Settlement-Adaptive Isolation Structure and Construction Method for Football Fields with Heterogeneous Foundations
By combining flexible settlement isolation strips with integral reinforced concrete raft slabs, the problems of cracks and safety hazards caused by differential settlement of heterogeneous foundations were solved, achieving the effects of convenient construction, controllable cost and shortened construction period, and ensuring the flatness and safety of the football field surface.
Patent Information
- Application Number
- CN202610914820.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-06-24
- Publication Date
- 2026-11-10
AI Technical Summary
When constructing a football field on a heterogeneous foundation, it is difficult to solve the cracks, misalignments and safety hazards caused by differential settlement. Existing technologies cannot effectively handle large displacement differential settlement, and the construction costs are high, the construction period is long, or it may affect surrounding buildings.
The system employs a combination of flexible settlement isolation strips and selective anchoring of integral reinforced concrete raft slabs, which allows for differentiated settlement between heterogeneous foundations and transforms it into smooth and continuous curved surface deformation through a flexible structure. This system includes a combination of flexible settlement isolation strips, multi-directional deformation hinge modules, elastic particle fillers, and integral reinforced concrete raft slabs, ensuring the flatness of the court surface.
It effectively transforms differential settlement into harmless curved surface deformation, avoids surface cracking and misalignment, reduces construction costs and time, ensures the flatness and safety of the court, and does not disturb surrounding buildings.
Smart Images

Figure CN123064073A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building engineering structural design and foundation treatment technology, and in particular to a settlement adaptive isolation structure for a football field with heterogeneous foundations and its construction method. Background Technology
[0002] With the acceleration of urbanization, the utilization of rooftop space is receiving increasing attention, and constructing football fields on top of existing concrete roofs has become a common space development method. However, when the load-bearing layer of a football field spans two or more heterogeneous foundations—for example, one part located on a cast-in-place concrete roof with high stiffness and minimal settlement, and the other part located in a backfilled soil area with significant consolidation creep—the settlement characteristics of the two foundations under their own weight and superstructure loads will differ significantly. Improper handling of this differential settlement can lead to defects such as cracks, misalignment, and abrupt slopes on the upper surface of the football field, seriously affecting the normal use of the field and the safety of sports activities.
[0003] Traditional engineering methods for dealing with differential settlement mainly include the following categories: The first type is the rigid partition method, which involves setting settlement joints or expansion joints at the junction of heterogeneous foundations to completely separate the superstructure and allow free deformation on both sides. However, for sports fields like football stadiums, which require extremely high surface flatness, settlement joints can cause the surface layer to crack along the joint, forming obvious misalignments and gaps. This not only affects usability but also poses serious safety hazards. Furthermore, the waterproofing and maintenance costs of settlement joints are high, and their long-term reliability is poor.
[0004] The second category is foundation reinforcement methods, which involve using methods such as pile foundation reinforcement, dynamic compaction, and grouting to increase the bearing capacity and compression modulus of the backfill area, attempting to fundamentally eliminate or reduce differential settlement. However, these methods have problems such as high construction costs, long construction periods, and significant vibration and noise. Especially when constructing around the roofs of existing buildings, dynamic compaction and pile driving processes can cause significant disturbance to the surrounding building structures. Furthermore, for large areas of backfill, completely eliminating settlement is often neither economical nor realistic.
[0005] The third type is the elastic buffering method, which involves laying a general-purpose elastic pad or shock-absorbing pad under the upper surface layer to buffer impact loads. However, this type of general-purpose elastic pad is usually only used to absorb dynamic impact energy. Its vertical compressive deformation is limited, and it does not have horizontal shear deformation capacity or particle redistribution mechanism, so it cannot absorb and digest differential settlement over a range of tens of millimeters or even larger. When the differential settlement is large, the elastic pad will either be crushed and fail, or it will directly transfer the uneven stress to the upper surface layer, causing the surface layer to crack.
