Modularized steel enclosing purlin assembly convenient to mount quickly
Through the modular design and telescopic structure of steel purlin components, the complex construction of traditional steel purlins is solved, rapid installation and stability enhancement, and construction efficiency is improved.
Patent Information
- Application Number
- CN202510863238.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-06-25
- Publication Date
- 2025-08-01
AI Technical Summary
The construction process of traditional steel purlins is complicated, and it is necessary to measure the span of the foundation pit and select support columns of different lengths, resulting in inconvenience in construction.
Modular steel purlin components are adopted, including I-shaped steel purlins, support seats, support columns and connecting sections. They are quickly installed through telescopic structures and modular designs, and length adjustment and fixation is used for hydraulic cylinders, bidirectional lead screws and sliding pipes.
The rapid installation and fixation of steel purlins is realized, the construction efficiency is improved, and the stability and safety of the construction site are enhanced.
Smart Images

Figure CN120401513A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of foundation pit support, and in particular to a modular steel purlin assembly that is easy to install quickly. Background Art
[0002] Steel purlins are a crucial component in foundation pit support projects, primarily used to enhance the overall stability of the retaining structure, prevent lateral displacement of the soil, and ensure construction safety. During deep foundation pit excavation, particularly during underground space development in urban environments, steel purlins are often required as part of the support system to protect surrounding buildings and underground facilities.
[0003] In traditional foundation pit support, steel purlins are typically fixed to both sides of the pit, followed by steel supports built between the two purlins to provide support for the pit. Traditional steel supports are typically assembled from multiple support columns, requiring the span of the pit to be measured before selecting support columns of varying lengths for assembly. This results in an inconvenient construction process that needs improvement. Summary of the Invention
[0004] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a modular steel purlin assembly that is easy to install quickly and has the effect of facilitating construction.
[0005] The above technical objectives of the present invention are achieved through the following technical solutions: a modular steel purlin assembly that is easy to install quickly, comprising: I-beam purlins are horizontally arranged on both sides of the foundation pit; A support base for connecting the I-beam purlins on each side; A support column is horizontally arranged on the support base; a connecting section, horizontally arranged between the pair of support columns; The connecting section includes a fixed tube and a pair of sliding tubes. The sliding tubes are horizontally slidably connected to the two ends of the fixed tube. The middle position of the fixed tube is horizontally rotatably connected to a bidirectional screw. Both ends of the bidirectional screw are threadedly connected to sliders. Both sides of each slider are rotatably connected to a pull rod, and the other end of the pull rod is rotatably connected to the sliding tube.
[0006] In a preferred example, the present invention can be further configured as follows: dovetail blocks are provided at both ends of the support column, grooves for the dovetail blocks to be embedded in and dovetail grooves connecting the grooves and for the dovetail blocks to be slidably embedded in are provided at the end positions of the support seat and the sliding tube, and bolts are provided at both ends of the support column that pass through the support seat or the sliding tube.
[0007] In a preferred embodiment, the present invention can be further configured as follows: The support base includes a seat tube, a seat body, and a hydraulic cylinder. The seat tube is connected to the support column. The seat body is slidably connected to the seat tube. The hydraulic cylinder is disposed within the seat tube and is used to control the horizontal sliding of the seat body.
[0008] In a preferred embodiment, the present invention can be further configured as follows: A hook for hooking the I-beam purlin is provided on the seat body.
[0009] In a preferred embodiment, the present invention can be further configured as follows: A vertical column is vertically provided at the middle position of the support column. The vertical column includes a base, a vertical rod, and a fixing head. The base is horizontally fixed to the bottom wall of the foundation pit. Multiple sections of the vertical rods are connected to each other and fixed to the base. The fixing head is provided on the uppermost vertical rod and is connected to the support column.
[0010] In a preferred embodiment, the present invention can be further configured as follows: A pair of clamping blocks are provided on the lower end surface of the vertical rod. Accommodating grooves for the clamping blocks to be inserted are provided on both the upper end surface of the base and the vertical rod, and clamping grooves connecting the accommodating grooves and for the clamping blocks to be inserted after rotation are also provided. A locking rod with a rectangular cross-section is vertically and slidably connected within the vertical rod. A spring for controlling the upward sliding of the locking rod is provided within the vertical rod. A locking hole for the locking rod to be inserted is provided on the base. An insertion rod for inserting into the uppermost vertical column is provided on the lower end surface of the fixing head.
[0011] In a preferred embodiment, the present invention can be further configured as follows: A handle is rotatably connected to the outer wall of the upper end of the uppermost vertical rod. A locking hook for hooking the fixing head is provided at the middle position of the handle.
