A method and system for vertical shaft guide and cut-off combined with backfill double-liquid grouting and water sealing
By using the methods of pressure relief and layered grouting, combined with the final sealing of the water guiding channel, the problem of preventing the spread of grout in the water from affecting the continuity of water sealing in vertical shafts was solved, and the stability and continuity of water sealing behind the shaft wall were achieved.
Patent Information
- Application Number
- CN202611566547.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-10
- Publication Date
- 2026-11-10
Smart Images

Figure CN123064482A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of water control technology for vertical shafts, and in particular to a method and system for sealing water by combined vertical shaft guide and interception with dual-liquid grouting behind the shaft wall. Background Technology
[0002] When a vertical shaft passes through areas such as bedrock fissures, aquifers, or fractured zones, groundwater may enter the shaft through rock fissures and voids behind the shaft wall, manifesting as visible water inflow, concentrated fissure water inflow, or water seepage through the shaft wall. Continuous water inflow not only affects the shaft construction environment but may also impact the pouring of the shaft wall concrete, the backfill condition of the shaft wall, and the subsequent use of the shaft.
[0003] Existing methods for controlling water in vertical wells typically include water diversion, water interception, and backfill grouting. For water seepage from localized fissures, water can be diverted through a collection box and a water pipe; for water seepage from the well wall, a water interception trough can be installed to guide the water into a collection facility; for water-bearing areas behind the well wall, cement-water glass dual-liquid grout can be used for backfill grouting through the well wall grouting holes, and the arrangement of grouting holes and grouting parameters can be adjusted according to the location of the leakage and the condition of the well wall.
[0004] When the above measures are implemented separately, the process connection between water diversion, water interception, and grouting behind the wall is weak. If grouting is performed directly when there is still strong dynamic water in the concentrated seepage channel, the grout is prone to migrate along the dominant seepage direction, and the external water interception and internal filling status are difficult to determine based on the actual sealing process; at the same time, the original water diversion position may still become a local residual seepage channel after the main grouting is completed, affecting the continuity of the water sealing area behind the wall. Summary of the Invention
[0005] To address the aforementioned issues, this invention provides a method and system for sealing water behind the shaft wall using a combined guide and cut-off method. Through the continuous coordination of pressure relief, layered grouting, and final sealing of the water channel, the influence of dynamic water on grout diffusion can be reduced, and the continuity of water sealing behind the shaft wall can be improved.
[0006] The above objectives can be achieved through the following approach: A method for sealing water in a vertical well using a combined guided and intercepted grouting system with dual-liquid grouting behind the well wall includes: collecting data on leakage locations, leakage patterns, water flow rates, water pressure parameters, and well wall quality at different depths and circumferential positions of the well wall; correlating the spatial distribution of leakage to determine the target sealing section and the main seepage channel; setting up a drainage component at the corresponding concentrated water outlet location in the target sealing section and setting up a water interception component in the water-spraying area of the well wall to collect the water discharged by the drainage component and the water interception component into a collection location; collecting the water flow rate and water pressure changes during the drainage and interception process to generate the basic state of the drainage and interception system; determining the location of the grouting holes behind the well wall based on the main seepage channel, the location of the drainage component, and the well wall quality state; dividing the grouting holes arranged around the periphery of the main seepage channel into an outer water interception hole group; dividing the grouting holes located between the outer water interception hole group and the main seepage channel into an inner filling hole group; generating the arrangement result of the grouting hole group; keeping the drainage component in a water-guiding state, and channeling water to the well wall through the outer water interception hole group. Afterwards, cement-water glass dual-liquid grout is injected, and the external grouting pressure and the water flow rate are collected and correlated over time to generate an external pressure-flow response. The water interception formation state is determined based on the external pressure-flow response. After the water interception formation state is reached, dual-liquid grouting is performed in the direction of the main seepage channel through the inner filling hole group. The inner grouting pressure and the water flow rate are collected to generate an inner pressure-flow response. The filling and sealing state is determined based on the inner pressure-flow response. After the filling and sealing state is reached, the drainage path of the guide assembly is closed, the guide assembly is switched to the grouting state, and cement-water glass dual-liquid grout is injected into the remaining seepage channel corresponding to the original water guide position through the guide assembly, so that the external water interception area, the inner filling area, and the original water guide position form a continuous wall back seal body. After the continuous wall back seal body reaches the preset consolidation state, the target water sealing section is inspected for grouting and the well wall leakage state is re-measured. The water sealing construction result is generated based on the inspection grouting result and the re-measured leakage state.
[0007] Based on the same inventive concept, this invention also provides a vertical shaft guide-interception combined with wall-mounted dual-liquid grouting and water sealing system. The system includes a leakage parameter acquisition component for acquiring leakage locations, leakage patterns, water flow rates, water pressure parameters, and well wall quality status at different depths and circumferential positions on the vertical shaft wall; a controller for analyzing the spatial continuity between the leakage locations and the correlation of the water flow rates to determine the target water sealing section and the dominant seepage channel; and a guide-interception execution component for guiding and draining water at the concentrated outlet location of the target water sealing section and intercepting water in the well wall's water-spraying area, allowing the water behind the wall to be discharged through a determined water-guiding path. The leakage parameter acquisition component is also used to acquire the water flow during the drainage process. The controller generates the basic state of the interception based on the water flow rate and water pressure parameters during the water diversion process. The controller is also used to determine the arrangement of the backfill grouting holes based on the location of the main seepage channel, the interception execution component, and the well wall quality state. The backfill grouting holes located around the main seepage channel form an outer interception hole group, and the backfill grouting holes located between the outer interception hole group and the interception execution component form an inner filling hole group, generating a backfill grouting hole group arrangement result. A dual-liquid grouting component is used to inject cement-water glass dual-liquid grout into the well wall through the outer interception hole group when the interception execution component maintains a water-conducting state. The controller controls the outer grouting pressure and... Simultaneously, the water flow rate is correlated according to a time correspondence to generate an external pressure-flow response. When the water flow rate continuously decreases relative to the interception foundation state and the external grouting pressure continuously increases, it is determined that the external water interception state has been reached. The dual-liquid grouting component is also used to perform dual-liquid grouting towards the main seepage channel through the inner filling hole group after the external water interception state is reached. The controller correlates the inner grouting pressure with the simultaneous water flow rate to generate an inner pressure-flow response. When the water flow rate decreases to the final sealing flow rate range determined according to the sealing target and the inner grouting pressure tends to stabilize, it is determined that the inner filling state has been reached. The channel switching component is used to achieve the desired water interception state when the target water interception state is reached. After the inner filling state is described, the drainage path of the intercepting execution component is closed, and the intercepting execution component is connected to the dual-liquid grouting path of the dual-liquid grouting component; the dual-liquid grouting component injects cement-water glass dual-liquid grout into the remaining seepage channel corresponding to the original water guiding position through the intercepting execution component, so that the outer water interception area, the inner filling area and the final sealing area corresponding to the original water guiding position are connected to each other to form a continuous wall back sealing body; the dual-liquid grouting component is also used to perform inspection grouting on the target sealing section after the continuous wall back sealing body is solidified, and the leakage parameter acquisition component is also used to re-measure the well wall leakage status, and the controller generates the sealing construction result based on the inspection grouting result and the re-measured well wall leakage status.
