CNC machine two-group product alternate feeding uninterrupted machining method
By automating the positioning and switching of two sets of interchangeable fixture plates, the problems of equipment interruption and low efficiency of manual loading and unloading in CNC machining are solved, enabling long-term uninterrupted machining and high-efficiency production of CNC machines.
Patent Information
- Application Number
- CN202511681919.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-17
- Publication Date
- 2026-01-16
AI Technical Summary
The single-unit structure of existing CNC machining fixtures reduces the effective operating time of the equipment, results in low efficiency of manual loading and unloading, easily leads to positioning deviations and quality problems, and has high labor costs, which cannot meet the needs of large-scale production in the 3C industry.
It adopts two sets of interchangeable jig plates with identical structures, equipped with lifting cylinders, side-pushing cylinders, lever cylinders, vacuum adsorption devices and central control systems, to realize the automated positioning, fixing and switching of jig plates, and to carry out processing and loading and unloading operations simultaneously.
It enables CNC machines to perform continuous processing for extended periods, reducing manpower input, improving processing efficiency and quality stability, lowering the defect rate, extending equipment lifespan, and meeting the high-efficiency production requirements of the 3C industry.
Smart Images

Figure CN121339964A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of CNC machining technology, specifically to a method for continuous machining of two sets of products on a CNC machine with alternating feeding. Background Technology
[0002] In the CNC machining of 3C product parts, fixtures are the core components for achieving precise part positioning and efficient machining. Currently, most mainstream CNC machining fixtures in the industry adopt a single-unit structure with a limited number of machining slots, commonly an 8-slot design. In actual operation, these fixtures require manual loading of semi-finished products and unloading of finished products: after the CNC machine finishes machining a set of parts, the operator must first shut down the machine, open the safety door, manually remove the finished products from the fixture plate, then load the semi-finished products one by one into the machining slots of the fixture plate, then re-secure the fixture plate, close the safety door, and only then can the machine restart machining. Throughout the entire loading and unloading process, the CNC machine spindle is in a completely standby state and cannot perform machining operations, resulting in a significant reduction in the effective operating time of the equipment.
[0003] Meanwhile, the traditional single-set fixture processing mode has many limitations: On the one hand, the efficiency of manual loading and unloading is greatly affected by the operator's skill level and physical condition. A single loading and unloading usually takes 15-20 seconds. For 3C parts with a short single-piece processing cycle, the loading and unloading time accounts for more than 30% of the total processing time, which seriously restricts the overall production efficiency. On the other hand, manual operation is prone to misalignment of semi-finished products due to positioning deviation and improper force control, which in turn leads to dimensional deviations and surface scratches, increasing the defect rate. In addition, one CNC machine requires one operator to be on duty at all times. When a company has multiple machines operating at the same time, it needs to invest a lot of manpower. Moreover, manual operation cannot be carried out 24 hours a day, which further limits the equipment capacity and makes it difficult to meet the large-scale and high-paced production needs of the 3C industry. Summary of the Invention
[0004] To address the aforementioned technical shortcomings, the purpose of this invention is to provide a method for continuous processing of two sets of products on a CNC machine, reducing processing downtime and manpower input.
[0005] To achieve the above objectives, the present invention adopts the following technical solution:
[0006] A method for continuous processing of two sets of products on a CNC machine with alternating feeding, comprising the following steps:
[0007] S1. Configure two sets of interchangeable jig plates with the same structure. Each set of interchangeable jig plates has 40 processing slots to adapt to 3C product parts. Simultaneously equipped with a semi-finished product feeding bin, a finished product picking box, a drive assembly consisting of a lifting cylinder, a side pushing cylinder, and a lever cylinder, as well as a vacuum adsorption device and a central control system.
[0008] S2. Load the semi-finished parts of 3C products one by one into the processing cavity of the two sets of interchangeable jig plates, so that the gap between the semi-finished product and the inner wall of the cavity does not exceed 0.03mm; put the interchangeable jig plates filled with semi-finished products into the two corresponding feeding bins of the CNC machine, and cooperate with the guide structure in the feeding bin to achieve positioning.
[0009] S3. Close the safety door of the CNC machine and start the machine through the central control system; the two side push cylinders simultaneously push the two sets of interchangeable fixture plates to the processing area according to the preset program until the edge of the interchangeable fixture plate is in contact with the positioning block of the processing area; the lifting cylinder pushes the interchangeable fixture plate upward so that the bottom of the interchangeable fixture plate is pressed against the limit protrusion in the push plate groove to complete the initial fixation.
[0010] S4. The lever cylinder drives the pressure block to press down on the four corners of the interchangeable fixture plate. At the same time, the vacuum adsorption device is activated and adsorbs the bottom of the interchangeable fixture plate. After the adsorption pressure stabilizes, the pressure block is opened, and the CNC machine spindle processes 40 acupoint products of one set of interchangeable fixture plates according to the preset processing parameters.
[0011] S5. During the processing of the current set of interchangeable fixture plates, the central control system controls another set of interchangeable fixture plates to move to the loading and unloading station, and simultaneously completes the unloading of finished products or the replenishment of semi-finished products, so as to realize the parallel processing and loading and unloading processes.
[0012] S6. After the first set of interchangeable fixture plates is processed, the side-push cylinder pushes it to the unloading position; at the same time, another set of interchangeable fixture plates that have been loaded is pushed to the processing area, and the pressing, adsorption fixing and processing actions of step S4 are repeated to complete the switching of the two sets of interchangeable fixture plates.
[0013] S7. For the interchangeable jig plate at the unloading position, the finished product is removed by mechanical grippers, and then the surface of the interchangeable jig plate and the inside of the cavity are cleaned by air gun; after removing residual chips, the semi-finished product is reloaded to form a cycle of interchangeable jig plate feeding.
[0014] S8. Repeat steps S4 to S7, continuously rotating the two sets of interchangeable fixture plates to achieve long-term uninterrupted continuous processing by the CNC machine.
[0015] Preferably, in step S1, the interchangeable fixture plate includes a cover plate and a base plate, which are detachably connected by a combination of snap-fit and positioning pins; the diameter of the positioning pin is 2.5-3mm, the fitting clearance between the positioning pin and the pin hole is 0.005-0.01mm, and the alignment deviation between the cover plate and the base plate does not exceed 0.01mm; each processing cavity has an elastic protective layer fixedly provided on its inner wall, the protective layer is made of food-grade silicone material with a Shore hardness of 48-52HA, the thickness is 0.9-1.1mm, and the surface is matte; the inner wall of the protective layer has an arc-shaped groove that matches the outer contour of the 3C product parts, and the groove depth is 1-1.5mm.
