Hoisting transportation method for completed basement
By setting up temporary lifting structures and support platforms in the completed basement, large equipment is transported layer by layer, and the problem of misalignment of basement lifting openings is solved, achieving safe transportation of equipment and improving construction efficiency.
Patent Information
- Application Number
- CN202510332255.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-20
- Publication Date
- 2025-05-30
AI Technical Summary
In the completed multi-floor basement, the lifting openings reserved for the base plates of some floors are dislocated, resulting in the inability of traditional lifting equipment to cover all lifting openings, and it is difficult to directly lift and transport large equipment to the target floor.
A lifting and transportation method for completed basements is proposed. By setting up a temporary lifting structure and a temporary support platform, the target equipment is hoisted and transported layer by layer to the uppermost transitional floor base, and then transported horizontally to the next floor using the temporary lifting structure until the target floor is reached.
It effectively solved the problem of misalignment of lifting openings in completed basements, achieved safe and secure lifting and transport of large-scale equipment to the target floor, simplified the transportation process and improved construction efficiency.
Smart Images

Figure CN120057791A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the technical field of hoisting construction, and particularly relates to a hoisting and transportation method for a completed basement. Background Art
[0002] In the related art, there are situations where large equipment needs to be hoisted and transported to the basement. For example, a chiller is hoisted and transported to the target floor in the basement. Specifically, most of the air-conditioning main engine rooms in public buildings are located in the basement, and the chiller needs to be installed in the air-conditioning main engine room. Among them, the weight of the chiller is about 10 tons at the lightest and can reach 20 tons at the heaviest. Therefore, most chillers are hoisted and transported to the basement through the reserved hoisting openings, and after the installation of the chiller and related equipment is completed, the reserved hoisting openings are closed.
[0003] However, for a completed multi-floor basement, there is a situation where the reserved hoisting openings on the floor slabs of at least some floors are misaligned with each other, resulting in that traditional hoisting equipment such as cranes (truck cranes, crawler cranes, and tire cranes) cannot cover all the hoisting openings, that is, large equipment cannot be directly hoisted and transported to the target floor in the basement, which brings difficulties to the transportation process of large equipment. Summary of the Invention
[0004] This application aims to solve at least one of the technical problems existing in the prior art. For this purpose, this application proposes a hoisting and transportation method for a completed basement, which can cope with the situation where the reserved hoisting openings on the floor slabs of each floor of the completed basement are misaligned with each other when hoisting and transporting large equipment into the completed basement.
[0005] According to the hoisting and transportation method for a completed basement in an embodiment of this application, the floor slab of the floor where the hoisting opening is misaligned relative to the floor slab of the upper floor is the transition floor slab for transferring the target equipment. The target equipment is hoisted and transported to the uppermost transition floor slab by a crane. Among them, the following steps are further included:
[0006] S1. Before or after the crane lifts the target equipment, a temporary hoisting structure is set on the floor slab of the upper floor of the current transition floor slab directly above the hoisting opening on the current transition floor slab, and a temporary support platform for temporarily bearing the target equipment is set on the floor slab of the lower floor of the current transition floor slab corresponding to the hoisting opening on the current transition floor slab;
[0007] S2. Horizontally transport the target equipment to the temporary support platform, and use the temporary hoisting structure to lift the target equipment;
[0008] S3. Remove the temporary support platform, and use the temporary hoisting structure to hoist and transport the target equipment to the floor slab of the lower floor of the current transition floor slab.
[0009] The hoisting and transportation method for a completed basement according to the embodiments of the present application has at least the following beneficial effects: When hoisting and transporting large equipment into a completed basement, the hoisting and transportation method for a completed basement according to the embodiments of the present application can handle the situation where the hoisting openings reserved on the floor slabs of each floor of the completed basement are misaligned with each other.
[0010] According to some embodiments of the present application, the following steps are further included:
[0011] If the floor slab of the lower floor of the current transition floor slab in step S3 is the target floor slab, after hoisting and transporting the target equipment to the floor slab of the lower floor of the current transition floor slab by using the temporary hoisting structure, horizontally transport the target equipment to the equipment foundation preset on the target floor slab for installing the target equipment;
[0012] If the floor slab of the lower floor of the current transition floor slab in step S3 is still a transition floor slab, after hoisting and transporting the target equipment to the floor slab of the lower floor of the current transition floor slab by using the temporary hoisting structure, continue to transfer the target equipment according to the methods of steps S1 to S3 until the target equipment is transported to the target floor slab, and then horizontally transport the target equipment to the equipment foundation preset on the target floor slab for installing the target equipment.
