A pipe pile concrete excess material recycling and utilizing system

By designing a recycling system for leftover concrete from pipe piles, and adopting a closed collection channel and crushing and grading mechanism, the problem of hardening and clumping of leftover materials during pipe pile production was solved. This enabled the timely recycling and reuse of leftover concrete, reducing production costs and environmental pollution, and improving recycling efficiency.

CN120481059BActive Publication Date: 2026-02-13FOSHAN SHUNDE HONGYE CEMENT PROD CO LTD +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202510806278.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-06-17
Publication Date
2026-02-13
Estimated Expiration
2045-06-17

AI Technical Summary

Technical Problem

During the production of concrete pipe piles, there are problems of waste and environmental pollution caused by leftover concrete, especially the waste of resources and environmental pollution caused by the hardening of leftover material from equipment such as mixer troughs, conveyor hoppers, and placing hoppers, which are difficult to effectively recycle and treat.

Method used

A system for recycling and reusing leftover concrete from pipe piles is designed. Through a closed collection channel, water pumps and cleaning pipelines for immediate flushing, combined with a crushing and grading mechanism, the system enables timely recycling and resource reuse of leftover concrete. The system uses a crushing drum and a forward and reverse drive mechanism to crush clumps online, and after screening, qualified raw materials are obtained for reuse in production.

Benefits of technology

It significantly reduces production costs, minimizes environmental pollution, improves recycling efficiency, meets the gradation requirements of different raw materials for pipe pile production, and enables efficient recycling and reuse of concrete residues.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120481059B_ABST
    Figure CN120481059B_ABST
Patent Text Reader

Abstract

The application discloses a pipe pile concrete excess material recycling and cyclic utilization system and relates to the technical field of pipe pile concrete excess material recycling, in particular to the pipe pile concrete excess material recycling and cyclic utilization system. The application is characterized in that the excess material recycling process is deeply embedded into the pipe pile production line, such as cloth feeding, flushing and mold sleeve cleaning links, through modular design, such as groove conveying and crushing and grading mechanisms, the production and recycling are simultaneously realized, the newly-added bottleneck nodes are avoided, the comprehensive cost is reduced through resource cyclic utilization, and the links of raw material, waste material treatment and water resource control are integrally completed.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of pipe pile concrete excess material recycling, in particular to a pipe pile concrete excess material recycling and recycling system. BACKGROUND

[0002] As a kind of concrete product, prestressed high-strength concrete pipe pile (PHC pipe pile, hereinafter referred to as pipe pile) is widely used in industrial and civil buildings, highways, railways, airports, water conservancy, ports and other fields. In the production process of pipe pile, concrete mixing and distribution are very important processes, as mentioned in the utility model patent with publication number CN209682554U.

[0003] During the mixing and discharging process, concrete may overflow from the side of the chute. If not collected, there will be excess material waste. In addition to the mixer chute, concrete excess material will accumulate in the material transport car, distribution hopper and distribution mold cover. To prevent the excess material from hardening and affecting normal production and product quality, the mixer chute, material transport car, distribution hopper and distribution mold cover need to be regularly or irregularly washed with water, which will generate a large amount of waste sand and stone. If not treated in time, these waste sand and stone will harden and can only be taken as construction waste for landfill. At present, many pipe pile factories simply discharge or landfill the concrete excess material (i.e. waste sand and stone), which not only wastes resources but also pollutes the environment.

[0004] The present application aims to solve the above problems and provide a pipe pile factory concrete excess material efficient recycling and recycling system to achieve deep recycling and recycling of concrete excess material (i.e. waste sand and stone) in the mixer chute, material transport car, distribution hopper and distribution mold cover, so as to reduce the production cost of pipe pile, save resources and protect the environment. SUMMARY

[0005] The present application aims to provide a pipe pile concrete excess material recycling and recycling system to solve the problems raised in the background art.

[0006] To achieve the above-mentioned purpose, the present application provides the following technical solution: a pipe pile concrete excess material recycling and recycling system, comprising a blank forming table, a raw material feeding table, a collection pool, a mixer, a chute, a track and a circulating water pool, the blank forming table is provided with a raw material feeding table, the raw material feeding table is provided with a mixer, and the mixer is provided with a chute, the blank forming table is provided with a collection pool and a circulating water pool.

