A wireline coring tool and construction method for tunnel surface drilling

By setting up an outer tube and an inner tube extension tube in the wireline coring tool, the problem of short inner tube size is solved by achieving synchronous lengthening, which improves drilling efficiency and construction convenience, and reduces auxiliary time.

CN120575801BActive Publication Date: 2026-11-17KUNMING PROSPECTING DESIGN INSTITUTE OF CHINA NONFERROUS METALS INDUSTRY CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202510980003.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-07-16
Publication Date
2026-11-17
Estimated Expiration
2045-07-16

AI Technical Summary

Technical Problem

Traditional wireline coring tools have short inner tubes, which leads to frequent interruptions during drilling, affecting continuity and efficiency, and causing excessive auxiliary time and increased construction costs.

Method used

By threading an extension tube between the centralizer and the spring clip chamber, and threading an extension tube between the inner tube and the inner tube assembly, the outer tube unit and the inner tube unit are extended synchronously, thus avoiding frequent removal of the inner tube.

Benefits of technology

It improved drilling efficiency, reduced the number of times the inner casing was removed and placed, shortened auxiliary time, and enhanced construction convenience and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120575801B_ABST
    Figure CN120575801B_ABST
Patent Text Reader

Abstract

This invention discloses a wireline coring drill for surface drilling in tunnels and its construction method. The drill consists of an outer tube unit and an inner tube unit. In the outer tube unit, the drill bit, reamer, and other components are sequentially threaded together. In the inner tube unit, the retaining spring seat, inner tube, and other components are also sequentially threaded together. Both outer and inner tube extension tubes are provided, with at least one of each of the same length. The construction method covers the steps of extending the outer and inner tube units. When extending the outer tube unit, first connect the outer tube and reamer and lower them, then successively connect the centralizer and the outer tube extension tube to the required length, and finally connect the retaining spring chamber and drill rod and lower them to the appropriate position. The inner tube unit is extended using a lowering assembly and inner tube clamps, sequentially connecting the inner tube and the inner tube extension tube to the required length, and gradually lowering it to the designated position. This invention solves the problems of short inner tube dimensions and the need for frequent core extraction and lowering in traditional methods, reducing auxiliary time, improving drilling efficiency, and has broad application prospects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of drilling technology, and more specifically to a wireline coring drill for tunnel surface drilling and a construction method thereof. Background Technology

[0002] In the field of drilling operations, wireline coring tools, as key coring tools, have gained extremely wide application due to their unique advantages. The traditional wireline coring drilling workflow is usually as follows: drop the inner casing to the bottom → add drill rod → deliver circulating slurry to the drill bit → return to the drilling position → retrieve the inner casing and extract the rock core → drop the inner casing again, and repeat this cycle for drilling operations.

[0003] However, traditional wireline coring technology has revealed several shortcomings in practical applications that urgently need to be addressed: Limited inner tube size: The inner tube of traditional coring devices is generally short, typically only about three meters, and in tunnel drilling, the length of most inner tubes is less than 1.5 meters. This limitation means that once the inner tube is filled with core samples during drilling operations, drilling cannot continue, necessitating an interruption for core extraction and other subsequent steps, significantly impacting the continuity and efficiency of drilling. Excessive auxiliary time: The auxiliary time consumed from retrieving the inner tube to deploying it is excessive, consuming a significant amount of valuable construction time. In drilling operations, time is efficiency; prolonged auxiliary operations severely affect overall drilling efficiency, increasing construction costs and timeframes.

[0004] To effectively overcome the shortcomings of the traditional wireline coring process, this invention proposes a wireline coring tool and construction method for tunnel surface drilling. Summary of the Invention

[0005] This invention provides a wireline coring drill for tunnel surfaces and a construction method thereof. By threading an outer tube extension pipe between the stabilizer and the spring clamp chamber, and threading an inner tube extension pipe between the inner tube and the inner tube assembly, the outer tube unit and the inner tube unit are simultaneously extended. This allows for continuous drilling without having to retrieve the inner tube, thus solving the problems existing in the background art.

