 2: Prefabrication

[0064] Component manufacturing: In a factory environment, the first steel component 12, the second steel component 13, the node I 600, and the node II 700 are manufactured according to the design drawings.

[0065] Module assembly: Use the manufactured first steel member 12 and the second steel member 13 to assemble into module A100, module B200, module C300, and module D400.

[0066] Quality inspection: Perform quality inspection on each module A100, module B200, module C300, and module D400 to ensure that they meet the design requirements.

[0067] Module identification: Each module is identified for easy identification during transportation and assembly.

[0068] Step 3: Transportation

[0069] Transportation Plan: Develop a detailed transportation plan to ensure that all modules and components are transported to the assembly site safely and efficiently.

[0070] Protective measures: Take necessary protective measures to prevent damage to the module during transportation.

[0071] Step 4: Ground treatment

[0072] Foundation preparation: Clean and level the foundation to make sure it is solid and level.

[0073] Foundation reinforcement: If necessary, perform foundation reinforcement to support the weight of the modular structure.

[0074] Step 5: Assembly

[0075] Module positioning: According to the planning drawings, place module A100, module B200, module C300, and module D400 in the correct positions.

[0076] Horizontal and vertical combination: Based on node I 600 and node II 700, module A 100, module B 200, module C 300, and module D 400 are horizontally and vertically combined into a building entity 500.

[0077] Structural Inspection: During assembly, the alignment and stability of the structure are checked regularly.

[0078] Fence 101 installation: According to the requirements, the fence 101 is fixedly connected to the surface of the prefabricated module A100 to increase the safety of the module A100.

[0079] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A modular steel structure house, characterized in that: include: Module A (100), wherein a plurality of modules A (100) are provided, and adjacent modules A (100) are assembled via nodes I (600) and II (700) in the upper, lower, left, and right directions; Module B (200), wherein module B (200) is assembled with module A (100) via node I (600) and node II (700); Module C (300), wherein the module C (300) is assembled with the module A (100) and the module B (200) via the node I (600) and the node II (700); Module D (400), wherein the module D (400) is assembled with the module C (300) via the node I (600) and the node II (700); Module A (100), module B (200), module C (300), and module D (400) are assembled horizontally and vertically based on node I (600) and node II (700) to form a modular steel structure house.

2. A modular steel structure house according to claim 1, characterized in that: The module A (100), module B (200), module C (300), and module D (400) are all assembled from a plurality of first steel components (12) and second steel components (13).

3. The modular steel structure house according to claim 1, characterized in that: The module A (100) is optionally equipped with a fence (101).

4. The modular steel structure house according to claim 1, characterized in that: The module B (200) is internally fixedly connected with a ladder frame (201).

5. The modular steel structure house according to claim 1, characterized in that: The node I (600) comprises a T-shaped plate (3), a first upper vertical plate (1), and a first lower vertical plate (5), wherein the first upper vertical plate (1) and the first lower vertical plate (5) are respectively fixedly connected to the upper and lower surfaces of the T-shaped plate (3), and the surfaces of the T-shaped plate (3), the first upper vertical plate (1), and the first lower vertical plate (5) are all provided with first elliptical bolt holes (2).

6. The modular steel structure house according to claim 5, characterized in that: The node II (700) comprises a cross plate (9), a second upper vertical plate (7), and a second lower vertical plate (10), and the second upper vertical plate (7) and the second lower vertical plate (10) are respectively fixedly connected to the upper and lower surfaces of the cross plate (9), and the surfaces of the cross plate (9), the second upper vertical plate (7), and the second lower vertical plate (10) are all provided with second elliptical bolt holes (6).

7. The modular steel structure house according to claim 6, characterized in that: A first reinforcing rib (4) is fixedly connected between the first upper vertical plate (1) and the first lower vertical plate (5) and the T-shaped plate (3), and a second reinforcing rib (8) is fixedly connected between the second upper vertical plate (7) and the second lower vertical plate (10) and the cross plate (9).

8. An assembly process for a modular steel structure house according to any one of claims 1 to 7, characterized in that: The following steps are involved: Step 1, planning drawings: prepare the first steel member (12), the second steel member (13), the node I (600), and the node II (700) that meet the requirements; Step 2, prefabrication: select a plurality of first steel members (12), a second steel member (13), a node I (600), and a node II (700) to prefabricate into a plurality of modules A (100), a module B (200), a module C (300), and a module D (400); Step 3, transportation: transporting the spare first steel member (12), the second steel member (13), the node I (600), the node II (700), the module A (100), the module B (200), the module C (300), and the module D (400) to the assembly site; Step 4: foundation treatment: place module A (100), module B (200), module C (300), and module D (400) on a solid and level foundation and level them; Step 5: Assembling: Based on step 1, several modules A (100), module B (200), module C (300), and module D (400) are assembled horizontally and vertically into a building (500).

9. The assembly process of a modular steel structure house according to claim 8, characterized in that: When prefabricating module A (100), module B (200), module C (300), and module D (400) based on the planning drawings, the bottom surface of module A (100) or module C (300) or module D (400) assembled on the top of module B (200) is an open structure; and the fence (101) is fixedly connected to the surface of the prefabricated module A (100) based on the needs.

Citation Information

Patent Citations

  • Modular multi-storeyed overall assembly type steel structural house structure system

    CN106592755A

  • Connecting joint applied to modularized steel structure building

    CN106948483A

  • Box-type house permanent module beam-column joint with cross-shaped steel plate and installation method thereof

    CN110820936A

  • Interlocking installation joint between steel structure module building modules and installation method thereof

    CN118390674A

  • System for architectural modular building construction

    US20230145279A1