A method for dewatering and excavating foundation pits

By combining external water-blocking, deep well construction, and intelligent pneumatic dewatering systems, the problem of poor stability in foundation pit dewatering was solved, achieving efficient and stable foundation pit dewatering, and ensuring construction safety and progress.

CN123064183APending Publication Date: 2026-11-10CHINA RAILWAY SIXTH GROUP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611286262.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-24
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

Existing methods for constructing foundation pits for dewatering and drainage have failed to establish a systematic three-dimensional control system that combines external water retention with internal dewatering and drainage. This results in difficulty controlling the infiltration of external surface water and internal groundwater, low drainage efficiency, and impacts construction progress and safety.

Method used

The method employs a comprehensive approach, including external water-retaining construction, deep well construction, pit bottom drainage construction, and precipitation monitoring. This involves site leveling, forming a water-retaining wall with precast concrete foundations and capping beams, deep well construction, setting up drainage ditches and collection wells, and coordinating with automatic water pumps. The pumping rate is monitored in real time and dynamically adjusted, and an intelligent pneumatic precipitation system is used for automated pumping.

Benefits of technology

This achieved effective control of surface water in the surrounding area and groundwater in the pit, improved drainage efficiency, ensured construction safety and progress, and achieved efficient and stable dewatering results.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123064183A_ABST
    Figure CN123064183A_ABST
Patent Text Reader

Abstract

This application discloses a method for constructing a foundation pit dewatering system, comprising: constructing an outer water-retaining structure, which involves leveling and compacting the site, pouring a foundation layer, laying raised precast concrete strip foundations to form the first water-retaining wall, and simultaneously reinforcing and pouring the second water-retaining wall with the diaphragm wall capping beam to form a second water-retaining wall, and setting up a drainage ditch at the top of the pit to connect to the municipal rainwater pipe network; constructing a deep well for dewatering, which involves sequentially setting up the well location, drilling, cleaning and slurry replacement, lowering the well pipe in the center, filling the outer perimeter with filter material, sealing the top of the pipe with clay to stop water, and completing the construction by washing the well and testing with pumping equipment; constructing drainage ditches and collection wells at the bottom of the pit simultaneously with the layered excavation of the foundation pit, with each layer equipped with an automatic start / stop pump to pump shallow water to the drainage ditch at the top of the pit; monitoring dewatering throughout the entire cycle of foundation pit excavation and main construction, simultaneously starting the deep wells for dewatering and the bottom pumps for continuous dewatering, and collecting real-time dynamic data on groundwater levels. This achieves a systematic and coordinated control of the outer water-retaining structure, the deep dewatering within the pit, and the bottom drainage.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of foundation pit construction technology, and in particular to a foundation pit dewatering construction method. Background Technology

[0002] In the field of foundation pit engineering, dewatering is a crucial step in ensuring the safe excavation of the foundation pit and the smooth progress of subsequent main structure construction. Especially in the construction of ultra-large foundation pits, the rational design and implementation of the dewatering system directly affects the stability of the pit slope, the effectiveness of groundwater level control, and the safety of the surrounding environment. Most existing foundation pit dewatering methods typically employ only single in-pit dewatering measures or simple top-drainage measures, failing to form a systematic, three-dimensional control system combining external water retention and in-pit dewatering. This leads to the easy infiltration of external surface water and precipitation into the foundation pit when dealing with complex hydrogeological conditions. Simultaneously, the efficiency of groundwater drainage within the pit is low, and the coordination between various construction stages is not tight enough, making it difficult to meet the overall dewatering requirements of the foundation pit, thus affecting construction progress and foundation pit safety. Summary of the Invention

[0003] In order to solve the above-mentioned technical problems, or at least partially solve the above-mentioned technical problems, this application provides a method for construction of foundation pit dewatering.