[0006] In summary, existing technologies either employ "rigid cutting," leading to surface damage; or "hard anti-settlement," resulting in soaring costs and difficulty in eradicating the problem; or use "universal buffers," which cannot cope with large-displacement differential settlement. Therefore, there is an urgent need for an isolation structure and construction method that can allow differential settlement between heterogeneous foundations, while transforming this differential settlement into gentle, continuous, and harmless curved surface deformation, thereby ensuring the flatness of the court surface. Summary of the Invention
[0007] The purpose of this invention is to provide a settlement adaptive isolation structure and construction method for football fields with heterogeneous foundations. In response to the differential settlement problem at the junction of two heterogeneous foundations, namely concrete roof and backfill soil, a combination system of flexible settlement isolation strip and selective anchoring of integral reinforced concrete raft slab is adopted. This system allows differential settlement between heterogeneous foundations and transforms the differential settlement into smooth and continuous curved surface deformation to ensure the flatness of the field surface.
[0008] To achieve the above-mentioned objectives, the present invention adopts the following technical solution: An adaptive settlement isolation structure for football fields with heterogeneous foundations addresses the differential settlement problem at the interface between concrete roofs and backfill soil foundations. It employs a combination of a flexible settlement isolation strip and selective anchoring of a monolithic reinforced concrete raft slab. This system allows for differential settlement between the heterogeneous foundations and transforms this differential settlement into smooth, continuous curved surface deformation, ensuring the flatness of the field surface. The isolation structure includes: A flexible settlement isolation strip is installed at the junction of the concrete roof and the backfill soil, and the isolation strip includes, from bottom to top, the following: A high-strength geogrid is laid at the bottom of the trench and anchored to the heterogeneous foundation areas on both sides. A multi-directional deformable hinge module layer is laid on top of the underlying geogrid. The multi-directional deformable hinge module is assembled from perforated flexible plastic modules connected by interlocking male and female tenon grooves on the sides. The module has multiple through vertical holes inside, and adjacent vertical holes are connected by ribs. The ribs have thin-walled areas for stress concentration, so that the module has vertical support strength while undergoing controllable elastic deformation under horizontal shear force. Elastic particle filler is used to fill the vertical holes and gaps between modules. The elastic particle filler is made of rubber particles with a particle size of 1 to 5 mm and medium-coarse sand in a volume ratio of 1:1. It is used to fill the gaps caused by deformation by flow and redistribution when differential settlement occurs. A top-layer secondary reinforced geogrid is laid on top of the multi-directional deformable hinge module layer to uniformly transfer the upper load to the lower multi-directional deformable hinge module. A non-woven geotextile isolation layer laid on top of the top geogrid; And, an integral reinforced concrete raft slab covering the concrete roof area, backfill area and flexible settlement isolation zone, wherein the raft slab is provided with structural steel mesh but not crack-resistant steel bars, so as to maintain the integrity of the raft slab and allow it to undergo slight bending deformation under differential settlement. The raft slab is rigidly anchored to the roof structure in the concrete roof area by steel bars to form a rigid anchorage zone. In the backfill area and above the flexible settlement isolation zone, it is not rigidly connected to any structure below it, forming a flexible transition zone.
[0009] Preferably, the width W of the flexible settlement isolation zone is determined by the formula W = ΔS / tan(θ), where ΔS is the expected maximum differential settlement and θ is the maximum allowable turning angle.
[0010] Preferably, the body of the multi-directional deformable hinge module is made of a polymer material with added anti-aging agents and toughening agents, and is injection molded in one step using a mold.
[0011] Preferably, both the bottom geogrid and the top geogrid are high-strength bidirectional geogrids, and the length of the bottom geogrid anchored to the heterogeneous foundation areas on both sides is not less than 1.0m.
[0012] Preferably, the nonwoven geotextile has a specification of not less than 400g / m². 2 .
[0013] Preferably, the thickness of the integral reinforced concrete raft slab is 15-20cm, and the structural steel mesh uses HRB400 grade steel bars with a diameter of 8-12mm and a spacing of 150mm×150mm.
