Offshore wind power infrastructure construction mechanism

By designing positioning rings and positioning wheels, the problem of disturbance of solidified soil slurry during offshore wind turbine pile foundation construction was solved, achieving complete coverage and reinforcement of the pile root, and improving the stability and efficiency of construction.

CN121519488APending Publication Date: 2026-02-13HEBEI UNIV OF ENG
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202511886415.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-12-15
Publication Date
2026-02-13

AI Technical Summary

Technical Problem

In existing technologies, the construction mechanism for offshore wind turbine pile foundations causes significant disturbance to the water body during the circular motion of the hull, crossarm, bracket, and discharge pipe, which affects the solidification of the soil slurry and results in poor construction efficiency and effectiveness.

Method used

The design employs positioning rings and positioning wheels to ensure stable vertical movement of the main and auxiliary pipelines. The oscillation of the main and auxiliary pipelines is controlled by the cooperation of the positioning rings and positioning wheels, achieving uniform spraying of the solidified soil slurry. Furthermore, the reinforcement mesh is stacked in a Z-shape within the foundation pit to ensure the coverage and strength of the solidified soil slurry.

Benefits of technology

It effectively reduced the disturbance to the solidified soil slurry, achieved complete coverage and reinforcement of the pile root, and improved the stability and efficiency of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN121519488A_ABST
    Figure CN121519488A_ABST
Patent Text Reader

Abstract

The invention discloses an offshore wind power infrastructure construction mechanism, which relates to the technical field of offshore wind power infrastructure construction, and comprises a positioning ring and a positioning wheel, the positioning ring is in sliding connection with the foundation pile through the positioning wheel, and the positioning wheel moves in the radial direction of the positioning ring to adapt to foundation piles with different diameters; the main pipelines are communicated with the dispersion box, the plurality of main pipelines are annularly arranged, the main pipelines are hinged to the dispersion box, and the main pipelines swing along hinge points; the auxiliary pipeline is arranged on the side wall of the main pipeline, and the driving assembly drives the auxiliary pipeline to swing synchronously; and the solidified soil slurry is discharged through the main pipelines and the auxiliary pipelines. The foundation pile root filling device has the beneficial effects that through the arrangement of the positioning rings and the positioning wheels, the main pipeline and the auxiliary pipeline stably move in the vertical direction, and basic movement of foundation pile root filling is achieved; swing of the main pipeline and the auxiliary pipeline is controlled, disturbance to the solidified soil slurry is reduced to the maximum extent, and meanwhile the solidified soil slurry is sprayed to the root of the foundation pile.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of offshore wind power foundation construction technology, and more specifically, to an offshore wind power foundation construction organization. Background Technology

[0002] Offshore wind turbine foundation solidification technology essentially transforms unreliable natural soft foundations into solid and reliable artificial foundations through "soil modification," thereby providing a more stable "foothold" for the wind turbine. In the prior art, for example, the document with application number CN202311657063.X, the prior art uses the circular motion of a ship around the pile foundation to drive the horizontal arm to move around the pile foundation; during the movement of the horizontal arm around the pile foundation, the moving unloading vehicle moves along the horizontal arm, causing the bracket to drive the limiting net to move outward in a spiral shape, and the limiting net is spirally arranged on the seabed around the pile foundation to form an anti-scouring spiral; although it can complete the solidification of the pile foundation root, it has the following defects; Since the surrounding vessel, cross arm, bracket, and discharge pipe need to make continuous circular motion during operation, and because of their large size, they generate significant convection in the surrounding water, especially causing significant disturbance to the solidified soil slurry and affecting its solidification, it is necessary to design a pile filling mechanism that avoids causing significant disturbance to the water. Summary of the Invention

[0003] To address the above deficiencies, this invention provides an offshore wind power foundation construction organization to solve the aforementioned problems.