[0006] To achieve the above objectives, the technical solution of the present invention is as follows: A wireline coring drill for tunnel surface use includes an outer tube unit and an inner tube unit. The outer tube unit includes a drill bit, a reamer, a centralizing ring, an outer tube, a centralizer, a seat ring, a spring-loaded chamber, and a drill rod. The centralizer is installed inside the reamer. The drill bit, reamer, outer tube, centralizer, spring-loaded chamber, and drill rod are sequentially threaded together to form the outer tube unit. The inner tube unit includes a circlip seat, a circlip, a circlip retainer, an inner tube, and an inner tube assembly. The circlip seat, inner tube, and inner tube assembly are sequentially threaded together to form the inner tube unit. An extended outer tube is threadedly connected between the centralizer and the spring-loaded chamber. An extended inner tube is threadedly connected between the inner tube and the inner tube assembly. At least one extended outer tube and one extended inner tube are provided, and the extended outer tube and the extended inner tube have the same length.

[0007] Furthermore, a seat ring is installed at the bottom of the ejector chamber.

[0008] Furthermore, the retaining ring is installed inside the retaining ring seat, and the retaining ring is installed inside the retaining ring seat and located on top of the retaining ring.

[0009] Furthermore, the inner tube assembly is equipped with a spring-loaded caliper, and the spring-loaded caliper chamber has a slot adapted to the spring-loaded caliper.

[0010] Furthermore, it also includes an inner tube wrench, which includes a pair of locking blades that are hinged together. The bottom dimension of the inner tube wrench is the same as the top dimension of the drill pipe. A pair of bearings are symmetrically threaded on the inner side of the inner tube wrench for fixing the inner tube and the inner tube extension tube.

[0011] Furthermore, a female locking head and a male locking head are respectively provided on both sides of the pair of locking blades, and the male locking head and the female locking head are engaged.

[0012] Furthermore, the female locking head has a locking hole, the male locking head has a positioning hole, the locking hole is threadedly connected to a locking screw, and the locking screw also engages with the positioning hole threadedly for limiting and fixing.

[0013] Furthermore, a pair of hanging ears are symmetrically fixed on the outer side of the pair of locking blades, and anti-slip strips are symmetrically arranged on the inner side of the pair of retaining plates. The anti-slip strips are spaced apart, and the inner side of the retaining plate is wider at the top and narrower at the bottom.

[0014] Furthermore, it also includes a lowering assembly, which includes a bearing, a connecting rod that is rotatably connected to the bearing, and a pair of hanging rings that are symmetrically fixed on both sides of the bottom of the connecting rod.