[0013] According to some embodiments of the present application, before hoisting and transporting the target equipment to any transition floor slab, a detachable temporary support structure is provided below the transition floor slab that will temporarily bear the target equipment.
[0014] According to some embodiments of the present application, the temporary support structure includes a first top supporting member and a first bracket provided at the bottom of the first top supporting member. The first top supporting member is used to support the transition floor slab, and the first bracket is used to support the first top supporting member.
[0015] According to some embodiments of the present application, the target equipment is horizontally transported by a floor tank.
[0016] According to some embodiments of the present application, when horizontally transporting the target equipment, an electric hoist is used to assist in transporting the target equipment.
[0017] According to some embodiments of the present application, the temporary support platform includes a second top supporting member and a second bracket provided at the bottom of the second top supporting member. The second top supporting member is used to bear the target equipment, and the second bracket is used to support the second top supporting member.
[0018] According to some embodiments of the present application, the second top support is a channel steel, and the second top support extends along the horizontal transportation direction of the target device, so that the second top support can serve as a guide rail for the ground tank when horizontally transporting the target device.
[0019] According to some embodiments of the present application, the second bracket includes a plurality of vertical support members and a plurality of intermediate connecting members. The vertical support members are used to support the second top support, the intermediate connecting members are detachably connected to the vertical support members, and the intermediate connecting members are used to connect and fix the plurality of vertical support members.
[0020] According to some embodiments of the present application, the temporary hoisting structure uses an electric hoist. Among them, the temporary hoisting structure includes a flexible connecting member, a first support member, and a second support member. A plurality of through holes are opened on the upper floor bottom plate of the current transition floor. Two mutually close first support members are placed corresponding to the through holes on the upper floor bottom plate of the current transition floor. A second support member is placed on the two first support members together. The flexible connecting member is passed through the through holes. One end of the flexible connecting member passes through the gap between the corresponding two first support members and is connected to the corresponding second support member, and the other end of the flexible connecting member hangs the electric hoist.
[0021] Additional aspects and advantages of the present application will be given in part in the following description, become apparent in part from the following description, or be learned through the practice of the present application. Description of the Drawings
[0022] The above and / or additional aspects and advantages of the present application will become apparent and easy to understand from the description of the embodiments in conjunction with the following drawings, wherein:
[0023] Figure 1 is a schematic flowchart of a hoisting and transportation method for a completed basement according to an embodiment of the present application;
[0024] Figure 2 is a schematic structural diagram when a crane hoists and transports a target device to the upper most transition floor bottom plate according to an embodiment of the present application;
[0025] Figure 3 is a schematic structural diagram when the target device is horizontally transported to a temporary support platform according to an embodiment of the present application;
[0026] Figure 4 is a schematic structural diagram when the temporary hoisting structure hoists the target device according to an embodiment of the present application;
[0027] Figure 5 is a schematic structural diagram after removing the temporary support platform according to an embodiment of the present application;
[0028] Figure 6 It is a schematic structural diagram when a target device is hoisted and transported to the floor slab of the lower floor of the transition floor slab by using a temporary hoisting structure in an embodiment of the present application;
[0029] Figure 7 It is a schematic structural diagram when the target device is horizontally transported to the equipment foundation preset on the target floor slab for installing the target device in an embodiment of the present application;
[0030] Figure 8 It is a view direction perpendicular to Figure 2 at this time Figure 2 a partial structural schematic diagram of the structure shown;
[0031] Figure 9 It is Figure 8 a partial enlarged schematic diagram at position A in
[0032] Reference numerals:
[0033] Hoisting opening a, target device b, ground tank c, electric hoist d, through hole e;
[0034] Transition floor slab 100;
[0035] Temporary hoisting structure 200, flexible connecting member 210, first support member 220, second support member 230;
[0036] Temporary support platform 300, second top supporting member 310, vertical support member 320, connecting portion 321, intermediate connecting member 330;
[0037] Temporary support structure 400, first top supporting member 410, first bracket 420. Detailed implementation manners
[0038] The embodiments of the present application will be described in detail below. Examples of the embodiments are shown in the drawings, where the same or similar reference numerals denote the same or similar elements or elements having the same or similar functions from beginning to end. The embodiments described below with reference to the drawings are exemplary and are only used to explain the present application, and should not be construed as a limitation to the present application.
[0039] In the description of the present application, it should be understood that if the orientation description is involved, such as the orientation or positional relationship indicated by up, down, front, back, left, right, etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation to the present application.