[0007] The blank forming platform fixed support is slidably connected with a moving hopper car, a distributing hopper is installed on the blank forming platform fixed support and located at the top of the moving hopper car, a distributing flat car is slidably connected with the track, and a pipe mold is placed on the distributing flat car, and a distributing mold sleeve is placed on the top of the pipe mold through a crown block hoist;

[0008] A groove is formed below the blank forming platform and below the distributing hopper, a mold sleeve cleaning machine is installed on one side of the track and located at the top of the groove, the groove extends to the collecting pool and is in communication with the collecting pool, a cross groove is arranged at the position of the collecting pool and is in communication with the groove, a sand scraping chain plate machine is installed in the groove, and a spiral feeding machine is installed in the cross groove, a crushing and grading mechanism is installed on the top of the blank forming platform, a water pump is installed on the blank forming platform, the water pump inlet is connected with the collecting pool, and a cleaning pipeline is fixedly connected with the water pump outlet.

[0009] Further, the crushing and grading mechanism comprises a rack, a movable sieve box and a crushing roller, the rack is fixed on the blank forming platform, the movable sieve box is slidably connected with the rack, the crushing roller is rollingly connected with the rack and located at the top of the movable sieve box, and a first collecting box and a second collecting box are arranged at the bottom of the movable sieve box.

[0010] Further, a motor is fixed on the rack through bolts, a crankshaft is movably connected with the rack, a swing rod is movably sleeved on the crankshaft, and one end of the swing rod is movably connected with the movable sieve box.

[0011] Further, a discharging assembly is fixedly connected with the rack, one side of the discharging assembly penetrates through the crushing roller and is movably connected with the crushing roller, an opening is arranged on the top of the discharging assembly, and a rolling fan blade is movably connected with the inner side of the opening, and a through groove is arranged in the crushing roller.

[0012] Further, a temporary storage hopper is installed in the crushing roller, one side of the temporary storage hopper is movably connected with the discharging assembly, the other side penetrates through the crushing roller and is sleeved with a belt pulley, a top column is slidably connected with the temporary storage hopper, and the top column is uniformly fixed with extrusion crushing blocks on the temporary storage hopper.

[0013] Further, a linkage gear shaft is movably connected with the rack and located at the side of the crushing roller, a gear on one side of the linkage gear shaft is in meshing connection with a gear installed on the outer wall of the crushing roller, and a stop ring set is movably connected with the rack, the stop ring set comprises a disc and a gear, and a gear on the other side of the linkage gear shaft is in meshing connection with a gear of the stop ring set.

[0014] Further, the rack is rotatably connected with an abutting rod, one side of the abutting rod abuts against the top column, and the other side abuts against the edge of the disc of the blocking ring set, a positive and negative driving mechanism is installed on the inner wall of the rack, and a gear is sleeved on the positive and negative driving mechanism and is in meshing connection with the gear on the linkage tooth shaft.

[0015] Further, the positive and negative driving mechanism includes a ratchet sleeve, a driving shaft and a linkage disc, the output end of the motor fixedly connected with the driving shaft is fixed on the side of the rack, the gear installed on the driving shaft is in meshing connection with the linkage tooth shaft, the ratchet sleeve is movably sleeved on the driving shaft, the linkage disc is fixedly sleeved on the driving shaft in the ratchet sleeve, the blocking block is in sliding connection with the linkage disc, the bottom of the blocking block is provided with a spring, and one side of the blocking block abuts against the inner side of the ratchet sleeve.

[0016] Compared with the prior art, the beneficial effects of the present application are:

[0017] 1、In the present application, the concrete excess material is recycled and recycled in time, the production cost is reduced and the environmental pollution is reduced, the closed collection channel built by the groove, the sand scraping chain plate machine and the spiral feeding mechanism, combined with the instant flushing of the water pump and the cleaning pipeline, ensures that the concrete excess material is quickly dispersed and transported to the collection pool before hardening, the excess material is soaked in water all the way, the probability of caking is greatly reduced, the recycling problem caused by the traditional landfill method is solved, and the recycled sand and gravel is treated by the crushing and grading mechanism to obtain qualified raw materials, which are directly used for pipe pile production, the washing water is reused after sedimentation and filtration in the circulating water pool, forming a closed loop system of "excess material recycling, crushing and screening, raw material recycling", which significantly reduces the consumption of raw materials and waste treatment cost, and reduces environmental pollution.