[0015] This invention also discloses a continuous coring method, which uses the drilling tool described in this invention and specifically includes the following steps: S1: Extension of Outer Tube Unit: First, connect the reamer, drill bit, and reamer's built-in centering ring to the outer tube in sequence. Use a power head or winch to lower the outer tube to a position where it protrudes at least 30 cm from the borehole opening. Secure and tighten the outer tube. Thread one end of the centering ring to the protruding end of the outer tube. After connection, use a power head or winch to lower the outer tube into the hole to a position where it protrudes at least 30 cm from the borehole opening. Secure and tighten the outer tube. Thread one end of the first outer tube extension to the other end of the centering ring. After connection, use a power head or winch to lower the first outer tube extension into the hole to a position where it protrudes at least 30 cm from the borehole opening. Secure and tighten the first extension. The outer tube extension tube is used to connect one end of the second outer tube extension tube to the exposed end of the first outer tube extension tube with a thread. After the connection is completed, the second outer tube extension tube is lowered into the hole using a power head or winch until it protrudes more than 30 cm from the hole opening. The second outer tube extension tube is then tightened. This process is repeated to add more outer tube extension tubes until the required number of outer tube extension tubes is reached. The other end of the last outer tube extension tube is then threaded to one end of the spring clamp chamber. The spring clamp chamber contains a seat ring. The other end of the spring clamp chamber is then threaded to the drill rod. After the connection is completed, the outer tube unit is lowered into the hole using a power head or winch until the drill bit is more than 1 meter from the bottom of the hole. S2: Inner Tube Unit Extension: Fix the first inner tube wrench at the drill rod end of the outer tube unit connected in S1. Install the snap ring into the snap ring seat and install the snap ring retainer on top of the snap ring. Thread one end of the inner tube to the snap ring seat. After connection, use a retrieval tool and lowering assembly to lower it into the outer tube until the threads of the other end of the inner tube protrude 20-30 cm from the inner tube wrench. Tighten the locking screw and fix the inner tube using the inner tube wrench. Fix the second inner tube wrench 20-30 cm from the threads at one end of the first inner tube extension. Thread the other end of the first inner tube extension to the other end of the inner tube. After connection, remove the first inner tube wrench and lower the first inner tube extension using the retrieval tool and lowering assembly. Place and fix the second inner tube wrench to the end of the drill pipe. After fixing, use the removed first inner tube wrench to fix it 20-30 cm away from the threaded end of the second inner tube extension. Thread the other end of the second inner tube extension to the end of the first inner tube extension where the second inner tube wrench is installed. After connection, remove the second inner tube wrench and use the retrieval tool and lowering assembly to lower the second inner tube while fixing the first inner tube wrench to the end of the drill pipe. Repeat this process to increase the number of inner tube extensions until the required number of inner tube extensions is reached. Remove the lowering assembly, thread the last inner tube extension to the inner tube assembly, and connect the inner tube assembly to the retrieval tool. After connection, remove the first and second inner tube wrenches and use the retrieval tool to lower the inner tube assembly to the designated position. The steps for lowering the inner tube in S2 are as follows: use the retrieval tool to fix the bearing at the end of the lowering assembly, and fix the inner tube wrench at one end of the inner tube. Use steel wire rope to connect the hanging ring at the bottom of the connecting rod and the hanging lug of the locking blade respectively. Lower the retrieval tool and rotate the inner tube to connect it to the threaded thread of the stabilizer when the other end of the inner tube is close to the threaded thread of the stabilizer. After the connection is completed, disconnect the connection between the hanging ring and the hanging lug. The lowering process of the inner tube extension tube is the same as the lowering process of the inner tube. The number of outer tube extensions added in S1 is the same as the number of inner tube extensions added in S2.

[0016] The present invention has the following beneficial effects: (1) By setting an extended outer tube and an extended inner tube, the present invention increases the length of the outer tube unit and the inner tube unit, solves the problem of the traditional short inner tube size, reduces the number of times the inner tube is frequently used to pick up and put out rock cores, significantly improves drilling efficiency, and also facilitates construction operations and shortens auxiliary time.

[0017] (2) The inner tube wrench fixes the inner tube by a pair of hinged locking blades and inner retaining plates. From the snap-fit ​​of the locking female and male heads to the threaded fit of the locking screw with the locking hole and positioning hole, multiple guarantees are provided for the locking of the inner tube wrench, ensuring that the locking blades are firmly connected and preventing the inner tube from falling off due to loosening of the inner tube wrench. Moreover, the setting of the outer lug of the locking blade facilitates the movement of the inner tube wrench, and the anti-slip strip on the inner side of the retaining plate and the upper-wide and lower-narrow design increase the anti-slip effect, improving the convenience and safety of construction.