[0008] Compared with the prior art, the present invention has the following advantages: This invention maintains a concentrated water outlet position during the peripheral dual-liquid grouting process, allowing water behind the wall to be released preferentially through a defined water channel. Furthermore, by utilizing the peripheral water interception hole group to first form a grout water interception area, it can reduce the disturbance of dynamic water to the grout diffusion and consolidation process.
[0009] This invention establishes an external pressure-flow response and an internal pressure-flow response by correlating grouting pressure with water flow rate, and controls the switching between the external water interception, internal filling and final sealing stages. This ensures that the grouting process behind the wall directly corresponds to the actual seepage state, reducing the mismatch caused by determining the construction stage solely based on a single grouting pressure.
[0010] This invention converts the drainage channel into a grouting channel after completing the outer water interception and inner filling, and finally seals the remaining seepage channels corresponding to the original concentrated water guiding position. This forms a continuous wall water seal body with the outer water interception area, the inner filling area and the original water guiding position, reducing the possibility of the local residual leakage channels being re-circulated. Attached Figure Description
[0011] Figure 1 This is a flowchart of the vertical shaft guide and interception combined with wall-mounted dual-liquid grouting and water sealing method according to an embodiment of the present invention; Figure 2 This is a schematic diagram of the wellbore expansion position reference, leakage location, and main seepage channel according to an embodiment of the present invention; Figure 3 This is a schematic diagram of the spatial arrangement of the guide assembly, the outer water interception hole group, and the inner filling hole group according to an embodiment of the present invention; Figure 4 This is a schematic diagram of the pressure-flow diversion response during the peripheral water interception stage of an embodiment of the present invention; Figure 5 This is a schematic diagram of the final sealing switching process of the inner filling and guide assembly according to an embodiment of the present invention; Figure 6 This is a schematic diagram of the water-sealing body formed after the outer water-cutting area, inner filling area and final sealing area of the present invention form a continuous wall; Figure 7 This is a schematic diagram of the vertical shaft guide and interception combined with the wall-mounted dual-liquid grouting and water sealing system according to an embodiment of the present invention. Detailed Implementation
[0012] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0013] Reference Figure 1 One embodiment of the present invention proposes a vertical shaft guide-cut-off combined wall-mounted dual-liquid grouting and water sealing method. Through the continuous coordination of guide-drainage pressure relief, layered grouting and final sealing of the water guide channel, the influence of dynamic water on grout diffusion can be reduced and the continuity of water sealing behind the vertical shaft wall can be improved.
[0014] The method described in this embodiment specifically includes: S1. Collect leakage locations, leakage patterns, water flow rates, water pressure parameters, and well wall quality status at different depths and circumferential positions of the vertical shaft wall. Analyze the spatial continuity relationship between leakage locations and the correlation relationship of water flow rates to determine the target sealing section and the main seepage channel. In one embodiment of the present invention, step S1 includes the following steps: Establish a well wall deployment position reference according to the depth direction of the vertical well and the circumferential position of the well wall. Map the concentrated water outlet position, the fissure water outlet position and the water spraying area of the well wall to the well wall deployment position reference to obtain the distribution of well wall leakage positions. The water flow rate, water pressure parameters and well wall quality status corresponding to each well wall leakage location are configured to the corresponding well wall unfolding position to form a well wall leakage status distribution. The distribution of well wall leakage status is correlated regionally based on the degree of spatial connectivity between adjacent well wall leakage locations, and the leakage extension direction is determined based on the continuous change of water flow rate with location within the correlated region. The target water sealing section is determined based on the leakage extension direction, water flow distribution, and water pressure distribution, and the leakage area that connects the centralized water outlet and is continuously distributed along the leakage extension direction is determined as the dominant seepage channel.
[0015] Specifically, such as Figure 2 As shown, the wellbore deployment position reference uses the wellbore axial depth and wellbore circumferential position as two-dimensional positioning dimensions, with the wellhead or construction survey control point as the depth zero point, and the fixed orientation determined by construction survey as the circumferential zero point. For an inner diameter of... The well shaft will... Circumferential angle of each leakage location Converted to circumferential distance after the well wall is unfolded : ; In the formula, Indicates the first The circumferential distance corresponding to each leakage location is shown in meters. This indicates the inner diameter of the well shaft, in meters. Indicates the first The angle of each leakage location relative to the circumferential zero position is expressed in degrees.
[0016] Record the leakage status at each leakage location. : ; In the formula, Indicates the first The well depth at each leakage location, in meters; This indicates the corresponding circumferential unfolded distance, in meters; This indicates the leakage type corresponding to concentrated water outflow, fissure water outflow, or water seepage from the well wall; This indicates the water flow rate at the corresponding location during the detection period, expressed in cubic meters per hour. This indicates the water pressure parameter at the corresponding location, in megapascals (MPa). This indicates the quality status of the well wall as obtained from external inspections, construction records, borehole exploration, or on-site testing.
[0017] For two adjacent leakage locations and Calculate the distance of the wellbore deployment position : ; In the formula, This represents the distance between two leakage locations within the wellbore's unfolded location reference, expressed in meters. The adjacent distance range used to determine spatial continuity is determined based on statistics of fracture spacing within the target area, construction joint locations, borehole exploration results, and on-site leakage distribution. For leakage locations within a spatially adjacent range that can be confirmed as having continuous extension through visible fractures, construction interfaces, backfill voids, or borehole backflow relationships, regional association is established. This is then combined with the continuous change in water flow and pressure from the concentrated outlet location to surrounding locations within the associated area to determine the leakage extension direction.
[0018] The leakage status records that have a spatial continuity and flow rate correlation with the centralized water outlet location and are continuously distributed along the leakage extension direction constitute the dominant seepage channel. : ; In the formula, Indicates the first in the dominant seepage channel A record of leakage status; This indicates the number of leakage status records contained in the dominant seepage channel. Each record is spatially correlated through at least one of the following: fracture extension, construction interface continuity, back-wall void connectivity, or borehole backflow relationship, and exhibits a continuous change in the distribution of water flow or water pressure, converging towards a concentrated outlet location.