[0016] Preferably, in step S3, the side-push cylinder has a built-in high-precision strain gauge pressure sensor. The pushing pressure is monitored in real time by the sensor, with a pressure value of 0.35-0.45 MPa and a sensor detection accuracy of ±0.005 MPa. The lifting cylinder has a clamping force of 0.22-0.28 MPa. The pushing process adopts a three-stage speed control of "slow-fast-slow". The initial stage speed is 30-40 mm / s, the middle stage speed is 80-100 mm / s, and the speed drops to 20-30 mm / s when approaching the push plate groove. When the pushing pressure is lower than 0.35 MPa or higher than 0.45 MPa, or the clamping force exceeds the range of 0.22-0.28 MPa, the central control system immediately suspends the operation of the drive components, displays "abnormal side-push pressure" or "abnormal lifting force" prompts on the human-machine interface, and triggers a buzzer to emit an intermittent alarm signal with a frequency of 1 time / second. After the fault is cleared, the operation is restored by manual reset.
[0017] Preferably, in step S4, the adsorption pressure of the vacuum adsorption device is adjusted to -0.055 to -0.065 MPa by the vacuum generator; the adsorption area covers 65%-70% of the bottom area of the interchangeable fixture plate, the diameter of the adsorption holes is 1.8-2.2 mm, the hole spacing is 6-7 mm, and the adsorption holes are uniformly distributed in a matrix; after adsorption and fixation, the pressure is kept stable for 4-5 seconds, during which the vacuum pressure sensor continuously collects pressure data; when the pressure fluctuation does not exceed ±0.002 MPa for 3 consecutive seconds, the CNC machine spindle is started for machining; when the adsorption pressure exceeds the range of -0.055 to -0.065 MPa, the vacuum generator automatically adjusts the pumping volume for pressure compensation; if the pressure still cannot be met after 3 compensations, the system pauses processing, displays the "adsorption failure" fault code, and records the fault occurrence time and pressure data.
[0018] Preferably, in step S5, the synchronization sequence of loading / unloading and processing is preset by a Siemens S7-1200 series PLC controller; the loading action is subdivided into three stages: semi-finished product picking, acupoint positioning and placement, and pre-fixing of interchangeable fixture plates; the semi-finished product picking stage lasts 18-22 seconds, with the gripper driven by a servo motor, and the gripper moving at a speed of 50-60 mm / s; the acupoint positioning and placement stage lasts 12-16 seconds, using an industrial camera for positioning, and the positional deviation of the semi-finished product placed in the acupoint does not exceed 0. 0.02mm; The pre-fixing stage of the interchangeable fixture plate lasts 6-8 seconds, and the interchangeable fixture plate is fixed by simple buckles; The total loading time is 36-46 seconds, and the processing time of a single interchangeable fixture plate is 55-65 seconds. The total loading time shall not exceed 80% of the processing time of a single interchangeable fixture plate; If the mechanical gripper jams during the loading process, the PLC controller sends a "loading delay" signal to the central control system, and the system temporarily extends the processing time of the current processing group by 5-10 seconds each time, up to a maximum of 3 times.
[0019] Preferably, in step S7, compressed air at 0.45-0.55 MPa is used for air gun purging; three air gun nozzles are evenly arranged circumferentially at the finished product unloading station, with the nozzle axis forming a 50-55° angle with the surface of the interchangeable fixture plate, and the distance between the nozzle and the surface of the interchangeable fixture plate is 12-14 mm; the purging time for a single purging is 6-7 seconds, and the purging sequence is first the inside of the acupoint, then the surface of the interchangeable fixture plate, with each acupoint purging for 1-1.2 seconds; after purging, residual chips on the surface of the interchangeable fixture plate are detected by an infrared dust sensor, with a sensor detection accuracy of ±1 mg; when the residual chip amount exceeds 5 mg, the system automatically restarts the purging program, repeating a maximum of 2 times; if it still does not meet the standard, a message "fixture cleaning is not thorough" is displayed, requiring manual intervention for cleaning; after cleaning, the interchangeable fixture plate is visually inspected to confirm that the acupoints are undamaged and undeformed, and then the semi-finished product is reinstalled.
[0020] Preferably, in step S6, the switching of the two sets of interchangeable fixture plates is achieved by the coordinated drive of dual-sided push cylinders. The switching process adopts a two-stage control of "rapid movement - precise alignment". The initial movement speed is 90-100 mm / s. When the interchangeable fixture plate is 10-15 mm away from the positioning block of the processing area, the speed drops to 25-30 mm / s, and the switching alignment deviation does not exceed 0.02 mm. The total switching time of the two sets of interchangeable fixture plates is 1.5-2 seconds. During the switching process, the CNC machine spindle maintains a low-speed standby state of 600-700 r / min. After the switching is completed, the central control system sends a "resume processing" command to the spindle. The spindle rises to the preset processing speed within 0.4-0.5 seconds. The preset processing speed is 3200-3800 r / min. After the spindle rises to the preset speed, processing begins immediately.
[0021] Preferably, the process also includes a finished product quality inspection step: after the finished product is removed from the interchangeable fixture plate, a vision inspection module performs full-size and surface quality inspection on the finished product; the vision inspection module includes a 2-megapixel industrial camera, a ring LED light source, and a defect recognition system; the industrial camera has a resolution of 1920×1080 and a frame rate of 30fps; the ring LED light source has a color temperature of 5800-6200K and an illumination uniformity of ≥90%; the defect recognition system is based on the Canny edge detection algorithm and grayscale contrast algorithm; during inspection, the industrial camera operates from three angles: the front, the top, and the side of the finished product. The system captures images at various angles; the image processor measures the length, width, and thickness of the finished product with a dimensional accuracy of ±0.005mm; it also identifies whether there are scratches on the surface of the finished product that are wider than 0.02mm and longer than 0.3mm, or dents that are deeper than 0.01mm; qualified finished products are placed into a storage box by mechanical grippers, while unqualified products are placed into a separate unqualified product collection box; the central control system synchronously records the batch number, defect type, defect location, and inspection time of unqualified products, and the data is automatically stored in the local database for a storage period of ≥1 year, and is also synchronously uploaded to the cloud server.