[0018] (3) By setting up a lowering component, when lowering the inner tube or the inner tube extension tube, the inner tube or the inner tube extension tube can be rotated due to the setting of bearings and connecting rods, which facilitates the threaded connection, improves work efficiency and saves working time. Attached Figure Description

[0019] Figure 1 This is a schematic diagram of the overall structure of the present invention; Figure 2 This is a schematic diagram of the outer tube unit structure of the present invention; Figure 3 This is a schematic diagram of the inner tube unit structure of the present invention; Figure 4 This is a schematic diagram of the card slot structure of the present invention; Figure 5 This is a schematic diagram of the internal tube clamp structure of the present invention; Figure 6 This is a schematic diagram of the locking blade hinge structure of the present invention; Figure 7 This is a schematic diagram of the bearing structure of the present invention; Figure 8 This is a schematic diagram of the extended outer tube unit structure of the present invention; Figure 9 This is a schematic diagram of the extended inner tube unit structure of the present invention; Figure 10 This is a schematic diagram of the structure of the lower component of the present invention; In the diagram, 1-Drill bit, 2-Reamer, 3-Stabilizing ring, 4-Outer tube, 5-Stabilizer, 6-Spring clasp chamber, 7-Drill rod, 8-Spring clasp seat, 9-Inner tube, 10-Inner tube assembly, 11-Extended outer tube, 12-Extended inner tube, 13-Seated ring, 14-Spring clasp, 15-Spring clasp retainer, 16-Spring clasp clamp, 17-Clad groove, 18-Inner tube wrench, 19-Locking blade, 20-Bearing plate, 21-Locking female head, 22-Locking male head, 23-Locking hole, 24-Locking screw, 25-Positioning hole, 26-Hanging lug, 27-Anti-slip strip, 28-Retrieving tool, 29-Connecting rod, 30-Bearing, 31-Hanging ring. Detailed Implementation

[0020] The specific embodiments of the present invention will be further described below with reference to the accompanying drawings. It should be noted that these descriptions are for the purpose of aiding understanding the present invention, but do not constitute a limitation thereof. Furthermore, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0021] Example 1

[0022] This embodiment discloses a wireline coring tool for surface drilling in tunnels, as shown in the attached diagram. Figure 1-7 and attached Figure 10As shown, the system includes an outer tube unit and an inner tube unit. The outer tube unit includes a drill bit 1, a reamer 2, a centralizing ring 3, an outer tube 4, a centralizing ring 5, a seat ring 13, a spring-loaded chuck chamber 6, and a drill rod 7. The drill bit 1, reamer 2, outer tube 4, centralizing ring 5, spring-loaded chuck chamber 6, and drill rod 7 are sequentially connected by threads to form the outer tube unit. The centralizing ring 3 is installed inside the reamer 2 to ensure the stability of the reamer 2 during operation, making the drilling operation more accurate and stable, and further improving the drilling quality. The spring-loaded chuck chamber... A seat ring 13 is installed at the bottom of the spring clip chamber 6; the seat ring 13 provides stable support and positioning for the spring clip chamber 6, enhances the structural strength of the spring clip chamber 6, and ensures its normal operation during drilling; in this embodiment, the drill rod 7 replaces the original spring clip stop, and a seat ring 13 is installed at the bottom of the spring clip chamber 6; and a centralizer 5 is threaded between the outer tube 4 and the spring clip stop to compensate for the center offset of the drill bit during drilling; the inner tube unit includes a circlip seat 8, a circlip 14, and a circlip stop. The inner tube 9, inner tube assembly 10, inner tube seat 8, inner tube 9, and inner tube assembly 10 are sequentially threaded together to form an inner tube unit. The retaining ring 14 is installed inside the retaining ring seat 8, and the retaining ring 15 is installed inside the retaining ring seat 8 and located on top of the retaining ring 14. This installation method can effectively fix the retaining ring 14, prevent the retaining ring 14 from shifting during drilling, ensure the retaining ring 14 reliably grips the rock core, and improve the core retrieval success rate. The centralizer 5 and the spring-loaded chamber 6 are threadedly connected by an outer... An extension tube 11 is provided, and an extension tube 12 is threadedly connected between the inner tube 9 and the inner tube assembly 10. At least one extension tube 11 and one extension tube 12 are provided, and their lengths are identical. By providing extension tubes 11 and 12, the lengths of the outer and inner tube units are effectively increased, solving the problem of the traditional short inner tube 9, reducing the frequency of core extraction and placement, and improving drilling efficiency. Simultaneously, the reasonable structural design facilitates construction operations and helps shorten auxiliary time.

