Linear engineering construction progress presentation method and device based on three-dimensional visualization technology
By utilizing 3D visualization and VR/AR technologies, the problem of the difficulty in intuitively displaying the construction progress of large-scale linear engineering projects has been solved, enabling digital-driven and resource-optimized management of construction progress, and improving the interactivity of construction plans and the intuitiveness of equipment investment.
Patent Information
- Application Number
- CN202511076653.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-01
- Publication Date
- 2025-11-21
AI Technical Summary
Existing technologies are insufficient to intuitively display the construction progress of large-scale linear engineering projects. Non-professionals find it difficult to understand the logical relationships between operations and the deployment of construction equipment, making it difficult to effectively manage the construction progress.
By employing 3D visualization technology, a linear engineering plan is obtained, broken down into the smallest unit of construction procedures, and a 3D visualized construction schedule is generated. The construction progress is controlled by equipment resources, and VR/AR technology is used to immerse the construction site.
It enables intuitive observation of construction progress, vividly displays the input of construction equipment and progress status, optimizes resource allocation, avoids waste, and improves the interactivity and digital-driven nature of construction plans.
Smart Images

Figure CN120997436A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of construction technology, and in particular to a method and apparatus for representing linear engineering construction progress based on three-dimensional visualization technology. Background Technology
[0002] Linear engineering projects refer to engineering projects that are linearly distributed, such as railways, highways, oil and gas pipelines, canals, pipelines, urban integrated pipe networks, power transmission lines, and cableways. Linear engineering projects are characterized by long construction lines, complex social and natural environments, high construction difficulty, long construction periods, high project costs, and significant social impact, requiring strong organizational and coordination capabilities. The core focus of linear engineering project organization and management is the management of the construction schedule. This requires the development of a scientific and reasonable construction schedule, close coordination of various tasks, and orderly organization of various resources to ensure the project progresses smoothly according to plan.
[0003] The existing method uses Gantt charts to represent the start and end points of tasks. This is simple and intuitive, reflecting the logical relationships between tasks and, for complex projects, showing the relationships between different levels of tasks. However, its shortcomings lie in the fact that large linear projects often involve hundreds or even thousands of tasks with complex logical relationships. Non-professionals or those not in charge of the project may find it difficult to understand these internal relationships, and problems in the plan are hard to spot. While the critical path can be identified, it's difficult to grasp the overall construction schedule from a macro perspective, and it doesn't provide a direct view of the construction progress or the deployment of construction equipment. Summary of the Invention
[0004] This specification provides a method and apparatus for representing the construction progress of linear engineering projects based on three-dimensional visualization technology, which solves the problem that the construction progress representation of large-scale linear engineering projects is not intuitive enough in the prior art.
[0005] The technical solutions provided in the embodiments of this specification are as follows: In a first aspect, embodiments of this application provide a method for representing linear engineering construction progress based on three-dimensional visualization technology, including: Obtain a linear engineering plan table, obtain several sub-project planning points based on the linear engineering plan table, obtain several sub-item planning points based on the sub-project planning points, and obtain the smallest unit construction procedure based on the sub-item planning points. The linear engineering plan table includes construction equipment parameters and quantities. Obtain the minimum unit construction procedure and construction period specifications; Based on the equipment parameters and quantity, as well as the construction specifications, determine the minimum construction period for each unit of construction process. The project schedule is obtained from the minimum unit construction procedure duration, and the section schedule is obtained from the project schedule. A 3D visualized construction schedule is generated based on the planned points and durations of each sub-project.
[0006] Furthermore, a linear project schedule is obtained based on the contract period, milestone requirements, and contractual requirements outlined in the tender documents.
[0007] Furthermore, based on the planned points and durations of each sub-project, a 3D visualized construction schedule is generated, including: Several sub-project planning points are horizontally set on the horizontal coordinate axis according to the route mileage to generate a mileage line horizontal coordinate system; The construction period of the sub-project planning point corresponding to the sub-project planning point is vertically set on the vertical coordinate axis to generate a time coordinate system; A three-dimensional visual construction schedule is generated based on the mileage line's horizontal coordinate system and time coordinate system.