[0012] In a preferred embodiment, the present invention can be further configured as follows: The fixing head includes a head end, a bracket, and a jack. The head end is provided on the uppermost vertical rod. The bracket is vertically and slidably connected to the head end. The jack is used to control the vertical sliding of the bracket.
[0013] In a preferred embodiment, the present invention can be further configured as follows: A hoop for clamping the support column is provided on the bracket.
[0014] In summary, the present invention has the following beneficial effects: 1. By providing a telescopic steel support structure, the length of the steel support structure can be freely adjusted, thereby tightly fixing the I-beam purlins on both sides of the foundation pit, making the construction process of the entire steel purlin assembly easier and more convenient; 2. By providing a modular and easily assembled steel support structure, rapid assembly and construction at the construction site can be achieved, improving construction efficiency; 3. By setting up vertical columns, the support of the entire steel support structure is realized, and the stability of the entire steel collar component during use is increased. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 is a schematic structural diagram of an embodiment; Figure 2 is a schematic diagram of the connection relationship of the embodiment; Figure 3 is a schematic structural diagram of the connecting section of the embodiment; Figure 4 is a schematic structural diagram of the column of the embodiment; Figure 5 is a schematic structural diagram of the vertical rod of the embodiment.
[0016] Reference numerals: 1, I-beam collar; 2, support base; 21, seat pipe; 22, seat body; 23, hydraulic cylinder; 24, hook; 3, support column; 31, dovetail block; 32, groove; 33, dovetail groove; 34, bolt; 4, connecting section; 41, fixed pipe; 42, sliding pipe; 43, bidirectional lead screw; 44, slider; 45, pull rod; 5, column; 51, base; 52, vertical rod; 53, fixed head; 531, insertion rod; 532, end head; 533, bracket; 534, jack; 535, hoop; 54, clamping block; 55, receiving groove; 56, clamping groove; 57, locking rod; 58, spring; 59, locking hole; 6, handle; 61, locking hook. DETAILED DESCRIPTION OF THE INVENTION
[0017] The present invention will be further described in detail below with reference to the accompanying drawings.
[0018] As Figure 1 , Figure 2 shown, a modular steel collar component convenient for quick installation includes an I-beam collar 1, a support base 2, a support column 3, and a connecting section 4.
[0019] As Figure 1 , Figure 2 shown, the I-beam collar 1 is horizontally arranged on both sides of the foundation pit, and the support base 2 is used to connect the I-beam collar 1 on each side. The support column 3 is horizontally arranged on the support base 2, and the connecting section 4 is horizontally arranged between a pair of support columns 3.
[0020] As Figure 1 , Figure 2 shown, the support base 2 includes a seat pipe 21, a seat body 22, and a hydraulic cylinder 23. The seat pipe 21 is connected to the support column 3, the seat body 22 is slidably connected to the seat pipe 21, and a hook 24 for hooking the I-beam collar 1 is arranged on the seat body 22. The hydraulic cylinder 23 is arranged in the seat pipe 21 and is used to control the horizontal sliding of the seat body 22.
[0021] AsFigure 2 , Figure 3 As shown in Figure 3 , the connecting section 4 includes a fixed pipe 41 and a pair of sliding pipes 42. The sliding pipes 42 are horizontally slidably connected to both ends of the fixed pipe 41. A bidirectional lead screw 43 is horizontally rotatably connected to the middle position of the fixed pipe 41. Both ends of the bidirectional lead screw 43 are threadedly connected with sliders 44. A pull rod 45 is rotatably connected to both sides of each slider 44, and the other end of the pull rod 45 is rotatably connected to the sliding pipe 42.
[0022] As Figure 2 , Figure 3 As shown in Figure 3 , dovetail blocks 31 are provided at both ends of the support column 3. Grooves 32 for the dovetail blocks 31 to be embedded in and dovetail grooves 33 connecting the grooves 32 and for the dovetail blocks 31 to be slidably embedded in are provided at the end positions of the seat body 22 and the sliding pipe 42. Bolts 34 passing through the seat body 22 or the sliding pipe 42 are provided at both ends of the support column 3.
[0023] When the foundation pit needs to be supported, first horizontally fix the I-beam purlin 1 on both sides of the foundation pit, then place the support column 3 between the support base 2 and the connecting section 4, and make the dovetail blocks 31 on the support column 3 be embedded in the grooves 32 at the ends of the seat body 22 and the sliding pipe 42. Then control the rotation of the support column 3 to make the dovetail blocks 31 be embedded in the dovetail grooves 33, and use the bolts 34 to fix the support column 3, the seat body 22 and the sliding pipe 42, completing the connection of the support base 2, the support column 3 and the connecting section 4, and completing the assembly connection of the entire steel support structure.