[0004] To achieve the above objectives, the present invention adopts the following technical solution: Offshore wind power foundation construction organization includes solidified soil slurry, foundation piles, foundation pits, sea surface, seabed and winches, with the winches installed on the upper end of the foundation piles, and also includes; The positioning ring and positioning wheel are used. The positioning ring is fitted onto the foundation pile and is coaxial with the foundation pile. The positioning ring is slidably connected to the foundation pile through the positioning wheel. The positioning wheel moves in the radial direction of the positioning ring to accommodate foundation piles of different diameters. The dispersion box and the main pipeline are connected to the dispersion box. There are multiple main pipelines arranged in a ring. The main pipeline is hinged to the dispersion box and swings along the hinge point. The drive component and the secondary pipe are located on the side wall of the main pipe and are connected to the main pipe. The drive component drives the secondary pipe to swing synchronously. The solidified soil slurry is discharged through multiple main pipes and secondary pipes, and the solidified soil slurry covers a circular area. The reinforcement mesh swings in a Z-shape as it adheres to the foundation pit along with the solidified soil slurry.

[0005] Furthermore, the positioning ring has a hollow structure. The winch traction end is fixedly connected to the positioning ring. A rectangular tube is installed on the inner wall of the positioning ring, and a telescopic rod is installed inside the rectangular tube. The telescopic rod and the rectangular tube have rectangular cross-sections. A positioning wheel is installed at one end of the telescopic rod. A bearing is installed on the positioning ring. A rotating shaft is installed on the inner ring of the bearing. A bevel gear is installed at one end of the rotating shaft, and an external thread is provided at the other end of the rotating shaft. A threaded hole that meshes with the external thread is opened on the rectangular tube. A bearing is installed on the inner side of the positioning ring. A support ring is installed on the outer ring of the bearing. A gear ring is installed on the outer side of the support ring that meshes with the bevel gear. A driver is installed on the inner side of the positioning ring. A gear set is installed on the rotating end of the driver. The driver is connected to the gear ring through the gear set.

[0006] Furthermore, a sealing sleeve is installed at one end of the telescopic rod, with one end of the sealing sleeve fixedly connected to the telescopic rod and the other end of the sealing sleeve fixedly connected to the positioning ring; four pairs of rectangular tubes are provided, evenly distributed on the four quadrant points of the positioning ring, with two rectangular tubes in each pair arranged in the vertical direction.

[0007] Furthermore, the dispersion box is installed below the positioning ring. The dispersion box has an annular cavity. The upper end of the dispersion box is equipped with a first flexible hose, and the lower end of the dispersion box is equipped with a second flexible hose. There are multiple second flexible hoses arranged in a ring. An input pipe is installed on the first flexible hose. The main pipeline is connected to the dispersion box through the second flexible hose. A hinge rod is installed at the lower end of the dispersion box. The hinge rod is hinged to the main pipeline. The main pipeline swings along the hinge point. A hydraulic rod is installed between the hinge rod and the main pipeline.

[0008] Furthermore, the cross-section of the annular cavity is trapezoidal, with the acute angle of the trapezoid facing downwards.

[0009] Furthermore, the drive assembly includes a sliding ring mounted on the main pipe, a hydraulic rod installed between the sliding ring and the main pipe, a flexible pipe installed on the lower side wall of the main pipe, multiple flexible pipes, a secondary pipe connected to the main pipe through the flexible pipe, a fixed rod installed at the lower end of the main pipe, the two sides of the secondary pipe hinged to the fixed rod, and a connecting rod installed between the secondary pipe and the sliding ring.

[0010] Furthermore, a mesh cage is installed on the side wall of the main pipeline, with a main shaft at the center of the mesh cage and an opening below the mesh cage. The reinforcing mesh is wound around the main shaft and expands and contracts through the opening. One end of the reinforcing mesh is connected to the main shaft. An electrically controlled clamp is installed on one side of the lower end of the secondary pipeline, and the other end of the reinforcing mesh is connected to the electrically controlled clamp.

[0011] Furthermore, electrically controlled valves are installed on both the main and secondary pipelines.

[0012] Furthermore, the positioning ring is divided into a left ring and a right ring, which are in a connected state. Each of the left and right rings is equipped with a flange, and connecting bolts are installed on the flange.

[0013] Furthermore, a lifting ring is installed on the positioning ring, and the traction end of the winch is connected to the lifting ring.