[0008] Furthermore, based on the smallest unit of construction procedure, a three-dimensional model of the construction procedure is constructed, and the three-dimensional model of the construction procedure is set at the coordinate point corresponding to the planned point of the sub-project.
[0009] Furthermore, the three-dimensional models of the construction procedures are distributed from bottom to top according to the construction sequence.
[0010] Secondly, embodiments of this application provide an apparatus for a linear engineering construction progress representation method based on three-dimensional visualization technology, including... The decomposition module is used to obtain a linear engineering plan table, obtain several sub-project planning points based on the linear engineering plan table, obtain several sub-item planning points based on the sub-project planning points, and obtain the smallest unit construction procedure based on the sub-item planning points. The linear engineering plan table includes construction equipment parameters and quantities. The processing module is used to obtain the minimum unit construction procedure duration and construction specification requirements; obtain the duration of completing the minimum unit construction procedure based on equipment parameters and quantities and construction specification requirements; obtain the sub-item plan point duration based on the minimum unit construction procedure duration; and obtain the sub-section plan point duration based on the sub-item plan point duration. The table module generates a 3D visualized construction schedule based on the planned points and durations of each sub-project.
[0011] Thirdly, embodiments of this application provide a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the method described above.
[0012] Fourthly, embodiments of this application provide an electronic device, including a memory, a processor, and a computer program stored in the memory and executable by the processor, wherein the processor executes the computer program to implement the method described above.
[0013] The above-mentioned at least one technical solution adopted in the embodiments of this application can achieve the following beneficial effects: it can intuitively observe the overall construction period and realize that the overall construction schedule of linear projects has three-dimensional visibility, digital driveability and interactive operation. Attached Figure Description
[0014] The accompanying drawings, which are included to provide a further understanding of this application and form part of this application, illustrate exemplary embodiments and are used to explain this application, but do not constitute an undue limitation of this application. In the drawings: Figure 1 This is a flowchart illustrating the method provided in the embodiments of this specification.
[0015] Figure 2 A simplified structural diagram of a linear engineering bridge provided for an embodiment of this specification.
[0016] Figure 3 This is an exploded view of the drilling pile process provided in the embodiments of this specification.
[0017] Figure 4 This document provides a diagram showing the quantity of bored piles for a single point in a linear engineering project, as part of an embodiment of this specification.
[0018] Figure 5 This specification provides a sectional engineering plan diagram along the longitudinal axis for embodiments of the present invention.
[0019] Figure 6 This is a construction schedule diagram for the drilled pile process provided in the embodiments of this specification.
[0020] Figure 7 This document provides a construction schedule diagram for each point on a linear mileage as part of an embodiment of the present specification.
[0021] Figure 8 A linear engineering project construction schedule diagram provided for the embodiments of this specification.
[0022] Figure 9 This is a three-dimensional visualization of the project schedule nodes provided in the embodiments of this specification.
[0023] Figure 10 This is a three-dimensional schematic diagram of a large floating crane hoisting steel beam provided for an embodiment of this specification.
[0024] Figure 11 The time and mileage plan diagram of the Macau-Taipa Four Bridges provided for the embodiments of this specification.
[0025] Figure 12 This is a resource-based three-dimensional image progress diagram provided for the embodiments of this specification.
[0026] Figure 13VR diagram of the construction progress of bored piles provided in the embodiments of this specification.
[0027] Figure 14 This is a schematic diagram of the device structure provided in the embodiments of this specification.
[0028] Figure 15 A schematic diagram of an electronic device provided in an embodiment of this disclosure. Detailed Implementation
[0029] To make the objectives, technical solutions, and advantages of this application clearer, the technical solutions of this application will be clearly and completely described below in conjunction with specific embodiments and corresponding drawings. Obviously, the described embodiments are only a part of the embodiments of this application, and not all of them. Based on the embodiments in this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0030] The technical solutions provided by the various embodiments of this application are described in detail below with reference to the accompanying drawings.