[0014] Preferably, a sports surface layer is also laid on top of the raft, the sports surface layer including artificial turf and a buffer layer.
[0015] This invention also provides a construction method for a settlement adaptive isolation structure for a football field with heterogeneous foundations. Addressing the differential settlement problem at the interface between a concrete roof and backfill soil foundations, a phased construction method is employed to construct a combined system of a flexible settlement isolation zone and selective anchoring of an integral reinforced concrete raft slab. This allows for differential settlement between the heterogeneous foundations and transforms the differential settlement into smooth, continuous curved surface deformation. The construction method includes the following steps: Foundation treatment for the backfill area: High-strength, low-compressibility graded crushed stone or gravel is used for layered backfilling, with each layer having a loose thickness of no more than 400mm. A hydraulic rammer with an energy level of 25kJ or above is used for compaction. After each layer is compacted, the compaction degree is tested to ensure that it is not less than 95%. After backfilling to the design elevation, a grader is used for fine leveling. Surface treatment of concrete roof areas: Remove oil, laitance and dust from the roof surface, roughen the roof surface with a chisel or sandblasting machine to expose solid aggregate, and fully wet the surface before pouring concrete, but there should be no standing water. Accurately mark the boundary between the concrete roof and the backfill and excavate a trench. The center line of the trench coincides with the boundary between the roof and the backfill. The width of the trench is the width of the designed isolation strip, and the depth of the trench extends 300-500mm below the top surface of the compacted backfill base. A high-strength geogrid is laid at the bottom of the excavated trench, and the bottom geogrid is anchored to the backfill area and the roof area on both sides for no less than 1.0m. A multi-directional deformable hinge module is installed above the bottom geogrid, and the perforated flexible plastic modules prefabricated in the factory are interlocked through the male and female tenon grooves on the side to form a continuous and complete module layer. Elastic particle filler is used to fill the vertical holes and gaps between the assembled multi-directional deformable hinge modules. The elastic particle filler is made by mechanically mixing rubber particles with a particle size of 1-5 mm and medium-coarse sand at a volume ratio of 1:1. During filling, it is ensured that all gaps are fully and densely filled. A top-layer secondary reinforced geogrid is laid on top of the filled multi-directional deformable hinge module layer, and a layer with a specification of not less than 400g / m² is fully laid on top of the top-layer geogrid. 2 Non-woven geotextile is used as the isolation layer; A graded crushed stone cushion layer is uniformly laid on top of the geotextile in the entire construction area and statically compacted with a road roller to form a flat construction working surface. Double-layer, bidirectional reinforced concrete raft foundation steel mesh is tied on the graded crushed stone cushion layer. The steel mesh uses HRB400 grade steel bars with a diameter of 8-12mm and a spacing of 150mm×150mm. In the concrete roof area, the bottom layer of the raft foundation steel mesh is reliably anchored to the roof structure to form a rigid anchoring zone. In the backfill area and above the flexible settlement isolation zone, the steel mesh is placed only on the cushion layer without being anchored to any underlying structure to form a flexible transition zone. Using the skip-pour method or a one-time continuous pouring method, pour micro-expansion concrete with a design strength of C30 / C35 to form an integral reinforced concrete raft slab. Strengthen vibration to ensure concrete compaction, especially in areas with dense reinforcement and above the isolation zone. After pouring, smooth the surface in time. The raft slab shall be kept moist for no less than 14 days. After the raft slab concrete reaches the design strength, the sports surface layer shall be laid on top of the raft slab.
[0016] Preferably, after the raft foundation is poured, an induction joint is set on the raft foundation according to the site conditions to release the temperature shrinkage stress of the concrete itself.
[0017] Preferably, after the sports surface layer is laid, settlement observation points are set up on the rafts on both sides of the boundary line and at the stable points on the field edge, and settlement observations are carried out regularly during the first year after delivery for use.
