Storage and maintenance device and method for prefabricated duct pieces

Through the combination of support units, spray units and control systems, the intelligent maintenance of prefabricated pipe sheets of wind power mixed towers is solved, efficient water resource conservation and construction progress improvement is achieved, and is suitable for the storage and maintenance of various types of prefabricated pipe sheets.

CN120481050APending Publication Date: 2025-08-15CHINA MCC22 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510919846.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-07-04
Publication Date
2025-08-15

AI Technical Summary

Technical Problem

The existing technology cannot meet the large-size characteristics and intelligent maintenance needs of prefabricated pipe sheets of wind power mixed towers. The traditional storage method leads to low space utilization, high water resources and manpower consumption, and extreme weather affects construction quality.

Method used

The support unit is used to cooperate with the monitoring unit to achieve accurate positioning and stable support. The spray unit is combined with the monitoring unit to automatically adjust the spray parameters. The control system realizes remote monitoring and management, and is equipped with foldable tarpaulin components to provide all-weather protection.

Benefits of technology

It improves the space utilization rate of the site, saves water resources and labor costs, improves maintenance quality and construction efficiency, adapts to various bad weather, and has significant economic and social benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120481050A_ABST
    Figure CN120481050A_ABST
Patent Text Reader

Abstract

The invention provides a storage and maintenance device and method for prefabricated pipe pieces, and the device comprises a base which comprises two steel beams arranged in parallel; the supporting units are arranged on the base at intervals, each supporting unit comprises arc-shaped steel channels and rubber pads arranged on the arc-shaped steel channels, and the supporting units are used for supporting prefabricated pipe pieces; the spraying unit comprises spraying nozzles arranged between the adjacent supporting units and is used for spraying water to the prefabricated duct pieces for maintenance; the monitoring unit comprises a pressure sensor arranged below the rubber pad and a temperature and humidity sensor arranged on the side of the supporting unit; the control system is in signal connection with the spraying unit, the monitoring unit and the foldable tarpaulin assembly; maintenance quality and construction efficiency of the prefabricated duct pieces are remarkably improved, labor cost and water resource consumption are reduced, and storage and maintenance requirements of various prefabricated duct pieces are met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of storage and maintenance of precast concrete segments of wind power hybrid towers, and in particular relates to a storage and maintenance device and method for precast segments. Background Art

[0002] After the prefabricated segments of the wind turbine hybrid tower are demoulded, they are usually stored in the open air for maintenance at the component factory. However, this traditional storage method faces many technical difficulties: limited stacking space in the factory leads to chaotic and disorderly storage; extensive maintenance methods result in untimely watering maintenance; and the mismatch between the production sequence of the prefabricated segments and the storage location affects management efficiency. These problems not only reduce the utilization rate of the factory space, but may also lead to the inability to ensure the later strength of the components. With the increase in the number of prefabricated segments, the traditional watering maintenance method consumes a lot of water resources and labor costs, and it is difficult to achieve accurate timed and quantitative spraying. Especially in extreme weather such as wind, rain or low temperatures, the open air storage environment seriously affects the quality of segment repair and surface spraying construction, thereby slowing down the construction progress of the entire wind turbine hybrid tower.

[0003] Most of the concrete curing equipment in the existing technology has a single function and cannot meet the large-size characteristics and intelligent maintenance requirements of prefabricated pipe segments of wind turbine hybrid towers. It is urgent to develop a device that can meet the traditional storage functions while achieving all-weather, heat preservation and moisture retention, automatic spraying and automated management. Summary of the Invention

[0004] The present invention provides a storage and maintenance device and method for prefabricated pipe segments, which is used to solve the problems that the maintenance equipment in the prior art cannot meet the large size characteristics and intelligent maintenance requirements of prefabricated pipe segments of wind turbine hybrid towers.