[0004] This application provides a method for dewatering and excavating foundation pits, applicable to the construction of ultra-large foundation pits. The method includes the following steps:

[0005] Step 1, External water barrier construction: (1) Level and compact the site and pour the cushion layer, lay the raised finished concrete strip foundation, and seal the joints with mortar to form the first water barrier; (2) Reinforce the cap beam of the diaphragm wall at the same time, and pour concrete after reinforcing the formwork to form the second water barrier; (3) Set up the intercepting ditch at the top of the pit, and connect it to the municipal rainwater pipe network after sedimentation; Step 2, construction of deep well drainage: (1) Measure and mark the well position and install the protective pipe. Drill the hole using a drilling rig. After the hole is formed, clean the hole and replace the slurry. Lower the well pipe and arrange it in the center; (2) Fill the outer perimeter of the well pipe with filter material. Use clay to seal the top of the filter material to stop water; (3) Use an air compressor to wash the well. After the well is washed, put in the pumping equipment for test pumping to complete the construction of deep well drainage. Step 3: Pit bottom drainage construction: The foundation pit is excavated in layers, and drainage ditches and collection wells are excavated immediately after each layer of foundation pit is excavated. Automatic water pumps are installed in the collection wells to pump the accumulated water to the intercepting ditch; wherein, the bottom surface of the drainage ditch and the collection well is lower than the excavation working surface. Step 4: Dewatering Monitoring: Throughout the entire process of foundation pit excavation and main construction, the dewatering well and the water pump at the bottom of the pit are continuously operated to simultaneously dewater; the groundwater level of the foundation pit is monitored in real time, and the pumping rate is dynamically adjusted based on the monitoring data.

[0006] According to the foregoing embodiments of this application, the precipitation monitoring step further includes: Settlement monitoring points are set up around the foundation pit. Soil settlement data are collected in real time at the settlement monitoring points. If the monitored settlement value exceeds the standard, water recharge is initiated simultaneously to suppress soil settlement.

[0007] According to the foregoing embodiments of this application, the foundation pit dewatering construction method further includes using an intelligent pneumatic dewatering system to manage all the deep wells for drainage, comprising the following steps: The air compressor and intelligent control cabinet are placed on the top slope of the foundation pit, and the air pipeline is distributed along each drainage well. The air compressor delivers compressed air to the air storage tank. The compressed air is distributed to each drainage well through the automatic control box, and the groundwater in the well is mixed with the air and then quickly discharged to the surface with the help of the water-air exchanger to achieve automated and uninterrupted water pumping.

[0008] According to the foregoing embodiments of this application, in the step of draining the deep well, a centralizer is installed when the well casing is lowered. The centralizer is distributed circumferentially on the outside of the well casing and is in close contact with the outer wall of the well casing so that the well casing is kept centered.

[0009] According to the foregoing embodiments of this application, the well pipe includes a solid pipe section, a water filtering section, and a sedimentation section. The water filtering section is located between the solid pipe section and the sedimentation section. The solid pipe section is located on the side closer to the wellhead. The sedimentation section is welded and fixed to the bottom plate of the well bottom. Both ends of the water filtering pipe are provided with the centralizer.

[0010] According to the aforementioned embodiments of this application, in the peripheral water-blocking construction step, the intercepting ditch is integrally cast with reinforced concrete, and sedimentation tanks are provided at intervals along the intercepting ditch, and multi-stage sedimentation tanks are provided at the connection between the intercepting ditch and the municipal rainwater pipe network.

[0011] According to the aforementioned embodiments of this application, the cross-sectional dimensions of the intercepting ditch are 0.6m x 0.8m, and the intercepting ditch is provided with a drainage slope of 5‰ along the longitudinal direction.

[0012] According to the aforementioned embodiments of this application, the bottom elevation of the intercepting ditch is lower than the road surface surrounding the foundation pit; when the bottom elevation of the intercepting ditch is lower than the first preset height of the road surface, a culvert is buried and a manhole is installed; when the bottom elevation of the intercepting ditch is lower than the second preset height of the road surface, a rainwater lifting manhole is installed; if the bottom elevation of the end of the intercepting ditch is lower than the bottom elevation of the municipal rainwater well, a lifting pump is installed at the end of the intercepting ditch.

[0013] According to the aforementioned embodiments of this application, a pre-dewatering test procedure is also performed before the foundation pit is excavated. The pre-dewatering test procedure includes the following steps: conducting four stages of tests in sequence: initial water level observation, single well pumping, group well pumping, and water level recovery; measuring the initial water head of the confined aquifer and the water inflow of a single well; verifying the feasibility of the dewatering plan; and optimizing the drainage-related parameters and the matching configuration of the pumping equipment.

