Fabricated ecological energy storage wall and wall construction method
Through the design of prefabricated ecological energy storage walls and the use of reinforced steel bars and sound insulation materials, the problems of low efficiency and poor sound insulation of traditional brick walls were solved, and efficient and high-strength wall construction was achieved.
Patent Information
- Application Number
- CN202511129355.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-13
- Publication Date
- 2025-09-26
AI Technical Summary
The traditional brick wall construction method has low construction efficiency, high labor intensity, poor sound insulation and thermal insulation effects, is difficult to meet the high standards of modern construction, and has low strength.
The assembled ecological energy storage wall is composed of a base plate, an assembled ecological box and a gripping assembly. Vertical and horizontal reinforcement steel bars are used to enhance the structural strength. Sound insulation cotton boards and honeycomb panels are used to improve the sound insulation performance. The raw materials are quickly filled in by a grouting machine to achieve rapid construction of the wall.
It reduces labor demand, lowers labor intensity, shortens the construction period, improves the construction efficiency and sound insulation performance of the wall, and enhances the structural strength.
Smart Images

Figure CN120701027A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of assembled ecological buildings, and in particular to an assembled ecological energy storage wall and a wall construction method. Background Art
[0002] Walls are vertical components of buildings, used to separate spaces, enclose the interior and exterior, and in some cases, bear weight. Walls can be made from a variety of materials, such as brick, stone, concrete, wood, and steel. Prefabricated ecological energy storage walls combine eco-friendly materials with modern prefabricated construction technology.
[0003] In existing technology, preparatory work is crucial during wall construction. Workers will comprehensively and meticulously prepare the materials required for wall construction, including bricks, cement, and sand. At the same time, they will check all kinds of tools to ensure that the materials are complete and the tools are intact and can be used normally. Afterwards, cement mortar is mixed according to the precise ratio requirements to ensure that the mortar performance meets the wall construction standards and lay the foundation for the quality of subsequent wall construction. After the preparatory work is completed, the wall construction process officially begins. Workers first evenly spread a layer of mixed mortar on the wall base, which plays a key role in connecting the wall base and the bricks. Then they place the bricks in order, carefully bonding each one with mortar. During the masonry process, workers will use tools such as spirit levels and plumb lines to ensure that the bricks are horizontal and vertical at all times to ensure the stability and verticality of the wall. After the bricks are laid, the finishing work cannot be ignored. Workers will clean up the excess mortar to make the wall neat and beautiful. Then they use professional testing tools to check the flatness of the wall surface and adjust and repair any uneven areas until the wall fully meets the quality requirements, thus completing the entire wall construction process.
[0004] However, the traditional brick walling method has limitations. In terms of construction efficiency, the speed of laying bricks one by one is slow, which consumes a lot of time and manpower, is labor-intensive and has a long cycle. In terms of performance, bricks have poor actual sound insulation and heat preservation effects, making it difficult to meet the high standards of modern buildings. In addition, they have low strength and insufficient support and protection capabilities in high-demand building scenarios.
[0005] During use, the invention is set up, so it is necessary to invent an assembled ecological energy storage wall and a wall construction method to solve the above problems. Summary of the Invention
[0006] The purpose of the present invention is to provide an assembled ecological energy storage wall and a wall construction method to solve the problems raised in the above background technology.
[0007] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: an assembled ecological energy storage wall, comprising a base plate, an assembled ecological box and a gripping assembly, an assembled ecological box is provided on the top of the base plate, a gripping assembly is provided on the bottom of the base plate, the top of the assembled ecological box is fixedly connected to the installation box, the bottom of the assembled ecological box is fixedly connected to the clamping plate, a screw block is rotatably connected in the installation box, one side of the screw block is fixedly connected to a screw rod, the end of the screw rod away from the screw block is fixedly connected to a connecting rod, and one end of the connecting rod is fixedly connected to the screw block. There are two screws, and a trapezoidal block is threadedly connected to the screw one. A spring is fixedly connected to the inside of the installation box, and a fixed plate is fixedly connected to one side of the spring one. A clamping plate is fixedly connected to the fixed plate one, and the clamping plate is slidably connected to the inside of the installation box through a through hole opened inside the installation box. A push block is threadedly connected to the screw two, and a spring is fixedly connected to the inside of the installation box. One side of the spring two is fixedly connected to the fixed plate two, and the fixed plate two is fixedly connected to the clamping plate two. The clamping plate two slides inside the installation box, and a reinforcement component is provided in the assembly ecological box.
