Roof leveling and anti-cracking integrated structure and synchronous construction method thereof

By introducing a combination structure of elastic stress buffer layer, active honeycomb waterproof unit and gradient protective surface layer into the roof leveling layer, the problems of stress concentration and self-repair after water seepage are solved, and the crack resistance and waterproof performance are improved and the construction efficiency is increased.

CN121473520AActive Publication Date: 2026-02-06CHINA RAILWAY NO 9 GROUP CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202610024721.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-01-09
Publication Date
2026-02-06
Estimated Expiration
2046-01-09

Smart Images

  • Figure CN121473520A_ABST
    Figure CN121473520A_ABST
Patent Text Reader

Abstract

The invention discloses a roof leveling and anti-cracking integrated structure and a synchronous construction method thereof, and relates to the technical field of building roof engineering.The roof leveling and anti-cracking integrated structure comprises an elastic stress buffer layer, an anti-cracking layer and an anti-cracking layer, the active honeycomb water stop unit array is pre-buried in the elastic stress buffer layer according to a preset spacing rule when the elastic stress buffer layer is paved, each active honeycomb water stop unit comprises a honeycomb-shaped hollow shell and a water-swelling water stop material filled in the honeycomb-shaped hollow shell, and the top of the shell is flush with the upper surface of the elastic stress buffer layer; water permeable holes are formed in the side wall of the shell; and the gradient protection surface layer is compounded on the elastic stress buffer layer and the water stop unit array, the elasticity modulus of the gradient protection surface layer is gradually decreased from bottom to top in a gradient mode, through the integrated structural design, the leveling layer has the self-adaptive crack resistance and water stop capacity, the working procedure is simplified by 30% or above, the crack resistance is improved by 50%, and the reliability and durability of roof engineering are remarkably improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of building roofing engineering, in particular to a roofing leveling and anti-cracking integrated structure and a synchronous construction method thereof. BACKGROUND

[0002] The roofing leveling layer is the key supporting layer of the waterproof system, and its cracking is the primary cause of roof leakage. The traditional cement mortar leveling layer is brittle and is prone to cracking under the action of temperature stress, dry shrinkage stress and base deformation. The current common technical remedies are "adding anti-cracking mesh cloth" and "setting sub-grid joints", which have the following inherent defects: (1) the mechanical bonding interface between the anti-cracking mesh cloth and the mortar is weak, which is prone to hollowing, and cannot inhibit structural cracks caused by uneven settlement of the base; (2) although the sub-grid joint can release stress, it itself becomes a weak link of waterproofing and needs additional sealing treatment, which increases the process and leakage points; (3) the leveling layer and the subsequent waterproof layer are constructed in layers, which has the risk of interlayer peeling.

[0003] The current common technical solution of "adding anti-cracking mesh cloth" mainly improves the crack resistance by adding short fibers and laying steel wire mesh, but does not solve the problems of stress concentration and self-repairing after water seepage. Another technical solution of "setting sub-grid joints" focuses on drainage, and the crack resistance mechanism still relies on traditional sub-grid joints. These technologies belong to the idea of "passive resistance" or "after-the-fact drainage", and cannot achieve "active adaptation" and "damage self-repairing" of the leveling layer from the structural design. SUMMARY

[0004] The present application aims to provide a roofing leveling and anti-cracking integrated structure and a synchronous construction method thereof, to solve the problems in the background art that the current common technical solution of "adding anti-cracking mesh cloth" mainly improves the crack resistance by adding short fibers and laying steel wire mesh, but does not solve the problems of stress concentration and self-repairing after water seepage. Another technical solution of "setting sub-grid joints" focuses on drainage, and the crack resistance mechanism still relies on traditional sub-grid joints. These technologies belong to the idea of "passive resistance" or "after-the-fact drainage", and cannot achieve "active adaptation" and "damage self-repairing" of the leveling layer from the structural design.