[0022] Preferably, in step S2, the semi-finished product feeding hopper adopts a 4-layer drawer structure, each layer can accommodate 2 interchangeable fixture plates, and the layer spacing is 180-190mm; each layer has two parallel guide rails at the bottom, the rails are made of 45# steel, chrome-plated, the chrome plating layer thickness is 0.08-0.1mm, and the surface roughness Ra≤0.8μm; the rail surface is coated with No. 2 lithium-based grease conforming to GB / T7324-2010 standard, and the sliding friction coefficient of the interchangeable fixture plates is 0.025-0.03; two photoelectric positioning sensors are installed at the feeding hopper inlet to... The sensors, positioned on both sides of the slide rail, have a detection accuracy of ±0.01mm. When the semi-finished product slides into the cavity of the interchangeable fixture plate along the slide rail, the sensors detect in real time whether the semi-finished product is fully in place. When the semi-finished product is detected to protrude more than 0.02mm from the edge of the cavity, the side pusher cylinder is triggered to finely adjust the position of the semi-finished product, ensuring that the feeding position deviation does not exceed 0.02mm. The feeding hopper is equipped with a semi-finished product balance monitoring function, which detects the remaining quantity of semi-finished products in each layer through an infrared ranging sensor. When the balance of a certain layer is less than 1 / 4 of the total capacity, a "semi-finished product balance insufficient" signal is sent to the central control system to prompt manual replenishment.
[0023] Preferably, the central control system uses an industrial-grade touchscreen and an STM32H743VIT6 main control chip; the industrial-grade touchscreen is 10.1 inches in size, with a resolution of 1280×800 and a response time of ≤50ms; data transmission uses Ethernet with a transmission rate of 100Mbps; the system collects the working status, processing progress, semi-finished product balance, vacuum adsorption pressure, and cylinder working pressure of the two sets of interchangeable fixture plates in real time, with the vacuum adsorption pressure and cylinder working pressure collected once per second; the collected data is dynamically displayed on the touchscreen; when it is detected that the loading of a certain set of interchangeable fixture plates is incomplete, the central control system... The control system sends an "extend processing" command to the CNC machine, extending the single processing time of the current processing group by 15-20 seconds. Different colored indicator lights distinguish the status of the two sets of interchangeable fixture plates: green indicates processing in progress, yellow indicates waiting to be loaded, and red indicates an error. If the waiting group still has not completed loading after the extended time, the system pauses processing and prompts "loading timeout". After loading is completed, the uninterrupted processing flow is restarted through the "one-key recovery" function. The system has a fault self-diagnosis function, which can automatically identify 12 common faults such as vacuum failure, abnormal cylinder pressure, and interchangeable fixture plate jamming, and provide corresponding troubleshooting suggestions.
[0024] Compared with the prior art, the beneficial effects of the present invention are as follows:
[0025] This invention enables CNC machining and loading / unloading processes to run in parallel by using two sets of interchangeable fixture plates. This completely avoids machine interruptions caused by loading / unloading during traditional single-set fixture processing, significantly improving the effective operating time of the equipment and ensuring long-term continuous processing capability.
[0026] Compared to the traditional manual loading and unloading mode, this method completes the positioning, fixing and switching of the fixture through the collaboration of the central control system and automated components. It does not require frequent manual intervention, which greatly reduces the manpower input of a single machine, reduces labor costs and human operation errors, improves the stability of parts processing quality, and reduces defective products caused by clamping misalignment and improper operation.
[0027] This method is adapted to the diverse processing needs of 3C product parts. By optimizing the fixture plate structure and processing sequence, it effectively increases the number of parts processed per unit time, while avoiding the wear and tear on spindle accuracy caused by frequent equipment start-ups and shutdowns, extending equipment lifespan, enhancing the overall capacity and production flexibility of CNC machining lines, and meeting the large-scale, high-efficiency production requirements of the 3C industry. Attached Figure Description
[0028] Figure 1 This is a schematic diagram of the fixture structure of the present invention;
[0029] Figure 2 This is a flowchart of the method of the present invention.
[0030] in:
[0031] 1. Interchangeable jig plate; 2. Side push cylinder; 3. Lifting cylinder; 4. Finished product picking box; 5. Semi-finished product feeding bin; 6. Lever cylinder. Detailed Implementation
[0032] The invention will now be further described with reference to the accompanying drawings.
[0033] like Figure 1 , Figure 2 As shown, a method for continuous processing of two sets of products on a CNC machine with alternating feeding includes the following steps:
[0034] S1. Two sets of interchangeable jig plates 1 with identical structures are configured. Each set of interchangeable jig plates 1 is equipped with 40 processing slots for 3C product parts. Simultaneously equipped with a semi-finished product feeding bin 5, a finished product picking box 4, a drive assembly consisting of a lifting cylinder 3, a side pushing cylinder 2, and a lever cylinder 6, as well as a vacuum adsorption device and a central control system.
[0035] S2. Load the semi-finished parts of 3C products one by one into the processing cavity of the two sets of interchangeable jig plates, so that the gap between the semi-finished products and the inner wall of the cavity does not exceed 0.03mm; put the interchangeable jig plate 1 filled with semi-finished products into the two corresponding feeding bins of the CNC machine, and cooperate with the guide structure in the feeding bin to achieve positioning.
[0036] S3. Close the safety door of the CNC machine and start the machine through the central control system; the two side push cylinders 2 simultaneously push the two sets of interchangeable fixture plates 1 to move towards the processing area according to the preset program until the edge of the interchangeable fixture plate is in contact with the positioning block of the processing area; the lifting cylinder pushes the interchangeable fixture plate upward so that the bottom of the interchangeable fixture plate is pressed against the limit protrusion in the push plate groove to complete the initial fixation.
[0037] S4. The lever cylinder drives the pressure block to press down on the four corners of the interchangeable fixture plate. At the same time, the vacuum adsorption device is activated and adsorbs the bottom of the interchangeable fixture plate. After the adsorption pressure stabilizes, the pressure block is opened, and the CNC machine spindle processes 40 acupoint products of one set of interchangeable fixture plates according to the preset processing parameters.
[0038] S5. During the processing of the current set of interchangeable fixture plates, the central control system controls another set of interchangeable fixture plates to move to the loading and unloading station, and simultaneously completes the unloading of finished products or the replenishment of semi-finished products, so as to realize the parallel processing and loading and unloading processes.
[0039] S6. After the first set of interchangeable fixture plates is processed, the side-push cylinder pushes it to the unloading position; at the same time, another set of interchangeable fixture plates that have been loaded is pushed to the processing area, and the pressing, adsorption fixing and processing actions of step S4 are repeated to complete the switching of the two sets of interchangeable fixture plates.
