Pile foundation concrete pouring real-time monitoring device

The real-time monitoring device for pile foundation concrete pouring, consisting of a guide unit and a monitoring unit, solves the problem of real-time monitoring during the concrete pouring process of bored piles, enabling timely detection of construction defects, ensuring project safety and reducing costs.

CN120908303APending Publication Date: 2025-11-07四川智能建造科技股份有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202511144951.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-08-15
Publication Date
2025-11-07

AI Technical Summary

Technical Problem

Existing technologies cannot achieve real-time monitoring of the concrete pouring process for bored piles, resulting in the inability to detect construction defects in a timely manner, which affects project safety and cost.

Method used

The real-time monitoring device for pile foundation concrete pouring consists of a guide unit and a monitoring unit. It includes a guide component, a monitoring component, a twin-drum winch, and a monitor. The monitor is driven by a cable and a motor to perform real-time monitoring around the guide pipe, covering the entire pouring area.

Benefits of technology

It enables real-time monitoring of defects during concrete pouring, avoiding safety hazards and material losses from post-construction inspections, and does not affect normal construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120908303A_ABST
    Figure CN120908303A_ABST
Patent Text Reader

Abstract

The invention discloses a pile foundation concrete pouring real-time monitoring device, which relates to the related technical field of foundation pile whole process monitoring and comprises a guide unit, a monitoring unit and a double-drum winch. The guide unit is assembled on the peripheral side of a guide pipe used during pile foundation concrete pouring and comprises a pair of guide assemblies assembled at the two ends of the peripheral side of the guide pipe correspondingly, each guide assembly comprises a base placed on the ground during use, a rotating rod is arranged at the upper end of each base, a spool is fixed to the peripheral side of each rotating rod, and a cable is arranged in a groove of each spool in a striding mode. The guide assembly further comprises a first semi-arc plate. The monitoring unit is assembled on the peripheral side of the guide pipe and located below the guide unit and comprises a pair of monitoring assemblies assembled at the two ends of the peripheral side of the guide pipe correspondingly, an arc-shaped guide rail is arranged on the lower end face of a second semi-arc plate, and a monitor is arranged at one end of a second rotating plate. Real-time monitoring of concrete defects in the pile foundation construction process can be achieved, and potential safety hazards and demolition material loss caused by post-detection during construction are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the technical field of full-process monitoring of pile foundations, and in particular to a real-time monitoring device for pile foundation concrete pouring. Background Technology

[0002] Drilled piles are the main foundation type for modern bridge engineering. Controlling construction defects in drilled piles is an important guarantee for ensuring the safety and reliability of bridge engineering. However, the current routine testing of drilled pile foundations is a post-event assessment, which cannot effectively control the impact of construction defects on engineering quality and safety, construction cost losses, and project delays.

[0003] The pile foundations mentioned above will employ methods such as... Figure 7 The casing 7 shown contains the reinforcing cage 6 of the pile foundation. Most of the reinforcing cage 6 and the casing 7 are below the drilled ground level, with a small portion above ground. During pouring, a guide pipe 5 is used to pour the concrete from bottom to top. Therefore, a device adapted to this pouring method is needed to achieve real-time monitoring of the concrete pouring quality. Summary of the Invention

[0004] To address the aforementioned shortcomings, this invention provides a real-time monitoring device for pile foundation concrete pouring, which enables real-time monitoring of concrete defects during pile foundation construction, avoiding safety hazards and material losses during demolition caused by post-construction inspections.

[0005] In order to achieve the objectives of this invention, the following technologies are proposed: A real-time monitoring device for pile foundation concrete pouring includes: The guide unit is assembled on the outer periphery of the guide pipe used during pile foundation concrete pouring. It includes a pair of guide components respectively assembled on both ends of the outer periphery of the guide pipe. The guide component includes a base placed on the ground during use. A rotating rod is provided on the upper end of the base. An I-beam wheel is fixed on the outer periphery of the rotating rod. A cable is strung in the groove of the I-beam wheel. The guide component also includes a first semi-circular arc plate. The rotating rod is rotatably engaged with one end of the outer periphery of the first semi-circular arc plate. Vertical plates extend from both ends of the outer periphery of the first semi-circular arc plate. Several first through holes are opened on the side of the vertical plates. The monitoring unit is arranged on the outer periphery of the guide pipe below the guide unit, and comprises a pair of monitoring assemblies arranged on the two ends of the outer periphery of the guide pipe, wherein each monitoring assembly comprises a second semicircular arc plate, the outer periphery of the second semicircular arc plate extends with a horizontal plate at each end, the horizontal plates of each monitoring assembly are arranged on the upper ends of the horizontal plates of the other monitoring assembly, the outer periphery of the second semicircular arc plate is provided with a mounting ring, the lower end of the cable is fixed with a lifting ring buckled with the mounting ring, the lower end surface of the second semicircular arc plate is provided with an arc-shaped guide rail, the lower end of the sliding block of the arc-shaped guide rail is provided with a first rotary motor, the outer periphery of the output shaft of the first rotary motor is provided with a first rotating plate, the lower end of the first rotating plate is provided with a second rotary motor, the outer periphery of the output shaft of the second rotary motor is provided with a second rotating plate, and one end of the second rotating plate is provided with a monitor. The double drum winch is arranged on one side of the guide unit and is used for pulling the two cables.