[0014] According to the foregoing embodiments of this application, the mud density of the drilling rig during drilling is 1.10 to 1.30.

[0015] The technical solutions provided in this application have the following advantages compared with the prior art: First, the external water-retaining construction step involved site leveling, simultaneous pouring of precast concrete strip foundations and capping beams to form the first and second water-retaining walls. Combined with the intercepting ditch at the top of the pit, this constituted an external water-retaining system, effectively blocking the infiltration path of external surface water and rainwater into the foundation pit, thus solving the problem of external water intrusion into the pit. Second, the deep well dewatering construction step involved procedures such as well location marking, drilling, lowering and centrally positioning well casings, filling with filter material, and sealing with clay to ensure the construction quality of the deep wells. This effectively dewatered the deep confined water, reducing the water pressure at the bottom of the pit. Third, the pit bottom drainage construction step involved timely installation of drainage ditches and collection wells during the layered excavation process. Automatically activated pumps drained accumulated water into the intercepting ditch, ensuring a dry working surface and preventing construction safety hazards caused by water softening the foundation soil. Finally, the precipitation monitoring step achieves precise control over the entire dewatering process by continuously operating the deep well and the bottom pump to simultaneously dewater, and by dynamically adjusting the pumping rate based on the real-time groundwater level. This enables the external water retention, the internal dewatering, and the bottom drainage to work in synergy, thereby solving the problems of poor systemicity and loose connection between various links in the existing dewatering system, and achieving a highly efficient, stable, and safe foundation pit dewatering effect. Attached Figure Description

[0016] Figure 1 This is a schematic flowchart of an embodiment of the foundation pit dewatering construction method of this application; Figure 2 This is a structural schematic diagram of the first retaining wall, the second retaining wall, the intercepting ditch, and the drainage ditch in the foundation pit dewatering construction method of this application; Figure 3 This is a top view schematic diagram of the dewatering deep well in the foundation pit dewatering construction method of this application; Figure 4 This is a schematic diagram of the deep well used in the foundation pit dewatering construction method of this application.

[0017] Icon labels: 10. First retaining wall; 20. Second retaining wall; 30. Intercepting ditch; 40. Drainage ditch; 50. Well pipe; 51. Solid pipe section; 52. Filter section; 53. Sedimentation section; 60. Centralizer; 70. Filter media. Detailed Implementation

[0018] To provide a clearer understanding of the technical features, objectives, and effects of this invention, specific embodiments are now described in detail with reference to the accompanying drawings. In the following description, it should be understood that the orientations or positional relationships indicated by terms such as "front," "rear," "upper," "lower," "left," "right," "longitudinal," "horizontal," "vertical," "horizontal," "top," "bottom," "inner," "outer," "head," and "tail" are based on the orientations or positional relationships shown in the accompanying drawings, and are constructed and operated in a specific orientation. They are only for the convenience of describing this technical solution and do not indicate that the device or element referred to must have a specific orientation; therefore, they should not be construed as limitations on this invention.

[0019] It should also be noted that, unless otherwise explicitly specified and limited, terms such as "installation," "connection," "linking," "fixing," and "setting" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components. When an component is referred to as being "on" or "below" another component, the component can be located "directly" or "indirectly" on the other component, or there may be one or more intermediary components. The terms "first," "second," "third," etc., are only for the convenience of describing this technical solution and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Therefore, features defined with "first," "second," "third," etc., may explicitly or implicitly include one or more of that feature. For those skilled in the art, the specific meaning of the above terms in this invention can be understood according to the specific circumstances.

[0020] In the following description, specific details such as particular system architectures and techniques are set forth for illustrative purposes and not for limitation, in order to provide a thorough understanding of the embodiments of the invention. However, those skilled in the art will understand that the invention can be implemented in other embodiments without these specific details. In other instances, detailed descriptions of well-known systems, apparatuses, circuits, and methods are omitted so as not to obscure the description of the invention with unnecessary detail.