[0019] According to the dominant seepage channel The target water-sealing section is determined by the coverage area along the well depth, combined with the well wall water-spraying area adjacent to the main seepage channel and the area of well wall quality anomalies. : ; In the formula, Indicates the upper well depth boundary of the target water-sealing section, in meters; This indicates the lower well depth boundary of the target water-sealing section, in meters. The two boundaries are jointly determined based on the depth coverage of the dominant seepage channel, adjacent leakage locations, and areas of abnormal well wall quality that need to be included in the water-sealing construction. Dominant seepage channel. Used to characterize the main confluence path of water behind the inner wall of the target water-sealing section, target water-sealing section Used to define the construction scope for subsequent drainage, interception, grouting hole layout, and grouting inspection.
[0020] For example, with an inner diameter as Taking a vertical shaft as an example, at a depth of... to A leakage investigation was conducted within the affected area, with due north as the circumferential zero point. The detected concentrated water outflow location A was located at a depth of [insert depth here]. Circumferential angle The water flow rate is Water pressure is Inspection of the well wall revealed continuous fractures near location A; the water outlet location B of the fractures is located at a depth of [depth missing]. Circumferential angle The water flow rate is Water pressure is The location of the water outlet in the fracture, C, is at a depth of [depth missing]. Circumferential angle The water flow rate is Water pressure is The water seepage zone D on the well wall is distributed at the well depth. to scope.
[0021] The circumferential unfolded distance at position A is: The circumferential unfolded distance at position B is: The circumferential unfolded distance at position C is: This results in three leakage status records: A, B, and C. ; ; The components are: the first component represents the well depth in meters; the second component represents the circumferential expansion distance in meters; the fourth component represents the water flow rate in cubic meters per hour; and the fifth component represents the water pressure parameter in megapascals. The distance between the well walls of points A and B is: The distance between the wellbore expansion positions of A and C is: On-site fracture mapping shows that the fracture at location B extends continuously towards location A, and the fracture at location C connects with a fracture near location A in another direction. Test borehole return water results further indicate a hydraulic connection behind the wall between locations B, A, and C. Meanwhile, the water conduction rates at locations B and C are respectively... and The water flow rate at the centralized outlet A increased to The water pressure also changes from positions B and C. and Added to position A This exhibits seepage characteristics converging towards location A. Therefore, according to the dominant seepage channel... The structure was backfilled to obtain: ;in, This represents the dominant seepage channel characterized by three spatially continuous leakage locations (B, A, and C) with a water-conducting relationship, where A is the corresponding concentrated outflow location. Combined with... In the direction of well depth Extend to The coverage area and the well wall water spray area D extend to The distribution range, and the scope of construction that needs to include the quality inspection of adjacent well walls, determine the upper boundary of the target water-sealing section as... The lower boundary is determined as According to the target water sealing section The structure was backfilled to obtain: This forms the dominant seepage channel. and the target water sealing section Both serve as the basis for setting the centralized water outlet location guide assembly in step S2 and determining the spatial arrangement of the outer intercepting hole group and the inner filling hole group in step S3.
[0022] S2. Set up a drainage component at the concentrated water outlet of the target water sealing section and intercept the water spray area on the well wall so that the water behind the wall is discharged through a determined drainage path. Collect the drainage flow rate and water pressure parameters during the drainage process to generate the basic state of the drainage system. In one embodiment of the present invention, step S2 includes the following steps: A water guiding channel communicating with the seepage space behind the wall is set at the centralized water outlet position so that the centralized seepage water is discharged to the water collection position through the water guiding channel. An interception channel is set along the water spraying area of the well wall to guide the water spraying on the well wall surface to the water collection position, so that the concentrated water and the water spraying on the well wall are discharged along the corresponding drainage paths respectively. While keeping the water guiding channel connected, the water guiding flow rate and corresponding water pressure parameters are collected, and the water guiding flow rate and water pressure parameters are correlated according to a unified time reference. Based on the corresponding water flow rate and water pressure parameters, a guide foundation state characterizing the water release state of the main body before grouting is generated.
[0023] Specifically, a drainage component is installed at the centralized water outlet location determined in step S1. The inlet of the drainage component is connected to the seepage space behind the wall corresponding to the centralized water outlet location, and the outlet is connected to the well collection location via a drainage branch, ensuring that the water behind the wall in the main seepage channel can still be released along the determined path during the subsequent peripheral interception and internal filling stages. For the well wall water-spraying area, intercepting channels, intercepting pipes, or water collection components adapted to the well wall surface are installed along the lower edge of the water-spraying area or the water flow convergence location, so that the well wall water-spraying enters an independent interception path and is discharged to the water collection location, avoiding surface water-spraying affecting the centralized water flow monitoring. Flow detection and water pressure detection locations are set in the drainage path of the drainage component to unify the sampling time. Forming the basic state record of the cutoff : ; In the formula, This indicates the first time before the main grouting begins. The water flow rate measured by the centralized water diversion path at each sampling time, in cubic meters per hour; The water pressure parameters at the same sampling time are expressed in megapascals (MPa). This indicates the number of sampling records during the baseline observation phase. To characterize the stable release level during the baseline observation phase, the average baseline flow rate was calculated. and average base water pressure : ; ; The basic state of the intercept includes a record set. Average basic water conduction flow and average base water pressure The observation duration and sampling interval are determined based on the fluctuation cycle of the on-site water diversion flow, the sampling capacity of the detection device, and the construction monitoring procedures. Subsequent peripheral water interception phases are assessed by comparing the concurrent water diversion flow with... The changes indicate the degree of restriction on water replenishment around the main seepage channel.
[0024] For example, following the target water-sealing section formed in step S1, a drainage pipe capable of switching between drainage and subsequent grouting is installed at the centralized water outlet location A. The water outlet end of the drainage pipe is first connected to the well casing water collection tank. A intercepting trough is set at the lower edge of the water-spraying area D to separately guide the surface water of area D to the water collection tank. After the drainage is completed, location A is... Basic observation, with the start time of basic observation as... Each interval A set of statistical records of water flow and water pressure were generated, forming a total of Group records. Among them, The flow rate of the water is Water pressure is ; The flow rate of the water is Water pressure is ; The flow rate of the water is Water pressure is ; The flow rate of the water is Water pressure is ; The flow rate of the water is Water pressure is According to the basic state record of the interception. The structure was backfilled to obtain: ;in, The first component of each ternary set represents the sampling time relative to the start time of the baseline observation, in minutes; the second component represents the water flow rate at the corresponding sampling time, in cubic meters per hour; and the third component represents the water pressure parameter at the corresponding sampling time, in megapascals.