[0018] Compared with existing technologies such as traditional settlement joints, foundation reinforcement, and general elastic cushion layers, this invention has the following advantages: 1. Allowing settlement rather than preventing settlement, thus completely avoiding rigid damage. This invention does not attempt to eliminate differential settlement, but rather actively absorbs and mitigates it through a flexible settlement isolation zone. The multi-directional deformable hinge module undergoes controllable elastic deformation under horizontal shear force, and the elastic particle filler flows and redistributes within the module's pores to fill the voids. Together, these two processes transform the severe differential settlement that might have been concentrated in a single crack into a gentle, continuous curved surface deformation distributed across the entire width of the isolation zone, completely preventing surface layer fracture and misalignment.
[0019] 2. A continuous transition is achieved through a monolithic floating raft slab. The monolithic reinforced concrete raft slab spans the rigid roof area and the backfill area. It is rigidly anchored in the roof area to ensure coordination with the existing structure, while it floats flexibly above the backfill area and the isolation zone to accommodate settlement. The raft slab is only equipped with structural reinforcement and not crack-resistant reinforcement, allowing for minor, harmless bending deformation. This ensures that the court surface presents a large-radius gentle slope that is imperceptible to the naked eye, guaranteeing normal use.
[0020] 3. Convenient construction and significantly shortened construction period. This invention eliminates the need for lengthy pre-settlement waiting time and heavy equipment such as pile foundations and dynamic compaction. The main materials are conventional concrete, steel bars, and engineering plastics. The construction process is clear, and it is friendly to surrounding building structures and the environment. Compared with traditional post-settlement methods, the construction period can be shortened by several months.
[0021] 4. Controllable costs and low maintenance expenses. This invention avoids the huge costs associated with periodic business shutdowns, excavation and repairs, and surface repaving caused by settlement issues. Furthermore, the cost of the main materials is controllable, resulting in significant long-term economic benefits.
[0022] 5. Multi-layered synergy and stress dispersion. The bottom and top geogrids are stretched and tensioned during deformation, dispersing the deformation over a wider area through their own tension, preventing deformation from concentrating on a narrow crack; the non-woven geotextile isolates the infiltration of the upper cushion material, ensuring unobstructed drainage channels. Attached Figure Description
[0023] Figure 1 This is a schematic diagram of the construction method of the present invention, showing the system relationship and mechanical transmission path between the rigid roof area, the backfill area, the flexible settlement isolation zone, the integral reinforced concrete raft slab and the sports field surface layer.
[0024] Figure 2This is a schematic diagram of the flexible settlement isolation zone structure of the present invention, showing the composition and spatial relationship of each structural layer of the isolation zone from bottom to top. Detailed Implementation
[0025] To further illustrate the technical means and effects of the present invention in achieving its intended purpose, the following detailed description of the specific implementation methods, structures, features, and effects of the present invention, in conjunction with the accompanying drawings and preferred embodiments, is provided below.
[0026] Phase 1: Foundation Treatment and Precise Leveling (1) Foundation treatment in the backfill area 1) Layered backfilling: High-strength, low-compressibility graded crushed stone or gravel is used for backfilling, and the loose thickness of each layer is strictly controlled to not exceed 400mm.
[0027] 2) High-strength compaction: A hydraulic rammer with an energy level of 25kJ or above is used for compaction. After each layer is compacted, the compaction degree is tested by sand cone method according to the specifications to ensure that the compaction degree is not less than 95%.
[0028] 3) Surface leveling: After backfilling to the design elevation, a grader is used for fine leveling to form a solid base layer.
[0029] (2) Treatment of concrete roof area 1) Surface cleaning and roughening: Thoroughly remove oil stains, laitance, dust and other debris from the roof surface. Use a roughening machine or sandblasting machine to roughen the roof surface to expose solid aggregate, thereby enhancing the adhesion to the subsequent concrete raft slab.
[0030] 2) Cleaning and wetting: After roughening, clean again and fully wet the surface before pouring concrete, but there should be no standing water.
[0031] Phase Two: Precise Construction of Flexible Settlement Isolation Zones (1) Setting out and excavation 1) According to the design drawings, accurately mark the location line of the isolation zone, and its center line should coincide with the boundary line between the roof and the backfill soil.