[0040] In the description of the present application, if words such as several, greater than, less than, exceeding, above, below, within, etc. appear, among them, the meaning of several is one or more, the meaning of multiple is more than two, greater than, less than, exceeding, etc. are understood as not including the present number, and above, below, within, etc. are understood as including the present number.
[0041] In the description of the present application, if words such as first, second, etc. appear, they are only used for the purpose of distinguishing technical features and cannot be understood as indicating or implying relative importance or implicitly indicating the quantity of the indicated technical features or implicitly indicating the sequence relationship of the indicated technical features.
[0042] In the description of the present application, unless otherwise clearly defined, words such as set, install, connect, etc. should be understood in a broad sense, and those skilled in the art can reasonably determine the specific meaning of the above words in the present application in combination with the specific content of the technical solution.
[0043] Refer to Figures 1 to 9 According to the hoisting and transportation method for a completed basement according to an embodiment of the present application, the floor slab of the floor where the hoisting opening a is misaligned relative to the floor slab of the upper floor is the transition floor slab 100 for transporting the target equipment b. The target equipment b is hoisted and transported to the uppermost transition floor slab 100 by a crane. Among them, the following steps are further included:
[0044] S1. Before or after the crane hoists the target equipment b, a temporary hoisting structure 200 is set on the upper floor slab of the current transition floor slab 100 directly above the hoisting opening a on the current transition floor slab 100, and a temporary support platform 300 for temporarily bearing the target equipment b is set on the lower floor slab of the current transition floor slab 100 corresponding to the hoisting opening a on the current transition floor slab 100;
[0045] S2. Horizontally transport the target equipment b to the temporary support platform 300, and use the temporary hoisting structure 200 to hoist the target equipment b;
[0046] S3. Remove the temporary support platform 300, and use the temporary hoisting structure 200 to hoist and transport the target equipment b to the lower floor slab of the current transition floor slab 100.
[0047] When hoisting and transporting large equipment into a completed basement, by adopting the hoisting and transportation method for a completed basement according to an embodiment of the present application, it is possible to cope with the situation where the hoisting openings a reserved on the floor slabs of each floor of the completed basement are misaligned with each other.
[0048] It should be noted that after the target equipment b arrives at the site, it is necessary to first inspect the arrived target equipment b.
[0049] In some of these embodiments, the hoisting and transportation method for a completed basement according to the embodiments of the present application further includes the following steps:
[0050] If the lower floor slab of the current transition floor slab 100 in step S3 is the target floor slab, after hoisting and transporting the target device b to the lower floor slab of the current transition floor slab 100 by using the temporary hoisting structure 200, horizontally transport the target device b to the equipment foundation preset on the target floor slab for installing the target device b;
[0051] If the lower floor slab of the current transition floor slab 100 in step S3 is still the transition floor slab 100, after hoisting and transporting the target device b to the lower floor slab of the current transition floor slab 100 by using the temporary hoisting structure 200, continue to transfer the target device b according to the methods of steps S1 to S3 until the target device b is transported to the target floor slab, and then horizontally transport the target device b to the equipment foundation preset on the target floor slab for installing the target device b.
[0052] Refer to Figures 2 to 7 , in some of these embodiments, before hoisting and transporting the target device b to any transition floor slab 100, a detachable temporary support structure 400 is provided below the transition floor slab 100 that will temporarily bear the target device b. By supporting the transition floor slab 100 through the temporary support structure 400, it is beneficial to prevent the transition floor slab 100 that temporarily bears the target device b from being damaged due to the excessive weight of the target device b, thereby being beneficial to ensuring the safety during the construction process. Among them, the temporary support structure 400 is detachably arranged below the transition floor slab 100. After the transfer of the target device b is completed, the temporary support structure 400 can be disassembled, so that it will not occupy the space of the basement and the function of the basement will not be affected.
[0053] Refer to Figures 2 to 7 , in some of these embodiments, the temporary support structure 400 includes a first top support member 410 and a first support 420 arranged at the bottom of the first top support member 410. The first top support member 410 is used to support the transition floor slab 100, and the first support 420 is used to support the first top support member 410. Its structure is simple and easy to implement.
[0054] Specifically, the first top support member 410 is a support plate, so that there is a large contact area between the first top support member 410 and the supported transition floor slab 100, which is beneficial to preventing the transition floor slab 100 from being damaged due to concentrated force in a local area.
[0055] Specifically, the first support 420 is a scaffold, and its technology is mature, which is beneficial to improving the construction efficiency.
[0056] Refer to Figures 2 to 7 , in some of the embodiments, the target device b is horizontally transported by the ground tank c (also known as the handling wheel, the handling trolley or the heavy load transporter), which is beneficial to improving the transportation efficiency.