[0005] To achieve the above-mentioned purpose, the present application provides the following technical solution: a roofing leveling and anti-cracking integrated structure, which is arranged on a roofing base, characterized in that it comprises: an elastic stress buffer layer composed of a cement-based composite material, having a set breaking elongation and compressive strength; Active honeycomb water-stop unit array: When the elastic stress buffer layer is laid, it is embedded in it at a preset spacing. The active honeycomb water-stop unit includes a honeycomb hollow shell and a water-swellable water-stop material filled in it. The top of the shell is flush with the upper surface of the elastic stress buffer layer, and the side wall of the shell is provided with water-permeable holes. Gradient protective surface layer: Composite on the elastic stress buffer layer and the water-stop unit array, its elastic modulus decreases gradually from bottom to top.

[0006] Preferably, the elastic stress buffer layer is a modified cement mortar layer containing crack-resistant fibers and micro-expansion agents, with an elongation at break of not less than 8%, a compressive strength of not less than 25 MPa, and a thickness of 20-30 mm.

[0007] Preferably, the crack-resistant fiber is a polyacrylonitrile fiber with a length of 12-15 mm, and the dosage is 2-4% of the mass of the cement-based material; the micro-expansion agent is an ettringite-based expansion agent, and the dosage is 1-3% of the mass of the cement-based material.

[0008] Preferably, the active honeycomb water-stop unit has a honeycomb pore size of 20-30mm, a shell made of polypropylene, and a wall thickness of 1-1.5mm; the water-swellable water-stop material has an expansion ratio of not less than 200%.

[0009] Preferably, the pre-embedded spacing of the active honeycomb water-stop unit is 300-500mm, and the pre-embedded depth is 1 / 2 to 2 / 3 of the thickness of the elastic stress buffer layer.

[0010] Preferably, the gradient protective surface layer comprises: The interfacial bonding layer is a polymer cement-based material with a thickness of 1-2 mm; The flexible transition layer is a rubber-modified asphalt coating with a thickness of 2-3 mm; The wear-resistant protective layer is a polymer coating containing aggregate, with a thickness of 0.5-1mm.

[0011] A method for simultaneous construction of an integrated roof leveling and crack prevention structure includes the following steps: S1. Base layer processing and interface preparation; S2. Spreading the prepared elastic stress buffer layer material; S3. Before the elastic stress buffer layer material initially sets, press the active honeycomb water-stop unit into its interior according to the designed array; S4. Perform stress pre-release treatment on the surface of the buffer layer after the water-stop unit is implanted; S5. On top of the buffer layer and water-stopping unit after stress pre-release treatment, the gradient protective surface layer is continuously constructed; S6. Apply a protective film to moisturize and nourish the skin.

[0012] Preferably, the stress pre-release treatment in step S4 includes surface rolling using a rolling device with a frequency of less than 5 Hz, supplemented by manual patting.

[0013] Preferably, in step S2, after paving, a vibration leveling device is used to compact the surface, with the vibration depth being 2 / 3 of the thickness of the buffer layer, and the vibration head is made of non-metallic elastic material to avoid damaging the pre-embedded water-stop unit shell.

[0014] Preferably, the construction interval between each layer of the gradient protective surface layer in step S5 is 4-6 hours, and the construction of the flexible transition layer must ensure the formation of a continuous, pinhole-free coating.

[0015] Compared with the prior art, the beneficial effects of the present invention are: 1. A fundamental breakthrough in crack resistance mechanism: shifting from the traditional "strengthening resistance" approach to an integrated proactive defense approach of "dredging and absorption + intelligent repair". By using a pre-embedded array of honeycomb water-stopping units, a regularly distributed stress absorption and water-stopping network is constructed within the leveling layer, solving the two core problems of stress concentration and micro-crack seepage diffusion.