[0032] 2) Excavate trenches along the marked lines. The width of the trenches should be the width of the designed isolation strip (preferably 3.0m), and the depth should extend to 300-500mm below the top surface of the compacted backfill soil base.
[0033] (2) Laying the bottom layer of geogrid 1) Lay a high-strength bidirectional geogrid at the bottom of the excavated trench. The geogrid model must meet the design tensile strength requirements.
[0034] 2) The grid should be backfilled and anchored for at least 1.0m in both the backfill area and the roof area to form effective reinforcement and prevent loss.
[0035] (3) Install the multi-directional deformable hinge module 1) Transport the prefabricated engineering plastic multi-directional deformable hinge modules from the factory to the site. The ribs of the modules have pre-designed thin-walled areas and male and female tenon grooves on the sides.
[0036] 2) Starting from one end of the trench, connect the modules using an interlocking mechanism to tightly assemble them into a continuous and complete layer. Ensure that the modules are in close contact and there is no looseness.
[0037] (4) Fill with elastic particle filler 1) Fill the vertical holes and gaps between the assembled multi-directional deformable hinge modules with elastic granular filler. The filler is made by mechanically mixing rubber granules with a particle size of 1-5mm and medium-coarse sand at a volume ratio of 1:1.
[0038] 2) When filling, use a small forklift in conjunction with manual labor to ensure that all gaps are fully and densely filled without leaving any voids.
[0039] (5) Laying the top layer of geogrid and non-woven geotextile 1) Lay a second layer of high-strength bidirectional geogrid on the top surface of the filled core layer (technical requirements are the same as the bottom layer).
[0040] 2) Finally, apply a layer of material with a specification of not less than 400g / m² to the top layer of the grid. 2 Non-woven geotextile is used as an isolation layer to prevent the infiltration of the upper crushed stone cushion material, while ensuring unobstructed drainage channels.
[0041] Phase 3: Construction of the integral raft foundation (1) Laying graded crushed stone subbase A 150mm thick layer of graded crushed stone is uniformly laid on top of the geotextile in the entire construction area (including the roof, isolation zone, and backfill area), and statically compacted with a road roller to form a flat construction working surface.
[0042] (2) Binding of steel mesh and selective anchoring 1) Tie a double-layer, bidirectional reinforced concrete raft foundation mesh on the foundation layer. The reinforcing bars are HRB400 grade, with a diameter of 8-12mm and a spacing of 150mm×150mm.
[0043] 2) Key Step – Selective Anchoring: In the concrete roof area, the bottom steel mesh of the raft slab is reliably anchored to the roof structure by means of rebar anchoring or pre-embedded steel bars, and the anchoring length and quantity meet the design specifications to form a rigid anchoring zone.
[0044] In the backfill area and directly above the flexible settlement isolation zone, the steel mesh is placed only on the subgrade and is not anchored to any underlying structure, forming a flexible transition zone. Concrete protective layer blocks can be installed under the steel mesh.
[0045] (3) Pouring concrete Pour micro-expansion concrete with a design strength of C30 / C35 using either the skip-pour method or a single continuous pouring method. Strengthen vibration to ensure concrete compaction, especially in areas with dense reinforcement and above the isolation strip. After pouring, promptly smooth the surface.
[0046] (4) Maintenance and seam cutting 1) Immediately after pouring, cover with plastic film and geotextile and keep moist for no less than 14 days.
[0047] 2) Depending on the site conditions, induced joints can be set on the raft slab to release the temperature shrinkage stress of the concrete itself.
[0048] Phase 4: Surface layer laying and subsequent monitoring (1) Laying of sports surface layer After the raft foundation concrete reaches its design strength, the sports surface system required by the design, such as artificial turf and elastic padding, is laid directly on it.
[0049] (2) Establish long-term monitoring points 1) Settlement observation points are set up on the rafts and stable areas at the edge of the site on both sides of the boundary line.