[0024] Then control the rotation of the bidirectional lead screw 43 to make the bidirectional lead screw 43 drive the sliders 44 to slide relative to each other, and control the flipping of the pull rods 45. Use the pull rods 45 to control the relative sliding of the sliding pipes 42, so as to realize the length adjustment of the entire steel support structure for adapting to foundation pits with different spans.
[0025] Subsequently, lift the support base 2, the support column 3 and the connecting section 4, and make the hooks 24 at both ends of the seat body 22 hook tightly on the I-beam purlin 1. Then start the hydraulic cylinder 23 to make the seat body 22 slide outwards and press tightly against the I-beam purlin 1, realizing the tight fixing of the I-beam purlin 1 and completing the support of the foundation pit.
[0026] Therefore, by setting the telescopic steel support structure, the free adjustment of the length of the steel support structure is realized, so as to tightly fix the I-beam purlins 1 on both sides of the foundation pit, making the construction process of the entire steel purlin assembly easier and more convenient. At the same time, by setting the modular and easily assembled steel support structure, the rapid assembly and construction at the construction site are realized, improving the construction efficiency.
[0027] As Figure 2 , Figure 4As shown, a vertical column 5 is vertically arranged at the middle position of the support column 3. The vertical column 5 includes a base 51, a vertical rod 52, and a fixing head 53. The base 51 is horizontally fixed to the bottom wall of the foundation pit. Multiple sections of the vertical rod 52 are connected to each other and fixed to the base 51. The fixing head 53 is arranged on the uppermost vertical rod 52 and is connected to the support column 3.
[0028] As Figure 2 、 Figure 4 shown, a pair of clamping blocks 54 are arranged on the lower end surface of the vertical rod 52. Accommodating grooves 55 for the clamping blocks 54 to be embedded are arranged on the upper end surfaces of the base 51 and the vertical rod 52, and clamping grooves 56 connected to the accommodating grooves 55 and into which the clamping blocks 54 can be rotated and embedded are arranged.
[0029] As Figure 2 、 Figure 4 、 Figure 5 shown, a locking rod 57 with a rectangular cross-section is vertically and slidably connected inside the vertical rod 52, and a spring 58 for controlling the upward sliding of the locking rod 57 is arranged inside the vertical rod 52. A locking hole 59 for the locking rod 57 to be inserted is arranged on the base 51, and an insertion rod 531 inserted into the uppermost vertical column 5 is arranged on the lower end surface of the fixing head 53.
[0030] As Figure 4 、 Figure 5 shown, a handle 6 is rotatably connected to the outer wall of the upper end of the uppermost vertical rod 52, and a locking hook 61 for hooking the fixing head 53 is arranged at the middle position of the handle 6.
[0031] As Figure 4 shown, the fixing head 53 includes a head end 532, a bracket 533, and a jack 534. The head end 532 is arranged on the uppermost vertical rod 52. The bracket 533 is vertically slidably connected to the head end 532. A hoop 535 for clamping the support column 3 is arranged on the bracket 533, and the jack 534 is used to control the vertical sliding of the bracket 533.
[0032] After the I-beam purlin 1 is supported, the vertical column 5 is taken out. First, the base 51 is fixed to the bottom of the foundation pit, and then the vertical rod 52 is taken out. The clamping block 54 at the lower end of the vertical rod 52 is embedded into the accommodating groove 55 on the base 51, and then the vertical rod 52 is controlled to rotate so that the clamping block 54 rotates into the clamping groove 56 to realize the connection between the vertical rod 52 and the base 51. Then, according to the same principle, each section of the vertical rod 52 is connected.
[0033] Meanwhile, the locking rod 57 in the lowermost vertical rod 52 is rotated to align with the locking hole 59 on the base 51, and at the same time, the locking rods 57 in the adjacent vertical rods 52 are aligned with each other. Then the fixing head 53 is taken out, placed on the uppermost vertical rod 52, and the insertion rod 531 at the lower end of the fixing head 53 is inserted into the uppermost vertical rod 52.
[0034] Then, control the handle 6 to flip upward, and control the locking hook 61 to hook the end 532 on the fixed head 53. Then, control the handle 6 to flip downward. Under the action of the lever principle, the fixed head 53 moves downward, and the insertion rod 531 is completely inserted into the vertical rod 52. At the same time, all the locking rods 57 in the vertical rod 52 slide downward completely. Finally, the lowermost locking rod 57 is inserted into the locking hole 59. Finally, fix the end 532 on the vertical rod 52 to complete the assembly and fixation of the entire column 5.