[0025] Depend on The average basic flow rate was calculated from the 5 sets of records: The average base water pressure is: This results in a complete time-series record. Average basic water conduction flow and average base water pressure The condition of the intercepting foundation was checked. Construction personnel simultaneously inspected the interception path in the water-spraying area D, confirming that surface water in area D did not enter the flow detection branch at location A, thus ensuring... The water flow record in the data mainly reflects the water release state behind the wall of the dominant seepage channel, and will... It is directly used as the basis for evaluating the degree of attenuation of the peripheral flow in step S4.
[0026] S3. Determine the arrangement of the back wall grouting holes based on the location of the main seepage channel, the guide assembly, and the well wall quality status. Form an outer water interception hole group by the back wall grouting holes located around the main seepage channel, and form an inner filling hole group by the back wall grouting holes located between the outer water interception hole group and the guide assembly, thereby generating the arrangement result of the back wall grouting hole group. In one embodiment of the present invention, step S3 includes the following steps: The grouting coverage area is determined based on the extension range of the main seepage channel in the wellbore deployment location reference. Multiple wall-mounted grouting holes are arranged along the periphery of the grouting coverage area, so that the multiple wall-mounted grouting holes form an enclosing relationship along the circumferential periphery and depth direction of the main seepage channel, thus obtaining a peripheral water interception hole group; Multiple wall-mounted grouting holes facing the main seepage channel are arranged between the outer water interception hole group and the guide assembly to obtain an inner filling hole group; The spatial relationship between the outer intercepting hole group and the inner filling hole group is adjusted according to the well wall quality condition, so that the slurry diffusion area corresponding to the outer intercepting hole group is located outside the slurry diffusion area corresponding to the inner filling hole group, and the slurry diffusion direction corresponding to the inner filling hole group is oriented towards the concentrated water outlet position corresponding to the guide and discharge assembly.
[0027] Specifically, such as Figure 3 As shown, the dominant seepage channel formed in step S1 The grouting coverage area is determined centered on the coverage range in the wellbore deployment reference. The orifice location, drilling direction, and effective depth into the back wall grouting area are determined by considering the wellbore thickness, back wall voids, rock fracture direction, construction joint location, and wellbore quality condition. A single back wall grouting hole record is represented as follows: ,in, Indicates the hole depth position, Indicates the circumferential angle of the orifice. This indicates the deflection angle of the borehole relative to the normal direction of the wellbore or a reference direction selected on-site. Indicates the effective drilling length. This indicates the type of borehole group. Grouting holes located around the main seepage channel and capable of forming an enclosing relationship in both the depth and circumferential directions constitute an outer intercepting borehole group. : ; The grouting holes located between the outer intercepting hole group and the concentrated water outlet, with the grout diffusion direction facing the inside of the main seepage channel, form the inner filling hole group. : ; In the formula, and These represent the number of peripheral intercepting holes and inner filling holes, respectively. The specific number is determined based on the length of the main seepage channel, the well wall coverage area, the degree of fracture development, and the results of on-site test drilling. The peripheral intercepting holes are not primarily intended to directly track the concentrated water outlet point, but are preferentially arranged around the main seepage channel, allowing multiple peripheral grout diffusion zones to overlap and form an outer constraint. The inner filling holes are located within the outer constraint and arranged along the direction of the concentrated water outlet, used to gradually fill the remaining space behind the main seepage channel after the outer constraint is formed. For locations with weak well wall quality or localized voids, the borehole opening and drilling direction are adjusted to avoid direct application of grouting pressure to areas with weak bearing capacity. After determining the hole positions, the arrangement of the peripheral intercepting hole group, the inner filling hole group, the guide assembly positions, and the main seepage channel positions together form the grouting hole group arrangement behind the wall, which directly serves as the basis for the grouting sequence in steps S4 and S5.
[0028] For example, following the BAC dominant seepage channel formed in step S1, six peripheral intercepting holes, numbered H01-H06, are arranged along the periphery of the channel in the well wall deployment reference; four inner filling holes, numbered H11-H14, are arranged between the peripheral intercepting hole group and the concentrated water outlet position A. Based on on-site fracture mapping, well wall quality inspection, and test drilling return water direction, the wellhead depth, circumferential angle, borehole deflection angle, and effective drilling length of each grouting hole are determined, where the hole group categories are respectively denoted as... and , Indicates the outer water interception hole, This indicates the inner filling hole.
[0029] according to The structure was used to backfill each grouting hole, resulting in: ; ; ; ; ; ; ; ; ; The record contains the following components: the first component represents the wellhead depth in meters; the second component represents the circumferential angle at the wellhead in degrees; the third component represents the borehole deflection angle determined by the return water direction during test drilling in degrees; the fourth component represents the effective drilling length in the fracture and void areas after entering the wellbore in meters; and the fifth component represents the borehole group type. The outer intercepting borehole group is formed by H01-H06. The inner filling hole group is formed by H11-H14: H01 and H02 are located outside position B, H03 and H04 are distributed on both sides of position A in the depth direction and circumferential direction, and H05 and H06 extend to the outside of position C, making... A circumferential angle is formed around the BAC-dominant seepage channel. to , well deep to The coverage area extends to the outer perimeter of the borehole. H11-H14 represent the circumferential angle from the outer perimeter of the borehole towards position A. Gradually approaching, H11 and H12 are closer to the inner side of the outer intercepting hole group, while H13 and H14 are closer to the concentrated water outlet position A, making... The arrangement of boreholes is formed, advancing towards the interior of the main seepage channel and the concentrated water outlet location. During the on-site trial drilling, the backflow connection of H01-H06 mainly occurred on the periphery of the continuous BAC area, while the backflow connection of H11-H14 with the water guide channel at location A was more direct. Therefore, the area corresponding to H01-H06 was designated as the outer interception construction area, and the area corresponding to H11-H14 was designated as the inner filling construction area. The final arrangement of the wall-mounted grouting borehole group was formed, with the outer interception borehole group, the inner filling borehole group, and the concentrated water outlet location A arranged sequentially from the outside to the inside. This arrangement was directly used as the basis for the grouting sequence in steps S4 and S5.