[0014] The beneficial effects of this invention are: by setting the positioning ring and positioning wheel, the main pipe and the auxiliary pipe can move stably in the vertical direction, realizing the basic movement of filling the root of the foundation pile; by controlling the swing of the main pipe and the auxiliary pipe, the disturbance to the solidified soil slurry is minimized, while the solidified soil slurry is sprayed onto the root of the foundation pile, and the spraying range of the solidified soil slurry can cover a complete circle. As the soil slurry is sprayed out, the reinforcing net is released, and the soil slurry presses the reinforcing net into the foundation pit; as the main pipe and the secondary pipe swing back and forth, the reinforcing net is stacked in a Z-shape in the foundation pit, thus achieving the purpose of reinforcing and solidifying the soil slurry. Attached Figure Description

[0015] Figure 1 This is a schematic diagram of the longitudinal section structure of the offshore wind power foundation construction mechanism described in this invention; Figure 2 This is a schematic diagram showing the relative positions of the positioning ring and the foundation pile; Figure 3 This is a schematic diagram showing the relative positions of the positioning ring, the dispersion box, and the main pipeline; Figure 4 This is a schematic diagram of the longitudinal section of the positioning ring; Figure 5 This is a schematic diagram of the longitudinal section of the main pipeline; Figure 6 This is a schematic diagram of a flange; In the diagram: 1. Solidified soil slurry; 2. Foundation pile; 3. Foundation pit; 4. Sea surface; 5. Seabed; 6. Winch; 7. Positioning ring; 8. Positioning wheel; 9. Dispersion box; 10. Main pipeline; 11. Drive assembly; 12. Secondary pipeline; 13. Reinforcing mesh; 71. Rectangular tube; 72. Telescopic rod; 73. Bearing 1; 74. Shaft; 75. Bevel gear 1; 76. External thread; 77. Threaded hole; 78. Bearing 2; 79. Support ring; 791. Gear ring 1; 792. Driver; 793. Gear set ; 721, Sealing sleeve; 91, Annular cavity; 92, Hoses I; 93, Hoses II; 94, Input pipe; 95, Hinge rod; 96, Hydraulic rod I; 111, Sliding ring; 112, Hydraulic rod II; 113, Flexible pipe; 114, Fixed rod; 115, Connecting rod; 101, Net cage; 102, Main shaft; 103, Opening; 104, Electrically controlled clamp; 121, Electrically controlled valve; 701, Left ring; 702, Right ring; 703, Flange; 704, Connecting bolt; 705, Lifting ring. Detailed Implementation

[0016] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.

[0017] This application provides a construction organization for offshore wind power foundations. Please refer to [the relevant documentation / reference]. Figures 1-6 The structure includes: 1. Solidified soil slurry; 2. Foundation piles; 3. Foundation pit; 4. Sea surface; 5. Seabed; and 6. Winch 6 is installed on the upper end of foundation piles 2. The structure also includes: Positioning ring 7 and positioning wheel 8: Positioning ring 7 is fitted on foundation pile 2 and is coaxial with foundation pile 2; Positioning ring 7 is slidably connected to foundation pile 2 through positioning wheel 8; Positioning wheel 8 moves in the radial direction of positioning ring 7 to adapt to foundation piles 2 of different diameters. The dispersion box 9 and the main pipeline 10 are connected to the dispersion box 9. Multiple main pipelines 10 are provided and arranged in a ring. The main pipeline 10 is hinged to the dispersion box 9 and swings along the hinge point. The drive assembly 11 and the secondary pipe 12 are located on the side wall of the main pipe 10 and are connected to the main pipe 10. The drive assembly 11 drives the secondary pipe 12 to swing synchronously. The solidified soil slurry 1 is discharged through multiple main pipes 10 and secondary pipes 12, and the solidified soil slurry 1 covers a circular area. The reinforcing mesh 13 swings in a Z-shape as it adheres to the foundation pit 3 along with the solidified soil slurry 1.