[0031] This specification provides an embodiment of a method for representing linear engineering construction progress based on 3D visualization technology. Please refer to [link / reference]. Figure 1 As shown, it includes: S1. Obtain a linear engineering plan table, obtain several sub-project planning points based on the linear engineering plan table, obtain several sub-item planning points based on the sub-project planning points, and obtain the smallest unit construction procedure based on the sub-item planning points. The linear engineering plan table includes construction equipment parameters and quantities. The linear engineering project is broken down step by step and item by item, down to the smallest unit of construction procedure.
[0032] Linear engineering projects undergo structural decomposition, breaking down the entire project into sub-projects and individual items. Items impacting the overall construction schedule are further decomposed into the smallest unit of work for schedule planning, and then visualized using 3D models. Specifically, CAD design drawings are imported into Revit or other 3D modeling software for model creation at a 1:1 scale to ensure accuracy. Temporary structures primarily used on-site, such as drilling platforms, pier caps, cofferdams, temporary steel trestle bridges, pier formwork, and bridge supports, are all modeled using Revit or other 3D software. Large specialized construction equipment used on-site is modeled using equipment drawings provided by the manufacturers. Conventional large equipment such as excavators and crawler cranes can be purchased from professional 3D websites.
[0033] S2. Obtain the minimum unit construction procedure duration and construction specification requirements; S3. Based on the equipment parameters and quantity, as well as the construction specifications, obtain the construction period for the minimum unit of construction process. S4. Obtain the project schedule for each item based on the construction period of the smallest unit of construction procedure, and obtain the project schedule for each section based on the project schedule for each item. S5. Generate a three-dimensional visual construction schedule based on the planned points and durations of each sub-project.
[0034] In one possible implementation, generating a 3D visualized construction schedule based on the planned points and durations of each sub-project includes: horizontally setting several planned points of the sub-project along the route mileage on a horizontal coordinate axis to generate a mileage-route horizontal coordinate system; vertically setting the durations of the corresponding sub-project planned points on a vertical coordinate axis to generate a time coordinate system; and generating a 3D visualized construction schedule based on the mileage-route horizontal coordinate system and the time coordinate system. For example: A 3D visualized process schedule is created and controlled by equipment resources. For each construction process, relevant construction machinery and equipment are configured, and the time required is determined by the equipment's production efficiency. The process duration is determined based on equipment parameters and quantities, and controlled by equipment resources. All of this is presented in a 3D visualized format, making it very easy to understand. Furthermore, through parameterized settings, the visualized, digitally driven process schedule can be adjusted in real time.
[0035] Develop a 3D visualization schedule for each sub-project. The development of the construction schedule for each sub-project at each point along the mileage direction of the linear project should be determined based on the number of sub-projects, equipment, and specification requirements at that point. Each sub-project schedule should be displayed using 3D visualization.
[0036] Develop a 3D visualization construction schedule for each section of the project along the longitudinal axis (Y-axis) at each point along the mileage direction. For each project point along the mileage direction, accumulate the time schedules of different sub-projects from bottom to top in chronological order to determine the completion period of the section project at that point. Develop a three-dimensional visualization-driven overall construction schedule for linear engineering projects. Using the vertical axis (Y-axis) as the time axis and the horizontal axis (X-axis) as the linear spatial (mileage) axis, based on the construction periods of each sub-project, adopt a reverse scheduling approach, compiling the schedule from top to bottom. The schedule fully considers the turnover and reuse of resources such as equipment, maximizing the efficiency of equipment and human resources. Through computer optimization, it avoids various resource wastes or shortages that could prevent meeting the contractually required construction period.