[0050] 2) During the first year after delivery and use, settlement observations should be conducted regularly to verify the system's working status and the data should be archived.
[0051] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any way. Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make some modifications or alterations to the above-disclosed technical content to create equivalent embodiments without departing from the scope of the present invention. Any simple modifications, equivalent changes and alterations made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the scope of the present invention.
Claims
1. A settlement adaptive isolation structure for football fields with heterogeneous foundations, characterized in that, To address the differential settlement issue at the interface between two heterogeneous foundations—concrete roof and backfill soil—a combination system of flexible settlement isolation strip and selective anchoring of integral reinforced concrete raft slab is adopted. This system allows for differential settlement between heterogeneous foundations and transforms the differential settlement into smooth and continuous curved surface deformation to ensure the flatness of the court surface. The isolation structure includes: A flexible settlement isolation strip is installed at the junction of the concrete roof and the backfill soil, and the isolation strip includes, from bottom to top, the following: A high-strength geogrid is laid at the bottom of the trench and anchored to the heterogeneous foundation areas on both sides. A multi-directional deformable hinge module layer is laid on top of the underlying geogrid. The multi-directional deformable hinge module is assembled from perforated flexible plastic modules connected by interlocking male and female tenon grooves on the sides. The module has multiple through vertical holes inside, and adjacent vertical holes are connected by ribs. The ribs have thin-walled areas for stress concentration, so that the module has vertical support strength while undergoing controllable elastic deformation under horizontal shear force. Elastic particle filler is used to fill the vertical holes and gaps between modules. The elastic particle filler is made of rubber particles with a particle size of 1 to 5 mm and medium-coarse sand in a volume ratio of 1:
1. It is used to fill the gaps caused by deformation by flow and redistribution when differential settlement occurs. A top-layer secondary reinforced geogrid is laid on top of the multi-directional deformable hinge module layer to uniformly transfer the upper load to the lower multi-directional deformable hinge module. A non-woven geotextile isolation layer laid on top of the top geogrid; And, an integral reinforced concrete raft slab covering the concrete roof area, backfill area and flexible settlement isolation zone, wherein the raft slab is provided with structural steel mesh but not crack-resistant steel bars, so as to maintain the integrity of the raft slab and allow it to undergo slight bending deformation under differential settlement. The raft slab is rigidly anchored to the roof structure in the concrete roof area by steel bars to form a rigid anchorage zone. In the backfill area and above the flexible settlement isolation zone, it is not rigidly connected to any structure below it, forming a flexible transition zone.
2. The adaptive isolation structure for settlement of a football field with heterogeneous foundations as described in claim 1, characterized in that, The width W of the flexible settlement isolation zone is determined by the formula W = ΔS / tan(θ), where ΔS is the expected maximum differential settlement and θ is the maximum allowable rotation angle.
3. The adaptive isolation structure for settlement of a football field with heterogeneous foundations as described in claim 1, characterized in that, The body of the multi-directional deformable hinge module is made of a polymer material with added anti-aging agents and toughening agents, and is injection molded in one step using a mold.
4. The adaptive isolation structure for settlement of a football field with heterogeneous foundations as described in claim 1, characterized in that, Both the bottom geogrid and the top geogrid are high-strength bidirectional geogrids, and the bottom geogrid has a reverse anchorage length of not less than 1.0m in each of the heterogeneous foundation areas on both sides.
5. The adaptive isolation structure for settlement of a football field with heterogeneous foundations as described in claim 1, characterized in that, The nonwoven geotextile has a specification of not less than 400g / m². 2 .
6. The adaptive isolation structure for settlement of a football field with heterogeneous foundations as described in claim 1, characterized in that, The thickness of the integral reinforced concrete raft slab is 15-20cm, and the structural steel mesh uses HRB400 grade steel bars with a diameter of 8-12mm and a spacing of 150mm×150mm.
7. The adaptive isolation structure for settlement of a football field with heterogeneous foundations as described in claim 1, characterized in that, A sports surface layer, including artificial turf and a cushioning layer, is also laid on top of the raft.