[0016] 2. Deep integration of structure and function: Leveling, stress buffering, waterproofing, and protection are integrated into a single continuous structural layer, eliminating the need for crack-resistant mesh, expansion joints, and their sealing processes. Engineering calculations show that this reduces construction steps by 30%-40% and overall costs by approximately 20%.

[0017] 3. Significantly improved interface reliability: The gradient protective surface layer and the underlying buffer layer are tightly connected through an interfacial adhesive layer, and the modulus transition is smooth, overcoming the "two-layer" phenomenon caused by the mismatch of material properties between the traditional waterproof layer and leveling layer. Tests show that the interlayer bond strength is more than 60% higher than that of traditional methods.

[0018] 4. Comprehensive enhancement of durability: After undergoing 50 cycles of (-20℃ to 60℃) and a 24-hour continuous rain erosion simulation test, no visible cracks or leaks were found in the integrated structure. The crack resistance and waterproof performance were improved by more than 50%, and the service life is expected to be doubled. Attached Figure Description

[0019] Fig. 1 This is a cross-sectional schematic diagram of the integrated structure of the present invention; Fig. 2 This is a three-dimensional structural diagram of the active honeycomb water-stopping unit of the present invention.

[0020] In the diagram: 1-Roof base layer, 2-Elastic stress buffer layer, 3-Active honeycomb water-stop unit, 4-Interface bonding layer, 5-Flexible transition layer, 6-Wear-resistant protective layer, 31-Shell, 32-Water-swellable water-stop material, 33-Water-permeable hole. Detailed Implementation

[0021] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0022] Example 1

[0023] Please see Figs. 1-2 This invention provides an integrated structure for roof leveling and crack prevention, installed on the roof base layer, characterized by comprising: Elastic stress buffer layer: Composed of cement-based composite materials, with a set elongation at break and compressive strength, the mortar matrix is ​​prepared using P•O 42.5 silicate cement, Grade II fly ash, and medium-fine sand (mass ratio 4:1:5). 9 kg of 12 mm long polyacrylonitrile fiber (approximately 3% of cement mass) and 6 kg of ettringite-based expansive agent (approximately 2% of cement mass) are added per cubic meter of mortar. After mixing and molding, the 28-day compressive strength was measured to be 28 MPa, and the elongation at break was 8.5%. The paving thickness is 25 mm. Active honeycomb water-stop unit array: Pre-embedded at preset intervals during the paving of the elastic stress buffer layer. Each active honeycomb water-stop unit comprises a honeycomb-shaped hollow shell and a water-swellable water-stopping material filled within it. The top of the shell is flush with the upper surface of the elastic stress buffer layer. The sidewalls of the shell have permeable holes. The shell is injection-molded from polypropylene, with regular hexagonal honeycomb cells, an inscribed circle diameter of 25mm, and a wall thickness of 1.2mm. The unit dimensions are 150mm × 150mm × 12mm (height). Each honeycomb cell is filled with a water-swellable rubber strip with an expansion ratio of 220%. The pre-embedded spacing is 400mm, and the units are vertically pressed in with a special press before the buffer layer initially sets (approximately 40 minutes after paving), to a depth of 12mm. Gradient protective surface layer: Composite on the elastic stress buffer layer and the water-stop unit array, its elastic modulus decreases gradually from bottom to top.

[0024] The elastic stress buffer layer is a modified cement mortar layer mixed with crack-resistant fibers and micro-expansion agents, with an elongation at break of not less than 8%, a compressive strength of not less than 25MPa, and a thickness of 20-30mm.

[0025] The crack-resistant fiber is a polyacrylonitrile fiber with a length of 12-15 mm, and the dosage is 2-4% of the mass of the cement-based material; the micro-expansion agent is an ettringite-based expansion agent, and the dosage is 1-3% of the mass of the cement-based material.

[0026] The active honeycomb water-stopping unit has a honeycomb pore size of 20-30mm, a shell made of polypropylene, and a wall thickness of 1-1.5mm; the water-swellable water-stopping material has an expansion ratio of not less than 200%.