[0018] In practical applications, the solidified soil slurry 1 is transported to the construction site by a transport ship. The winch 6 and the transport ship are existing technologies and will not be described in detail. After the foundation pile 2 and the foundation pit 3 reach the predetermined target, the solidified soil slurry 1 can be filled. First, the positioning ring 7 and positioning wheel 8 are put on the foundation pile 2 and fixed with external supports to prevent them from falling. Then, a pair of winches 6 are symmetrically fixed on the foundation pile 2, and the traction end of the winch 6 is fixedly connected to the positioning ring 7. At this time, the operation of the winch 6 can pull the positioning ring 7 up or down. Finally, the main pipe 10, the auxiliary pipe 12 and the drive assembly 11 are installed. A connecting channel is provided between the dispersion box 9 and the transport ship. The transport ship is equipped with equipment for actively conveying solidified soil slurry 1. The winch 6 is controlled to extend its traction end, and the positioning ring 7, main pipe 10 and auxiliary pipe 12 are in the lowest position. At this time, the main pipe 10 and auxiliary pipe 12 are in a retracted state, and the openings of the main pipe 10 and auxiliary pipe 12 face the root of the foundation pile 2. At this time, the solidified soil slurry 1 enters the main pipe 10 and auxiliary pipe 12 through the first hose 92, the dispersion box 9 and the second hose 93, and is finally discharged through the main pipe 10 and auxiliary pipe 12. At the same time, the main pipe 10 is slowly oscillating, the angle between the main pipe 10 and the foundation pile 2 gradually increases, the angle between the secondary pipe 12 and the main pipe 10 also gradually increases, and the discharge range of the solidified soil slurry 1 gradually increases. Through the setting of multiple secondary pipes 12 and main pipes 10, the secondary pipes 12 and main pipes 10 can discharge the solidified soil slurry 1 around the foundation pile 2 in one oscillation, and the solidified soil slurry 1 will fill the surrounding circular area. Afterwards, the main pipe 10 and the secondary pipe 12 shrink, and a second filling is carried out. Repeating the above operation can fill the foundation pit 3. In the above filling process, in order to improve the structural strength of the solidified soil slurry 1 after solidification, the reinforcing mesh 13 can be added to the filling work of the solidified soil slurry 1, so as to cover the solidified soil slurry 1 and strengthen the strength of the solidified soil slurry 1.

[0019] Reference Figure 1 , Figure 2 , Figure 3 and Figure 4 The positioning ring 7 is a hollow structure. The traction end of the winch 6 is fixedly connected to the positioning ring 7. A rectangular tube 71 is installed on the inner wall of the positioning ring 7. A telescopic rod 72 is installed inside the rectangular tube 71. The telescopic rod 72 and the rectangular tube 71 have rectangular cross-sections. The positioning wheel 8 is installed at one end of the telescopic rod 72. A bearing 73 is installed on the positioning ring 7. A rotating shaft 74 is installed on the inner ring of the bearing 73. A bevel gear 75 is installed at one end of the rotating shaft 74. The other end of the rotating shaft 74 is provided with an external thread 76. A threaded hole 77 that meshes with the external thread 76 is opened on the rectangular tube 71. A bearing 78 is installed on the inner side of the positioning ring 7. A support ring 79 is installed on the outer ring of the bearing 78. A gear ring 791 that meshes with the bevel gear 75 is installed on the outer side of the support ring 79. A driver 792 is installed on the inner side of the positioning ring 7. A gear set 793 is installed on the rotating end of the driver 792. The driver 792 is connected to the gear ring 791 through the gear set 793.

[0020] In practical applications, during operation, the positioning wheel 8 is in close contact with the foundation pile 2. In order to accommodate foundation piles 2 of different diameters, the positioning wheel 8 is in a retractable state. The driver 792 rotates forward, which drives the support ring 79 and gear ring 791 to rotate through the transmission of the gear set 793. The gear ring 791 drives four pairs of bevel gears 75 to rotate, and the bevel gears 75 drive the rotating shaft 74 and the external thread 76 to rotate. The rotating shaft 74 rotates stably through the action of bearing 73, and the support ring 79 rotates stably through the action of bearing 78. The rotating shaft 74 drives the positioning wheel 8 and the telescopic rod 72 to extend out of the rectangular tube 7 through the threaded hole 77 and the external thread 76. This is suitable for foundation piles 2 with small diameters. When the control driver 792 reverses, the positioning wheel 8 and the telescopic rod 72 retract into the rectangular tube 7, at which point a large-diameter foundation pile 2 is applicable.