[0008] Preferably, the reinforcement component includes a sound insulation cotton board, which is fixedly connected to both ends of the assembly eco-box, a honeycomb panel fixedly connected to the sound insulation cotton board, a honeycomb panel fixedly connected to the honeycomb panel, a pouring port is opened on the top of the assembly eco-box, a reinforcement block is fixedly connected in the assembly eco-box, a reinforcement pipe is fixedly connected in the reinforcement block, connecting pipes are fixedly connected at both ends of the reinforcement block, vertical reinforcement steel bars are slidably connected in the connecting pipes, and horizontal reinforcement steel bars are slidably connected in the reinforcement block.
[0009] Preferably, the assembly eco-box is provided with through holes, and the vertical reinforcement steel bars and the horizontal reinforcement steel bars pass through the assembly eco-box through the through holes and are distributed in a crisscross pattern inside the assembly eco-box.
[0010] Preferably, a through hole is provided on the snap-in plate, and one set of assembly eco-boxes can be snap-connected with the first and second card plates through the through hole on the snap-in plate, so that the two sets of assembly eco-boxes are connected to each other.
[0011] Preferably, when the two groups of pallet 1 and pallet 2 approach each other at the same time, the two groups of assembled eco-boxes will separate from each other.
[0012] Preferably, when the trapezoidal block and the push block are simultaneously away from the twist block 1, the clamping plate 1 and the clamping plate 2 will enter the clamping plate to complete the assembly of the two sets of assembly eco-boxes.
[0013] Preferably, the gripping assembly includes an insertion tube, which is fixedly connected to the bottom of the base plate, with screw three rotatably connected inside the insertion tube, with screw block two fixedly connected to the top of screw three, with a movable fixing frame fixedly connected to the inner side of the insertion tube, with a conical triangular pushing block threadedly connected to screw three, with a parallel insertion block slidingly connected to the inner side of the movable fixing frame, and a through hole being provided on the insertion tube, through which the parallel insertion block is slidably connected to the inside of the insertion tube.
[0014] Preferably, a sliding groove is provided on the parallel insertion block, and the conical triangular pushing block is slidably connected to the inside of the parallel insertion block through the sliding groove.
[0015] Preferably, when the conical triangular pushing block is away from the bottom plate, the connecting rod slides out of the insertion tube and embeds into the soil; when the conical triangular pushing block is close to the second screw block, the parallel insertion block is separated from the soil.
[0016] A method for constructing an assembled ecological energy storage wall, comprising the following steps:
[0017] Step 1: Insert the insertion tube at the bottom of the base plate into the soil, turn the screw block 2, and drive the screw rod 3 to rotate. The conical triangular push block on the screw rod 3 will rotate accordingly and gradually move away from the screw block 2, pushing the parallel insertion block to slide in the mobile fixing frame. As the conical triangular push block moves away from the screw block 2, the parallel insertion block slides out of the insertion tube and into the soil, firmly fixing the base plate to the ground, completing the paving;
[0018] Step 2: Place the assembled eco-box on top of the base plate and insert vertical reinforcement steel bars. The vertical reinforcement steel bars first enter the interior of the assembled eco-box, then enter the connecting pipe in the reinforcement block, and finally penetrate the assembled eco-box and the base plate into the soil. Insert until one end is completely inserted into the interior of the assembled eco-box. According to the width of the wall, the assembled eco-boxes are placed side by side on both sides of the preliminarily fixed assembled eco-box. Each group is inserted with vertical reinforcement steel bars to complete the fixation with the base plate. Then insert the horizontal reinforcement steel bars so that they penetrate the assembled eco-box and are inserted into the interior of the reinforcement block. Because the horizontal reinforcement steel bars are longer, the parallel assembled eco-boxes can be connected through and through. The vertical reinforcement steel bars form a well shape inside the assembled eco-box.