[0030] S4. Keep the drainage assembly in the water-guiding state, inject cement-water glass dual-liquid slurry into the well wall through the peripheral water-cutting hole group, correlate the peripheral grouting pressure with the water-guiding flow rate at the same time according to the time correspondence, generate peripheral pressure-guiding response, when the water-guiding flow rate continues to decrease relative to the water-cutting foundation state and the peripheral grouting pressure continues to increase, determine that the peripheral water-cutting state has been reached. In one embodiment of the present invention, step S4 includes the following steps: Maintain the connection between the drainage assembly and the water collection location so that the water behind the wall in the main seepage channel is continuously discharged during the external double-liquid grouting process; Double-liquid grouting is carried out sequentially according to the spatial arrangement of the peripheral intercepting holes along the periphery of the main seepage channel, and the peripheral grouting pressure and the water flow rate corresponding to the guide assembly at each grouting position are recorded simultaneously. The peripheral grouting pressure and the concurrent water flow rate are correlated according to a continuous observation time window to determine the changing trend of the peripheral grouting pressure and the attenuation trend of the water flow rate relative to the state of the guide foundation, thereby generating a peripheral pressure-flow response. When the peripheral grouting pressure continues to increase and the water flow rate continues to decrease within the continuous observation time window, it is determined that the peripheral grout diffusion area has formed a peripheral constraint on the dominant seepage channel, generating a peripheral water interception state.
[0031] Specifically, such as Figure 4As shown, during the peripheral water interception stage, the drainage path corresponding to the concentrated water outlet position remains open, ensuring that when the grout diffuses from the peripheral water interception holes to the cracks and voids behind the wall, the water behind the wall in the main seepage channel can still be discharged along the concentrated water outlet position. The cement slurry concentration, the mixing ratio of cement slurry and water glass, and the allowable grouting pressure range of the cement-water glass dual-liquid grout are determined based on the water pressure parameters obtained in step S1, the well wall quality condition, and in conjunction with the material gel time test before construction, the results of on-site trial injection, and construction records of similar sections; when the well wall quality is weak, the upper limit of the allowable grouting pressure is correspondingly limited. Peripheral grouting is advanced hole by hole or group by group according to the spatial arrangement sequence of the peripheral water interception hole group, and a peripheral grouting record is formed. : ; In the formula, Indicates the sampling time The corresponding external grouting pressure is expressed in megapascals (MPa). This indicates the water flow rate of the drainage component at the same time, expressed in cubic meters per hour. This indicates the number of the peripheral intercepting borehole currently involved in grouting. Continuous recordings are divided into multiple observation time windows. Calculate the first one respectively Average peripheral grouting pressure during the observation time window and average water conduction flow Then calculate the pressure change in adjacent observation time windows. Changes in water flow rate : ; ; Simultaneously, the average basic water conduction flow rate obtained in step S2 is used. Calculate the current flow attenuation level : ; The external pressure-fluid diversion response is determined by the observation time window. , , , and Composition. When multiple consecutive observation time windows meet and Furthermore, if the flow attenuation trend does not significantly recover after the cessation of single-hole grouting, it indicates that the peripheral grout diffusion area is gradually restricting the connection between the dominant seepage channel and the peripheral water replenishment space, thus confirming the achievement of peripheral water interception. The length of the continuous observation time window and the number of windows that need to maintain the trend are determined based on the on-site flow fluctuation characteristics and test injection records, and a uniform and fixed value for different wellbores is not adopted.
[0032] For example, the peripheral water interception hole group formed in step S3 Under the condition of continuous drainage at the centralized water outlet A, double-liquid grouting is carried out according to the spatial arrangement sequence from H01 to H06. Based on the target section approximately... Based on the water pressure and well wall quality inspection results, and combined with on-site test injection, the allowable grouting pressure for the outer stage was determined to be no higher than [the specified value]. Within the specified range; based on the material gel time test, it was determined that the peripheral grouting should adopt a two-liquid grout state that can maintain peripheral diffusion.
[0033] After the external grouting begins, the moment the grouting begins is taken as... Each interval The current grouting hole, the external grouting pressure, and the water flow rate at position A were recorded simultaneously. A total of 8 consecutive sampling times were selected for explanation. At that time, the current grouting hole is H01, and the external grouting pressure is... The water flow rate at location A is ; At that time, the current grouting hole is H02, and the external grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H02, and the external grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H03, and the external grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H04, and the external grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H05, and the external grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H05, and the external grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H06, and the external grouting pressure is... The water flow rate is According to the external grouting records The structure was backfilled to obtain: ; In each quaternion, the first component represents the sampling time relative to the start of the peripheral grouting, in minutes; the second component represents the peripheral grouting pressure at the corresponding sampling time, in megapascals; the third component represents the concurrent water flow rate at location A, in cubic meters per hour; and the fourth component represents the peripheral intercepting hole number participating in the grouting at the corresponding sampling time. This establishes a correspondence between the actual grouting location, grouting pressure, and concurrent water flow rate of the peripheral intercepting holes according to a unified time reference.
[0034] Will to Divided into 4 consecutive observation time windows to Each observation time window contains two adjacent sets of sampling records. The average peripheral grouting pressure and average water flow rate of the first observation time window are as follows: ; Similarly, we get: ; ; Taking the fourth observation time window as an example, the change in peripheral grouting pressure relative to the third observation time window is: The change in water diversion flow rate during the same period is: The fourth observation time window is relative to the average baseline flow rate formed in step S2. The degree of conduction attenuation is: As can be seen from the four consecutive observation time windows, the average peripheral grouting pressure is in accordance with... , , and The average flow rate at location A continues to rise, according to... , , and The pressure continued to decrease, and the external grouting pressure remained within the allowable grouting pressure range determined on-site. After completing the grouting at H06, grout supply was briefly suspended. The water flow rate at location A did not recover to the level before the previous observation time window. Based on this, it was confirmed that the grout diffusion area corresponding to H01-H06 had formed an external constraint on the dominant seepage channel of BAC, creating an external water interception state. This refers to the final water flow rate at the end of the peripheral interception stage at the beginning of step S5.
[0035] S5. After the outer water interception state is reached, double-liquid grouting is carried out towards the main seepage channel through the inner filling hole group. The inner grouting pressure is correlated with the water flow rate at the same time to generate an inner pressure-flow response. When the water flow rate drops to the final sealing flow rate range determined according to the sealing target and the inner grouting pressure tends to stabilize, the inner filling state is determined to be reached. In one embodiment of the present invention, step S5 includes the following steps: While maintaining the peripheral grout diffusion area as a constraint on the main seepage channel, double-liquid grouting is carried out sequentially from the periphery to the corresponding concentrated water outlet position of the guide and discharge assembly according to the direction of the inner filling hole group. The inner grouting pressure corresponding to the inner filling hole group and the water flow rate corresponding to the guide and discharge assembly are recorded simultaneously, and the inner pressure-flow response is generated according to the continuous observation time window. The degree of change of the inner grouting pressure between adjacent consecutive observation time windows and the degree of residual water flow relative to the outer water interception state are determined based on the inner pressure-flow response. When the variation of the inner grouting pressure tends to converge between continuous observation time windows, and the water flow rate decreases to the final sealing flow rate range determined according to the allowable leakage state of the target sealing section, the inner filling state is generated.