[0037] In a specific implementation, before developing a construction schedule, the linear engineering project is decomposed into sections from surface to line and from line to point (see...). Figure 2 ),like Figure 2A simplified linear project can be divided into ten points horizontally (X-axis) from P1 to P10. At point P1, it can be further divided vertically (Y-axis) into sub-projects such as bored piles, pile caps, piers, and superstructure. When preparing the construction schedule, the sub-projects are first decomposed into work processes (see...). Figure 3 This connects linear engineering projects from points to lines, and from lines to surfaces, into a unified whole (see...). Figure 4 , 5 2); Linear projects are generally not distributed in a straight line, but rather in a linear pattern with many turns and deviations. To address this, the project will be straightened according to the route mileage and placed on the horizontal (X-axis) coordinate axis, with the main sub-projects and sub-projects placed on the mileage line. Each major sub-project is decomposed into work processes, and each construction process is visualized using a 3D model. The completion time of each process is determined based on the equipment performance. Parametric digitally driven 3D software is used to integrate the processes of each sub-project. By parametrically changing the parameters of one process, the time of other processes will be linked together. The sub-project work sequence plan is mainly driven by equipment resources. For example, the sub-project work sequence for bored piles mainly includes installing the casing, drilling, lowering the reinforcing cage, and pouring concrete. Each process is equipped with relevant equipment, and the time required is determined by the production efficiency of the equipment. All of these are represented in a 3D visualization format, which is very easy to understand. Furthermore, through parameter settings, adjustments can be made in real time (see...). Figure 6 The process and technology will be displayed in the form of animation, which can reflect the construction methods of each sub-project. The animations of the process and technology of each sub-project will be compiled to form a process animation library.
[0038] The construction schedule for each sub-item of the linear project along the mileage direction is determined based on the number of sub-items, equipment, and specification requirements at that point. For example, there are 6 bored piles at point P1 (see...). Figure 4 According to the specifications, two piles must be constructed simultaneously at a certain distance. This determines the maximum number of machines that can be placed. The construction period for the bored piles at this location is then determined based on the number of machines and their production efficiency (see [link]). Figure 7 ).
[0039] For each point in a linear project, the total completion time of each sub-project along the vertical axis (Y-axis) is calculated, which is the construction schedule plan for that sub-project at that point.
[0040] By accumulating the time plans of different sub-projects from bottom to top in chronological order, the completion period of the sub-project at that point can be determined.
[0041] Develop an overall construction schedule for the linear project, using the vertical axis (Y-axis) as the time axis and the horizontal axis (X-axis) as the linear spatial (mileage) axis. Based on the construction periods of each sub-project, develop an overall construction schedule for the linear project (see...). Figure 8 ).
[0042] Methodology: The schedule is planned from top to bottom using a reverse scheduling approach. The schedule fully considers the turnover and reuse of resources such as equipment, and makes full use of the efficiency of equipment and human resources. The schedule is optimized by computer to avoid various wastes or shortages of resources that do not match the contractual schedule requirements.
[0043] Presentation format: The vertical axis represents time, with a sliding time slider that can be moved up or down to display the specific year, month, and day, reflecting the passage of time. The horizontal axis represents linear mileage, with major engineering projects distributed at corresponding mileage nodes. Engineering projects have three display states: 1) not displayed when construction has not started; 2) displayed in blue when under construction; and 3) displayed in red when completed. Major construction equipment is also displayed on the map, reflecting its construction status and movement trajectory at corresponding times. The equipment movement trajectory can be set to either visible or hidden.
[0044] Develop other 3D visualization professional construction schedules, and develop 3D visualization professional construction schedules with different requirements based on the characteristics and needs of the project.
[0045] A 3D visualization of the key milestone schedule for an engineering project is created by extracting the construction status of milestone completion points from the overall linear project construction schedule and compiling a 3D milestone schedule (see...). Figure 9 This allows us to understand the on-site construction status at each milestone, drawing attention from all parties and preventing fines due to improper work arrangements that could lead to failure to meet milestones.
[0046] A three-dimensional visualization plan for the lifting of steel beams using large floating cranes was developed for the bridge project, addressing the large number of steel beams to be lifted at sea and the complexity of the lifting sequence. (See [link]) Figure 10 The steel beams to be lifted by the floating crane are divided into sections and marked with different colors. The horizontal direction indicates the position of the steel beams, and the vertical direction indicates the time of beam erection.
[0047] A three-dimensional time-mileage construction progress chart is used, with the horizontal axis representing project mileage and the vertical axis representing construction period. This time-mileage chart allows for checking the rationality of the plan and visually and intuitively reflects the work content and sequence of each construction and installation component (see...). Figure 11 This allows for an overall grasp of the project's construction schedule and pace, serving as a supplement to the Gantt chart plan.