[0006] Further, the upper end of the base is provided with a support rod, the upper end of the support rod is provided with an outer seat, the outer seat is provided with a first rotary groove on one side surface, the one end of the rotating rod is rotatably matched in the first rotary groove, the outer periphery of the first semicircular arc plate is provided with an inner seat at one end, the inner seat is provided with a second rotary groove on one side surface, and the other end of the rotating rod is rotatably matched in the second rotary groove.

[0007] Further, the first semicircular arc plates of the two guide assemblies are fixedly connected by screwing the corresponding first through holes of the two guide assemblies.

[0008] Further, the inner periphery of the first semicircular arc plate is further provided with a plurality of first rollers, and the outer periphery of the first roller abuts against the outer periphery of the guide pipe during work.

[0009] Further, the second semicircular arc plates of the two monitoring assemblies are fixedly connected by screwing the corresponding second through holes of the two monitoring assemblies.

[0010] Further, the inner periphery of the second semicircular arc plate is further provided with a plurality of second rollers, and the outer periphery of the second roller abuts against the outer periphery of the guide pipe during work.

[0011] Further, the lower end of the sliding block of the arc-shaped guide rail is provided with a hanging plate, the lower end of the hanging plate is provided with a first hanging bracket and a first rotary seat, the first rotary motor is arranged at the lower end of the first hanging bracket, and the output shaft of the first rotary motor is rotatably matched in the first rotary seat.

[0012] Further, the lower end of the first rotating plate is provided with a second hanging bracket and a second rotary seat, the second rotary motor is arranged at the lower end of the second hanging bracket, and the output shaft of the second rotary motor is rotatably matched in the second rotary seat.

[0013] Further, the monitor adopts an air-coupled ultrasonic probe or a laser ultrasonic probe.

[0014] The beneficial effects of the technical scheme are as follows: 1. The guide unit and monitoring unit can be quickly assembled onto the outer periphery of the guide tube on the construction site. After the monitoring unit is lowered and a double-drum winch is placed, the concrete can be continuously monitored at short intervals during the concrete pouring process. This device can achieve real-time monitoring of pile foundation quality through a relatively convenient operation method.

[0015] 2. The monitoring unit can adjust the position and orientation of the monitor through the arc-shaped guide rail, the first rotary motor, and the second rotary motor. Therefore, although only two monitors are used, the monitoring direction can be cyclically covered to cover the entire circular area, that is, continuous monitoring can be carried out from various positions above the area where the concrete is poured.

[0016] 3. Through non-contact monitoring, it is suitable for real-time monitoring of fluid concrete, and does not require destructive sampling, thus not affecting normal pile foundation concrete pouring work. Attached Figure Description

[0017] Figure 1 A perspective view showing the positional relationship between the overall structure and the catheter in an embodiment of this application is shown.

[0018] Figure 2 A perspective view showing the positional relationship between the entire embodiment of this application and the guide pipe reinforcement cage is shown.

[0019] Figure 3 A perspective view of the guide unit according to an embodiment of this application is shown.

[0020] Figure 4 A partial exploded view of the guide unit according to an embodiment of this application is shown.

[0021] Figure 5 A perspective view of the monitoring unit according to an embodiment of this application is shown.

[0022] Figure 6 A partial exploded view of the monitoring unit in an embodiment of this application is shown.

[0023] Figure 7 The illustration shows a perspective view of the conduit, reinforcing cage, and sleeve in the background art of this application.