[0019] Step 3: Put cement, sand, gravel, polyvinyl alcohol fiber, nano-silica, rice husk ash and other raw materials into the mixer and mix them evenly. Then put them into the grouting machine, insert the grouting machine tube into the assembly eco-box through the pouring port, and use the grouting machine to inject the mixed raw materials into the assembly eco-box to complete the construction of the first layer of the wall.
[0020] Step 4: Place the connecting plate at the bottom of the assembly eco-box on the top of the constructed assembly eco-box. Insert the installation box on the top of one set of assembly eco-boxes into the inner side of the second fixed plate at the bottom of another set. Turn the screw block one to drive the screw rod one to rotate in the installation box. The trapezoidal block on the screw rod one rotates and gradually moves away from the screw block one. At the same time, it drives the screw rod two outside the connecting rod to rotate. The screw rod two drives the push block to slowly move away from the screw block one. The trapezoidal block pushes the card plate one to slide out. The push block pushes the card plate two to slide out of the installation box. The card plates one and two enter the interior of the fixed plate two. According to the width of the wall, install the assembly eco-boxes side by side on the top of the first layer to complete the second layer assembly.
[0021] Step 5: Insert the vertical reinforcement steel bars through the second-layer assembly eco-box into the first layer, and then insert the horizontal reinforcement steel bars through the second-layer assembly eco-box to complete the second-layer foundation construction. Use a grouting machine to fill the raw materials into the assembly eco-box to complete the second-layer construction;
[0022] Step 6: Repeat steps 4 and 5 according to the wall height until the designed wall height is reached.
[0023] Compared with the prior art, the present invention provides an assembled ecological energy storage wall and a wall construction method, which has the following beneficial effects:
[0024] 1. Place the bottom clamping plate of the assembled eco-box on the top of the built box, insert one set of top-mounted boxes into another set of bottom fixing plates, turn the screw block one, drive the components to slide the clamping plate in and fix it, install other boxes side by side according to the wall width, insert horizontal and vertical steel bars to complete the foundation construction, and finally fill with grouting, which is conducive to reducing labor, reducing labor intensity, and shortening the construction period;
[0025] 2. The sound insulation cotton board is matched with the honeycomb board with special internal structure to effectively improve the sound insulation performance of the assembled eco-box; the vertical and horizontal reinforcement steel bars are used to enhance the overall structural strength of the assembled eco-box;
[0026] 3. The connecting rod slides out of the insertion tube along with the parallel insertion block and embeds into the soil; when it approaches the second twist block, the parallel insertion block is separated from the soil. The setting of the parallel insertion block is conducive to embedding into the soil, which is conducive to enhancing the grip of the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. Those skilled in the art can also derive other drawings based on these drawings without inventive work.
[0028] Figure 1 A schematic diagram of the overall structure of an assembled ecological energy storage wall provided by the present invention;
[0029] Figure 2 A schematic diagram of the internal structure of an assembled ecological energy storage wall provided by the present invention;
[0030] Figure 3 A schematic diagram of the structure of a prefabricated ecological energy storage wall provided by the present invention;
[0031] Figure 4 A schematic diagram of the internal structure of a prefabricated ecological energy storage wall provided by the present invention;
[0032] Figure 5This is a schematic diagram of the internal structure of the eco-box assembled from the side of the present invention;
[0033] Figure 6 This is a schematic diagram of the reinforcement assembly structure of the present invention;
[0034] Figure 7 This is a schematic diagram of the internal component structure of the installation box of the present invention;
[0035] Figure 8 For the present invention Figure 7 A schematic diagram of the enlarged structure at point A;
[0036] Figure 9 For the present invention Figure 7 A schematic diagram of the enlarged structure at point B;
[0037] Figure 10 This is a schematic diagram of the structure of the grip assembly of the present invention.