[0048] Actual progress is shown in comparison with the plan.
[0049] (1) Compile a resource-based three-dimensional image progress chart It not only reflects the on-site construction progress, but also the resource input (see...). Figure 12 This involves comparing the resources invested with those in the plan to identify and correct any problems.
[0050] By filling in information on human, material, and machine resources and displaying the progress, the actual progress can be compared with the plan, which will allow for a more accurate and efficient grasp of the on-site situation, timely identification of problems, and the proposal of effective countermeasures.
[0051] The actual progress can be displayed through animation, and a three-dimensional progress map is prepared every week to intuitively grasp the on-site construction progress and the status of plan completion. The focus of the progress map is different in different stages of construction. During the bored pile construction stage, the equipment and personnel invested in the bored piles of the main bridge are highlighted, while during the pier cap construction stage, the construction process of the pier cap is highlighted.
[0052] The start and completion dates, the input of personnel, materials and equipment, and the progress of work completion will be fed back to the 4DBIM cloud platform in real time. By leveraging the advantages of information integration, the distribution of on-site resources and the construction status can be well grasped.
[0053] (2) Use VR / AR technology to reflect the construction progress status at the construction site. VR / AR technology can be used to reflect the construction progress status at the construction site, allowing for an immersive experience of the construction progress. A VR project showcasing the construction progress of bored piles was created using BIM technology (see...). Figure 13 The system also includes AR technology for the construction progress of the main bridge girder of the interchange. Wearing a VR headset allows for an immersive experience, displaying the type and quantity of devices along with text descriptions. Users can also view the progress of bored piles on their mobile phones. (3) Comparison of BIM model plan and actual on-site progress pictures By comparing the BIM model with actual on-site progress photos, the gap between the planned and actual progress can be seen very clearly and intuitively.
[0054] Advantages of linear engineering 3D visualization digital-driven construction schedule planning: First, it can visually and intuitively demonstrate the progress and completion sequence of linear engineering projects over time, providing an intuitive understanding of the rationality of the project construction arrangement. Second, it can display the quantity, working time, and operating trajectory of major construction machinery and equipment. Third, it can decompose sub-projects on the critical path into work processes, determine the minimum construction unit's working time through the equipment input of construction processes, and thus determine the overall construction period. By using a reverse scheduling approach, the construction period can be optimized, resources can be allocated rationally, and resource waste can be avoided. Fourth, through the time slider, the construction progress plan can be freely simulated forward or backward, and by setting parameterized work process durations, the construction date can be easily adjusted, enabling digital-driven operation.
[0055] like Figure 14 As shown, an apparatus for representing linear engineering construction progress based on three-dimensional visualization technology is characterized by comprising: The decomposition module 301 is used to obtain a linear engineering plan table, obtain several sub-project planning points based on the linear engineering plan table, obtain several sub-item planning points based on the sub-project planning points, and obtain the smallest unit construction procedure based on the sub-item planning points. The linear engineering plan table includes construction equipment parameters and quantities. Processing module 302 is used to obtain the minimum unit construction procedure duration and construction specification requirements; obtain the minimum unit construction procedure duration based on equipment parameters and quantity and construction specification requirements; obtain the sub-item plan point duration based on the minimum unit construction procedure duration; and obtain the sub-section plan point duration based on the sub-item plan point duration. Table module 303 generates a three-dimensional visual construction schedule based on the planned points and durations of each sub-project.
[0056] The following is for reference. Figure 15 The diagram illustrates a structural schematic of an electronic device 50 suitable for implementing embodiments of the present disclosure. The electronic devices in the embodiments of the present disclosure may include, but are not limited to, mobile terminals such as mobile phones, laptops, digital broadcast receivers, PDAs (personal digital assistants), PADs (tablet computers), PMPs (portable multimedia players), in-vehicle terminals (e.g., in-vehicle navigation terminals), and fixed terminals such as digital TVs and desktop computers. Figure 15 The electronic device shown is merely an example and should not be construed as limiting the functionality and scope of the embodiments disclosed herein.