[0035] Subsequently, use the jack 534 to control the bracket 533 to move upward, and use the hoop 535 to tightly hold the support column 3 to achieve the support and fixation of the support column 3, thereby realizing the support of the entire steel support structure and increasing the stability during the use of the entire steel waling assembly.
[0036] The specific embodiments are only explanations of the present invention and are not limitations thereto. After reading this specification, those skilled in the art can make modifications to the embodiments without creative contributions as needed, but as long as they are within the scope of the claims of the present invention, they are protected by the patent law.
Claims
1. A modular steel waling beam assembly that is convenient for quick installation, characterized in that: Including: I-beam purlins (1), horizontally arranged on both sides of the foundation pit; Support seats (2), used to connect the I-beam purlins (1) on each side; Support columns (3), horizontally arranged on the support seats (2); Connection segments (4), horizontally arranged between a pair of the support columns (3); The connection segment (4) includes a fixed pipe (41) and a pair of sliding pipes (42), the sliding pipes (42) are horizontally slidably connected to both ends of the fixed pipe (41), a bidirectional lead screw (43) is horizontally rotatably connected to the middle position of the fixed pipe (41), both ends of the bidirectional lead screw (43) are threadedly connected with sliders (44), both sides of each slider (44) are rotatably connected with pull rods (45), and the other ends of the pull rods (45) are rotatably connected to the sliding pipes (42).
2. The modular steel waling beam assembly for facilitating quick installation according to claim 1, wherein: Dovetail blocks (31) are arranged at both ends of the support column (3), grooves (32) for the dovetail blocks (31) to be embedded and dovetail grooves (33) connecting the grooves (32) and for the dovetail blocks (31) to slide and be embedded are arranged at the end positions of the support seat (2) and the sliding pipes (42), and bolts (34) penetrating through the support seat (2) or the sliding pipes (42) are arranged at both ends of the support column (3).
3. The modular steel waling beam assembly for facilitating quick installation according to claim 1, characterized in that: The support seat (2) includes a seat pipe (21), a seat body (22) and a hydraulic cylinder (23), the seat pipe (21) connects the support column (3), the seat body (22) is slidably connected to the seat pipe (21), the hydraulic cylinder (23) is arranged in the seat pipe (21) and is used to control the horizontal sliding of the seat body (22).
4. A modular steel waling beam assembly facilitating quick installation according to claim 3, characterized in that: A hook (24) for hooking the I-beam purlin (1) is arranged on the seat body (22).
5. A modular steel waling beam assembly facilitating quick installation according to claim 1, wherein: A vertical column (5) is vertically arranged at the middle position of the support column (3), the vertical column (5) includes a base (51), a vertical rod (52) and a fixed head (53), the base (51) is horizontally fixed to the bottom wall of the foundation pit, multiple sections of the vertical rods (52) are connected to each other and fixed to the base (51), the fixed head (53) is arranged on the uppermost vertical rod (52) and connects the support column (3).
6. The modular steel waling beam assembly for facilitating quick installation according to claim 5, wherein: A pair of clamping blocks (54) are arranged on the lower end surface of the vertical rod (52), receiving grooves (55) for the clamping blocks (54) to be embedded and clamping grooves (56) connecting the receiving grooves (55) and for the clamping blocks (54) to be rotated and embedded are arranged on the upper end surfaces of the base (51) and the vertical rod (52), a locking rod (57) with a rectangular cross-section is vertically slidably connected in the vertical rod (52), a spring (58) for controlling the upward sliding of the locking rod (57) is arranged in the vertical rod (52), a locking hole (59) for the locking rod (57) to be inserted is arranged on the base (51), and an insertion rod (531) inserted into the uppermost vertical column (5) is arranged on the lower end surface of the fixed head (53).
7. The modular steel waling beam assembly for facilitating quick installation according to claim 6, wherein: The upper end outer wall of the uppermost vertical rod (52) is rotatably connected with a handle (6), and a locking hook (61) for hooking the fixed head (53) is arranged at the middle position of the handle (6).
8. A modular steel waling beam assembly facilitating quick installation according to claim 5, characterized in that: The fixed head (53) includes a head end (532), a bracket (533) and a jack (534). The head end (532) is arranged on the uppermost vertical rod (52). The bracket (533) is vertically and slidably connected to the head end (532), and the jack (534) is used to control the vertical sliding of the bracket (533).
9. A modular steel waling beam assembly facilitating quick installation according to claim 8, characterized in that: A hoop (535) for clamping the support column (3) is arranged on the bracket (533).