[0018] 2、In the present application, the crushing and screening mechanism is innovated to improve the recycling efficiency and the applicability of the raw materials, the crushing roller is provided with a temporary storage hopper and an extrusion crushing block, the time sequence of the forward rotation and the reverse rotation of the crushing roller is controlled by the positive and negative driving mechanism, the caked material is impacted and crushed by the extrusion crushing block driven by the top column in the temporary storage hopper, the particles that are not completely crushed are temporarily stored and then discharged for re-screening, the caking treatment efficiency and the sand and gravel recovery rate are significantly improved, the movable sieve box is screened by the swing of the swing rod, the screen can be replaced according to the specification requirements of the sand and gravel, and the particles after screening fall into the first or second material receiving box according to the particle size, so as to meet the raw material grading requirements of different pipe pile production, and avoid the resource waste caused by the traditional single screening. BRIEF DESCRIPTION OF DRAWINGS

[0019] Figure 1 It is a whole structure schematic view of the pipe pile concrete excess material recycling and recycling system of the present application.

[0020] Figure 2 It is a main collection pool schematic view of the pipe pile concrete excess material recycling and recycling system of the present application.

[0021] Figure 3 It is the overall structure schematic view of the crushing and grading mechanism of the present application.

[0022] Figure 4 It is the main view structure schematic view of the crushing and grading mechanism of the present application.

[0023] Figure 5 It is the top view structure schematic view of the crushing and grading mechanism of the present application.

[0024] Figure 6 It is the installation structure schematic view of the temporary storage hopper in the crushing roller of the present application.

[0025] Figure 7 It is the installation structure schematic view of the movable sieve box on the machine frame of the present application.

[0026] Figure 8 It is the movable schematic view of the top column driving extrusion crushing block on the temporary storage hopper in the crushing roller of the present application.

[0027] Figure 9 It is the overall structure schematic view of the forward and reverse driving mechanism of the present application.

[0028] In the figure: 1, blank forming table; 2, raw material feeding table; 3, collection pool; 4, mixer; 5, moving hopper car; 6, distributing hopper; 7, rail; 8, distributing flat car; 9, distributing mold cover; 10, sand scraping chain plate machine; 11, mold cover cleaning machine; 12, spiral feeder; 13, chute; 14, crushing and grading mechanism; 141, machine frame; 142, movable sieve box; 143, crushing roller; 144, first-stage material collecting box; 145, second-stage material collecting box; 15, water pump; 16, cleaning pipeline; 17, circulating pool; 18, swing rod; 19, discharging assembly; 20, temporary storage hopper; 21, top column; 22, extrusion crushing block; 23, linkage gear shaft; 24, check ring group; 25, abutment rod; 26, forward and reverse driving mechanism; 261, ratchet sleeve; 262, driving shaft; 263, linkage disc; 264, check block; 265, spring. DETAILED DESCRIPTION

[0029] The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the present application.

[0030] Please refer to Figures 1-9 The present application provides a technical solution:

[0031] The pipe pile concrete excess material recycling and utilization system of the application is divided by modular work areas, a excess material flushing and collecting groove line is constructed between the blank forming table 1 and the raw material feeding table 2, and a fixed cleaning pipeline 16 is arranged to quickly realize flushing of the related material groove 13, the mobile bucket car 5, the material distribution car and the material distribution mold sleeve 9 after pipe pile pouring is completed, and the mortar directly falls into the corresponding groove, is transported through the sand scraping chain plate machine 10 and the spiral feeder 12, and finally reaches the crushing and grading mechanism 14 and the collecting pool 3 for waiting for processing.