[0023] Specifically, the inner tube assembly 10 is equipped with a spring clamp 16, and the spring clamp chamber 6 has a groove 17 adapted to the spring clamp 16. The cooperative design of the spring clamp 16 and the groove 17 enables precise connection and positioning between the inner tube assembly 10 and the spring clamp chamber 6, ensuring the stability of the inner tube 9 during drilling, preventing the inner tube 9 from shaking or falling off, thereby ensuring the smooth progress of the coring operation.

[0024] Specifically, it also includes an inner tube wrench 18, which includes a pair of locking blades 19. The pair of locking blades 19 are hinged together. The bottom dimension of the inner tube wrench 18 is the same as the top dimension of the drill rod 7. The inner side of the inner tube wrench 18 is symmetrically threaded with a pair of bearings 20 for fixing the inner tube 9 and the inner tube extension tube 12.

[0025] Specifically, it also includes a lowering component, which includes a bearing 30, a connecting rod 29 that is rotatably connected to the bearing 30, and a pair of hanging rings 31 that are symmetrically fixed on both sides of the bottom of the connecting rod 29.

[0026] Example 2

[0027] To enhance the locking effect on the inner tube 9, the difference from the above embodiment is as follows: Figure 5 As shown, a pair of locking blades 19 are symmetrically provided with a female locking head 21 and a male locking head 22 on each side, and the male locking head 22 and the female locking head 21 are engaged in a snap-fit ​​design. The snap-fit ​​design of the male locking head 22 and the female locking head 21 enables the pair of locking blades 19 to be quickly and firmly connected together, further enhancing the fixing effect of the inner tube wrench 18 on the inner tube 9, and also facilitating the opening and closing operation of the inner tube wrench 18.

[0028] Example 3

[0029] To further enhance the locking and fixing effect of the internal tube wrench 18, as shown in the attached... Figure 5 As shown, the difference from the above embodiment is that the female locking head 21 has a locking hole 23, and the male locking head 22 has a positioning hole 25. The locking hole 23 is threadedly connected to a locking screw 24, and the locking screw 24 also engages with the positioning hole 25 for limiting and fixing. The threaded engagement of the locking screw 24 with the locking hole 23 and the positioning hole 25 provides double protection for the locking of the inner tube wrench 18, ensuring the firmness and stability of the locking blade 19 connection, and preventing the inner tube 9 from falling off due to loosening of the inner tube wrench 18 during construction, thus delaying the construction progress.

[0030] Example 4

[0031] To facilitate the movement of the internal pipe wrench 18, as shown in the attached document... Figure 5-6 As shown, the difference from the above embodiment is that a pair of hooks 26 are symmetrically fixed on the outer side of the pair of locking blades 19; in order to further increase the anti-slip effect, anti-slip strips 27 are symmetrically arranged on the inner side of the pair of retaining plates 20, the anti-slip strips 27 are spaced apart, and the inner side of the retaining plate 20 is wider at the top and narrower at the bottom.