[0021] In the embodiments of this application, "extra-large foundation pit" generally refers to foundation pit projects with an excavation area or depth exceeding the conventional scale and having high requirements for dewatering and drainage systems. For ease of description, the longitudinal direction of the intercepting ditch in this application refers to its extension direction, and the description of the ditch bottom elevation being lower than the surrounding road surface and other height directions is based on the horizontal plane.

[0022] Figure 1 This is a flowchart illustrating a foundation pit dewatering construction method provided in an embodiment of this application.

[0023] like Figure 1 As shown in the figure, this application provides a method for dewatering and excavating a foundation pit. This method is applied to the construction of ultra-large foundation pits and includes the following steps: S101. Construction of the outer water barrier: (1) Level and compact the site and pour the cushion layer, lay the raised finished concrete strip foundation, and seal the joint with mortar to form the first water barrier 10; (2) Reinforce the crown beam of the ground wall at the same time, and pour concrete after reinforcing the formwork to form the second water barrier 20; (3) Set up the intercepting ditch 30 at the top of the pit, and connect it to the municipal rainwater pipe network after sedimentation.

[0024] It should be noted that the mortar used to seal the joints between the concrete strips is a 1:2.5 cement mortar, to ensure a tight seal and prevent surface water from seeping into the foundation pit through the gaps, thus improving the overall waterproofing and seepage prevention effect of the first retaining wall. S102, construction of deep well for drainage: (1) Measure and mark the well position and install the protective pipe. Use a drilling rig to drill the hole. After the hole is formed, clean the hole and replace the slurry. Lower the well pipe 50 and arrange it in the center; (2) Fill the outer periphery of the well pipe 50 with filter material 70. Use clay to seal the upper part of the filter material 70 to stop water; (3) Use an air compressor to wash the well. After the well is washed, put in the pumping equipment for trial pumping and complete the construction of deep well 10 for drainage.

[0025] S103. Pit bottom drainage construction: The foundation pit is excavated in layers, and a drainage ditch 40 and a water collection well are excavated immediately after each layer of foundation pit is excavated. An automatic start-stop water pump is installed in the water collection well to pump the accumulated water to the intercepting ditch 3030. The bottom surface of the drainage ditch 40 and the water collection well is lower than the excavation working surface.

[0026] S104. Dewatering Monitoring: During the entire process of foundation pit excavation and main construction, the deep well 10 and the water pump at the bottom of the pit are continuously activated to simultaneously dewater; the groundwater level of the foundation pit is monitored in real time, and the pumping rate is dynamically adjusted based on the monitoring data.

[0027] The foundation pit dewatering construction method of this embodiment firstly involves the construction of the outer water-retaining structure. This is achieved through site leveling, simultaneous pouring of precast concrete strip foundations and capping beams to form the first and second water-retaining walls 20. Combined with the pit top intercepting ditch 30, this constitutes the outer water-retaining system, effectively blocking the infiltration path of external surface water and rainwater into the foundation pit, thus solving the problem of external water intrusion. Secondly, the deep well dewatering construction step involves procedures such as well location marking, drilling, lowering and centrally arranging well pipes 50, filling with filter material 70, and sealing with clay to ensure the construction quality of the deep wells. This effectively dewaters the deep confined water, reducing the water pressure at the bottom of the foundation pit. Thirdly, the pit bottom drainage construction step involves timely installation of drainage ditches 40 and collection wells during layered excavation. Automatically start-stop pumps drain accumulated water into the intercepting ditch 30, ensuring the dryness of the excavation surface and preventing construction safety hazards caused by water softening the foundation soil. Finally, the precipitation monitoring step achieves precise control over the entire dewatering process by continuously operating the deep well and the bottom pump to simultaneously dewater, and by dynamically adjusting the pumping rate based on the real-time groundwater level. This enables the external water retention, the internal dewatering, and the bottom drainage to work in synergy, thereby solving the problems of poor systemicity and loose connection between various links in the existing dewatering system, and achieving a highly efficient, stable, and safe foundation pit dewatering effect.