[0027] The pre-embedded spacing of the active honeycomb water-stop unit is 300-500mm, and the pre-embedded depth is 1 / 2 to 2 / 3 of the thickness of the elastic stress buffer layer.

[0028] The gradient protection surface layer includes: The interface bonding layer uses an acrylic copolymer cement-based coating, applied in one coat with a thickness of approximately 1.5 mm. The flexible transition layer uses butyl rubber modified emulsified asphalt coating, applied in two coats, with a thickness of approximately 2.5 mm. The wear-resistant protective layer is made of quartz sand-reinforced acrylic topcoat, applied in one coat with a thickness of approximately 0.8 mm.

[0029] A method for simultaneous construction of an integrated roof leveling and crack prevention structure includes the following steps: S1. Substrate treatment and interface preparation: clean the substrate, repair defects, and apply cement-based penetrating crystalline interface agent; S2. Spread the prepared elastic stress buffer layer material mechanically, and compact it using a rubber-headed vibrator (frequency 35Hz) to a depth of about 17mm. S3. Before the elastic stress buffer layer material initially sets, press the active honeycomb water-stop unit into its interior according to the design array, immediately press the active honeycomb water-stop unit into the layout position, and gently tap the top of the active honeycomb water-stop unit with a scraper to make it flush with the mortar surface. S4. Perform stress pre-release treatment on the surface of the buffer layer after the water-stop unit is implanted. After the water seepage on the surface of the buffer layer disappears, use a low-frequency (3Hz) rubber wheel roller with a self-weight of about 50kg to roll it once in both the longitudinal and transverse directions at a speed of 0.8m / min. At the same time, the worker pats the surface with a wooden trowel. S5. After the buffer layer and water-stop unit have completed stress pre-release treatment, the gradient protective surface layer is continuously applied. After the surface of the buffer layer has hardened (about 6 hours), the interface bonding layer, the flexible transition layer (5 hours apart), and the wear-resistant protective layer are applied in sequence (5 hours apart). S6. Cover with a plastic film for moisturizing and maintenance, and finally cover with a plastic film and spray water for 10 days.

[0030] The stress pre-release treatment described in step S4 includes surface rolling using a rolling device with a frequency of less than 5 Hz, supplemented by manual patting.

[0031] In step S2, after paving, a vibratory leveling device is used to compact the surface. The compaction depth is 2 / 3 of the thickness of the buffer layer, and the vibrator head is made of non-metallic elastic material to avoid damaging the pre-embedded water-stop unit shell.

[0032] In step S5, the construction interval between each layer of the gradient protective surface layer is 4-6 hours, and the construction of the flexible transition layer must ensure the formation of a continuous, pinhole-free coating.

[0033] Example 2

[0034] The difference from Example 1 is that: The thickness of the buffer layer was increased to 30mm, and the fiber length was 15mm to accommodate greater deformation of the steel structure.

[0035] The pre-embedded spacing of the active honeycomb water-stop unit is increased to 300mm to provide stronger stress dispersion capability.

[0036] During the curing period, cover the film with a shade cloth to control the surface temperature to not exceed 35℃.

[0037] Performance Verification: The finished surfaces of the two embodiments were monitored for one year and inspected using infrared thermal imaging and tapping methods. The results showed that the roof flatness met the standards, and no cracks, hollow areas, or leaks were found. Compared with the control area constructed using traditional methods (using mesh cloth leveling + roll waterproofing), the area of ​​this invention performed significantly better after experiencing high summer temperatures and low winter temperatures, with no cracks appearing.