[0005] In a first aspect, the present invention provides a storage and curing device for prefabricated segments, characterized by comprising: a base, comprising two parallel steel beams; Support units are arranged at intervals on the base. Each group of support units includes an arc-shaped channel steel and a rubber pad arranged thereon, which is used to support the prefabricated segments. A spray unit, comprising spray nozzles disposed between adjacent support units, for spraying water for curing the prefabricated segments; The monitoring unit includes a pressure sensor provided below the rubber pad and a temperature and humidity sensor provided on the side of the support unit; The control system is connected to the spray unit, the monitoring unit and the foldable tarpaulin assembly by signals.

[0006] Compared with the prior art, the beneficial effects of the present invention are as follows: By adopting a support unit in cooperation with a monitoring unit, accurate positioning and stable support of precast segments are achieved, significantly improving the utilization rate of site space; The spraying unit combined with the monitoring unit can automatically adjust the spraying parameters according to environmental conditions, ensuring the maintenance quality and significantly saving water resources; The foldable tarpaulin assembly provides all-weather protection, effectively coping with various harsh weather conditions; The control system enables remote monitoring and management, allowing operators to always grasp the segment status and make necessary adjustments; It not only significantly improves the maintenance quality and construction efficiency of precast segments, but also reduces labor costs and water resource consumption, having prominent economic and social benefits, and is applicable to the storage and maintenance requirements of various precast segments.

[0007] Further, a continuous guide rail is provided on the inner side wall of the steel beam, and the support unit is slidably engaged with the guide rail through a slider.

[0008] Further, a magnetic force self-locking device is also provided on the slider of the support unit, including: A magnetic box, fixedly installed at the bottom of the slider; A neodymium iron boron permanent magnet, embedded inside the magnetic box; A magnetic force control switch, provided on the side of the magnetic box; Among them, the magnetic force control switch can switch the on / off state of the magnetic force self-locking device. When it is turned on, the neodymium iron boron permanent magnet generates magnetic suction force to tightly fix the slider and the guide rail, and when it is turned off, the magnetic attraction is released to achieve sliding adjustment.

[0009] Further, it also includes: a foldable tarpaulin assembly, including a folding skeleton and a tarpaulin, which is slidably connected to the base; The folding skeleton is a U-shaped structure with an open bottom, and the tarpaulin is fixedly covered on the outer surfaces of multiple folding skeletons; A slide rail is provided on the upper flange of the steel beam, and both ends of the folding skeleton are slidably connected to the slide rail through rollers.

[0010] Further, the control system includes: A control box provided at a corner of the base; A PLC controller provided inside the control box, which is signal-connected to the spraying unit, the monitoring unit and the foldable tarpaulin assembly; A touch display screen provided on the surface of the control box; A 5G communication module integrated in the PLC controller; A warning light provided on the outer surface of the control box.

[0011] Further, the touch screen display real-time displays the number, production date, maintenance age, as well as the rebound strength and environmental temperature and humidity data at the corresponding age of the precast segment.

[0012] In a second aspect, the present invention provides a method for storing and curing prefabricated segments, which is performed using the storage and curing device for prefabricated segments described in the first aspect and includes the following steps: S1. Adjust the spacing between support units, hoist the prefabricated segments above the support units, and confirm their position using pressure sensors. S2. Input the information of the prefabricated segments through the control system, start the curing process, and record the curing data; S3. Control the opening and closing of the spray unit and the foldable tarpaulin assembly according to the data from the monitoring unit, and lift the prefabricated pipe segment after the curing treatment is completed.

[0013] Furthermore, the spraying unit adopts an intermittent mode, and the spraying duration and interval are dynamically adjusted according to the maintenance stage.

[0014] Furthermore, maintenance data is transmitted to mobile terminals in real time via the 5G network for remote monitoring and emergency control. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 Schematic diagram of a storage and maintenance device in one embodiment of the present invention; Figure 2 Schematic diagram of placement of prefabricated segments in one embodiment of the present invention; Figure 3 Detailed diagram of a foldable tarpaulin assembly in one embodiment of the present invention; Figure 4 is a front elevation view of a storage and curing device in one embodiment of the present invention; Figure 5 is a side elevation view of a storage and curing device in one embodiment of the present invention; Figure 6 2 is a top view of a storage and maintenance device according to an embodiment of the present invention.