[0057] Specifically, a plurality of ground tanks c distributed in a rectangular array are arranged below the target device b to disperse the pressure transmitted by the ground tanks c to the transition floor bottom plate 100, which is beneficial to preventing the transition floor bottom plate 100 from being damaged due to concentrated stress in a local area.
[0058] It should be noted that, in some other embodiments, the target device b can also be horizontally transported by the rolling bar.
[0059] In some of the embodiments, when horizontally transporting the target device b, the electric hoist d is used to assist in transporting the target device b, which is beneficial to improving the transportation efficiency.
[0060] Specifically, the electric hoist d is used to pull the target device b in front of the target device b to move horizontally along the horizontal direction.
[0061] In addition, a manual hoist tail is arranged behind the target device b, that is, the manual hoist is used to pull the target device b behind the target device b to prevent the target device b from deflecting during the moving process.
[0062] It should be noted that, in some other embodiments, when horizontally transporting the target device b, the target device b can also be pushed horizontally by manpower or by a hydraulic jacking system.
[0063] Refer to Figures 2 to 4 and Figure 8 , in some of the embodiments, the temporary support platform 300 includes a second top support member 310 and a second bracket arranged at the bottom of the second top support member 310. The second top support member 310 is used to carry the target device b, and the second bracket is used to support the second top support member 310. Its structure is simple and easy to implement.
[0064] Refer to Figure 8 , in some of the embodiments, the second top support member 310 is a channel steel, and the second top support member 310 extends along the horizontal transportation direction of the target device b, so that the second top support member 310 can be used as a guide rail for the ground tank c when horizontally transporting the target device b, thereby being able to limit the moving track of the ground tank c, and further being able to limit the moving track of the target device b to prevent the target device b from deflecting during the moving process.
[0065] Refer to Figures 2 to 4 and Figure 8In some embodiments, the second bracket includes a plurality of vertical support members 320 and a plurality of intermediate connectors 330. The vertical support members 320 are used to support the second top supporting member 310. The intermediate connectors 330 are detachably connected to the vertical support members 320. The intermediate connectors 330 are used to connect and fix the plurality of vertical support members 320. The structure is simple and easy to implement. The intermediate connectors 330 are detachably connected to the vertical support members 320. Therefore, the spacing between the guide rails can be adjusted by replacing the intermediate connectors 330 of different sizes, so as to adapt to target devices b of different sizes. In particular, when multiple target devices b of different sizes need to be hoisted and transported on site, it is beneficial to improve the construction efficiency.
[0066] Specifically, the vertical support member 320 is fixedly connected to the bottom of the second top supporting member 310 , a connecting portion 321 is provided on the side of the vertical support member 320 , and the intermediate connecting member 330 is connected to the connecting portion 321 by bolts.
[0067] When it is necessary to hoist and transport target equipment b of different sizes, a hoisting point is set on the second top supporting member 310 or the vertical supporting member 320, and the temporary supporting platform 300 is hoisted by the corresponding temporary hoisting structure 200, and then the intermediate connecting members 330 of different sizes are replaced to assemble the temporary supporting platform 300 of the required size. In the process of replacing the intermediate connecting members 330 of different sizes, the temporary supporting platform 300 is hoisted by the corresponding temporary hoisting structure 200, which is convenient for adjusting the spacing between the vertical supporting members 320, which is conducive to improving the construction efficiency.
[0068] Reference Figures 2 to 9 In some embodiments, the temporary hoisting structure 200 uses an electric hoist d, wherein the temporary hoisting structure 200 includes a flexible connector 210, a first support 220 and a second support 230, a plurality of through holes e are opened on the floor of the previous floor of the current transition floor 100, two first supports 220 close to each other are placed on the floor of the previous floor of the current transition floor 100 corresponding to the through holes e, a second support 230 is placed on the two first supports 220, and the flexible connector 210 is inserted into the through hole e, wherein one end of the flexible connector 210 passes through the gap between the corresponding two first supports 220 and is connected to the corresponding second support 230, and the other end of the flexible connector 210 is hung with an electric hoist d, and the above structure is easy to implement and easy to dismantle. Among them, the plurality of through holes e can cooperate with the plurality of flexible connectors 210 to hang a plurality of electric hoists d, so that the target equipment b can be lifted at multiple lifting points, which is conducive to improving the stability during the lifting and transportation process.
[0069] Specifically, the flexible connecting member 210 is made of a steel wire rope, the first support member 220 is made of an I-beam, and the second support member 230 is made of a steel round bar.