[0040] S7. For the interchangeable jig plate at the unloading position, the finished product is removed by mechanical grippers, and then the surface of the interchangeable jig plate and the inside of the cavity are cleaned by air gun; after removing residual chips, the semi-finished product is reloaded to form a cycle of interchangeable jig plate feeding.
[0041] S8. Repeat steps S4 to S7, continuously rotating the two sets of interchangeable fixture plates to achieve long-term uninterrupted continuous processing by the CNC machine.
[0042] Furthermore, in step S1, the interchangeable fixture plate includes a cover plate and a base plate, which are detachably connected by a combination of snap-fit and positioning pins; the diameter of the positioning pin is 2.5-3mm, the fitting clearance between the positioning pin and the pin hole is 0.005-0.01mm, and the alignment deviation between the cover plate and the base plate does not exceed 0.01mm; each processing cavity has an elastic protective layer fixedly installed on its inner wall, the protective layer is made of food-grade silicone material with a Shore hardness of 48-52HA, the thickness is 0.9-1.1mm, and the surface is matte; the inner wall of the protective layer has an arc-shaped groove that matches the outer contour of the 3C product parts, and the groove depth is 1-1.5mm.
[0043] Furthermore, in step S3, the side-push cylinder has a built-in high-precision strain gauge pressure sensor. The pushing pressure is monitored in real time by the sensor, with a pressure value of 0.35-0.45MPa and a sensor detection accuracy of ±0.005MPa. The clamping force of the lifting cylinder is 0.22-0.28MPa. The pushing process adopts a three-stage speed control of "slow-fast-slow". The initial stage speed is 30-40mm / s, the middle stage speed is 80-100mm / s, and the speed drops to 20-30mm / s when approaching the push plate slot. When the pushing pressure is lower than 0.35MPa or higher than 0.45MPa, or the clamping force exceeds the range of 0.22-0.28MPa, the central control system immediately suspends the operation of the drive components, displays "abnormal side-push pressure" or "abnormal lifting force" prompts on the human-machine interface, and triggers a buzzer to emit an intermittent alarm signal with a frequency of 1 time / second. After the fault is cleared, the operation is restored by manual reset.
[0044] Furthermore, in step S4, the adsorption pressure of the vacuum adsorption device is adjusted to -0.055 to -0.065 MPa by the vacuum generator; the adsorption area covers 65%-70% of the bottom area of the interchangeable fixture plate, the diameter of the adsorption holes is 1.8-2.2 mm, the hole spacing is 6-7 mm, and the adsorption holes are uniformly distributed in a matrix; after adsorption and fixation, the pressure is maintained for 4-5 seconds for a stable pressure time, during which the vacuum pressure sensor continuously collects pressure data; when the pressure fluctuation does not exceed ±0.002 MPa for 3 consecutive seconds, the CNC machine spindle is started for machining; when the adsorption pressure exceeds the range of -0.055 to -0.065 MPa, the vacuum generator automatically adjusts the pumping volume for pressure compensation; if the pressure still cannot be met after 3 compensations, the system pauses processing, displays the "adsorption failure" fault code, and records the fault occurrence time and pressure data.
[0045] Furthermore, in step S5, the synchronization sequence of loading / unloading and processing is preset by a Siemens S7-1200 series PLC controller; the loading action is subdivided into three stages: semi-finished product picking, acupoint positioning and placement, and pre-fixing of interchangeable fixture plates; the semi-finished product picking stage lasts 18-22 seconds, with the gripper driven by a servo motor, and the gripper moving at a speed of 50-60 mm / s; the acupoint positioning and placement stage lasts 12-16 seconds, using an industrial camera for positioning, and the deviation of the semi-finished product placement position does not exceed [a certain value]. 0.02mm; the pre-fixing stage of the interchangeable fixture plate lasts 6-8 seconds, and the interchangeable fixture plate is fixed by simple buckles; the total loading time is 36-46 seconds, the processing time of a single interchangeable fixture plate is 55-65 seconds, and the total loading time does not exceed 80% of the processing time of a single interchangeable fixture plate; if the mechanical gripper jams during the loading process, the PLC controller sends a "loading delay" signal to the central control system, and the system temporarily extends the processing time of the current processing group by 5-10 seconds each time, up to a maximum of 3 times.
[0046] Furthermore, in step S7, compressed air at 0.45-0.55MPa is used for air gun purging; three air gun nozzles are evenly arranged circumferentially at the finished product unloading station, with the nozzle axis forming a 50-55° angle with the surface of the interchangeable fixture plate, and the distance between the nozzle and the surface of the interchangeable fixture plate is 12-14mm; the single purging time is 6-7 seconds, and the purging sequence is first the inside of the acupoint, then the surface of the interchangeable fixture plate, with each acupoint purging time being 1-1.2 seconds; after purging, residual chips on the surface of the interchangeable fixture plate are detected by an infrared dust sensor, with a sensor detection accuracy of ±1mg; when the residual chip amount exceeds 5mg, the system automatically restarts the purging program, repeating a maximum of 2 times; if it still does not meet the standard, a message "fixture cleaning is not thorough" is displayed, requiring manual intervention for cleaning; after cleaning, the interchangeable fixture plate is visually inspected to confirm that the acupoints are undamaged and undeformed, and then the semi-finished product is reinstalled.
[0047] Furthermore, in step S6, the switching of the two sets of interchangeable fixture plates is achieved through the coordinated drive of dual-side push cylinders. The switching process adopts a two-stage control of "rapid movement - precise alignment". The initial movement speed is 90-100 mm / s. When the fixture plate is 10-15 mm away from the positioning block of the processing area, the speed drops to 25-30 mm / s, and the switching alignment deviation does not exceed 0.02 mm. The total switching time of the two sets of interchangeable fixture plates is 1.5-2 seconds. During the switching process, the CNC machine spindle maintains a low-speed standby state of 600-700 r / min. After the switching is completed, the central control system sends a "resume processing" command to the spindle. The spindle rises to the preset processing speed within 0.4-0.5 seconds. The preset processing speed is 3200-3800 r / min. After the spindle rises to the preset speed, processing begins immediately.