[0024] The following components are marked in the diagram: Guide unit 1, base 11, support rod 111, outer seat 12, rotating rod 13, I-beam wheel 14, first semi-circular arc plate 15, inner seat 16, vertical mounting plate 17, first through hole 18, first roller 19, monitoring unit 2, second semi-circular arc plate 21, horizontal mounting plate 22, second through hole 221, second roller 23, outer plate 24, mounting ring 241, lifting ring 41, arc-shaped guide rail 25, lifting plate 251, first hanger 252, first rotating seat 253, first rotating motor 26, first rotating plate 261, second hanger 262, second rotating seat 263, second rotating motor 27, second rotating plate 271, monitor 28, double drum winch 3, cable 4, guide tube 5, steel cage 6, sleeve 7. Detailed Implementation

[0025] The present application will be further described below with reference to the accompanying drawings and embodiments.

[0026] like Figures 1-6 The device shown is a real-time monitoring device for pile foundation concrete pouring, including a guide unit 1, a monitoring unit 2, and a double-drum winch 3.

[0027] like Figures 1-4 As shown, the guide unit 1 is assembled on the outer periphery of the guide pipe 5 used during pile foundation concrete pouring. It includes a pair of guide components respectively assembled at both ends of the outer periphery of the guide pipe 5. The guide component includes a base 11 placed on the ground during use. A support rod 111 is provided at the upper end of the base 11. An outer seat 12 is provided at the upper end of the support rod 111. A first rotating groove is opened on one side of the outer seat 12. A rotating rod 13 extending outward is rotatably fitted in the first rotating groove. An I-beam wheel 14 is fixed on the outer periphery of the rotating rod 13. A cable 4 is strung in the groove of the I-beam wheel 14, and the two ends of the cable 4 extend in the horizontal direction and the vertical downward direction, respectively. The guide component also includes a first semi-circular arc plate 15. An inner seat 16 is provided at one end of the outer periphery of the first semi-circular arc plate 15. A second rotating groove is opened on one side of the inner seat 16. One end of the rotating rod 13 is rotatably fitted into the second rotating groove. Vertical plates 17 extend from both ends of the outer circumferential surface of the first semi-circular plate 15. Several first through holes 18 are provided on the side of the vertical plates 17. The first semi-circular plates 15 of the two guide components are fixedly connected by screwing the corresponding first through holes 18 of the two guide components. A complete circumferential surface is formed between the two first semi-circular plates 15. Several first rollers 19 are also provided on the inner circumferential side of the first semi-circular plate 15. The axis of the first rollers 19 is located on the horizontal plane. During operation, the outer circumferential side of the first rollers 19 abuts against the outer circumferential side of the guide tube 5. More specifically, several pairs of first fixing plates are provided on the inner circumferential side of the first semi-circular plate 15. A first wheel axle passing through both ends of the first rollers 19 is provided between each pair of two first fixing plates.

[0028] like Figure 1 , Figure 2 , Figure 5 , Figure 6As shown, the monitoring unit 2 is assembled on the outer peripheral side of the guide pipe 5 below the guide unit 1, and includes a pair of monitoring assemblies assembled on the two ends of the outer peripheral side of the guide pipe 5, each monitoring assembly including a second semicircular arc plate 21, the outer peripheral surface of which extends with a horizontal plate 22 at each end, and the horizontal plate 22 extends outward from the end surface of the second semicircular arc plate 21, each horizontal plate 22 of one monitoring assembly is located at the upper end of each horizontal plate 22 of the other monitoring assembly, and the second semicircular arc plates 21 of the two monitoring assemblies are fixedly connected by screwing corresponding second through holes 221 of each monitoring assembly, and a plurality of second rollers 23 are arranged on the inner peripheral side of the second semicircular arc plate 21, the axis of the second roller 23 is located in the horizontal plane, and in operation, the outer peripheral side of the second roller 23 abuts against the outer peripheral side of the guide pipe 5, more specifically, a plurality of pairs of second fixing plates are arranged on the inner peripheral side of the second semicircular arc plate 21, a second shaft is arranged between each pair of two second fixing plates, and the second shaft passes through the two ends of the second roller 23, an outer plate 24 is arranged on the outer peripheral side of the second semicircular arc plate 21, a mounting ring 241 is arranged on the upper end of the outer plate 24, a lifting ring 41 is fixedly arranged at the lower end of the cable 4 and buckled with the mounting ring 241, and specifically, there are two embodiments, one is to buckle the mounting ring 241 and the lifting ring 41 directly during processing, for example, the lifting ring 41 is welded by a part that has been buckled into the mounting ring 241 and another part, and the other is to replace the lifting ring 41 with a structure having a lock portion at one end that can be opened and closed, an arc-shaped guide rail 25 is arranged on the lower end surface of the second semicircular arc plate 21, a lifting plate 251 is arranged on the sliding block of the arc-shaped guide rail 25, a first lifting frame 252 and a first rotating seat 253 are arranged on the lower end of the lifting plate 251, a first rotating motor 26 is arranged on the lower end of the first lifting frame 252, the output shaft of the first rotating motor 26 is rotatably connected to the first rotating seat 253, a first rotating plate 261 is arranged on the outer peripheral side of the output shaft of the first rotating motor 26, a second lifting frame 262 and a second rotating seat 263 are arranged on the lower end of the first rotating plate 261, a second rotating motor 27 is arranged on the lower end of the second lifting frame 262, the output shaft of the second rotating motor 27 is rotatably connected to the second rotating seat 263, a second rotating plate 271 is arranged on the outer peripheral side of the output shaft of the second rotating motor 27, a monitor 28 is arranged at one end of the second rotating plate 271, the monitor 28 is an air-coupled ultrasonic probe or a laser ultrasonic probe, the connecting line of the monitor 28 is directly pulled out vertically above the ground and connected to the detection equipment host on the ground, the pulling-out mode of the connecting line is simple, and therefore the connecting line is omitted in each drawing, and technicians can also easily implement it, the line includes various required cables of the monitor 28, including power lines, data lines, etc.