[0028] In practical applications, the overall action / work process of this foundation pit dewatering construction method is as follows: First, before excavating the foundation pit, the site is leveled and compacted, then raised strip foundations are laid and the joints are sealed with mortar, forming the first line of defense. Subsequently, during the construction of the underground continuous wall capping beam, concrete is poured simultaneously to form the second water-retaining wall 20, which, together with the first wall, constitutes a water barrier. Simultaneously, the intercepting ditch 30 at the top of the pit begins to collect and guide surface water, which, after sedimentation, is discharged into the municipal pipe network, effectively cutting off the external water source. Next, the deep well for drainage is constructed. The drilling rig is positioned, and drilling begins after the protective casing is installed. Holes are formed using mud slurry, and after cleaning and replacing the slurry, the well casing 50 is lowered to the bottom of the hole, surrounded by filter material 70, and sealed with clay. After well washing, a smooth water collection channel is formed inside the well, and groundwater flows into the well casing 50 under pressure. After the foundation pit begins layered excavation, bottom drainage and dewatering monitoring are initiated. As each layer of earth is excavated, a drainage ditch 40 with a lower bottom and a sump are immediately excavated on the working surface. The seeping groundwater and construction water flow into the sump under gravity. The automatic water pump in the sump automatically starts when the water level reaches the set height, and discharges the accumulated water to the intercepting ditch 30. During this process, the pumping equipment in the deep well and the pump at the bottom of the pit operate synchronously and continuously. The groundwater level monitoring equipment transmits data to the control terminal in real time. The system dynamically adjusts the pumping rate of all pumps according to the water level changes to keep the groundwater level stable below the design safety line until the main structure is completed.

[0029] The precipitation monitoring step in the above embodiment further includes: setting up settlement monitoring points around the foundation pit, collecting soil settlement data in real time at these points, and simultaneously initiating recharge to suppress soil settlement if the monitored settlement value exceeds the standard. In this way, while precipitation keeps the interior of the foundation pit dry, parallel monitoring of soil settlement outside the pit constitutes a complete dual-control mechanism of "precipitation inside the pit and settlement control outside the pit." When excessive pumping causes the water level outside the pit to drop too quickly, leading to soil compression, recharge can promptly compensate for the groundwater, raising the local water level and effectively suppressing further consolidation settlement of the soil layer. Compared to systems that can only passively pump water, this changes risk control from "post-event remediation" to "in-event intervention," achieving the beneficial effect of avoiding environmental damage caused by excessive precipitation.

[0030] In some embodiments, the foundation pit dewatering construction method further includes using an intelligent pneumatic dewatering system to manage all the dewatering deep wells. The specific method includes the following steps: placing an air compressor and an intelligent control cabinet on the top slope of the foundation pit, and distributing the air pipeline along each dewatering deep well; using the air compressor to deliver compressed air to the air storage tank; distributing the compressed air to each dewatering deep well through the automated control box, and using a water-air exchanger to mix the groundwater in the well with the air and then quickly discharge it to the surface to achieve automated and uninterrupted pumping.

[0031] Those skilled in the art will understand that this intelligent pneumatic dewatering system forms a highly efficient pumping network with centralized air supply and decentralized drainage. The air compressor and air storage tank serve as a centralized power assembly, intelligently distributing high-pressure gas through an automated control box to each dewatering deep well. A water-air exchanger installed in each well utilizes the energy of compressed air to mix well water with air, generating a low-density gas-water mixture, which is then rapidly lifted to the surface under the pressure difference between the inside and outside of the well. This "air-based pumping" method ensures that each dewatering deep well consists only of a water-air exchanger with no moving parts and an air pipeline, fundamentally avoiding the problems of easy damage, blockage, and difficult maintenance of downhole electric pumps. Simultaneously, centralized management through the intelligent control cabinet enables automated, uninterrupted pumping at all well points, not only improving pumping efficiency but also reducing manual inspection and management costs, achieving a combined effect of highly efficient, low-maintenance, and intelligent pumping through the synergy of various subordinate features.

[0032] Figure 3 This is a top view schematic diagram of the dewatering deep well in the foundation pit dewatering construction method of this application; Figure 4 This is a schematic diagram of the deep well used in the foundation pit dewatering construction method of this application.