[0038] In the figure: 1. Base plate; 21. Assembly eco-box; 22. Installation box; 23. Snap-on plate; 24. Twist block one; 25. Screw one; 26. Connecting rod; 27. Screw two; 28. Trapezoidal block; 29. Spring one; 210. Fixing plate one; 211. Clamping plate one; 212. Spring two; 213. Fixing plate two; 214. Clamping plate two; 215. Sound insulation cotton board; 216. Honeycomb board; 217. Pouring nozzle; 218. Reinforcement block; 219. Reinforcement pipe; 220. Connecting pipe; 221. Vertical reinforcement steel bar; 222. Horizontal reinforcement steel bar; 223. Push block; 31. Insertion pipe; 32. Twist block two; 33. Screw three; 34. Mobile fixing frame; 35. Conical triangle push block; 36. Parallel insertion block. DETAILED DESCRIPTION
[0039] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.
[0040] In the present invention, unless otherwise expressly specified or limited, the terms "mounted," "connected," "connect," "fixed," etc. should be understood broadly. For example, they may refer to fixed connection, detachable connection, or integration; mechanical connection or electrical connection; direct connection or indirect connection through an intermediate medium; internal communication between two components or interaction between two components. Those skilled in the art will understand the specific meanings of the above terms in the present invention based on specific circumstances.
[0041] Example 1:
[0042] See also Figure 1-10 The present invention provides a technical solution: an assembled ecological energy storage wall, comprising a base plate 1, an assembled ecological box 21 and a gripping assembly. The top of the base plate 1 is provided with the assembled ecological box 21, and the bottom of the base plate 1 is provided with a gripping assembly. The top of the assembled ecological box 21 is fixedly connected to the installation box 22, and the bottom of the assembled ecological box 21 is fixedly connected to the clamping plate 23. A screw block 24 is rotatably connected in the installation box 22, and a screw rod 25 is fixedly connected to one side of the screw block 24. The end of the screw rod 25 away from the screw block 24 is fixedly connected to a connecting rod 26, and one end of the connecting rod 26 is fixedly connected to a screw 27. A trapezoidal block 28 is threadedly connected to the screw 25. The installation box 22 A spring 29 is fixedly connected to the inside, a fixed plate 210 is fixedly connected to one side of the spring 29, a card plate 211 is fixedly connected to the fixed plate 210, and the card plate 211 is slidably connected to the inside of the installation box 22 through a through hole opened inside the installation box 22, a push block 223 is threadedly connected to the screw 27, a spring 212 is fixedly connected to the inside of the installation box 22, a fixed plate 213 is fixedly connected to one side of the spring 212, a card plate 214 is fixedly connected to the fixed plate 213, and the card plate 214 slides inside the installation box 22, and a reinforcement component is provided in the assembly ecological box 21; the reinforcement component includes a sound insulation cotton board 215, and the sound insulation cotton board 215 is fixedly connected to the inside of the installation box 22. Connected to the two ends of the assembly eco-box 21, the sound insulation cotton board 215 is fixedly connected to the honeycomb board 216, and the honeycomb board 216 is fixedly connected to the honeycomb board 216. A pouring port 217 is opened on the top of the assembly eco-box 21. A reinforcement block 218 is fixedly connected to the assembly eco-box 21. A reinforcement pipe 219 is fixedly connected to the reinforcement block 218. Both ends of the reinforcement block 218 are fixedly connected to the connecting pipe 220. The connecting pipe 220 is slidably connected to the vertical reinforcement steel bar 221. The reinforcement block 218 is slidably connected to the horizontal reinforcement steel bar 222. First, place the clamping plate 23 at the bottom of the assembly eco-box 21 on the top of the built assembly eco-box 21, and insert one set of top installation boxes 22 into the other set. On the inner side of the fixed plate 213 at the bottom, the screw block 24 is then rotated, driving the screw 25 to rotate in the installation box 22, and the trapezoidal block 28 on it rotates and moves away from the screw block 24, while driving the screw 27 to rotate, so that the push block 223 also moves away from the screw block 24, and the trapezoidal block 28 pushes the card plate 1 211, and the push block 223 pushes the card plate 214 to slide out of the installation box 22 and enter the fixed plate 2 213, and then, according to the width of the wall, it is assembled with the ecological box 21 and installed side by side on the top of the first layer, after which, the vertical reinforcement steel bar 221 is inserted through the second layer into the first layer, and then the horizontal reinforcement steel bar 222 is inserted through the second layer to complete the foundation construction, and finally the grouting machine is used to fill the raw materials to complete the construction.