[0016] Description of reference numerals: 1. Control box; 2. Base; 3. Arc channel steel; 4. Rubber pad; 5. Spray unit; 51. Spray nozzle; 6. Warning light; 7. Temperature and humidity sensor; 8. Foldable tarpaulin assembly; 81. Roller; 82. Folding frame; 9. Guide rail; 10. Prefabricated pipe segment. DETAILED DESCRIPTION

[0017] To make the objectives, technical solutions, and advantages of the present invention more clear, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts shall fall within the scope of protection of the present invention.

[0018] See also Figures 1 to 6 The present invention provides a storage and maintenance device for prefabricated segments, comprising: Base 2, comprising two parallel steel beams; Support units are arranged at intervals on the base 2. Each group of support units includes an arc-shaped channel steel 3 and a rubber pad 4 arranged thereon, which is used to support the prefabricated pipe segment 10; The spray unit 5 includes spray nozzles 51 disposed between adjacent support units and is used to spray water for curing the prefabricated segments 10; The monitoring unit includes a pressure sensor provided below the rubber pad 4 and a temperature and humidity sensor 7 on the side of the support unit; The control system is connected to the spray unit 5, the monitoring unit and the foldable tarpaulin assembly 8 by signals.

[0019] The storage and maintenance device for prefabricated pipe segments provided by the present invention adopts a support unit in conjunction with a monitoring unit to achieve precise positioning and stable support of the prefabricated pipe segments, greatly improving the site space utilization rate; the spray unit is combined with the monitoring unit to automatically adjust the spray parameters according to environmental conditions, which not only ensures the maintenance quality but also significantly saves water resources; the foldable tarpaulin assembly provides all-weather protection and effectively copes with various severe weather conditions; the control system realizes remote monitoring and management, allowing operators to grasp the status of the pipe segments at any time and make necessary adjustments; it not only significantly improves the maintenance quality and construction efficiency of the prefabricated pipe segments, but also reduces labor costs and water resource consumption, has outstanding economic and social benefits, and is suitable for the storage and maintenance needs of various prefabricated pipe segments.

[0020] The base 2 is made of high-strength materials such as channel steel or I-steel, and provides a basic carrier for the installation of the support unit, the spray unit 5 and the electric control pipeline, and the installation of the foldable tarpaulin assembly 8.

[0021] Furthermore, the support unit, consisting of curved channel steel 3, rubber pads 4, and a self-locking device, primarily supports the prefabricated segments 10. When a prefabricated segment 10 is placed on the support unit, the pressure triggers a pressure sensor, which provides feedback to the control interface, indicating that the position is occupied. Otherwise, it indicates that the position is unloaded. Furthermore, the curved channel steel 3 can be moved in four directions: forward, backward, left, and right, facilitating adjustment of the support unit based on segment size.

[0022] A continuous guide rail 9 is provided on the inner sidewall of the steel beam, and the support unit slides in engagement with the guide rail 9 via a slider. The slider of the support unit is also equipped with a magnetic self-locking device, comprising: a magnetic box fixedly mounted on the bottom of the slider; a neodymium iron boron permanent magnet embedded within the magnetic box; and a magnetic control switch located on the side of the magnetic box. The magnetic control switch switches the magnetic self-locking device on and off. When on, the neodymium iron boron permanent magnet generates magnetic attraction, tightly securing the slider to the guide rail 9; when off, the magnetic attraction is released, enabling sliding adjustment.

[0023] The spray unit 5 is mainly used for spraying water on the prefabricated pipe segments 10 for maintenance. The opening and closing of the spray unit 5 is controlled by a temperature and humidity sensor, and can also be controlled through a control interface.

[0024] The temperature and humidity sensor 7 is mainly used for real-time dynamic monitoring of the environment around the prefabricated pipe segment 10, and then controls the opening and closing of the spray unit 5, so as to achieve the purpose of no one guarding around the clock.