[0029] As shown in Figure 1 , Figure 2 , the double-drum hoist 3 is arranged on one side of the guide unit 1 and also placed on the ground, and is used to pull the two cables 4, and in operation, one end of each cable 4 is mounted on the outer peripheral side of the two drums of the double-drum hoist 3.

[0030] Working mode: First, the reinforcement cage 6 and the sleeve 7 have been set on the ground, at this time, the two monitoring assemblies of the monitoring unit 2 are assembled on the outer circumferential side of the guide pipe 5 on the ground, then they are lowered for a distance, then the two guiding assemblies of the guiding unit 1 are assembled on the ground, the cable 4 is wound around the capstan 14 in the manner as shown in the figure, and then is installed to the double-drum hoist 3, the specific installation manner is not described herein, and the conventional hoist cable installation manner can be used. Figure 1 or Figure 2 The specific installation manner is not described herein, and the conventional hoist cable installation manner can be used.

[0031] Next, the concrete is poured, and the concrete is monitored in time. The common pouring steps in the industry are as follows: after a predetermined amount of concrete is poured, the guide pipe 5 is lifted, then the concrete is poured again, and the guide pipe 5 is lifted again until the pouring is completed. According to the pouring steps, the operation of pulling the monitoring unit by the double-drum hoist 3 includes two kinds: the first kind is that during the pouring of the concrete, the monitor 28 is always close to the pouring surface of the concrete, and the monitoring unit 2 is slowly lifted along with the rising of the pouring surface, specifically, if the monitor 28 adopts an air-coupled ultrasonic probe, the monitoring distance is generally controlled to be within 10 cm, and if the monitor 28 adopts a laser ultrasonic probe, the monitoring distance can be generally 1 m to 2 m; the second kind is that when the guide pipe 5 is lifted, the monitoring unit 2 does not slide relative to the guide pipe 5, so as to be lifted synchronously, or the monitoring unit 2 slides downward relative to the guide pipe 5 by a small distance, so as to prepare for the monitoring in the next pouring.

[0032] During the monitoring, the monitor 28 can move along the arc direction of a circular arc through the arc-shaped guide rail 25, and the orientation of the monitor 28 can be deflected along the radial direction of the circle drawn with any point on the guide pipe axis through the first rotating motor 26, and the monitor 28 can be moved to the joint of the two second semicircular arc plates 21 through the second rotating motor 27, so that the monitoring direction is directed to the area which is not covered by the projection of the arc-shaped guide rail 25 on the pouring surface of the concrete.

[0033] After the monitoring of the concrete of one pile foundation is completed, the monitoring unit 2 has also been lifted to the ground, and the guiding unit 1 and the monitoring unit 2 are disassembled.

[0034] The above only lists some embodiments of the present application, and is not used to limit the present application.