[0032] The coarse and fine particles are graded to obtain graded raw material sand and gravel which can be used for subsequent pipe pile production. Since the excess material is recycled in a timely manner and the concrete excess material is washed and dispersed in water and is immersed in water, the probability of hardening and caking is low, and the concrete excess material is easily turned into loose sand and gravel, thereby solving the difficulty of hardening and caking of the concrete excess material which is not easy to recycle and process. The recycled sand and gravel is used for pipe pile raw material production, and the concrete excess material generated during the production process is recycled and used for production again, thereby achieving efficient recycling and utilization, reducing the production cost of pipe piles, saving resources and protecting the environment.

[0033] As shown in FIG. 1, a groove is formed in the blank forming table 1, the groove is directly below the material distribution hopper 6, extends from the mold sleeve cleaning machine 11 to the collecting pool 3 and is in communication with the collecting pool 3, and the front of the collecting pool 3 is crossed with the groove and is lower than the cross groove position away from the groove. The sand scraping chain plate machine 10 is installed in the groove, and the semi-open spiral feeder 12 is installed in the cross groove position. Figure 1 The pipe pile production related process is as follows. After the pipe mold is placed on the material distribution flat car 8 after the cage is dropped and the material distribution mold sleeve 9 is covered, the material distribution flat car 8 is located below the material distribution hopper 6 and can move forward or backward on the rail 7 by traction steel wire rope or friction wheel transmission. After the concrete material is mixed by the mixer 4, it is discharged into the material groove 13 and is transported to the top of the material distribution hopper 6 by the material bucket car and is evenly discharged by opening the bottom valve, so that the concrete material is distributed to the material distribution mold sleeve 9 and the pipe mold below the material distribution hopper 6.

[0034] After the distribution is completed, the material distribution flat car 8, the pipe mold and the material distribution mold sleeve 9 are moved away from the position below the material distribution hopper 6, the material distribution mold sleeve 9 is lifted by the crown block to the mold sleeve cleaning machine 11 for cleaning, and the lifted upper mold is placed on the pipe mold for mold closing operation. Subsequently, the pipe pile is prepared by centrifugal rotation.

[0035]

[0036] ​The water pump 15 is installed on the blank forming table 1, the end of the water pump 15 is connected with the circulating water tank 17, the other side is connected with the cleaning pipeline 16, the cleaning pipeline 16 is used for cleaning the fixed area, and the mold for ending the blanking is timely flushed, and for the cloth mold cover 9, the length is limited, and the cloth mold cover 9 needs to be processed separately through the mold cover cleaning machine 11, the concrete excess material of the mixer 4 chute 13 falls into the collecting tank 3 for further processing, and the concrete excess material of the material conveying hopper, the cloth hopper 6 and the cloth mold cover 9 falls into the groove;

[0037] The sand chain plate machine 10 is moved, and then the spiral feeding machine 12 is used to send the concrete excess material into the crushing and grading mechanism 14 for screening treatment, so that the classified qualified raw material sand and stone can be obtained and can be used for subsequent pipe pile production, if the crushing and grading mechanism 14 needs to be stopped for maintenance, the spiral feeding machine 12 is not started, and at this time, the concrete excess material is scraped to the collecting tank 3 for storage after the spiral feeding machine 12;

[0038] The flushing water flows into the circulating water tank 17 on the blank forming table 1, is filtered after sedimentation and is supplied to the water pump 15 for recycling, the pipe pile factory concrete excess material efficient recycling and utilization system can realize continuous production and continuous recycling, so that the difficulty that the concrete excess material is not easy to recycle due to hardening and caking is solved, the recycled sand and stone is used for pipe pile raw material production, the concrete excess material produced in the production process is recycled and used for production again, efficient recycling and utilization can reduce the pipe pile production cost, save resources and protect the environment.