[0032] Example 5

[0033] This embodiment discloses a continuous coring construction method, as shown in the attached figure. Figure 8-9 As shown, this construction method uses the drilling tool described in this invention, and the method specifically includes the following steps: This embodiment uses the example of extending two outer tubes 4 and two inner tubes 12 to illustrate the process: S1: Extension of the outer tube unit: First, connect the outer tube 4 sequentially to the reamer 2, drill bit 1, and the centralizing ring 3 inside the reamer 2. Use a power head or winch (the power head and winch are commercially available devices, not shown in the figure, but the same applies) to lower the outer tube 4 to a position where it protrudes more than 30 cm from the hole opening. Secure the outer tube 4. Thread one end of the centralizer 5 to the protruding end of the outer tube 4. After connection, use a power head or winch to lower the outer tube 4 into the hole to a position where it protrudes more than 30 cm from the hole opening. Secure the outer tube 4 (in this embodiment, clamping the outer tube can be done with pipe wrenches or external equipment; this process will not be described in detail here). Thread one end of the first outer tube extension tube 11 to the other end of the centralizer 5. After connection, use a power head... Alternatively, a winch can be used to lower the first outer tube extension 11 into the hole to a position where it protrudes more than 30 cm from the hole opening. The first outer tube extension 11 is then tightened and secured. One end of the second outer tube extension 11 is threadedly connected to the protruding end of the first outer tube extension 11. After the connection is completed, a power head or a winch can be used to lower the second outer tube extension 11 into the hole to a position where it protrudes more than 30 cm from the hole opening. The second outer tube extension 11 is then tightened and secured. The other end of the second outer tube extension 11 is threadedly connected to one end of the spring clamp chamber 6. The spring clamp chamber 6 contains a seat ring 13. The other end of the spring clamp chamber 6 is threadedly connected to the drill rod 7. After the connection is completed, a power head or a winch can be used to lower the outer tube unit into the hole until the drill bit 1 is more than 1 meter from the bottom of the hole. S2: Inner Tube Unit Extension: Fix the first inner tube clamp 18 at the end of the drill rod 7 of the outer tube unit connected in S1. Install the snap ring 14 into the snap ring seat 8 and install the snap ring retainer 15 on top of the snap ring 14. Thread one end of the inner tube 9 to the snap ring seat 8. After connection, use the retrieval tool 28 and the lowering assembly to lower it into the outer tube 4 until the threads of the inner tube 9 protrude 20-30 cm from the inner tube clamp 18. Tighten the locking screw 24 to fix the inner tube 9 through the inner tube clamp 18. Fix the second inner tube clamp 18 20-30 cm away from the threads at one end of the first inner tube extension tube 12. Thread the other end of the first inner tube extension tube 12 to the other end of the inner tube 9. After connection, remove the first inner tube clamp 18 and pass the first inner tube extension tube 12 through the retrieval tool. 28. With the lowering assembly, the second inner tube 9 is lowered and the second inner tube wrench 18 is fixed to the end of the drill pipe 7. After fixing, the first inner tube wrench 18 is removed and fixed 20-30 cm away from the threaded end of the second inner tube extension tube 12. The other end of the second inner tube extension tube 12 is threadedly connected to the end of the first inner tube extension tube 12 where the second inner tube wrench 18 is installed. After the connection is completed, the second inner tube wrench 18 is removed and the second inner tube 9 is lowered through the retrieval tool 28 with the lowering assembly. The first inner tube wrench 18 is fixed to the end of the drill pipe 7. The lowering assembly is removed, and the inner tube assembly 10 is threadedly connected to the second inner tube extension tube 12. The inner tube assembly 10 is then connected to the retrieval tool 28. After the connection is completed, the first inner tube wrench 18 and the second inner tube wrench 18 are removed, and the inner tube assembly 10 is lowered to the specified position using the retrieval tool 28. The steps for lowering the inner tube in S2 are as follows: use the retrieval tool 28 to fix the bearing 30 at the end of the lowering assembly, and fix the inner tube clamp to one end of the inner tube 9. Use steel wire rope to connect the bottom hanging ring 31 of the connecting rod 29 to the hanging ear 26 of the locking blade 19 respectively. Lower the retrieval tool 28 and rotate the inner tube 9 to connect it to the threaded connection of the centralizer 5 when the other end of the inner tube 9 is close to the threaded connection of the centralizer 5. After the connection is completed, disconnect the connection between the hanging ring 31 and the hanging ear 26. The lowering process of the inner tube extension tube 12 is the same as the lowering process of the inner tube 9, and will not be described again here. It should be noted that the number of outer tube extension tubes 11 added in S1 is the same as the number of inner tube extension tubes 12 added in S2.