[0048] Furthermore, the process includes a finished product quality inspection step: after the finished product is removed from the fixture plate, a vision inspection module performs full-size and surface quality inspections. The vision inspection module includes a 2-megapixel industrial camera, a ring LED light source, and a defect recognition system. The industrial camera has a resolution of 1920×1080 and a frame rate of 30fps. The ring LED light source has a color temperature of 5800-6200K and an illumination uniformity of ≥90%. The defect recognition system is based on the Canny edge detection algorithm and grayscale contrast algorithm. During inspection, the industrial camera operates from three angles: the front, top, and side of the finished product. The system captures images at various angles; the image processor measures the length, width, and thickness of the finished product with a dimensional accuracy of ±0.005mm; it also identifies whether there are scratches on the surface of the finished product that are wider than 0.02mm and longer than 0.3mm, or dents that are deeper than 0.01mm; qualified finished products are placed into a storage box by mechanical grippers, while unqualified products are placed into a separate unqualified product collection box; the central control system synchronously records the batch number, defect type, defect location, and inspection time of unqualified products, and the data is automatically stored in the local database for a storage period of ≥1 year, and is also synchronously uploaded to the cloud server.
[0049] Furthermore, in step S2, the semi-finished product feeding hopper adopts a 4-layer drawer structure, with each layer accommodating two interchangeable jig plates, and the layer spacing is 180-190mm; each layer has two parallel guide rails at the bottom, the rails are made of 45# steel, chrome-plated, with a chrome plating thickness of 0.08-0.1mm and a surface roughness Ra≤0.8μm; the rail surface is coated with No. 2 lithium-based grease conforming to GB / T7324-2010 standard, and the sliding friction coefficient of the jig plates is 0.025-0.03; two photoelectric positioning sensors are installed at the feeding hopper inlet. Symmetrically arranged on both sides of the slide rail, the sensor detection accuracy is ±0.01mm; when the semi-finished product slides into the fixture plate cavity along the slide rail, the sensor detects in real time whether the semi-finished product is fully in place; when the semi-finished product is detected to protrude more than 0.02mm from the edge of the cavity, the side pusher cylinder is triggered to finely adjust the position of the semi-finished product, and the feeding position deviation does not exceed 0.02mm; the feeding hopper is equipped with a semi-finished product balance monitoring function, which detects the remaining quantity of semi-finished products in each layer through an infrared ranging sensor; when the balance of a certain layer is less than 1 / 4 of the total capacity, a "semi-finished product balance insufficient" signal is sent to the central control system to prompt manual replenishment.
[0050] Furthermore, the central control system employs an industrial-grade touchscreen and an STM32H743VIT6 main control chip. The industrial-grade touchscreen is 10.1 inches in size, with a resolution of 1280×800 and a response time of ≤50ms. Data transmission uses Ethernet with a transmission rate of 100Mbps. The system collects real-time data on the working status, processing progress, semi-finished product balance, vacuum adsorption pressure, and cylinder working pressure of the two sets of interchangeable fixture plates. The vacuum adsorption pressure and cylinder working pressure are collected once per second. The collected data is dynamically displayed on the touchscreen. When it is detected that a fixture plate has not been fully loaded, the central control system... The central control system sends an "extend processing" command to the CNC machine, extending the single processing time of the current processing group by 15-20 seconds. Different colored indicator lights distinguish the status of the two sets of interchangeable fixture plates: green indicates processing in progress, yellow indicates waiting to be loaded, and red indicates an error. If the waiting group still has not completed loading after the extended time, the system pauses processing and prompts "loading timeout". After loading is completed, the uninterrupted processing flow is restarted through the "one-key recovery" function. The system has a fault self-diagnosis function, which can automatically identify 12 common faults such as vacuum failure, abnormal cylinder pressure, and fixture plate jamming, and provide corresponding troubleshooting suggestions.
[0051] Example 1: Continuous CNC machining of aluminum alloy 3C product frames
[0052] 1. Equipment configuration and parameter settings
[0053] Two sets of interchangeable jig plates with identical structures are configured. Each jig plate has 40 processing holes that are compatible with an aluminum alloy frame (120mm×80mm×5mm in size). The diameter of the positioning pins of the cover plate and the base plate is set to 2.8mm, the clearance between the positioning pin and the pin hole is 0.008mm, and the alignment deviation between the cover plate and the base plate is controlled within 0.009mm. The elastic protective layer on the inner wall of the processing holes is made of food-grade silicone with a Shore hardness of 50HA, a thickness of 1.0mm, and an arc groove depth of 1.2mm, which completely fits the outer contour of the aluminum alloy frame.
[0054] The semi-finished product feeding hopper has a 4-layer drawer structure, with each layer accommodating 2 interchangeable jig plates and a layer spacing of 185mm. The guide rails are made of 45# steel with a chrome-plated layer thickness of 0.09mm and a surface roughness Ra=0.6μm. The surface of the rails is coated with No. 2 lithium-based grease conforming to GB / T7324-2010 standard, and the sliding friction coefficient of the jig plate is 0.028.
[0055] The side-push cylinder has a pushing pressure of 0.4 MPa, and the lifting cylinder has a clamping force of 0.25 MPa. The pushing speed is 35 mm / s in the initial stage, 90 mm / s in the middle stage, and drops to 25 mm / s when approaching the push plate groove. The vacuum adsorption device has an adsorption pressure of -0.06 MPa, an adsorption hole diameter of 2.0 mm, a hole spacing of 6.5 mm, and the adsorption area covers 68% of the bottom area of the fixture plate.
[0056] The CNC machine spindle is preset to a machining speed of 3500 r / min and a feed rate of 800 mm / min. The machining time for a single jig plate is 60 seconds. The total loading time is 38 seconds, including 20 seconds for the semi-finished product unloading stage (gripper movement speed 55 mm / s), 14 seconds for the acupoint positioning and placement stage, and 4 seconds for the jig plate pre-fixing stage.
[0057] 2. Processing Execution Flow
[0058] The semi-finished aluminum alloy frame is loaded one by one into the machining cavity of the two sets of interchangeable jig plates, ensuring that the gap between the semi-finished product and the inner wall of the cavity is 0.02mm. Then, the two sets of interchangeable jig plates are placed into the two feeding hoppers of the CNC machine, and the photoelectric positioning sensor of the feeding hopper confirms that the jig plate is fully in place.
[0059] When the CNC machine safety door is closed, the central control system starts the machine. The side push cylinders on both sides push the two sets of interchangeable fixture plates to the processing area. After the edges of the interchangeable fixture plates are in contact with the positioning blocks, the lifting cylinder pushes the bottom of the fixture plate to tighten the push plate groove limit protrusion, completing the initial fixation.