[0039] In embodiment 2, a small part of the sand and stone discharged into the crushing and grading mechanism 14 is caked, and the crushing and grading mechanism 14 adopts a drum screening mode, the residual caked material is crushed online, and the overall sand and stone recovery rate is improved, as shown in the drawing, the main frame 141 has two layers, the top is provided with a rolling crushing drum 143, and the bottom is provided with a movable sieve box 142 moving left and right, and the spiral feeding machine 12 is provided with a discharging assembly 19 corresponding to the side of the crushing drum 143; Figure 3

[0040] As shown in the drawing, the discharging assembly 19 is installed on the frame 141 on one side of the crushing drum 143 and is movably connected with the frame 141, the top opening is used for discharging the sand material, and the sidewall motor is connected with the material winding blade, the sand material is sent into the crushing drum 143 while rotating, and falls into the crushing drum 143 through the groove; Figure 8 As shown in the drawing, the discharging assembly 19 is installed on the frame 141 on one side of the crushing drum 143 and is movably connected with the frame 141, the top opening is used for discharging the sand material, and the sidewall motor is connected with the material winding blade, the sand material is sent into the crushing drum 143 while rotating, and falls into the crushing drum 143 through the groove;

[0041] Figure 9 As shown in the drawing, the discharging assembly 19 is installed on the frame 141 on one side of the crushing drum 143 and is movably connected with the frame 141, the top opening is used for discharging the sand material, and the sidewall motor is connected with the material winding blade, the sand material is sent into the crushing drum 143 while rotating, and falls into the crushing drum 143 through the groove; Figure 8 ​​It is understood that the broken drum 143 gear same side is also provided with temporary storage hopper 20, temporary storage hopper 20 is located in the broken drum 143 inside and outside unfolding, for taking the large particle agglomerate which is not sieved in the process of broken drum 143 rotation, because temporary storage hopper 20 is movably connected with broken drum 143, and one side is provided with pulley, need to set up independent driving source drive;

[0042] At the same time, the temporary storage hopper 20 is also provided with a slideable top column 21, and the top column 21 is uniformly provided with an extrusion crushing block 22 inside the broken drum 143. The agglomerate falling between the two is crushed by the unilateral movement of the top column 21 and the impact of the extrusion crushing block 22, realizing online crushing in the process of agglomerate screening.

[0043] But if the crushed agglomerate cannot be discharged from the temporary storage hopper 20, the material continues to be fed into the reversed broken drum 143, the agglomerate between the extrusion crushing blocks 22 gradually increases, and the impact crushing effect decreases linearly. At this time, the broken agglomerate in the temporary storage hopper 20 needs to be discharged.

[0044] As shown in Figure 8 and Figure 9 The entire drive shaft 262 is movably sleeved with a ratchet sleeve 261, the inner wall of the ratchet sleeve 261 is provided with a tooth pattern, and the outer side of the ratchet sleeve 261 is sleeved with a belt and a belt pulley at the end of the temporary storage hopper 20. The rotation of the ratchet sleeve 261 realizes the rotation of the entire temporary storage hopper 20 in the broken drum 143, controls the opening direction of the temporary storage hopper 20, and when the opening is downward, the broken agglomerate automatically falls onto the broken drum 143, realizing automatic discharge.

[0045] As for the rotation control of the ratchet sleeve 261, when rotating forward, the drive shaft 262 is sleeved with a linkage disc 263, and the outer wall of the linkage disc 263 is provided with a stop block 264. When rotating clockwise, the stop block 264 extrudes the spring 265, so that the entire ratchet sleeve 261 cannot be driven to rotate. The end gear of the drive shaft 262 can drive the entire broken drum 143 to rotate through the linkage gear shaft 23, so that the temporary storage hopper 20 does not move while the entire broken drum 143 rotates, completing the feeding work of the unscreened agglomerate into the temporary storage hopper 20. At this time, the extrusion crushing block 22 on the top column 21 realizes the crushing of the entire agglomerate.

[0046] When discharging is needed, the drive shaft 262 rotates counterclockwise at this time, driving the entire ratchet sleeve 261 to rotate, and the entire temporary storage hopper 20 rotates at the same time. The broken drum 143 and the temporary storage hopper 20 rotate at the same time, completing the discharge work of the broken agglomerate. The ratio of forward and reverse rotation time is usually controlled at 5:1. In one minute of rotation time, 50 seconds are forward rotation and 10 seconds are reverse rotation.