[0036] Specifically, the inner filling stage follows the outer water-blocking state established in step S4, without reopening or disrupting the grout diffusion area corresponding to the outer water-blocking hole group. The inner filling hole group is progressively advanced from the periphery towards the concentrated water outlet position, allowing the dual-liquid grout to preferentially fill the remaining cracks and voids behind the wall within the outer constraint. The cement grout concentration and the cement grout-to-water glass ratio in the inner stage are determined based on the outer pressure-conduction response, the current remaining water flow rate, and the results of on-site material gel time tests, ensuring the grout can enter the remaining space of the main seepage channel without prematurely setting near the orifice. An inner grouting record is then generated. : ; In the formula, This indicates the grouting pressure during the inner filling stage. This indicates the concentrated water diversion flow rate during the same period. This indicates the current inner filling hole number. The records are statistically analyzed according to a continuous observation time window. and The degree of pressure change is characterized by the absolute value of the average grouting pressure difference between adjacent time windows. : ; The average flow rate at the end of step S4 As a benchmark for the external water interception status, calculate the current remaining water conductance. : ; The final sealing flow range is determined based on the design allowable leakage conditions of the target sealing section, well drainage requirements, and construction and acceptance requirements, and its upper limit is denoted as [missing value]. The allowable change in the grouting pressure stabilization determination is denoted as... , The determination is based on pressure fluctuations of the on-site grouting equipment, test grouting data, and statistics from similar construction sections. When the continuous observation time window meets the requirements... ,and Gradually reduce and enter The defined scope indicates that the main remaining space within the outer constraints has been filled, generating an inner filling state. After the inner filling state is formed, the final water guiding path at the concentrated water outlet position is retained for the conversion of the drainage path to the final sealing grouting path in step S6.
[0037] For example, following the outer water interception state formed in step S4, the water flow rate at position A when entering the inner filling stage is... The inner filling hole group formed according to step S3 Two-component grouting was carried out sequentially from the outer perimeter towards the concentrated water outlet point A. Based on the target wellbore sealing requirements and construction acceptance criteria, the upper limit of the water guiding flow rate before final sealing conversion was determined to be... Based on the stable fluctuation range of the grouting pump and pressure detection device during the on-site test grouting process, the allowable change in pressure stabilization is determined as follows: .
[0038] After the internal filling grouting begins, the moment of grouting commencement is taken as... Each interval The current inner filling hole, inner grouting pressure, and water flow rate at position A were recorded simultaneously, and a total of 8 consecutive sampling times were selected for explanation. At that time, the current grouting hole is H11, and the inner grouting pressure is... The water flow rate at location A is ; At that time, the current grouting hole is H11, and the inner grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H12, and the inner grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H12, and the inner grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H13, and the inner grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H13, and the inner grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H14, and the inner grouting pressure is... The water flow rate is ; At that time, the current grouting hole is H14, and the inner grouting pressure is... The water flow rate is According to the internal grouting record The structure was backfilled to obtain: (5,0.82,2.9,H11),(10,0.86,2.7,H11),(15,0.89,2,H12),(20,0.93,1.8,H12),(25,0.94,1.3,H13),(30,0.96,1.1,H13),(35,0.96,0.76,H14),(40,0.98,0.68,H14); where, the first component of each quaternion represents the sampling time relative to the start time of the inner filling grouting, in minutes; the second component represents the inner grouting pressure at the corresponding sampling time, in megapascals; the third component represents the water flow rate at position A during the same period, in cubic meters per hour; and the fourth component represents the inner filling hole number that participated in the grouting at the corresponding sampling time. Therefore, the actual grouting locations of H11-H14, the inner grouting pressure, and the concurrent water flow at location A are established according to a unified time reference to form a corresponding relationship.
[0039] Will to Divided into 4 consecutive observation time windows to Each observation time window contains two adjacent sets of sampling records. The average inner grouting pressure and average water flow rate of the first observation time window are as follows: ; Similarly, we get: ; ; The degree of change in inner grouting pressure between adjacent observation time windows is as follows: ; ; Therefore, it can be seen that the variation range of the inner grouting pressure between adjacent observation time windows is from... Reduce to Reduce to The flow rate gradually converges. The terminal water diversion flow rate at the point where the peripheral interception state is formed in step S4 is considered. As a baseline, the residual conductivity corresponding to the fourth observation time window is: At this point, the average water flow rate satisfies: At the same time, the degree of pressure change satisfies: Therefore, after H11-H14 were gradually filled from the periphery towards the concentrated water outlet A, the water flow rate at location A had entered the final sealing flow rate range, and the variation range of the inner grouting pressure had converged to the allowable range determined on site. Based on this, the inner filling state was generated, and the remaining water at location A was filled. The water guiding path is retained until step S6 for the final sealing conversion between the drainage path and the dual-liquid grouting path.
[0040] S6. After the inner filling state is reached, the drainage path of the guide assembly is closed, the guide assembly is connected to the dual-liquid grouting path, and cement-water glass dual-liquid grout is injected into the remaining seepage channel corresponding to the original water guiding position through the guide assembly, so that the outer water interception area, the inner filling area and the final sealing area corresponding to the original water guiding position are connected to each other to form a continuous wall post-sealing water body. In one embodiment of the present invention, step S6 includes the following steps: The final seal transition state when the water flow rate enters the final seal flow range is determined based on the internal pressure-flow response. In response to the final sealing transition state, the drainage path between the guide assembly and the water collection location is closed, and the guide assembly is connected to the dual-liquid grouting path, so that the guide assembly is converted from a water discharge channel behind the wall to a dual-liquid grout input channel; After conversion, the guide and discharge assembly performs dual-liquid grouting into the remaining seepage channel corresponding to the original centralized water outlet position, so that the dual-liquid grout diffuses from the original water guiding position to the inner filling area; Based on the changes in grouting pressure during the final sealing process, the remaining seepage channels corresponding to the original concentrated water outlet position are determined to be blocked, so that the final sealing area is connected with the inner filling area and the outer intercepting area to form a continuous wall back sealing body.