Claims

1. A wireline coring tool for tunnel surface drilling, characterized in that, The system includes an outer tube unit and an inner tube unit. The outer tube unit includes a drill bit (1), a reamer (2), a centralizing ring (3), an outer tube (4), a centralizer (5), a seat ring (13), a spring-loaded chamber (6), and a drill rod (7). The centralizing ring (3) is installed inside the reamer (2). The drill bit (1), reamer (2), outer tube (4), centralizer (5), spring-loaded chamber (6), and drill rod (7) are sequentially connected by threads to form the outer tube unit. A seat ring (13) is installed at the bottom of the spring-loaded chamber (6). The inner tube unit includes a snap ring seat (8), a snap ring (14), and a snap ring retainer. (15), inner tube (9), inner tube assembly (10), the snap ring seat (8), inner tube (9), inner tube assembly (10) are sequentially threaded together to form an inner tube unit, the centralizer (5) and the spring clip chamber (6) are threaded together with an outer tube extension tube (11), the inner tube (9) and the inner tube assembly (10) are threaded together with an inner tube extension tube (12), the outer tube extension tube (11) and the inner tube extension tube (12) are at least one, and the outer tube extension tube (11) and the inner tube extension tube (12) are of the same length, the outer tube extension tube (11) and the inner tube extension tube (12) are of the same length, the outer tube extension tube (11) and the inner tube extension tube (12) are threaded together with an inner tube extension tube (12) 1) The number of inner tube extension tubes (12) is the same; the drill bit also includes an inner tube wrench (18), the inner tube wrench (18) includes a pair of locking blades (19), the pair of locking blades (19) are hinged, the bottom dimension of the inner tube wrench (18) is the same as the top dimension of the drill rod (7), the inner side of the inner tube wrench (18) is symmetrically threaded with a pair of bearings (20) for fixing the inner tube (9) and the inner tube extension tube (12), the pair of locking blades (19) are symmetrically provided with locking female heads (21) and locking male heads (22) on both sides, the locking male heads (22) are respectively provided with locking female heads (21) and locking male heads (22) The locking blade (22) and the locking female head (21) are engaged. The locking female head (21) has a locking hole (23), and the locking male head (22) has a positioning hole (25). The locking hole (23) is threadedly connected to the locking screw (24). The locking screw (24) is also threadedly engaged with the positioning hole (25) for limiting and fixing. A pair of hanging ears (26) are symmetrically fixed on the outer side of the locking blade (19). A pair of anti-slip strips (27) are symmetrically arranged on the inner side of the pair of bearings (20). The anti-slip strips (27) are spaced apart. The inner side of the bearing (20) is wider at the top and narrower at the bottom.

2. The wireline coring tool for tunnel surface drilling according to claim 1, characterized in that, The retaining ring (14) is installed inside the retaining ring seat (8), and the retaining ring (15) is installed inside the retaining ring seat (8) and located on top of the retaining ring (14).

3. The wireline coring tool for tunnel surface drilling according to claim 2, characterized in that, The inner tube assembly (10) is provided with a spring caliper (16), and the spring caliper chamber (6) is provided with a caliper groove (17) adapted to the spring caliper (16).

4. The wireline coring tool for tunnel surface drilling according to claim 3, characterized in that, It also includes a lowering assembly, which includes a bearing (30), the bearing (30) being tumbledly connected to a connecting rod (29), and a pair of hanging rings (31) being symmetrically fixed on both sides of the bottom of the connecting rod (29).