Claims

1. A pile foundation concrete pouring real-time monitoring device, characterized in that, The utility model relates to a pile foundation concrete pouring guiding device, including: Guiding unit (1) is equipped with the outer periphery side of the guide pipe (5) used when pile foundation concrete is poured, including a pair of guiding assembly respectively equipped with the both ends of the outer periphery side of guide pipe (5), guiding assembly includes the base (11) placed on the ground when using, the upper end of base (11) is equipped with the rotating rod (13), the outer periphery side of rotating rod (13) is fixed with the spool (14), the slot of spool (14) is equipped with the cable (4) across, guiding assembly still includes the first half circular arc plate (15), the rotating rod (13) rotation cooperation is in the one end of the outer periphery side of first half circular arc plate (15), and the outer periphery surface both ends of first half circular arc plate (15) respectively extend have vertical installation board (17), and the lateral surface of vertical installation board (17) is equipped with a plurality of first through -hole (18); Monitoring unit (2) is equipped with the outer periphery side of guide pipe (5) and is located guiding unit (1) below, including a pair of monitoring assembly respectively equipped with the both ends of the outer periphery side of guide pipe (5), and monitoring assembly includes the second half circular arc plate (21), and the outer periphery surface both ends of second half circular arc plate (21) respectively extend have horizontal installation board (22), and the upper end of each horizontal installation board (22) of one monitoring assembly is located each horizontal installation board (22) of another monitoring assembly, and the outer periphery side of second half circular arc plate (21) is equipped with the mounting ring (241), and the lower end of cable (4) is fixed with the lifting ring (41) of the buckle joint of mounting ring (241), and the lower end surface of second half circular arc plate (21) is equipped with arc guide rail (25), and the slider lower end of arc guide rail (25) is equipped with first rotary motor (26), and the output shaft outer periphery side of first rotary motor (26) is equipped with first rotating plate (261), and the lower end of first rotating plate (261) is equipped with second rotary motor (27), and the output shaft outer periphery side of second rotary motor (27) is equipped with second rotating plate (271), and one end of second rotating plate (271) is equipped with monitor (28); Double cylinder hoist (3) is located one side of guiding unit (1), is used for pulling two cable (4).

2. The pile foundation concrete pouring real-time monitoring device according to claim 1, characterized in that, The upper end of base (11) is equipped with support rod (111), and the upper end of support rod (111) is equipped with outer seat (12), and one side surface of outer seat (12) is equipped with first rotary groove, and one end of rotating rod (13) is rotationally fitted in first rotary groove, and one end of the outer periphery side of first half circular arc plate (15) is equipped with inner seat (16), and one side surface of inner seat (16) is equipped with second rotary groove, and the other end of rotating rod (13) is rotationally fitted in second rotary groove.

3. The pile concrete pouring real-time monitoring device according to claim 1, characterized in that, By screwing the corresponding first through -hole (18) of each pair of guiding assembly, the first half circular arc plate (15) of two guiding assembly is fixedly connected.

4. The pile concrete pouring real-time monitoring device according to claim 1, characterized in that, The inner periphery side of first half circular arc plate (15) is further equipped with a plurality of first roller (19), and in working, the outer periphery side of first roller (19) is in abutment with the outer periphery side of guide pipe (5).

5. The pile concrete pouring real-time monitoring device according to claim 1, characterized in that, By screwing the corresponding second through -hole (221) of each pair of monitoring assembly, the second half circular arc plate (21) of two monitoring assembly is fixedly connected.

6. The pile concrete pouring real-time monitoring device according to claim 1, characterized in that, The inner periphery side of second half circular arc plate (21) is further equipped with a plurality of second roller (23), and in working, the outer periphery side of second roller (23) is in abutment with the outer periphery side of guide pipe (5).

7. The pile concrete pouring real-time monitoring device according to claim 1, characterized in that, The lower end of the slider of the arc-shaped guide rail (25) is provided with a hanging plate (251), the lower end of the hanging plate (251) is provided with a first hanging bracket (252) and a first rotating seat (253), a first rotating motor (26) is arranged at the lower end of the first hanging bracket (252), and the output shaft of the first rotating motor (26) is rotationally fitted in the first rotating seat (253).

8. The pile concrete pouring real-time monitoring device according to claim 1, characterized in that, The lower end of the first rotating plate (261) is provided with a second hanging bracket (262) and a second rotating seat (263), a second rotating motor (27) is arranged at the lower end of the second hanging bracket (262), and the output shaft of the second rotating motor (27) is rotationally fitted in the second rotating seat (263).

9. The pile concrete pouring real-time monitoring device according to claim 1, characterized in that, The monitor (28) adopts an air-coupled ultrasonic probe or a laser ultrasonic probe.