[0025] The foldable tarpaulin assembly 8 consists of a foldable frame 82 and a tarpaulin, which is slidably connected to the base 2. The foldable frames 82 are a downward-facing, shaped structure, and the tarpaulin is fixedly covered on the outer surfaces of the foldable frames 82. The upper flange of the steel beam is provided with a slide rail, and the ends of the foldable frames 82 are slidably connected to the slide rail via rollers 81. The foldable tarpaulin assembly 8 is normally stowed and can be unfolded as needed to provide full coverage of the pipe segments within the entire device, thereby creating a suitable and stable working environment and reducing the impact of external factors on the quality of the components.

[0026] The control system includes: a control box 1 located at a corner of the base 2; a PLC controller located inside the control box 1, which is signal-connected to the spray unit 5, the monitoring unit and the foldable tarpaulin assembly 8; a touch screen display located on the surface of the control box 1; a 5G communication module integrated in the PLC controller; and a warning light 6 located on the outer surface of the control box 1.

[0027] The control system is mainly used to control the output display, input control, opening and closing of the sprinkler system, and opening and closing of the foldable tarpaulin of the entire device. It can also be interconnected with the APP in the mobile phone through 5G technology to realize remote monitoring and management by management personnel.

[0028] The control interface realizes two-way interaction of output and input through the touch screen display. While displaying values such as vacancy, segment number, production date, temperature and humidity, the control system can be called through interface operation to realize different functions of the device.

[0029] The alarm device is a red warning light. When you need to locate the position of a certain pipe segment, you can place an order with one click through the mobile phone APP. At this time, the red warning light will light up, which plays a role in quick positioning.

[0030] The present invention further provides a method for storing and curing prefabricated segments, which is performed using the above-mentioned storage and curing device for prefabricated segments 10 and includes the following steps: S1. Adjust the spacing between the support units, hoist the prefabricated segments 10 above the support units, and confirm their position using pressure sensors. S2. Inputting information of the prefabricated segments 10 through the control system and starting the curing process, and recording the curing data; S3. Control the opening and closing of the spray unit 5 and the foldable tarpaulin assembly 8 according to the data of the monitoring unit, and lift the prefabricated pipe segment 10 after the curing process is completed.

[0031] Furthermore, the spray unit 5 adopts an intermittent mode, and the spraying duration and interval are dynamically adjusted according to the maintenance stage. Maintenance data is transmitted to mobile terminals in real time via the 5G network for remote monitoring and emergency control.

[0032] The specific implementation of the device in this application is as follows: First, assemble the steel base 2 and secure it to a predetermined location within the factory. A support unit consisting of curved channel steel 3 and rubber pads 4 is connected to the guide rails 9 on the inner side of the steel beam of the base 2 via sliders, forming an adjustable segment support structure. Based on the dimensions of the prefabricated segments 10, the support unit is slid along the guide rails 9 to adjust the spacing to the desired position and then locked securely.

[0033] The prefabricated segment 10 is hoisted onto the support unit, ensuring that the bottom of the segment is fully aligned with the rubber pad 4. The segment's position is confirmed by a pressure sensor embedded below the rubber pad 4. Basic information about the prefabricated segment 10, such as its serial number and production date, is then entered through the touchscreen display of the control box 1. The control system automatically begins recording the curing age.

[0034] During operation, temperature and humidity sensors 7 located on the sides of the support units monitor environmental parameters in real time. When the humidity is detected to be below a set threshold, the control system automatically activates the spray unit 5, spraying and curing the prefabricated segments 10 through adjustable spray nozzles 51 between adjacent support units. When the temperature drops below a set threshold, the foldable tarpaulin assembly 8 is deployed along the slide rails on the upper flange of the steel beam, creating a thermally insulated curing space. The tarpaulin assembly consists of multiple sets of ⌚-shaped frames connected in series via hinged axes. When deployed, it forms a continuous, all-around covering structure, creating a suitable and stable working environment and minimizing the impact of external factors on component quality.