[0043] See also Figure 2-9In this embodiment, a through hole is opened on the assembly eco-box 21, and the vertical reinforcing steel bars 221 and the horizontal reinforcing steel bars 222 pass through the assembly eco-box 21 through the through hole and are distributed in a well shape inside the assembly eco-box 21. Since the vertical reinforcing steel bars 221 are provided, it is beneficial to cooperate with the horizontal reinforcing steel bars 222 to improve the firmness of the device; a through hole is opened on the clamping plate 23, and one group of assembly eco-boxes 21 can be clamped with the clamping plate 1 211 and the clamping plate 2 214 through the through hole on the clamping plate 23, so that the two groups of assembly eco-boxes 21 are connected to each other. Since the assembly eco-box 21 is provided, it is beneficial It serves as the basis for installing other components; when the two groups of card plates 1 211 and card plates 2 214 approach each other at the same time, the two groups of assembled eco-boxes 21 will separate from each other. Since card plate 1 211 is provided, it is convenient to cooperate with card plate 214 to insert into the interior of fixed plate 213 to realize the assembly of the two groups of assembled eco-boxes 21; when the trapezoidal block 28 and the push block 223 are away from the screw block 1 24 at the same time, card plate 1 211 and card plate 214 will enter the clamping plate 23 to complete the assembly of the two groups of assembled eco-boxes 21. Since the screw block 1 24 is provided, it is convenient to rotate the screw block 1 24 to drive the screw 1 25 to rotate.
[0044] See also Figure 10 In this embodiment, the grip assembly includes an insertion tube 31, which is fixedly connected to the bottom of the base plate 1. A screw rod 33 is rotatably connected inside the insertion tube 31, and a screw block 2 32 is fixedly connected to the top of the screw rod 33. A movable fixing frame 34 is fixedly connected to the inner side of the insertion tube 31, and a conical triangular pushing block 35 is threadedly connected to the screw rod 33. A parallel insertion block 36 is slidably connected to the inner side of the movable fixing frame 34. A through hole is provided on the insertion tube 31, and the parallel insertion block 36 is slidably connected to the inside of the insertion tube 31 through the through hole. Due to the provision of the screw rod 33, the cone-shaped triangular pushing block 35 is driven. The conical triangular pushing block 35 moves up and down; a sliding groove is provided on the parallel insertion block 36, and the conical triangular pushing block 35 is slidably connected to the inside of the parallel insertion block 36 through the sliding groove. Due to the provision of the conical triangular pushing block 35, it is convenient for the parallel insertion block 36 to slide out of the inside of the insertion tube 31; when the conical triangular pushing block 35 is away from the bottom plate 1, the connecting rod 26 slides out of the insertion tube 31 and embeds into the soil; when the conical triangular pushing block 35 is close to the screw block 2 32, the parallel insertion block 36 is separated from the soil. Due to the provision of the parallel insertion block 36, it is convenient for the parallel insertion block 36 to embed into the soil, thereby improving the grip;
[0045] A method for constructing an assembled ecological energy storage wall, comprising the following steps:
[0046] Step 1: Insert the insertion tube 31 at the bottom of the base plate 1 into the soil, rotate the second screw block 32, and drive the third screw 33 to rotate. The conical triangular pushing block 35 on the third screw 33 rotates accordingly and gradually moves away from the second screw block 32, pushing the parallel insertion block 36 to slide in the movable fixing frame 34. As the conical triangular pushing block 35 moves away from the second screw block 32, the parallel insertion block 36 slides out of the insertion tube 31 and into the soil, firmly fixing the base plate 1 to the ground, completing the paving;