[0047] For the movement of the top column 21 in the temporary storage hopper 20 and reset, its own in the temporary storage hopper 20 is provided with multiple spring 265 abutment, in addition to extrusion broken block 22 impact area, temporary storage hopper 20 will be set up to close the shell, to avoid the agglomeration of falling in the extrusion area, hinder the movement of the top column 21, wherein the top column 21 one end is located outside the broken drum 143, the rack 141 is also movably connected with the ring group 24;

[0048] As Figure 5 and Figure 6 The ring group 24 is composed of gear and turntable, the gear segment ring group 24 is driven to rotate by the linkage shaft 23, and the side wall of the turntable segment is not flat, and is provided with a protrusion, and the abutment rod 25 is rotatably connected to the rack 141, as Figure 4 As shown in the figure, with the rotation of the ring group 24, the protrusion on the turntable contacts the abutment rod 25, and the other side of the abutment rod 25 contacts the top column 21, so as to push the top column 21 to move in the temporary storage hopper 20, realize the automatic crushing of the agglomerated material in the rotating process, compared with the external discharge type screening and crushing, the overall sandstone agglomerate treatment efficiency is higher;

[0049] For the continuously falling screening concrete waste on the broken drum 143, the rack 141 is also provided with a movable sieve box 142, the bottom screen aperture is adjusted according to the specification of the recycled concrete waste, if the requirement is low, the movable sieve box 142 can not be started, and the crushed material screened out by the broken drum 143 is directly taken, if the requirement is high, the crankshaft is driven to rotate by the motor, as Figure 7 As shown in the figure, the movable swing rod 18 is sleeved on the crankshaft to pull the movable sieve box 142 to move left and right, the fine selection of the material after primary crushing and screening is completed, the screened material falls into the secondary material box 145, and the unfiltered material falls into the primary material box 144, and different diameter of the crushed material particles are used for different purposes.

[0050] The above content is only an example and description of the structure of the present application, and those skilled in the art can make various modifications or supplements or use similar ways to replace the described specific embodiments, as long as they do not deviate from the structure of the invention or exceed the scope defined by the present application, which shall belong to the protection scope of the present application.

Claims

1. A system for recycling and reusing leftover concrete from pipe piles, comprising a billet forming platform (1), a raw material feeding platform (2), a collection tank (3), a mixer (4), a material trough (13), a track (7), and a circulating water tank (17), characterized in that, The blank forming table (1) is equipped with a raw material feeding table (2), a mixer (4) is installed on the raw material feeding table (2), and a material trough (13) is opened on the side of the mixer (4). The top of the blank forming table (1) is evenly equipped with a track (7), and the blank forming table (1) is provided with a collection pool (3) and a circulating water pool (17). A mobile trolley (5) is slidably connected to a fixed bracket on the blank forming table (1). A cloth hopper (6) is installed on the fixed bracket on the blank forming table (1) and at the bottom of the mobile trolley (5). A cloth flatcar (8) is slidably connected to the track (7). A tube mold is placed on the cloth flatcar (8). A cloth mold sleeve (9) is placed on the top of the tube mold by a crane. The blank forming table (1) has a groove located directly below the feeding hopper (6). A mold cleaning machine (11) is installed on the track (7) on one side and at the top of the groove. The groove extends to the collection pool (3) and is connected to it. A cross groove connected to the groove is set on the side of the collection pool (3) near the groove. A scraper chain plate machine (10) is installed in the groove. A spiral feeder (12) is installed in the cross groove. A crushing and grading mechanism (14) is installed on the top of the blank forming table (1). A water pump (15) is installed on the blank forming table (1). The water inlet of the water pump (15) is connected to the collection pool (3), and the water outlet of the water pump (15) is connected to a cleaning pipeline (16). The cleaning pipeline (16) is used to clean the fixed area and to rinse the mold after the material is unloaded. As for the feeding mold (9), due to its own length limitation, it needs to be processed separately by the mold cleaning machine (11). The concrete residue that falls into the trench is moved by the scraper chain conveyor (10) and then fed into the crushing and grading mechanism (14) for screening by the screw conveyor (12). If the crushing and grading mechanism (14) needs to be shut down for maintenance, the screw conveyor (12) will not be started. At this time, the concrete residue will continue to be scraped to the collection pool (3) for storage after the screw conveyor (12).