5. A construction method using the coring drill bit as described in claim 4, characterized in that, Includes the following steps: S1: Extending the outer tube unit: First, connect the reamer (2), drill bit (1), and reamer (2) with the inner straightening ring (3) in sequence using the outer tube (4). Use a power head or winch to lower the outer tube (4) to a position where it protrudes more than 30 cm from the hole opening. Clamp the outer tube (4). Thread one end of the straightening device (5) to the protruding end of the outer tube (4). After the connection is completed, use a power head or winch to lower the outer tube (4) into the hole to a position where it protrudes more than 30 cm from the hole opening. Clamp the outer tube (4). Thread one end of the first outer tube extension tube (11) to the other end of the straightening device (5). After the connection is completed, use a power head or winch to lower the first outer tube extension tube (11) into the hole to a position where it protrudes more than 30 cm from the hole opening. Clamp the first outer tube extension tube (11) to the hole. The long pipe (11) is connected by thread to the exposed end of the first outer pipe extension pipe (11) with one end of the second outer pipe extension pipe (11). After the connection is completed, the second outer pipe extension pipe (11) is lowered into the hole to a position more than 30 cm above the hole opening using a power head or winch. The second outer pipe extension pipe (11) is clamped and tightened. The outer pipe extension pipe (11) is added in this way until the required number of outer pipe extension pipes (11) is reached. The other end of the last outer pipe extension pipe (11) is connected by thread to one end of the spring clamp chamber (6). The spring clamp chamber (6) has a seat ring (13) inside. The other end of the spring clamp chamber (6) is connected by thread to the drill rod (7). After the connection is completed, the outer pipe unit is lowered into the hole using a power head or winch until the drill bit (1) is more than 1 meter away from the bottom of the hole. S2: Inner tube unit extension: Fix the first inner tube wrench (18) at the end of the drill rod (7) of the outer tube unit connected in S1, install the snap ring (14) in the snap ring seat (8) and install the snap ring retainer (15) on the top of the snap ring (14), and thread one end of the inner tube (9) to the snap ring seat (8). After the connection is completed, use the retrieval tool (28) and the lowering assembly to lower it into the outer tube (4) until the thread of the other end of the inner tube (9) is exposed in the inner tube wrench (18) 20- At a position of 30 cm, the locking screw (24) is used to fix the inner tube (9) with the inner tube wrench (18). The second inner tube wrench (18) is fixed 20-30 cm from the thread at one end of the first inner tube extension tube (12). The other end of the first inner tube extension tube (12) is threaded to the other end of the inner tube (9). After connection, the first inner tube wrench (18) is removed, and the first inner tube extension tube (12) is lowered using the retrieval tool (28) and the lowering assembly. The second inner tube wrench (18) is fixed to the end of the drill rod (7). After fixing, the first inner tube wrench (18) is removed and fixed 20-30 cm away from the threaded end of the second inner tube extension tube (12). The other end of the second inner tube extension tube (12) is threadedly connected to the end of the first inner tube extension tube (12) where the second inner tube wrench (18) is installed. After the connection is completed, the second inner tube wrench (18) is removed and the second inner tube (9) is lowered through the retrieval tool (28) and in conjunction with the lowering assembly. Place and fix the first inner tube wrench (18) to the end of the drill rod (7), and repeat this process to increase the number of inner tube extension tubes (12) until the required number of inner tube extension tubes (12) is reached. Remove the lowering assembly, use the last inner tube extension tube (12) to thread and connect the inner tube assembly (10), and connect the inner tube assembly (10) to the retrieval tool (28). After the connection is completed, remove the first inner tube wrench (18) and the second inner tube wrench (18), and use the retrieval tool (28) to lower the inner tube assembly (10) to the specified position. The steps for lowering the inner tube in S2 are as follows: use the retrieval tool (28) to fix the bearing (30) at the end of the lowering assembly, and fix the inner tube wrench at one end of the inner tube (9). Use steel wire rope to connect the bottom hanging ring (31) of the connecting rod (29) and the hanging ear (26) of the locking blade (19) respectively. Lower the retrieval tool (28) and rotate the inner tube (9) to connect it with the threaded connection of the centralizer (5) when the other end of the inner tube (9) is close to the threaded connection of the centralizer (5). After the connection is completed, disconnect the connection between the hanging ring (31) and the hanging ear (26). The lowering process of the inner tube extension tube (12) is the same as the lowering process of the inner tube (9). The number of outer tube extension tubes (11) added in S1 is the same as the number of inner tube extension tubes (12) added in S2.