[0041] Specifically, the drainage component maintains the function of draining water behind the wall during the external water interception and internal filling stages. After the internal filling state is achieved in step S5, the drainage branch connecting to the water collection point is first closed, and then the grouting branch connecting to the dual-liquid grouting component is opened, changing the concentrated water outlet from the drainage outlet of the main seepage channel to the dual-liquid grout inlet. To prevent air or well water from entering the grouting branch during channel switching, the dual-liquid grouting pipeline is filled and pressure checked before switching. The allowable grouting pressure range for the final sealing stage is determined based on water pressure parameters, well wall quality, and the end pressure of the internal filling stage, and is limited by on-site trial injection and construction safety requirements. The final sealing process is recorded as follows: : ; In the formula, This indicates that the original centralized water outlet location has been converted into a grouting inlet. The final sealing grouting pressure at each sampling time was measured. The final sealing process was divided into continuous observation time windows, and the average final sealing grouting pressure within each window was calculated. and pressure changes in adjacent windows : ; The final sealing pressure reaches the range determined based on the wellbore quality condition, and the pressure changes in adjacent time windows gradually decrease and remain stable, indicating that the remaining dominant seepage space corresponding to the original concentrated water outlet location has been occupied by the dual-liquid slurry. The final sealing slurry diffuses from the original concentrated water outlet location to the inner filling area formed in step S5, and overlaps with the solidified or solidifying slurry in the inner filling area; the inner filling area then overlaps with the outer intercepting area formed in step S4, spatially forming a continuous backwater sealing body composed of the outer intercepting area, the inner filling area, and the final sealing area. The cement slurry concentration and the cement slurry to water glass ratio in the final sealing stage are determined based on the inner filling state, the remaining channel dimensions, and on-site gel time tests to meet the requirements for rapid sealing of the remaining channels.
[0042] For example, following the inner filling state formed in step S5, the water flow rate at position A has decreased. And enter the final sealing flow range. Construction personnel close the drain valve between the A-position drain pipe and the water collection tank, disconnecting the original drainage branch. Then, they open the switching valve between the A-position drain pipe and the dual-liquid grouting pipe, changing the A-position from the backwater discharge position to the dual-liquid grout input position. Based on the water pressure parameters obtained in step S1, the end pressure of the inner filling stage in step S5, and the well wall quality inspection results, combined with on-site test injection, the grouting pressure control range for the final sealing stage is determined to be... to .
[0043] After the final sealing grouting begins, the moment when the two-component grout starts to be introduced at position A is taken as the starting point. Each interval The final sealing grouting pressure was collected once, and a total of 8 consecutive sampling times were selected for explanation. The final sealing grouting pressure is ; The final sealing grouting pressure is ; The final sealing grouting pressure is ; The final sealing grouting pressure is ; The final sealing grouting pressure is ; The final sealing grouting pressure is ; The final sealing grouting pressure is ; The final sealing grouting pressure is According to the final sealing process record The structure was backfilled to obtain: In each binary tuple, the first component represents the sampling time relative to the start of the final grouting, in minutes; the second component represents the final grouting pressure at the corresponding sampling time, in megapascals. This forms a continuous pressure record at position A after the transition from the guide-drainage state to the final grouting state.
[0044] Will to Divided into 4 consecutive observation time windows to Each observation time window contains two adjacent sets of sampling records. The average final sealing grouting pressure for the first observation time window is: Similarly, we get: ; ; Based on the relationship between the average final sealing grouting pressure of adjacent observation time windows, calculate the pressure change in the second observation time window relative to the first observation time window: The pressure change in the third observation time window relative to the second observation time window is: The pressure change in the fourth observation window relative to the third observation window is: Therefore, as the two-component grout enters the remaining seepage channel corresponding to the original concentrated water outlet location from position A, the average final sealing grouting pressure increases from... Gradually rise to The pressure change in adjacent observation time windows was from Reduce to Reduce to This indicates that the remaining seepage space is gradually occupied by the grout, and the pressure increase caused by continued grouting tends to stabilize. The average final sealing grouting pressure in the third and fourth observation time windows both reached the levels determined on-site. to The final sealing pressure range was determined after the grout supply was suspended following the fourth observation window. No rapid pressure drop was observed, indicating that the remaining seepage channel at location A had reached the sealing state. The final sealing grout diffused from location A towards the inner filling areas corresponding to H13 and H14, forming an overlap. The inner filling areas corresponding to H11-H14 continued to connect with the outer intercepting areas corresponding to H01-H06, thus forming a continuous backwater sealing body comprised of the outer intercepting area, the inner filling area, and the final sealing area at location A.
[0045] S7. After the water-sealing body behind the continuous wall has solidified, the target water-sealing section is inspected and grouting is carried out, and the leakage status of the well wall is re-measured. The water-sealing construction result is generated based on the inspection and grouting results and the re-measured leakage status.
[0046] In one embodiment of the present invention, step S7 includes the following steps: After the continuous wall back seal water body reaches the solidification state, the outer water interception area, the inner filling area and the final sealing area are inspected along the target water sealing section; The locations with remaining injectable space are determined based on the backflow status of each inspection location, the amount of grout that can be injected, and the grouting pressure. For inspection locations with remaining injectable space, supplementary double-liquid grouting is carried out, and after the supplementary double-liquid grouting is completed, the concentrated water outflow status, well wall water spray status, and well barrel leakage status of the target water sealing section are re-measured; The water leakage status of the re-measured well wall is compared with the allowable water leakage status corresponding to the target water sealing section to generate the water sealing construction result.
[0047] Specifically, the consolidation waiting time for the water seal behind the continuous wall is determined based on the gel time of the cement-water glass double-liquid grout used in construction, the results of early strength tests, and the site temperature conditions. After the allowable conditions for grouting inspection are met, inspection locations are selected in the outer water-cutting area, the inner filling area, and the final sealing area. An inspection record is generated for each inspection location. : ; In the formula, Indicates the inspection location number; This indicates the backflow status during the inspection process; a value of 1 indicates backflow, and a value of 0 indicates no backflow. This indicates the amount of grout that can be injected at the corresponding grouting pressure, expressed in liters. This indicates the grouting pressure at the corresponding inspection location, in megapascals (MPa). The range of remaining injectable grout volume and the range of inspection grouting pressure used to determine the remaining injectable space are determined based on design requirements, grout consolidation tests, and acceptance data from similar well construction projects. When backflow occurs at the inspection location, or grout can still be continuously drawn in at the specified inspection grouting pressure, or the remaining injectable grout volume exceeds the on-site inspection standard, the corresponding location is determined to have remaining injectable space, and supplementary two-component grouting is implemented.