[0047] Step 2: Place the assembled eco-box 21 on top of the base plate 1 and insert the vertical reinforcing steel bar 221. The vertical reinforcing steel bar 221 first enters the interior of the assembled eco-box 21, then enters the connecting pipe 220 in the reinforcement block 218, and finally penetrates the assembled eco-box 21 and the base plate 1 deep into the soil. Insert it until one end is completely inserted into the interior of the assembled eco-box 21. According to the width of the wall, the assembled eco-boxes 21 are placed side by side on both sides of the preliminarily fixed assembled eco-box 21. Each group is inserted with the vertical reinforcing steel bar 221 to complete the fixation with the base plate 1. Then, insert the horizontal reinforcing steel bar 222, so that it penetrates the assembled eco-box 21 and is inserted into the interior of the reinforcement block 218. Because the horizontal reinforcing steel bar 222 is longer, the parallel assembled eco-boxes 21 can be connected through and through, and the vertical reinforcing steel bar 221 forms a well shape inside the assembled eco-box 21.
[0048] Step 3: Put cement, sand, gravel, polyvinyl alcohol fiber, nano-silica, rice husk ash and other raw materials into a mixer and mix them evenly. Then put them into a grouting machine. Insert the grouting machine tube through the pouring port 217 into the assembly eco-box 21. Use the grouting machine to inject the mixed raw materials into the assembly eco-box 21 to complete the construction of the first layer of the wall.
[0049] Step 4: Place the connecting plate 23 at the bottom of the assembly eco-box 21 on the top of the assembled eco-box 21. Insert the installation box 22 on the top of one group of assembly eco-boxes 21 into the inner side of the fixed plate 213 at the bottom of another group. Turn the screw block 1 24 to drive the screw 1 25 to rotate in the installation box 22. The trapezoidal block 28 on the screw 1 25 rotates accordingly and gradually moves away from the screw block 1 24. At the same time, it drives the screw 2 27 outside the connecting rod 26 to rotate. The screw 2 27 drives the push block 223 to slowly move away from the screw block 1 24. The trapezoidal block 28 pushes the card plate 1 211 to slide out. The push block 223 pushes the card plate 214 to slide out of the installation box 22. The card plate 1 211 and the card plate 214 enter the fixed plate 213. According to the width of the wall, the assembly eco-boxes 21 are installed side by side on the top of the first layer to complete the second layer assembly.
[0050] Step 5: Insert the vertical reinforcement steel bars 221 through the second-layer assembly eco-box 21 into the first layer, and then insert the horizontal reinforcement steel bars 222 through the second-layer assembly eco-box 21 to complete the second-layer foundation construction. Use a grouting machine to fill the raw materials into the assembly eco-box 21 to complete the second-layer construction;
[0051] Step 6: Repeat steps 4 and 5 according to the wall height until the designed wall height is reached.
[0052] It should be noted that, in this document, relational terms such as first and second, etc., are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms "comprises," "comprising," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or device comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or elements inherent to such process, method, article, or device. In the absence of further limitations, an element defined by the phrase "comprising a..." does not exclude the presence of additional identical elements in the process, method, article, or device comprising the element.