[0060] The lever cylinder drives the pressure block to press the four corners of the fixture plate. The vacuum adsorption device is activated and maintains a stable pressure time of 4.5 seconds with a pressure fluctuation of 0.001MPa. After the fixture is deemed to be in good condition, the pressure block is opened and the CNC machine spindle is started to process the 40 acupoint aluminum alloy frames of the first set of interchangeable fixture plates.
[0061] During the processing of the first set of interchangeable jig plates, the central control system controls the second set of jig plates to move to the loading and unloading station. The mechanical gripper completes the semi-finished product replenishment. During the replenishment process, the industrial camera positions the semi-finished product to ensure that the position deviation of the placement of the semi-finished product into the cavity is 0.015mm. The total loading time is 38 seconds, which is less than 80% (48 seconds) of the processing time of the first set of interchangeable jig plates, which is 60 seconds.
[0062] After the first set of interchangeable fixture plates is processed, the side-push cylinder pushes it to the unloading position. At the same time, the second set of fixture plates is pushed to the processing area. The clamping, adsorption and fixing and processing actions are repeated. The total switching time is 1.8 seconds. The spindle idle speed is 650 r / min. After the switching is completed, it rises to 3500 r / min within 0.45 seconds and starts processing.
[0063] The first set of interchangeable fixture plates at the unloading position removes the finished product using mechanical grippers. An air gun blows the product with 0.5MPa compressed air, with the nozzle 13mm away from the surface of the fixture plate. The blowing time for a single cycle is 6.5 seconds, and each acupoint is blown for 1.1 seconds. An infrared dust sensor detects a chip residue of 3mg. Once the requirement is met, the semi-finished product is reloaded and enters the next cycle.
[0064] 3. Implementation Results
[0065] The machine operates continuously for 8 hours, with two sets of interchangeable fixture plates rotating without interruption, processing a total of 12,800 aluminum alloy mid-frames. The finished product dimensional inspection pass rate is 99.8%, and the surface scratch and dent defect rate is 0.2%. Compared with the traditional 8-cavity fixture (12 seconds per CT), the single CT is reduced to 3 seconds, improving processing efficiency by 75%, and eliminating the need for frequent manual loading and unloading, reducing the manpower input per machine by 80%.
[0066] Example 2: Continuous CNC machining of ABS plastic buttons for 3C products
[0067] 1. Equipment configuration and parameter settings
[0068] It is equipped with two sets of interchangeable jig plates, and 40 acupoints are compatible with ABS plastic buttons (10mm×8mm×3mm in size); the diameter of the positioning pins of the cover plate and the base plate is 2.6mm, the fit clearance is 0.006mm, and the alignment deviation is 0.008mm; the elastic protective layer of the acupoints is made of food-grade silicone with a Shore hardness of 49HA, a thickness of 0.95mm, and an arc groove depth of 1.1mm.
[0069] The semi-finished product feeding hopper has a layer spacing of 182mm, the guide rail has a chrome plating layer thickness of 0.085mm, a surface roughness Ra=0.7μm, and a sliding friction coefficient of 0.026; the photoelectric positioning sensor has a detection accuracy of ±0.01mm, and the side pusher cylinder has a fine adjustment stroke of 0.5mm.
[0070] The side-push cylinder has a pushing pressure of 0.38 MPa, the lifting cylinder has a clamping force of 0.23 MPa, the pushing speed is 32 mm / s in the initial stage, 85 mm / s in the middle stage, and drops to 22 mm / s when approaching the push plate groove. The vacuum adsorption pressure is -0.058 MPa, the adsorption hole diameter is 1.9 mm, the hole spacing is 6.2 mm, and the adsorption area covers 66% of the bottom area of the fixture plate.
[0071] The CNC machine spindle is preset to a machining speed of 3200 r / min and a feed rate of 600 mm / min. The machining time for a single jig plate is 58 seconds. The total loading time is 42 seconds, including 19 seconds for the semi-finished product unloading stage (gripper movement speed 52 mm / s), 15 seconds for the acupoint positioning and placement stage, and 8 seconds for the jig plate pre-fixing stage.
[0072] 2. Processing Execution Flow
[0073] The ABS plastic button semi-finished products are loaded into the acupoints of two sets of interchangeable jig plates with a fitting gap of 0.025mm. After the jig plates are placed into the feeding hopper, the photoelectric positioning sensor detects that one semi-finished product protrudes 0.022mm from the edge of the acupoint. The side pusher cylinder is activated for fine adjustment, correcting the position deviation to 0.018mm.
[0074] Start the CNC machine. The side-push cylinder and the lifting cylinder work together to initially fix the jig plate. After the lever cylinder presses it, the vacuum adsorption device is started. The pressure stabilization time is 4 seconds and the pressure fluctuation is 0.0015MPa. After the requirements are met, the spindle starts to process the buttons of the first set of interchangeable jig plates.
[0075] During the first set of processing, the second set of fixture plates moves to the loading and unloading station, and the mechanical grippers replenish the semi-finished products. The industrial camera positioning ensures that the positional deviation is 0.019mm. During the replenishment process, the mechanical grippers briefly jam, and the PLC controller sends a "loading delay" signal. The system extends the processing time of the first set of interchangeable fixture plates by 7 seconds to ensure that the loading is completed.
[0076] After the first set of processing is completed, the two sets of interchangeable fixture plates are switched, with a switching time of 1.6 seconds. The spindle standby speed is 620 r / min, which is increased to 3200 r / min within 0.4 seconds and the second set of processing is started. When the first set of interchangeable fixture plates is unloaded, the air gun blows with compressed air at 0.48 MPa. After the blowing is completed, the infrared dust sensor detects that the residual chip amount is 4 mg. After visual inspection confirms that the acupoints are undamaged, the material is reloaded.
[0077] After the finished product is removed, the visual inspection module takes images from the front, top, and side. The measurement shows that the length deviation of the button is 0.004mm and the width deviation is 0.003mm. No excessive scratches or dents are detected. Qualified finished products are placed in the storage box, while one unqualified product with a size deviation of 0.055mm is placed in a separate collection box. The system records the batch number, defect type, and inspection time of the unqualified product.
[0078] 3. Implementation Results
[0079] After 10 hours of continuous processing, a total of 16,550 ABS plastic buttons were processed, with a finished product qualification rate of 99.7%. Among the defective products, 60% had dimensional deviations and 40% had surface defects. The single-piece CT was reduced to 3.1 seconds, which is 74% more efficient than the traditional 8-cavity jig (single-piece CT 12 seconds). The elastic protective layer of the jig plate effectively prevented the plastic buttons from being crushed, and the defect rate was reduced from 1.5% in traditional processing to 0.3%.