[0070] In the description of this specification, if there are descriptions of reference terms such as "one embodiment", "some embodiments", "schematic embodiments", "examples", "specific examples", and "some examples", it means that the specific features, structures, materials, or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic expressions of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described can be combined in a suitable manner in any one or more embodiments or examples.
[0071] Although the embodiments of the present application have been shown and described, those of ordinary skill in the art can understand that various changes, modifications, substitutions, and variations can be made to these embodiments without departing from the principles and purposes of the present application. The scope of the present application is defined by the claims and their equivalents.
Claims
1. A method for hoisting and transporting a completed basement, characterized in that: The floor floor with the lifting port misaligned relative to the floor floor of the upper floor is the transition floor floor for transporting the target equipment. The target equipment is hoisted and transported to the uppermost transition floor floor by a crane, which also includes the following steps: S1. Before or after the crane lifts the target equipment, a temporary lifting structure is set on the floor of the upper floor of the current transition floor, which is located directly above the lifting opening on the floor of the current transition floor, and a temporary support platform for temporarily carrying the target equipment is set on the floor of the lower floor of the current transition floor, corresponding to the lifting opening on the floor of the current transition floor; S2, transport the target equipment horizontally to a temporary support platform, and lift the target equipment using a temporary lifting structure; S3. Remove the temporary support platform and use the temporary lifting structure to lift and transport the target equipment to the floor plate of the next floor plate of the current transition floor plate.
2. The method for hoisting and transporting a completed basement according to claim 1, characterized in that: The following steps are also included: If the floor plate next to the current transition floor plate in step S3 is the target floor plate, the target equipment is hoisted and transported to the floor plate next to the current transition floor plate by using a temporary hoisting structure, and then the target equipment is horizontally transported to the equipment foundation preset on the target floor plate for installing the target equipment; If the next floor plate of the current transition floor plate in step S3 is still the transition floor plate, after using the temporary lifting structure to lift and transport the target equipment to the next floor plate of the current transition floor plate, continue to transport the target equipment according to the methods of steps S1 to S3 until the target equipment is transported to the target floor plate, and then transport the target equipment horizontally to the equipment foundation preset on the target floor plate for installing the target equipment.
3. The method for hoisting and transporting a completed basement according to claim 1 or 2, characterized in that: Before the target equipment is hoisted and transported to any transition floor bottom plate, a detachable temporary support structure is arranged below the transition floor bottom plate that will temporarily carry the target equipment.
4. The method for hoisting and transporting a completed basement according to claim 3, characterized in that: The temporary supporting structure includes a first top supporting member and a first bracket arranged at the bottom of the first top supporting member, the first top supporting member is used to support the bottom plate of the transition floor, and the first bracket is used to support the first top supporting member.
5. The method for hoisting and transporting a completed basement according to claim 1 or 2, characterized in that: The target equipment is transported horizontally by ground tanks.
6. The method for hoisting and transporting a completed basement according to claim 5, characterized in that: When transporting the target equipment horizontally, an electric hoist is used to assist in transporting the target equipment.
7. The method for hoisting and transporting a completed basement according to claim 5, characterized in that: The temporary support platform includes a second top supporting member and a second bracket arranged at the bottom of the second top supporting member, the second top supporting member is used to carry the target device, and the second bracket is used to support the second top supporting member.
8. The method for hoisting and transporting a completed basement according to claim 7, characterized in that: The second top supporting member is a channel steel, and the second top supporting member extends along the horizontal transportation direction of the target equipment, so that the second top supporting member can serve as a guide rail of the tank when the target equipment is horizontally transported.
9. The method for hoisting and transporting a completed basement according to claim 7, characterized in that: The second bracket includes a plurality of vertical support members and a plurality of intermediate connecting members, wherein the vertical support members are used to support the second top supporting member, and the intermediate connecting members are detachably connected to the vertical support members, and the intermediate connecting members are used to connect and fix the plurality of vertical support members.
10. The method for hoisting and transporting a completed basement according to claim 1 or 2, characterized in that: The temporary lifting structure adopts an electric hoist, wherein the temporary lifting structure includes a flexible connector, a first support member and a second support member, a plurality of through holes are opened on the floor plate of the upper floor of the current transition floor, two first support members close to each other are placed corresponding to the through holes on the floor plate of the upper floor of the current transition floor, a second support member is placed on the two first support members together, and the flexible connector is passed through the through holes, wherein one end of the flexible connector passes through the gap between the corresponding two first support members and is connected to the corresponding second support member, and the electric hoist is hung on the other end of the flexible connector.