2. The system for recycling and reusing leftover concrete from pipe piles according to claim 1, characterized in that, The crushing and grading mechanism (14) includes a frame (141), a movable screen box (142), and a crushing drum (143). The frame (141) is fixed on the billet forming table (1). The movable screen box (142) is slidably connected to the frame (141). The crushing drum (143) is slidably connected to the frame (141) and located on top of the movable screen box (142). A primary receiving box (144) and a secondary receiving box (145) are respectively provided on the frame (141) and located at the bottom of the movable screen box (142).

3. The system for recycling and reusing leftover concrete from pipe piles according to claim 2, characterized in that, A motor is fixed to the frame (141) by bolts. A crankshaft is movably connected to the frame (141), and a swing rod (18) is movably connected to the crankshaft. The other end of the swing rod (18) is movably connected to the movable screen box (142).

4. The system for recycling and reusing residual concrete from pipe piles according to claim 3, characterized in that, A discharge assembly (19) is fixedly connected to the frame (141), and one side of the discharge assembly (19) passes through the crushing drum (143) and is movably connected to it. The top of the discharge assembly (19) is provided with an opening, and a material winding fan blade is movably connected to the inside. The part of the discharge assembly (19) located inside the crushing drum (143) is provided with a through groove.

5. The system for recycling and reusing residual concrete from pipe piles according to claim 4, characterized in that, A temporary storage bucket (20) is installed inside the crushing drum (143). One side of the temporary storage bucket (20) is movably connected to the discharge assembly (19), and the other side passes through the crushing drum (143) and is fitted with a pulley. A top column (21) is slidably connected inside the temporary storage bucket (20), and the top column (21) is located on the temporary storage bucket (20). Crushed blocks (22) are uniformly fixed on the top column (21).

6. The system for recycling and reusing residual concrete from pipe piles according to claim 5, characterized in that, A linkage gear shaft (23) is movably connected on the frame (141) and located on the side of the crushing drum (143). A gear on one side of the linkage gear shaft (23) meshes with a gear installed on the outer wall of the crushing drum (143). A retaining ring group (24) is also movably connected on the frame (141). The retaining ring group (24) consists of a disc and a gear. A gear is sleeved on the other side of the linkage gear shaft (23) and meshes with the gear on the retaining ring group (24).

7. A system for recycling and reusing leftover concrete from pipe piles according to claim 6, characterized in that, A contact rod (25) is rotatably connected to the frame (141). One side of the contact rod (25) abuts against the top column (21), and the other side abuts against the edge of the disc on the retaining ring assembly (24). For the top column (21) to move and reset in the temporary storage bucket (20), the top column (21) abuts against the multi-section spring set in the temporary storage bucket 20. A forward and reverse drive mechanism (26) is installed on the inner wall of the frame (141), and a gear is sleeved on the forward and reverse drive mechanism (26) and meshes with a gear on one side of the linkage gear shaft (23).

8. A system for recycling and reusing leftover concrete from pipe piles according to claim 7, characterized in that, The forward and reverse drive mechanism (26) includes a ratchet sleeve (261), a drive shaft (262), and a linkage disc (263). The output end of the fixed motor on the side of the frame (141) is fixedly connected to the drive shaft (262). A gear is installed on the drive shaft (262) and meshes with the linkage gear shaft (23). The ratchet sleeve (261) is movably connected on the drive shaft (262). The linkage disc (263) is fixedly installed on the drive shaft (262) and inside the ratchet sleeve (261). A stop block (264) is slidably connected on the linkage disc (263), and a spring (265) is installed at the bottom of the stop block (264). One side of the stop block (264) abuts against the inner toothed pattern of the ratchet sleeve (261).

Citation Information

Patent Citations

  • Concrete excess material recovery device for tubular pile

    CN209682554U

  • Longitudinal multi-span internal circulation self-cleaning tubular pile production line and production process

    CN118081970A

  • Brickmaking production line capable of recycling concrete cleaning waste

    CN211566353U