Claims
1. An assembled ecological energy storage wall, comprising a bottom plate (1), characterized in that: The utility model also includes an assembly ecological box (21) and a gripping assembly. The top of the bottom plate (1) is provided with the assembly ecological box (21), the bottom of the bottom plate (1) is provided with the gripping assembly, the top of the assembly ecological box (21) is fixedly connected with the installation box (22), the bottom of the assembly ecological box (21) is fixedly connected with the clamping plate (23), the installation box (22) is rotatably connected with a screw block (24), one side of the screw block (24) is fixedly connected with a screw rod (25), the end of the screw rod (25) away from the screw block (24) is fixedly connected with a connecting rod (26), one end of the connecting rod (26) is fixedly connected with a screw rod (27), the screw rod (25) is threadedly connected with a trapezoidal block (28), the inner side of the installation box (22) is provided with a screw rod (28). A spring (29) is fixedly connected, a fixed plate (210) is fixedly connected to one side of the spring (29), a clamping plate (211) is fixedly connected to the fixed plate (210), the clamping plate (211) is slidably connected to the inside of the installation box (22) through a through hole opened inside the installation box (22), a push block (223) is threadedly connected to the screw rod (27), a spring (212) is fixedly connected to the inside of the installation box (22), a fixed plate (213) is fixedly connected to one side of the spring (212), a clamping plate (214) is fixedly connected to the fixed plate (213), the clamping plate (214) slides inside the installation box (22), and a reinforcement component is provided in the assembly ecological box (21).
2. The assembled ecological energy storage wall according to claim 1, characterized in that: The reinforcement component comprises a sound insulation cotton board (215), the sound insulation cotton board (215) is fixedly connected to both ends of the assembly ecological box (21), a honeycomb board (216) is fixedly connected to the sound insulation cotton board (215), and a honeycomb board (216) is fixedly connected to the honeycomb board (216), a pouring port (217) is provided on the top of the assembly ecological box (21), a reinforcement block (218) is fixedly connected in the assembly ecological box (21), a reinforcement pipe (219) is fixedly connected in the reinforcement block (218), a connecting pipe (220) is fixedly connected at both ends of the reinforcement block (218), a vertical reinforcement steel bar (221) is slidably connected in the connecting pipe (220), and a horizontal reinforcement steel bar (222) is slidably connected in the reinforcement block (218).
3. The assembled ecological energy storage wall according to claim 2, characterized in that: The assembly ecological box (21) is provided with a through hole, and the vertical reinforcement steel bars (221) and the horizontal reinforcement steel bars (222) pass through the through hole and penetrate the assembly ecological box (21) and are distributed in a well shape inside the assembly ecological box (21).
4. The assembled ecological energy storage wall according to claim 3, characterized in that: A through hole is provided on the snap-in plate (23), and one group of assembled eco-boxes (21) can be snap-connected with the first snap-in plate (211) and the second snap-in plate (214) through the through hole on the snap-in plate (23), so that the two groups of assembled eco-boxes (21) are connected to each other.
5. The assembled ecological energy storage wall according to claim 4, characterized in that: When the two groups of pallet 1 (211) and pallet 2 (214) approach each other at the same time, the two groups of assembled eco-boxes (21) will separate from each other.
6. The assembled ecological energy storage wall according to claim 5, characterized in that: When the trapezoidal block (28) and the push block (223) are simultaneously away from the screw block (24), the first clamping plate (211) and the second clamping plate (214) will enter the clamping plate (23) to complete the assembly of the two sets of assembly ecological boxes (21).
7. The assembled ecological energy storage wall according to claim 6, characterized in that: The gripping assembly comprises an insertion tube (31), the insertion tube (31) is fixedly connected to the bottom of the base plate (1), a screw rod (33) is rotatably connected inside the insertion tube (31), a screw block (32) is fixedly connected to the top of the screw rod (33), a movable fixing frame (34) is fixedly connected to the inner side of the insertion tube (31), a conical triangular pushing block (35) is threadedly connected to the screw rod (33), a parallel insertion block (36) is slidably connected to the inner side of the movable fixing frame (34), a through hole is opened on the insertion tube (31), and the parallel insertion block (36) is slidably connected to the inside of the insertion tube (31) through the through hole.
8. The assembled ecological energy storage wall according to claim 7, characterized in that: A sliding groove is provided on the parallel insertion block (36), and the conical triangular pushing block (35) is slidably connected to the inside of the parallel insertion block (36) through the sliding groove.