[0021] Reference Figure 1 , Figure 2 , Figure 3 and Figure 4One end of the telescopic rod 72 is equipped with a sealing sleeve 721. One end of the sealing sleeve 721 is fixedly connected to the telescopic rod 72, and the other end of the sealing sleeve 721 is fixedly connected to the positioning ring 7. There are four pairs of rectangular tubes 71, which are evenly distributed on the four quadrant points of the positioning ring 7. Each pair of rectangular tubes 71 has two tubes and they are arranged in the vertical direction.

[0022] In practical applications, the sealing sleeve 721 prevents seawater from flowing into the positioning ring 7 through the position of the telescopic rod 72. The rectangular tube 71 has four pairs of positioning wheels, and four pairs of positioning wheels 8 are also provided to make the positioning ring 7 move up and down stably.

[0023] Reference Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 The dispersion box 9 is installed below the positioning ring 7. The dispersion box 9 has an annular cavity 91 inside. The upper end of the dispersion box 9 is provided with a first hose 92, and the lower end of the dispersion box 9 is provided with a second hose 93. There are multiple second hoses 93 arranged in a ring. An input pipe 94 is installed on the first hose 92. The main pipeline 10 is connected to the dispersion box 9 through the second hose 93. The lower end of the dispersion box 9 is provided with a hinge rod 95, which is hinged to the main pipeline 10. The main pipeline 10 swings along the hinge point. A hydraulic rod 96 is installed between the hinge rod 95 and the main pipeline 10.

[0024] In practical applications, the input pipe 94 and hose 92 are used to connect the transport ship. The dispersion box 9 delivers the solidified soil slurry 1 into multiple hoses 93. The main pipe 10 is supported by the hinge rod 95. The main pipe 10 rotates along the hinge point of the hinge rod 95. The specific angle of the main pipe 10 can be controlled by the extension and retraction of the hydraulic rod 96.

[0025] Reference Figure 1 , Figure 2 , Figure 3 and Figure 4 The cross-section of the annular cavity 91 is trapezoidal, with the acute angle of the trapezoid facing downwards.

[0026] In practical applications, the trapezoidal acute angle is positioned downwards to facilitate the flow of the solidified soil slurry 1 to the second hose 9, thus preventing the solidified soil slurry 1 from remaining in the annular cavity 91.

[0027] Reference Figure 1 , Figure 2 , Figure 3 and Figure 5The drive assembly 11 includes a sliding ring 111, which is mounted on the main pipe 10. A hydraulic rod 112 is installed between the sliding ring 111 and the main pipe 10. A flexible pipe 113 is installed on the lower side wall of the main pipe 10. Multiple flexible pipes 113 are provided. A secondary pipe 12 is connected to the main pipe 10 through the flexible pipe 113. A fixed rod 114 is installed at the lower end of the main pipe 10. The two sides of the secondary pipe 12 are hinged to the fixed rod 114. A connecting rod 115 is installed between the secondary pipe 12 and the sliding ring 111.

[0028] In practical applications, the extension and retraction of hydraulic rod 112 can drive sliding ring 111 to slide on main pipe 10. When sliding ring 111 slides upward, it pulls secondary pipe 12 upward through connecting rod 115, which can increase the discharge area of ​​solidified soil slurry 1. When sliding ring 111 slides downward, it can reduce the discharge area of ​​solidified soil slurry 1.

[0029] Reference Figure 1 , Figure 2 , Figure 3 and Figure 5 A mesh basket 101 is installed on the side wall of the main pipe 10. A main shaft 102 is located at the center of the mesh basket 101. An opening 103 is located below the mesh basket 101. A reinforcing mesh 13 is wound around the main shaft 102. The reinforcing mesh 13 can extend and retract through the opening 103. One end of the reinforcing mesh 13 is connected to the main shaft 102. An electrically controlled clamp 104 is installed on one side of the lower end of the secondary pipe 12. The other end of the reinforcing mesh 13 is connected to the electrically controlled clamp 104.