Claims
1. A CNC machine two groups of product rotation loading uninterrupted processing method, characterized in that, The method comprises the following steps: S1, configure two groups of interchangeable jig plates with consistent structure, each group of interchangeable jig plates is provided with 40 machining holes suitable for 3C product parts; simultaneously, a semi-finished product feeding bin, a finished product taking box, a driving assembly composed of a jacking cylinder, a side pushing cylinder and a lever cylinder, and a vacuum adsorption device and a central control system are provided; S2, load the 3C product part semi-finished products into the machining holes of the two groups of interchangeable jig plates one by one, so that the gap between the semi-finished products and the inner wall of the hole is not more than 0.03mm; load the interchangeable jig plates filled with semi-finished products into the corresponding two feeding bins of the CNC machine respectively, and realize positioning by cooperating with the guiding structure in the feeding bin; S3, close the safety door of the CNC machine, and start the machine table through the central control system; the two side pushing cylinders simultaneously push the two groups of interchangeable jig plates to move towards the machining area according to the preset program until the edges of the interchangeable jig plates are attached to the positioning blocks of the machining area; the jacking cylinder pushes the interchangeable jig plates upwards so that the interchangeable jig plates are tightly pushed against the limiting protrusions in the push plate groove, and the preliminary fixing is completed; S4, the lever cylinder drives the pressing block to press the four corner positions of the interchangeable jig plate downwards, and the vacuum adsorption device is started and adsorbs the bottom of the interchangeable jig plate; after the adsorption pressure is stable, the pressing block is opened, and the main shaft of the CNC machine processes the 40 hole products of one group of interchangeable jig plates according to the preset processing parameters; S5, during the processing of the current group of interchangeable jig plates, the central control system controls the other group of interchangeable jig plates to move to the feeding and discharging station, and simultaneously completes the finished product discharging or semi-finished product reloading action, so that the processing and feeding and discharging processes are parallel; S6, after the processing of the first group of interchangeable jig plates is completed, the side pushing cylinder pushes them to the discharging position; at the same time, the other group of interchangeable jig plates that have completed feeding are pushed to the machining area, and the pressing, adsorption fixing and processing actions of step S4 are repeated to complete the switching of the two groups of interchangeable jig plates; S7, the interchangeable jig plate at the discharging position is taken out by the mechanical clamping jaw, and the surface of the interchangeable jig plate and the inside of the hole are blown and cleaned by the air gun; after the residual chips are removed, the semi-finished products are reloaded to form a circulating feeding of the interchangeable jig plate; S8, repeat steps S4 to S7, and continuously rotate the two groups of interchangeable jig plates to realize long-time uninterrupted continuous processing of the CNC machine.
2. The CNC machine two-group product rotation loading non-stop processing method according to claim 1, characterized in that, In step S1, the interchangeable jig plate comprises a cover plate and a bottom plate, which are detachably connected by a buckle and a positioning pin combination; the diameter of the positioning pin is 2.5-3mm, the gap between the positioning pin and the pin hole is 0.005-0.01mm, and the deviation of the cover plate and the bottom plate is not more than 0.01mm; an elastic protective layer is fixedly arranged on the inner wall of each machining hole, the protective layer is made of food-grade silicone material with a Shore hardness of 48-52HA, the thickness is 0.9-1.1mm, and the surface is matte treated; the inner wall of the protective layer is provided with an arc-shaped groove matched with the outer contour of the 3C product part, and the groove depth is 1-1.5mm.
3. The CNC machine two group product rotation feeding non-stop processing method according to claim 1, characterized in that, In step S3, the side pushing cylinder is provided with a high-precision strain pressure sensor, the pushing pressure is monitored in real time through the sensor, the pressure value is 0.35-0.45 MPa, the sensor detection accuracy is ±0.005 MPa; the jacking force of the jacking cylinder is 0.22-0.28 MPa, the pushing process adopts a "slow-fast-slow" three-stage speed control, the initial stage speed is 30-40 mm / s, the intermediate stage speed is 80-100 mm / s, and the speed is reduced to 20-30 mm / s when approaching the push plate groove; when the pushing pressure is lower than 0.35 MPa or higher than 0.45 MPa, or the jacking force exceeds the range of 0.22-0.28 MPa, the central control system immediately suspends the driving assembly action, displays "side pushing pressure abnormal" or "jacking force abnormal" prompt on the man-machine interaction interface, and triggers the buzzer to issue intermittent alarm signals, the alarm signal frequency is 1 time / s; after troubleshooting, the action is restored by manual reset.
4. The CNC machine two group product rotation feeding non-stop processing method according to claim 1, characterized in that, In step S4, the adsorption pressure of the vacuum adsorption device is adjusted to-0.055 to-0.065 MPa by the vacuum generator; the adsorption area covers 65%-70% of the bottom area of the interchangeable jig plate, the adsorption hole diameter is 1.8-2.2 mm, the hole spacing is 6-7 mm, and the adsorption holes are uniformly distributed in a matrix; after adsorption and fixation, the pressure is stable for 4-5 seconds, and the vacuum pressure sensor continuously collects pressure data during this period; when the pressure fluctuation is not more than ±0.002 MPa for 3 seconds, the CNC machine spindle is started; when the adsorption pressure exceeds the range of-0.055 to-0.065 MPa, the vacuum generator automatically adjusts the air extraction amount for pressure compensation; if the compensation fails for 3 times, the system will pause the processing, display the "adsorption failure" fault code, and record the fault time and pressure data.
5. The CNC machine two group product rotation feeding non-stop processing method according to claim 1, characterized in that, In step S5, the synchronization timing of the feeding and processing procedures is preset by the Siemens S7-1200 series PLC controller; the feeding action is divided into three stages: semi-finished product taking, acupoint positioning and placing, and interchangeable jig plate pre-fixing; the semi-finished product taking stage lasts for 18-22 seconds, the clamping jaw is driven by a servo motor to take the material, and the clamping jaw moves at a speed of 50-60 mm / s; the acupoint positioning and placing stage lasts for 12-16 seconds, and an industrial camera is used for positioning and shooting, and the position deviation of the semi-finished product placed in the acupoint is not more than 0.02 mm; the interchangeable jig plate pre-fixing stage lasts for 6-8 seconds, and the interchangeable jig plate is fixed by a simple buckle; the total feeding time is 36-46 seconds, the processing time of a single interchangeable jig plate is 55-65 seconds, and the total feeding time is not more than 80% of the processing time of a single interchangeable jig plate; when the mechanical clamping jaw is stuck during the feeding process, the PLC controller sends a "feeding delay" signal to the central control system, the system temporarily extends the processing time of the current processing group, and each extension is 5-10 seconds, and the maximum extension is 3 times.