8. A construction method for a settlement-adaptive isolation structure for a football field with heterogeneous foundations, characterized in that, To address the differential settlement issue at the interface between concrete roofs and backfill soil foundations, a phased construction method is employed to construct a combined system of flexible settlement isolation zones and selective anchoring of integral reinforced concrete raft slabs. This allows for differential settlement between the heterogeneous foundations and transforms the differential settlement into smooth, continuous curved surface deformation. The construction method includes the following steps: Foundation treatment for the backfill area: High-strength, low-compressibility graded crushed stone or gravel is used for layered backfilling, with each layer having a loose thickness of no more than 400mm. A hydraulic rammer with an energy level of 25kJ or above is used for compaction. After each layer is compacted, the compaction degree is tested to ensure that it is not less than 95%. After backfilling to the design elevation, a grader is used for fine leveling. Surface treatment of concrete roof areas: Remove oil, laitance and dust from the roof surface, roughen the roof surface with a chisel or sandblasting machine to expose solid aggregate, and fully wet the surface before pouring concrete, but there should be no standing water. Accurately mark the boundary between the concrete roof and the backfill and excavate a trench. The center line of the trench coincides with the boundary between the roof and the backfill. The width of the trench is the width of the designed isolation strip, and the depth of the trench extends 300-500mm below the top surface of the compacted backfill base. A high-strength geogrid is laid at the bottom of the excavated trench, and the bottom geogrid is anchored to the backfill area and the roof area on both sides for no less than 1.0m. A multi-directional deformable hinge module is installed above the bottom geogrid, and the factory-prefabricated perforated flexible plastic modules are interlocked through the male and female tenon grooves on the side to form a continuous and complete module layer. Elastic particle filler is used to fill the vertical holes and gaps between the assembled multi-directional deformable hinge modules. The elastic particle filler is made by mechanically mixing rubber particles with a particle size of 1-5 mm and medium-coarse sand at a volume ratio of 1:
1. During filling, it is ensured that all gaps are fully and densely filled. A top-layer secondary reinforced geogrid is laid on top of the filled multi-directional deformable hinge module layer, and a layer with a specification of not less than 400g / m² is fully laid on top of the top-layer geogrid. 2 Non-woven geotextile is used as the isolation layer; A graded crushed stone cushion layer is uniformly laid on top of the geotextile in the entire construction area and statically compacted with a road roller to form a flat construction working surface. Double-layer, bidirectional reinforced concrete raft foundation steel mesh is tied on the graded crushed stone cushion layer. The steel mesh uses HRB400 grade steel bars with a diameter of 8-12mm and a spacing of 150mm×150mm. In the concrete roof area, the bottom layer of the raft foundation steel mesh is reliably anchored to the roof structure to form a rigid anchoring zone. In the backfill area and above the flexible settlement isolation zone, the steel mesh is placed only on the cushion layer without being anchored to any underlying structure to form a flexible transition zone. Using the skip-pour method or a one-time continuous pouring method, pour micro-expansion concrete with a design strength of C30 / C35 to form an integral reinforced concrete raft slab. Strengthen vibration to ensure concrete compaction, especially in areas with dense reinforcement and above the isolation zone. After pouring, smooth the surface in time. The raft slab shall be kept moist for no less than 14 days. After the raft slab concrete reaches the design strength, the sports surface layer shall be laid on top of the raft slab.
9. The construction method for a settlement-adaptive isolation structure for a football field with heterogeneous foundations as described in claim 8, characterized in that, After the raft foundation is poured, induced joints are set on the raft foundation according to the site conditions to release the temperature shrinkage stress of the concrete itself.
10. The construction method for a settlement-adaptive isolation structure for a football field with heterogeneous foundations as described in claim 8, characterized in that, After the sports surface layer is laid, settlement observation points are set up on the rafts on both sides of the boundary line and at the stable points on the field edge, and settlement observations are carried out regularly during the first year after delivery for use.