[0030] In practical applications, to enhance the strength of the solidified soil slurry 1, the reinforcing net 13 is actively released when filling the solidified soil slurry 1. Initially, one end of the reinforcing net 13 needs to be manually fixed to the electrically controlled clamp 104. At this time, the reinforcing net 13 covers the main pipe 10 and the secondary pipe 12. As the solidified soil slurry 1 is discharged, the reinforcing net 13 is gradually released, and the solidified soil slurry 1 presses the reinforcing net 13 into the foundation pit 3. As the main pipe 10 and the secondary pipe 12 swing back and forth, the reinforcing net 13 is stacked in a Z-shape in the foundation pit 3. After the first filling, the control electric clamp 104 releases the reinforcing net 13.

[0031] Reference Figure 1 , Figure 2 , Figure 3 and Figure 5 Electrically controlled valves 121 are installed on the main pipe 10 and the secondary pipe 12.

[0032] In practical applications, the flow rate of the solidified soil slurry 1 at the corresponding location can be controlled by setting the electrically controlled valve 121.

[0033] Reference Figure 1 , Figure 2 , Figure 3and Figure 6 The positioning ring 7 is divided into a left ring 701 and a right ring 702. The left ring 701 and the right ring 702 are in a connected state. A flange 703 is installed on each of the left ring 701 and the right ring 702. A connecting bolt 704 is installed on the flange 703.

[0034] In practical applications, the positioning ring 7 can be divided into two parts by setting the left ring 701 and the right ring 702. Although it needs to be connected later by connecting bolts 704, it has good flexibility in transportation.

[0035] Reference Figure 1 , Figure 2 , Figure 3 and Figure 4 A lifting ring 705 is installed on the positioning ring 7, and the traction end of the winch 6 is connected to the lifting ring 705.

[0036] In practical applications, the lifting ring 705 facilitates the connection between the traction end of the winch 6 and the positioning ring 7.

Claims

1. A construction organization for offshore wind power foundations, comprising a solidified soil slurry (1), foundation piles (2), a foundation pit (3), a sea surface (4), a seabed (5), and a winch (6), wherein the winch (6) is installed on the upper end of the foundation piles (2), characterized in that, Also includes; Positioning ring (7) and positioning wheel (8). Positioning ring (7) is fitted on pile (2) and is coaxial with pile (2). Positioning ring (7) is slidably connected to pile (2) through positioning wheel (8). Positioning wheel (8) moves in the radial direction of positioning ring (7) to adapt to piles (2) of different diameters. Dispersion box (9) and main pipeline (10), the main pipeline (10) is connected to the dispersion box (9), the main pipeline (10) is provided in multiple and arranged in a ring, the main pipeline (10) is hinged to the dispersion box (9), and the main pipeline (10) swings along the hinge point; The drive assembly (11) and the secondary pipe (12) are located on the side wall of the main pipe (10) and are connected to the main pipe (10). The drive assembly (11) drives the secondary pipe (12) to swing synchronously. The solidified soil slurry (1) is discharged through multiple main pipes (10) and secondary pipes (12), and the solidified soil slurry (1) covers a circular area. The reinforcing net (13) swings in a Z-shape as the solidified soil slurry (1) adheres to the foundation pit (3).