[0033] In one embodiment, such as Figure 3 and Figure 4 As shown, in the process of draining a deep well, a stabilizer 60 is installed when the well casing 50 is lowered. The stabilizers 60 are distributed circumferentially on the outer side of the well casing 50 and are tightly attached to the outer wall of the well casing 50 to keep the well casing 50 centered. Specifically, the stabilizers 60 can be arc-shaped blocks or annular clamps made of steel or high-strength engineering plastics, which are fixed to the outer wall of the well casing 50 by bolts or welding. When the well casing 50 is slowly lowered into the borehole filled with mud, the circumferentially distributed stabilizers 60 will contact the borehole wall, using their outer edges as support points to apply radial restraint force to the well casing 50, automatically correcting any possible tilting and ensuring that the well casing 50 is ultimately precisely suspended in the center of the borehole. This central setting ensures uniform space around the well pipe 50, allowing a uniform annular filter layer to be formed when the filter material 70 is filled. This avoids localized missing or bridging of the filter material 70 caused by the well pipe 50 being tilted and attached to the wall, effectively preventing sediment from flowing into the well from weak points, and improving the quality of the deep well drainage and the purity of the effluent.

[0034] Specifically, such as Figure 4 As shown, the well casing 50 includes a solid pipe section 51, a water filtering section 52, and a sedimentation section 53. The water filtering section 52 is located between the solid pipe section 51 and the sedimentation section 53. The solid pipe section 51 is located on the side closer to the wellhead. The sedimentation section 53 is welded and fixed to the bottom plate of the well. Both ends of the water filtering section 52 are equipped with centralizers 60.

[0035] Those skilled in the art will understand that the well casing 50 is clearly divided into three functional zones from top to bottom, and its effective function is ensured by the precise positioning of the centralizer 60. The upper solid pipe section 51 serves to block the upper groundwater and seal the water-stopping clay; the middle filter section 52 faces the main aquifer, and groundwater can only enter the pipe through the filter gaps in this section; the bottom sedimentation section 53 is a closed blind pipe section, sealed by welding the bottom plate, providing a dedicated sedimentation and temporary storage space for the small amount of fine-particle silt that may be brought in from the filter section 52, preventing it from accumulating and clogging the pumping equipment.

[0036] It is worth noting that by placing the centralizers 60 at both ends of the filtration section 52, two precise positioning base points are provided for this most critical functional section. This ensures that the entire filtration section 52112 remains stably centered in the borehole, thereby maximizing the uniformity of the filter media 70 surrounding the filtration section 52. This combined structure effectively improves the filtration efficiency, water intake flow, and long-term operational reliability of the entire deep well, solving the problems of equipment blockage and reduced water output caused by sediment accumulation during long-term pumping operations.

[0037] In some embodiments, during the external water-blocking construction, the intercepting ditch 30 is integrally cast with reinforced concrete, and sedimentation tanks are spaced along its length. Multi-stage sedimentation tanks are also installed at the junction of the intercepting ditch 30 and the municipal stormwater drainage network. Through integral casting, the intercepting ditch 30 possesses excellent impermeability and structural strength, avoiding the cracking and leakage defects common in masonry ditches. The spaced sedimentation tanks along its length utilize the principle of reduced flow velocity due to a sudden expansion of the channel cross-section, allowing coarse sediment carried by the water to gradually and locally settle during flow, preventing ditch blockage caused by long-distance transport. Finally, before being discharged into the municipal drainage network, the water undergoes a final deep clarification through the gradual overflow of the multi-stage sedimentation tanks, ensuring that only the supernatant is discharged into the municipal drainage network. This combination of "online decentralized sedimentation" and "terminal centralized purification" effectively solves the problem of drainage from foundation pits with high sediment content easily clogging the municipal drainage network.

[0038] As a specific implementation method, the intercepting ditch 30 has a cross-sectional dimension of 0.6m × 0.8m, and the intercepting ditch 30 is provided with a drainage slope of 5‰ along the longitudinal direction. This cross-sectional dimension provides sufficient flow capacity to cope with the conventional catchment area of ​​the ultra-large foundation pit, while the 5‰ longitudinal slope ensures the gravity flow velocity of the water while avoiding erosion of the ditch bottom caused by excessive slope or slow flow velocity and siltation caused by excessive slope.