[0038] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. An integrated structure for roof leveling and crack prevention, installed on the roof base layer, characterized in that: include: Elastic stress buffer layer: composed of cement-based composite materials, with a set elongation at break and compressive strength; Active honeycomb water-stop unit array: When the elastic stress buffer layer is laid, it is embedded in it at a preset spacing. The active honeycomb water-stop unit includes a honeycomb hollow shell and a water-swellable water-stop material filled in it. The top of the shell is flush with the upper surface of the elastic stress buffer layer, and the side wall of the shell is provided with water-permeable holes. Gradient protective surface layer: Composite on the elastic stress buffer layer and the water-stop unit array, its elastic modulus decreases gradually from bottom to top.

2. The integrated roof leveling and crack prevention structure according to claim 1, characterized in that: The elastic stress buffer layer is a modified cement mortar layer mixed with crack-resistant fibers and micro-expansion agents, with an elongation at break of not less than 8%, a compressive strength of not less than 25MPa, and a thickness of 20-30mm.

3. The integrated structure for roof leveling and crack prevention according to claim 2, characterized in that: The crack-resistant fiber is a polyacrylonitrile fiber with a length of 12-15 mm, and the dosage is 2-4% of the mass of the cement-based material; the micro-expansion agent is an ettringite-based expansion agent, and the dosage is 1-3% of the mass of the cement-based material.

4. The integrated roof leveling and crack prevention structure according to claim 1, characterized in that: The active honeycomb water-stopping unit has a honeycomb pore size of 20-30mm, a shell made of polypropylene, and a wall thickness of 1-1.5mm; the water-swellable water-stopping material has an expansion ratio of not less than 200%.

5. The integrated structure for roof leveling and crack prevention according to claim 1, characterized in that: The pre-embedded spacing of the active honeycomb water-stop unit is 300-500mm, and the pre-embedded depth is 1 / 2 to 2 / 3 of the thickness of the elastic stress buffer layer.

6. The integrated structure for roof leveling and crack prevention according to claim 1, characterized in that: The gradient protection surface layer includes: The interfacial bonding layer is a polymer cement-based material with a thickness of 1-2 mm; The flexible transition layer is a rubber-modified asphalt coating with a thickness of 2-3 mm; The wear-resistant protective layer is a polymer coating containing aggregate, with a thickness of 0.5-1mm.

7. A synchronous construction method for constructing an integrated roof leveling and crack prevention structure as described in any one of claims 1-6, characterized in that: Includes the following steps: S1. Base layer processing and interface preparation; S2. Spreading the prepared elastic stress buffer layer material; S3. Before the elastic stress buffer layer material initially sets, press the active honeycomb water-stop unit into its interior according to the designed array; S4. Perform stress pre-release treatment on the surface of the buffer layer after the water-stop unit is implanted; S5. On top of the buffer layer and water-stopping unit after stress pre-release treatment, the gradient protective surface layer is continuously constructed; S6. Apply a protective film to moisturize and nourish the skin.

8. The synchronous construction method of the integrated roof leveling and crack prevention structure according to claim 7, characterized in that: The stress pre-release treatment described in step S4 includes surface rolling using a rolling device with a frequency of less than 5 Hz, supplemented by manual patting.

9. The synchronous construction method of the integrated roof leveling and crack prevention structure according to claim 7, characterized in that: In step S2, after paving, a vibratory leveling device is used to compact the surface. The compaction depth is 2 / 3 of the thickness of the buffer layer, and the vibrator head is made of non-metallic elastic material to avoid damaging the pre-embedded water-stop unit shell.

10. The synchronous construction method of the integrated roof leveling and crack prevention structure according to claim 7, characterized in that: In step S5, the construction interval between each layer of the gradient protective surface layer is 4-6 hours, and the construction of the flexible transition layer must ensure the formation of a continuous, pinhole-free coating.

Citation Information

Patent Citations

  • Coated fabrics including expandable graphite

    CN104937165A

  • Building roof waterproof layer structure and construction method thereof

    CN117005623A

  • Green ecological waterproof roofing of plane water storage

    CN207647051U

  • Waterproof sheet

    KR1020100021831A

  • Coated fabrics including expandable graphite

    US20170030081A1