[0057] like Figure 15As shown, electronic device 50 may include a processing unit (e.g., a central processing unit, a graphics processing unit, etc.) 501, which can perform various appropriate actions and processes according to a program stored in read-only memory (ROM) 502 or a program loaded from storage device 508 into random access memory (RAM) 503. RAM 503 also stores various programs and data required for the operation of electronic device 50. The processing unit 501, ROM 502, and RAM 503 are interconnected via bus 504. Input / output (I / O) interface 505 is also connected to bus 504.
[0058] Typically, the following devices can be connected to I / O interface 505: input devices 506 including, for example, touchscreens, touchpads, keyboards, mice, image sensors, microphones, accelerometers, gyroscopes, etc.; output devices 507 including, for example, liquid crystal displays (LCDs), speakers, vibrators, etc.; storage devices 508 including, for example, magnetic tapes, hard disks, etc.; and communication devices 509. Communication device 509 allows electronic device 50 to communicate wirelessly or wiredly with other devices to exchange data. Although an electronic device 50 with various devices is shown in the figure, it should be understood that it is not required to implement or possess all the devices shown. More or fewer devices may be implemented or possessed alternatively.
[0059] In particular, according to embodiments of this disclosure, the processes described above with reference to the flowcharts can be implemented as computer software programs. For example, embodiments of this disclosure include a computer program product comprising a computer program carried on a computer-readable medium, the computer program containing program code for performing the methods shown in the flowcharts. In such embodiments, the computer program can be downloaded and installed from a network via a communication device 509, or installed from a storage device 508, or installed from a ROM 502. When the computer program is executed by the processing device 501, it performs the functions defined in the methods of embodiments of this disclosure.
[0060] It should be noted that the computer-readable medium described in this disclosure can be a computer-readable signal medium or a computer-readable storage medium, or any combination thereof. A computer-readable storage medium can be, for example,—but not limited to—an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any combination thereof. More specific examples of a computer-readable storage medium may include, but are not limited to: an electrical connection having one or more wires, a portable computer disk, a hard disk, random access memory (RAM), read-only memory (ROM), erasable programmable read-only memory (EPROM or flash memory), optical fiber, portable compact disk read-only memory (CD-ROM), optical storage device, magnetic storage device, or any suitable combination thereof. In this disclosure, a computer-readable storage medium can be any tangible medium containing or storing a program that can be used by or in conjunction with an instruction execution system, apparatus, or device. In this disclosure, a computer-readable signal medium can include a data signal propagated in baseband or as part of a carrier wave, carrying computer-readable program code. Such propagated data signals can take various forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination thereof. A computer-readable signal medium can be any computer-readable medium other than a computer-readable storage medium, which can send, propagate, or transmit a program for use by or in connection with an instruction execution system, apparatus, or device. The program code contained on the computer-readable medium can be transmitted using any suitable medium, including but not limited to: wires, optical fibers, RF (radio frequency), etc., or any suitable combination thereof.
[0061] The aforementioned computer-readable medium may be included in the aforementioned electronic device; or it may exist independently and not assembled into the electronic device.
[0062] The aforementioned computer-readable medium carries one or more programs, which, when executed by the electronic device, enable the electronic device to perform the relevant steps of the above-described method embodiments.
[0063] Alternatively, the aforementioned computer-readable medium carries one or more programs, which, when executed by the electronic device, enable the electronic device to perform the relevant steps of the above method embodiments.
[0064] Computer program code for performing the operations of this disclosure can be written in one or more programming languages or a combination thereof, including object-oriented programming languages such as Java, Smalltalk, and C++, and conventional procedural programming languages such as the "C" language or similar programming languages. The program code can be executed entirely on the user's computer, partially on the user's computer, as a standalone software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In cases involving remote computers, the remote computer can be connected to the user's computer via any type of network—including a local area network (LAN) or a wide area network (WAN)—or can be connected to an external computer (e.g., via the Internet using an Internet service provider).