[0039] In one embodiment, the bottom elevation of the intercepting ditch 30 is lower than the road surface surrounding the foundation pit to adapt to sloping terrain or deep foundation pits. When the bottom elevation of the intercepting ditch 30 is lower than the first preset height of the road surface, it means that the ditch is buried at a greater depth. In this case, by burying a concealed pipe and installing a manhole to connect the water flow, the drainage slope can be guaranteed, and the excavation and land occupation of an excessively deep open ditch can be avoided. When the bottom elevation of the intercepting ditch 30 is lower than the second preset height of the road surface, the height difference between it and the road surface further increases. Simply relying on gravity to flow through the concealed pipe is no longer economical or feasible. In this case, a rainwater lifting manhole is installed, and a water pump is used to actively lift the water accumulated at the lower level to a higher level before connecting it to the subsequent system. If the bottom elevation of the intercepting ditch 30 at the end is even lower than the bottom elevation of the municipal rainwater well, a lifting pump needs to be installed at the end of the intercepting ditch 30 to perform terminal forced lifting before connection. This series of drainage schemes, selected progressively based on elevation differences, dynamically adapts to various complex terrains, ensuring that the water collected by the intercepting ditch 30 can be successfully discharged into the municipal pipe network under any elevation difference, thus achieving full-condition connectivity of the external drainage system under complex terrains.

[0040] It should be noted that the first preset height in this embodiment is 1.2m and the second preset height is 2m. Those skilled in the art can make adaptive adjustments to the values ​​of the first preset height and the second preset height according to the actual construction terrain conditions, drainage requirements and municipal pipeline layout. The above values ​​are only preferred examples for this project and do not constitute a limitation on the scope of protection.

[0041] Furthermore, a pre-dewatering test procedure can be performed before the foundation pit excavation. This pre-dewatering test procedure includes the following steps: conducting four stages of tests in sequence: initial water level observation, single-well pumping, group well pumping, and water level recovery; measuring the initial water head of the confined aquifer and the single-well inflow, verifying the feasibility of the dewatering plan, and optimizing drainage-related parameters and the matching configuration of pumping equipment. Before large-scale formal dewatering construction, this small-scale, scientific in-situ test can accurately obtain the hydrogeological parameters of the aquifer, allowing for reverse verification and correction of the design plan. For example, if the measured single-well inflow is higher than the design value, the pump power can be increased or the number of wells increased in advance; conversely, the number of wells can be appropriately reduced, thereby avoiding the risk of resource waste or dewatering failure caused by blind construction, and achieving accurate prediction and parameter optimization of the formal dewatering process.

[0042] As a specific implementation method, the mud density is controlled at 1.10 to 1.30 during drilling. Mud within this density range can form a dense and stable mud cake on the borehole wall when drilling through loose or easily collapsible formations, effectively balancing formation pressure and preventing borehole wall collapse, while avoiding formation leakage or significant reduction in drilling speed due to excessive mud density.

[0043] The above description is only a preferred embodiment of the present invention. It should be noted that for those skilled in the art, several improvements and substitutions can be made without departing from the technical principles of the present invention, and these improvements and substitutions should also be considered within the scope of protection of the present invention.

Claims

1. A method for dewatering and clearing a foundation pit, applied to the construction of ultra-large foundation pits, characterized in that, The construction method includes the following steps: Step 1, External water barrier construction: (1) Level and compact the site and pour the cushion layer, lay the raised finished concrete strip foundation, and seal the joints with mortar to form the first water barrier; (2) Reinforce the cap beam of the diaphragm wall at the same time, and pour concrete after reinforcing the formwork to form the second water barrier; (3) Set up the intercepting ditch at the top of the pit, and connect it to the municipal rainwater pipe network after sedimentation; Step 2, construction of deep well drainage: (1) Measure and mark the well position and install the protective pipe. Drill the hole using a drilling rig. After the hole is formed, clean the hole and replace the slurry. Lower the well pipe and arrange it in the center; (2) Fill the outer perimeter of the well pipe with filter material. Use clay to seal the top of the filter material to stop water; (3) Use an air compressor to wash the well. After the well is washed, put in the pumping equipment for test pumping to complete the construction of deep well drainage. Step 3: Pit bottom drainage construction: The foundation pit is excavated in layers, and drainage ditches and collection wells are excavated immediately after each layer of foundation pit is excavated. Automatic water pumps are installed in the collection wells to pump the accumulated water to the intercepting ditch; wherein, the bottom surface of the drainage ditch and the collection well is lower than the excavation working surface. Step 4: Dewatering Monitoring: Throughout the entire process of foundation pit excavation and main construction, the dewatering well and the water pump at the bottom of the pit are continuously operated to simultaneously dewater; the groundwater level of the foundation pit is monitored in real time, and the pumping rate is dynamically adjusted based on the monitoring data.