2. The offshore wind power foundation construction organization according to claim 1, characterized in that, The positioning ring (7) is a hollow structure. The traction end of the winch (6) is fixedly connected to the positioning ring (7). A rectangular tube (71) is installed on the inner wall of the positioning ring (7). A telescopic rod (72) is installed inside the rectangular tube (71). The telescopic rod (72) and the rectangular tube (71) have rectangular cross-sections. The positioning wheel (8) is installed at one end of the telescopic rod (72). A bearing (73) is installed on the positioning ring (7). A rotating shaft (74) is installed on the inner ring of the bearing (73). A bevel gear (75) is installed at one end of the rotating shaft (74). An external thread is provided at the other end of the rotating shaft (74). The rectangular tube (71) has a threaded hole (77) that meshes with the external thread (76); a bearing (78) is installed inside the positioning ring (7), a support ring (79) is installed on the outer ring of the bearing (78), a gear ring (791) that meshes with the bevel gear (75) is installed on the outer side of the support ring (79), a driver (792) is installed inside the positioning ring (7), a gear set (793) is installed on the rotating end of the driver (792), and the driver (792) is connected to the gear ring (791) through the gear set (793).

3. The offshore wind power foundation construction organization according to claim 2, characterized in that, A sealing sleeve (721) is installed at one end of the telescopic rod (72). One end of the sealing sleeve (721) is fixedly connected to the telescopic rod (72), and the other end of the sealing sleeve (721) is fixedly connected to the positioning ring (7). There are four pairs of rectangular tubes (71), which are evenly distributed on the four quadrant points of the positioning ring (7). There are two rectangular tubes (71) in each pair and they are arranged in the vertical direction.

4. The offshore wind power foundation construction organization according to claim 3, characterized in that, The dispersion box (9) is installed below the positioning ring (7). The dispersion box (9) has an annular cavity (91). The upper end of the dispersion box (9) is provided with a first hose (92), and the lower end of the dispersion box (9) is provided with a second hose (93). There are multiple second hoses (93) arranged in a ring. An input pipe (94) is installed on the first hose (92). The main pipeline (10) is connected to the dispersion box (9) through the second hose (93). The lower end of the dispersion box (9) is provided with a hinge rod (95). The hinge rod (95) is hinged to the main pipeline (10). The main pipeline (10) swings along the hinge point. A hydraulic rod (96) is installed between the hinge rod (95) and the main pipeline (10).

5. The offshore wind power foundation construction organization according to claim 4, characterized in that, The cross-section of the annular cavity (91) is trapezoidal, with the acute angle of the trapezoid facing downwards.

6. The offshore wind power foundation construction organization according to claim 5, characterized in that, The drive assembly (11) includes a sliding ring (111), which is mounted on the main pipe (10). A hydraulic rod (112) is installed between the sliding ring (111) and the main pipe (10). A flexible pipe (113) is installed on the lower side wall of the main pipe (10). Multiple flexible pipes (113) are provided. The secondary pipe (12) is connected to the main pipe (10) through the flexible pipe (113). A fixed rod (114) is installed at the lower end of the main pipe (10). The two sides of the secondary pipe (12) are hinged to the fixed rod (114). A connecting rod (115) is installed between the secondary pipe (12) and the sliding ring (111).

7. The offshore wind power foundation construction organization according to claim 6, characterized in that, A mesh basket (101) is installed on the side wall of the main pipe (10). A main shaft (102) is provided at the center of the mesh basket (101). An opening (103) is provided below the mesh basket (101). The reinforcing mesh (13) is wrapped around the main shaft (102). The reinforcing mesh (13) expands and contracts through the opening (103). One end of the reinforcing mesh (13) is connected to the main shaft (102). An electric clamp (104) is installed on one side of the lower end of the secondary pipe (12). The other end of the reinforcing mesh (13) is connected to the electric clamp (104).

8. The offshore wind power foundation construction organization according to claim 7, characterized in that, Electrically controlled valves (121) are installed on the main pipeline (10) and the secondary pipeline (12).

9. The offshore wind power foundation construction organization according to any one of claims 1-8, characterized in that, The positioning ring (7) is divided into a left ring (701) and a right ring (702). The left ring (701) and the right ring (702) are in a connected state. A flange (703) is installed on the left ring (701) and the right ring (702). A connecting bolt (704) is installed on the flange (703).

10. The offshore wind power foundation construction organization according to claim 9, characterized in that, A lifting ring (705) is installed on the positioning ring (7), and the traction end of the winch (6) is connected to the lifting ring (705).

Citation Information

Patent Citations

  • Offshore wind power anti-scour device

    CN117364852B