[0065] The flowcharts and block diagrams in the accompanying drawings illustrate the architecture, functionality, and operation of possible implementations of systems, methods, and computer program products according to various embodiments of this disclosure. In this regard, each block in a flowchart or block diagram may represent a module, segment, or portion of code containing one or more executable instructions for implementing a specified logical function. It should also be noted that in some alternative implementations, the functions indicated in the blocks may occur in a different order than those indicated in the drawings. For example, two consecutively indicated blocks may actually be executed substantially in parallel, and they may sometimes be executed in reverse order, depending on the functions involved. It should also be noted that each block in the block diagrams and / or flowcharts, and combinations of blocks in the block diagrams and / or flowcharts, can be implemented using a dedicated hardware-based system that performs the specified function or operation, or using a combination of dedicated hardware and computer instructions.
[0066] The units described in the embodiments of this disclosure can be implemented in software or in hardware.
[0067] It should be understood that the various parts of this disclosure can be implemented in hardware, software, firmware, or a combination thereof.
[0068] The above description is merely a specific embodiment of this disclosure, but the scope of protection of this disclosure is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the scope of the technology disclosed in this disclosure should be included within the scope of protection of this disclosure. Therefore, the scope of protection of this disclosure should be determined by the scope of the claims.
Claims
1. A method for representing linear engineering construction progress based on three-dimensional visualization technology, characterized in that, include: Obtain a linear engineering plan table, obtain several sub-project planning points based on the linear engineering plan table, obtain several sub-item planning points based on the sub-project planning points, and obtain the smallest unit construction procedure based on the sub-item planning points. The linear engineering plan table includes construction equipment parameters and quantities. Obtain the minimum unit construction procedure and construction period specifications; Based on the equipment parameters and quantity, as well as the construction specifications, determine the minimum construction period for each unit of construction process. The project schedule is obtained from the minimum unit construction procedure duration, and the section schedule is obtained from the project schedule. A 3D visualized construction schedule is generated based on the planned points and durations of each sub-project.
2. The method for representing linear engineering construction progress based on three-dimensional visualization technology according to claim 1, characterized in that, A linear project schedule was obtained based on the contract period, milestone requirements, and contractual requirements outlined in the tender documents.
3. The method for representing linear engineering construction progress based on three-dimensional visualization technology according to claim 1, characterized in that, Based on the planned points and durations of each sub-project, a 3D visualized construction schedule is generated, including: Several sub-project planning points are horizontally set on the horizontal coordinate axis according to the route mileage to generate a mileage line horizontal coordinate system; The construction period of the sub-project planning point corresponding to the sub-project planning point is vertically set on the vertical coordinate axis to generate a time coordinate system; A three-dimensional visual construction schedule is generated based on the mileage line's horizontal coordinate system and time coordinate system.
4. The method for representing linear engineering construction progress based on three-dimensional visualization technology according to claim 3, characterized in that, Based on the smallest unit of construction procedure, a three-dimensional model of the construction procedure is constructed, and the three-dimensional model of the construction procedure is set at the coordinate point corresponding to the planned point of the sub-project.
5. A method for representing linear engineering construction progress based on three-dimensional visualization technology according to claim 4, characterized in that, The three-dimensional model of the construction process is arranged from bottom to top according to the construction sequence.
6. A device for representing linear engineering construction progress based on three-dimensional visualization technology, characterized in that, include The decomposition module is used to obtain a linear engineering plan table, obtain several sub-project planning points based on the linear engineering plan table, obtain several sub-item planning points based on the sub-project planning points, and obtain the smallest unit construction procedure based on the sub-item planning points. The linear engineering plan table includes construction equipment parameters and quantities. The processing module is used to obtain the minimum unit construction procedure duration and construction specification requirements; obtain the duration of completing the minimum unit construction procedure based on equipment parameters and quantities and construction specification requirements; obtain the sub-item plan point duration based on the minimum unit construction procedure duration; and obtain the sub-section plan point duration based on the sub-item plan point duration. The table module generates a 3D visualized construction schedule based on the planned points and durations of each sub-project.
7. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the program is executed by the processor, it implements the method as described in any one of claims 1-5.
8. An electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that, When the processor executes the computer program, it implements the method as described in any one of claims 1-5.