2. The foundation pit dewatering construction method according to claim 1, characterized in that, The precipitation monitoring steps also include: Settlement monitoring points are set up around the foundation pit. Soil settlement data are collected in real time at the settlement monitoring points. If the monitored settlement value exceeds the standard, water recharge is initiated simultaneously to suppress soil settlement.

3. The foundation pit dewatering construction method according to claim 1, characterized in that, The aforementioned pit dewatering construction method also includes using an intelligent pneumatic dewatering system to manage all deep wells, comprising the following steps: The air compressor and intelligent control cabinet are placed on the top slope of the foundation pit, and the air pipeline is distributed along each drainage well. The air compressor delivers compressed air to the air storage tank. The compressed air is distributed to each drainage well through the automatic control box, and the groundwater in the well is mixed with the air and then quickly discharged to the surface with the help of the water-air exchanger to achieve automated and uninterrupted water pumping.

4. The foundation pit dewatering construction method according to claim 1, characterized in that, In the process of draining the deep well, a centralizer is installed when the well casing is lowered. The centralizer is distributed circumferentially on the outside of the well casing and is in close contact with the outer wall of the well casing to keep the well casing centered.

5. The foundation pit dewatering construction method according to claim 4, characterized in that, The well casing includes a solid pipe section, a filter section, and a sedimentation section. The filter section is located between the solid pipe section and the sedimentation section. The solid pipe section is located on the side closer to the wellhead. The sedimentation section is welded and fixed to the bottom plate of the well. Both ends of the filter pipe are equipped with the centralizer.

6. The method for constructing a foundation pit dewatering system according to claim 1, characterized in that, In the aforementioned peripheral water-blocking construction step, the intercepting ditch is integrally cast with reinforced concrete, and sedimentation tanks are set at intervals along the intercepting ditch, and multi-stage sedimentation tanks are set at the connection between the intercepting ditch and the municipal rainwater pipe network.

7. The foundation pit dewatering construction method according to claim 1, characterized in that, The intercepting ditch has a cross-sectional dimension of 0.6m x 0.8m and a longitudinal drainage slope of 5‰.

8. The method for dewatering and clearing a foundation pit according to claim 1, characterized in that, The bottom elevation of the intercepting ditch is lower than the road surface surrounding the foundation pit; when the bottom elevation of the intercepting ditch is lower than the first preset height of the road surface, a culvert is installed and a manhole is installed; when the bottom elevation of the intercepting ditch is lower than the second preset height of the road surface, a rainwater lifting manhole is installed; if the bottom elevation of the end of the intercepting ditch is lower than the bottom elevation of the municipal rainwater well, a lifting pump is installed at the end of the intercepting ditch.

9. The method for dewatering and clearing a foundation pit according to claim 1, characterized in that, Before the excavation of the foundation pit, a pre-dewatering test procedure is also performed. The pre-dewatering test procedure includes the following steps: conducting four stages of tests in sequence: initial water level observation, single well pumping, group well pumping, and water level recovery; measuring the initial water head of the confined aquifer and the water inflow of a single well; verifying the feasibility of the dewatering plan; and optimizing the drainage-related parameters and the matching configuration of the pumping equipment.

10. The method for dewatering and clearing a foundation pit according to claim 1, characterized in that, The drilling rig uses a mud density of 1.10 to 1.30 during drilling.