6. The CNC machine two group product rotation feeding non-stop processing method according to claim 1, characterized in that, In step S7, the air gun blowing uses 0.45-0.55 MPa compressed air; 3 air gun nozzles are uniformly arranged on the circumference of the finished product unloading station, the axis of the nozzle forms an angle of 50-55° with the surface of the interchangeable jig plate, the distance between the nozzle and the surface of the interchangeable jig plate is 12-14 mm; the single blowing time is 6-7 seconds, the blowing sequence is first inside the acupuncture point and then the surface of the interchangeable jig plate, and the blowing time for each acupuncture point is 1-1.2 seconds; after blowing, the residual chips on the surface of the interchangeable jig plate are detected by an infrared dust sensor, the detection accuracy of the sensor is ±1 mg; when the residual chip amount exceeds 5 mg, the system automatically restarts the blowing program, and the maximum repetition is 2 times; if it still does not meet the standard, it prompts "incomplete jig cleaning" and needs manual intervention for cleaning; after cleaning, the interchangeable jig plate is reloaded into the semi-finished product after visual detection confirms that the acupuncture point is not damaged and not deformed.
7. The CNC machine two group product rotation feeding non-stop processing method according to claim 1, characterized in that, In step S6, the switching of the two groups of interchangeable jig plates is achieved by the coordinated driving of the double-sided push air cylinders, and the switching process adopts two-stage control of "fast movement-accurate positioning"; the initial movement stage speed is 90-100 mm / s, the speed is reduced to 25-30 mm / s when the interchangeable jig plate is 10-15 mm away from the positioning block of the machining area, and the switching positioning deviation is not more than 0.02 mm; the total switching time of the two groups of interchangeable jig plates is 1.5-2 seconds; during the switching process, the CNC machine spindle maintains a low speed standby state of 600-700 r / min; After the switching is completed, the central control system sends the "resume machining" instruction to the spindle, and the spindle rises to the preset machining speed within 0.4-0.5 seconds, the preset machining speed is 3200-3800 r / min, and the spindle starts machining immediately after rising to the preset speed.
8. The CNC machine two group product rotation feeding non-stop processing method according to claim 1, characterized in that, It also includes a finished product quality detection step: after the finished product is taken out from the interchangeable jig plate, the full size and surface quality of the finished product are detected by a visual detection module; the visual detection module includes a 2 million pixel industrial camera, a ring LED light source and a defect recognition system; the resolution of the industrial camera is 1920x1080, and the frame rate is 30 fps; the color temperature of the ring LED light source is 5800-6200 K, and the light uniformity is ≥90%; the defect recognition system is based on Canny edge detection algorithm and gray scale contrast algorithm; during detection, the industrial camera shoots images from three angles of front, top and side of the finished product; the image processor measures the length, width and thickness of the finished product, and the size detection accuracy is ±0.005 mm; at the same time, it identifies whether there are scratches with a width of more than 0.02 mm and a length of more than 0.3 mm, or depressions with a depth of more than 0.01 mm on the surface of the finished product; the qualified finished products are put into the storage box by the mechanical clamping jaw, and the unqualified products are put into a separate unqualified product collection box; the central control system synchronously records the batch number, defect type, defect position and detection time of the unqualified product, and automatically stores the data to the local database with a storage period of ≥1 year, and synchronously uploads to the cloud server.
9. The CNC machine two group product rotation feeding non-stop processing method according to claim 1, characterized in that, In step S2, the semi-finished product feeding bin adopts a 4-layer drawer structure, each layer can accommodate 2 interchangeable jig plates, and the layer spacing is 180-190 mm; the bottom of each layer is provided with two parallel guide rails, the guide rails are made of 45# steel, the surface is chrome plated, the thickness of the chrome plated layer is 0.08-0.1 mm, and the surface roughness Ra is ≤0.8 μm; the surface of the guide rail is coated with No. 2 lithium-based lubricating grease in accordance with the GB / T7324-2010 standard, the sliding friction coefficient of the interchangeable jig plate is 0.025-0.03; two photoelectric positioning sensors are arranged at the entrance of the feeding bin, symmetrically arranged on both sides of the guide rail, and the sensor detection accuracy is ±0.01 mm; when the semi-finished product slides into the interchangeable jig plate hole along the guide rail, the sensor detects whether the semi-finished product is completely positioned in real time; when the semi-finished product protrudes beyond the edge of the hole by more than 0.02 mm, the side edge pushing cylinder is triggered to fine-tune the position of the semi-finished product, and the feeding position deviation is not more than 0.02 mm; the feeding bin is provided with a semi-finished product excess monitoring function, which detects the number of remaining semi-finished products in each layer through an infrared distance sensor; when the amount of a certain layer is less than 1 / 4 of the total capacity, a "semi-finished product shortage” signal is sent to the central control system, prompting manual feeding.
10. The CNC machine two group product rotation feeding non-stop processing method according to claim 1, characterized in that, The central control system adopts an industrial-grade touch screen and an STM32H743VIT6 main control chip; the industrial-grade touch screen is 10.1 inches in size, with a resolution of 1280×800 and a response time of ≤50 ms; data transmission uses Ethernet, with a transmission rate of 100 Mbps; the system collects the working state, processing progress, semi-finished product excess, vacuum suction pressure and cylinder working pressure of the two interchangeable jig plates in real time, with a collection frequency of 1 time per second; the collected data is dynamically displayed on the touch screen; when the feeding of a certain group of interchangeable jig plates is not completed, the central control system sends a "processing extension” instruction to the CNC machine, extending the single processing time of the current processing group by 15-20 seconds; different color indicator lights are used to distinguish the state of the two groups of interchangeable jig plates, green indicates processing, yellow indicates waiting for feeding, and red indicates abnormality; when the feeding of the waiting group is not completed after the extension time, the system pauses processing and prompts "feeding timeout”; after feeding is completed, the "one-key recovery” function is used to restart the uninterrupted processing process; the system has a fault self-diagnosis function, which can automatically identify 12 common faults such as vacuum failure, cylinder pressure abnormality and interchangeable jig plate jamming, and give corresponding troubleshooting suggestions.