[0035] During maintenance, operators can remotely monitor the status of the segments through a control system integrated with a 5G communication module. When a precast segment 10 reaches its scheduled maintenance age, the system triggers a flashing warning light 6 and sends a notification via a mobile app, facilitating quick location and lifting operations.

[0036] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the above embodiments, or replace some or all of the technical features therein with equivalents. If these modifications and variations fall within the scope of the claims of the present invention and their equivalent technologies, they should be considered to be within the scope of protection of the present invention.

Claims

1. A storage and maintenance device for prefabricated segments, characterized in that: Comprising: A base, including two parallel steel beams; Support units, spacedly arranged on the base, each group of support units including an arc channel steel and a rubber pad arranged thereon, for supporting precast segments; A spray unit, including spray nozzles arranged between adjacent support units, for spraying water for the maintenance of precast segments; A monitoring unit, including a pressure sensor arranged under the rubber pad and a temperature and humidity sensor arranged on the side of the support unit; A control system, signal-connected to the spray unit, the monitoring unit and the foldable tarpaulin assembly.

2. The storage and maintenance device for prefabricated segments according to claim 1, characterized in that: Continuous guide rails are provided on the inner side walls of the steel beams, and the support units are slidably fitted with the guide rails through sliders.

3. The storage and maintenance device for prefabricated segments according to claim 2, characterized in that: A magnetic force self-locking device is further provided on the slider of the support unit, including: A magnetic box, fixedly installed at the bottom of the slider; A neodymium iron boron permanent magnet, embedded inside the magnetic box; A magnetic force control switch, arranged on the side of the magnetic box; Wherein, the magnetic force control switch can switch the on / off state of the magnetic force self-locking device. When it is turned on, the neodymium iron boron permanent magnet generates a magnetic attraction force to tightly fix the slider and the guide rail. When it is turned off, the magnetic attraction is released to achieve sliding adjustment.

4. The storage and maintenance device for prefabricated segments according to claim 1, characterized in that: It further includes: A foldable tarpaulin assembly, including a folding frame and a tarpaulin, slidably connected to the base; The folding frame is a U-shaped structure with an open bottom, and the tarpaulin is fixedly covered on the outer surfaces of multiple folding frames; Slide rails are provided on the upper flanges of the steel beams, and both ends of the folding frame are slidably connected to the slide rails through rollers.

5. The storage and maintenance device for prefabricated segments according to claim 1, characterized in that: The control system includes: A control box arranged at a corner of the base; A PLC controller arranged inside the control box, signal-connected to the spray unit, the monitoring unit and the foldable tarpaulin assembly; A touch display screen arranged on the surface of the control box; A 5G communication module integrated in the PLC controller; A warning light arranged on the outer surface of the control box.

6. The storage and maintenance device for prefabricated segments according to claim 5, characterized in that: The touch display screen displays in real time the number, production date, maintenance age, as well as the rebound strength and environmental temperature and humidity data at the corresponding age of the precast segments.

7. A method for storing and curing prefabricated segments, using the storage and curing device for prefabricated segments according to any one of claims 1 to 6, characterized in that: Including the following steps: S1. Adjust the spacing of the support units, hoist the precast segment above the support units, and confirm the就位 by the pressure sensor; S2. Enter the information of the precast segment through the control system and start the maintenance process, and record the maintenance data; S3. Control the opening and closing of the spray unit and the foldable tarpaulin assembly according to the data of the monitoring unit. After the maintenance process is completed, hoist away the precast segment.

8. The method for storing and curing prefabricated segments according to claim 7, characterized in that: The spray unit adopts an intermittent mode, and the spray duration and interval are dynamically adjusted according to the maintenance stage.

9. The method for storing and curing prefabricated segments according to claim 7, characterized in that: The maintenance data is transmitted to the mobile terminal in real time through the 5G network for remote monitoring and emergency control.