9. The assembled ecological energy storage wall according to claim 8, characterized in that: When the conical triangular pushing block (35) is away from the bottom plate (1), the connecting rod (26) slides out of the insertion tube (31) and is embedded in the soil. When the conical triangular pushing block (35) is close to the second screw block (32), the parallel insertion block (36) is separated from the soil.
10. A method for constructing an assembled ecological energy storage wall, characterized by: The method for constructing the assembled ecological energy storage wall according to any one of claims 1 to 9 comprises the following steps: Step 1: Insert the insertion tube (31) at the bottom of the base plate (1) into the soil, rotate the screw block 2 (32), drive the screw rod 3 (33) to rotate, and the conical triangular pushing block (35) on the screw rod 3 (33) rotates accordingly and gradually moves away from the screw block 2 (32), pushing the parallel insertion block (36) to slide in the movable fixing frame (34). As the conical triangular pushing block (35) moves away from the screw block 2 (32), the parallel insertion block (36) slides out of the insertion tube (31) and enters the soil, so that the base plate (1) is firmly fixed to the ground, and the paving is completed; Step 2: Place the assembled eco-box (21) on the top of the base plate (1), insert the vertical reinforcing steel bar (221), the vertical reinforcing steel bar (221) first enters the inside of the assembled eco-box (21), then enters the connecting pipe (220) in the reinforcing block (218), and finally penetrates the assembled eco-box (21) and the base plate (1) deep into the soil, and is inserted until one end completely enters the inside of the assembled eco-box (21). According to the width of the wall, the assembled eco-boxes (21) are placed side by side on both sides of the assembled eco-box (21) that has been initially fixed. Each group is inserted with the vertical reinforcing steel bar (221) to complete the fixation with the base plate (1), and then the transverse reinforcing steel bar (222) is inserted so that it penetrates the assembled eco-box (21) and is inserted into the inside of the reinforcing block (218). Because the transverse reinforcing steel bar (222) is longer, the parallel assembled eco-boxes (21) can be penetrated and connected, and the vertical reinforcing steel bar (221) forms a well shape inside the assembled eco-box (21); Step 3: Put cement, sand, gravel, polyvinyl alcohol fiber, nano-silicon dioxide, rice husk ash and other raw materials into a mixer and mix them evenly, then put them into a grouting machine, insert the grouting machine pipe into the assembly eco-box (21) through the pouring port (217), and use the grouting machine to inject the mixed raw materials into the assembly eco-box (21), thereby completing the construction of the first layer of the wall; Step 4: Place the clamping plate (23) at the bottom of the assembly eco-box (21) on the top of the assembled eco-box (21), insert the installation box (22) at the top of one set of assembly eco-boxes (21) into the inner side of the fixing plate 2 (213) at the bottom of another set, rotate the screw block 1 (24), drive the screw rod 1 (25) to rotate in the installation box (22), and the trapezoidal block (28) on the screw rod 1 (25) rotates accordingly and gradually moves away from the screw block 1 (24), while driving the connecting rod (26) ) The external screw rod 2 (27) rotates, and the screw rod 2 (27) drives the push block (223) to slowly move away from the screw block 1 (24), and the trapezoidal block (28) pushes the card plate 1 (211) to slide out, and the push block (223) pushes the card plate 2 (214) to slide out of the installation box (22), and the card plate 1 (211) and the card plate 2 (214) enter the interior of the fixed plate 2 (213). According to the width of the wall, the ecological box (21) is installed side by side on the top of the first layer to complete the second layer assembly; Step 5: Insert the vertical reinforcement steel bar (221) through the second-layer assembly eco-box (21) into the first layer, and then insert the horizontal reinforcement steel bar (222) through the second-layer assembly eco-box (21) to complete the second-layer foundation construction, and use a grouting machine to fill the raw materials into the assembly eco-box (21) to complete the second-layer construction; Step 6: Repeat steps 4 and 5 according to the wall height until the designed wall height is reached.