[0048] After the supplementary grouting is completed and consolidated again, the locations of concentrated water outflow, fissure water outflow, and water-spraying areas on the well wall recorded in step S1 are re-measured point by point, and the leakage flow rate corresponding to each re-measured location is recorded as follows: The total leakage volume of the target water-sealing section is obtained by summing the leakage flow rates at all retest locations. : ; In the formula, This indicates the total leakage volume measured again in the target water-sealing section, expressed in cubic meters per hour. Indicates the first The leakage flow rate corresponding to each retest location is expressed in cubic meters per hour. This indicates the number of retest locations with measurable leakage flow rate. The results of the water sealing construction are generated by comparing the re-measurement status of each original leakage location with the allowable leakage status of the target water sealing section. The results of the water sealing construction should include at least the target water sealing section number, inspection location results, supplementary grouting location, re-measurement of total leakage, and construction judgment, for use in construction acceptance and subsequent well waterproofing status records.
[0049] For example, following the continuous wall sealing water body formed in step S6, after determining the consolidation waiting time based on the current dual-liquid slurry material test and the wellbore ambient temperature, inspection position J1 is set in the outer water interception area, inspection position J2 is set in the inner filling area, and inspection position J3 is set in the final sealing area at position A. The inspection record structure is backfilled. Under the grouting pressure check, no backflow occurred at J1, and the grouting volume can continue to be injected. If backflow occurs at J2, the injection volume of grout can continue to be [amount missing]. No backflow was observed in J3, so the grout injection volume can continue to be [amount missing]. ,get: ; ; In each quaternion, the first component represents the inspection location number, the second component represents the backflow status marker, the third component represents the amount of grout that can be injected further, in liters, and the fourth component represents the inspection grouting pressure, in megapascals. According to the grouting inspection standards for this project, J1 and J3 have relatively small amounts of grout that can be injected further and no backflow has occurred, therefore it is determined that there is no significant remaining injectable space in the corresponding areas requiring further treatment; J2 has backflow but can still be injected under the same inspection grouting pressure. Therefore, J2 was identified as the inspection location where there was remaining injectable space, and supplementary double-liquid grouting was performed on J2 until the inspection grouting pressure stabilized.
[0050] After the grouting and consolidation, areas A, B, C, and D in step S1 were re-tested. Area A did not regain its original concentrated water outflow; only localized seepage flow was measured. No continuous fissures were formed at locations B and C, so the corresponding leakage flow rate is recorded as 0; the residual water flow rate in area D is calculated as follows: At this point, the number of retest locations with measurable leakage flow rate is: According to the total leakage volume retested Fill in the calculation relationships: The maximum allowable leakage in the target water-sealing section of this project is determined based on the construction design. The comparison yields: Meanwhile, a stable and concentrated water outflow channel did not re-establish itself at location A, and continuous fissure water outflow did not resume at locations B and C. Therefore, the water sealing construction result was not achieved. Record the target water sealing section as the well depth. to The supplementary grouting location is J2, and the total leakage volume is re-measured. The construction assessment concluded that the target water sealing requirements were met.
[0051] Based on the same inventive concept, such as Figure 7 As shown, the present invention also provides a vertical shaft guide and cut-off combined wall-mounted dual-liquid grouting and water sealing system, the system comprising: The leakage parameter acquisition component is used to collect leakage location, leakage type, water flow rate, water pressure parameters and well wall quality status at different depths and circumferential positions of the vertical well wall; The controller is used to analyze the spatial continuity between the leakage locations and the correlation between the water flow rate to determine the target sealing section and the main seepage channel. The guide and interception execution component is used to guide and discharge water at the concentrated outlet position of the target water sealing section and to intercept the water spray area on the well wall, so that the water behind the wall is discharged through a determined water guiding path; the leakage parameter acquisition component is also used to acquire the water flow rate and water pressure parameters during the guide and discharge process, and the controller generates the basic state of the guide and interception based on the water flow rate and water pressure parameters during the guide and discharge process. The controller is also used to determine the arrangement of the back wall grouting holes based on the location of the main seepage channel, the guide and cut-off execution component and the well wall quality status, form an outer water interception hole group by forming the back wall grouting holes located outside the main seepage channel, and form an inner filling hole group by forming the back wall grouting holes located between the outer water interception hole group and the guide and cut-off execution component, thereby generating the arrangement result of the back wall grouting hole group. The dual-liquid grouting assembly is used to inject cement-water glass dual-liquid grout into the well wall through the peripheral water-cutting hole group when the guide-cutting execution assembly is in a water-guiding state. The controller correlates the peripheral grouting pressure with the concurrent water-guiding flow rate according to the time correspondence to generate a peripheral pressure-guiding response. When the water-guiding flow rate continuously decreases relative to the guide-cutting foundation state and the peripheral grouting pressure continuously increases, it is determined that the peripheral water-cutting state has been reached. The dual-liquid grouting assembly is also used to perform dual-liquid grouting towards the main seepage channel through the inner filling hole group after the peripheral water-cutting state has been reached. The controller correlates the inner grouting pressure with the concurrent water-guiding flow rate to generate an inner pressure-guiding response. When the water-guiding flow rate decreases to the final sealing flow rate range determined according to the sealing target and the inner grouting pressure tends to stabilize, it is determined that the inner filling state has been reached. The channel switching component is used to close the drainage path of the intercepting execution component after the inner filling state is reached, and to connect the intercepting execution component with the dual-liquid grouting path of the dual-liquid grouting component; the dual-liquid grouting component injects cement-water glass dual-liquid grout into the remaining seepage channel corresponding to the original water guiding position through the intercepting execution component, so that the outer water interception area, the inner filling area and the final sealing area corresponding to the original water guiding position are connected to each other to form a continuous wall post-sealing water body; The dual-liquid grouting assembly is also used to perform inspection grouting on the target water sealing section after the water sealing body behind the continuous wall has solidified. The leakage parameter acquisition assembly is also used to re-measure the water leakage status of the well wall. The controller generates water sealing construction results based on the inspection grouting results and the re-measured water leakage status of the well wall.
[0052] All equivalent changes and modifications made in accordance with the teachings of this invention are still within the scope of this invention. Those skilled in the art will readily conceive of other embodiments of this invention upon considering the specification and the disclosure of practical truth. This application is intended to cover any variations, uses, or adaptations of this invention that follow the general principles of this invention and include common knowledge or conventional techniques in the art not described herein.
Claims
1. A method for vertical shaft guide and cut-off combined with wall-mounted dual-liquid grouting and water sealing, characterized in that, The method includes: The leakage location, leakage form, water flow rate, water pressure parameters and well wall quality status at different depths and circumferential positions of the vertical shaft were collected. The spatial continuity relationship between leakage locations and the correlation of water flow rate were analyzed to determine the target water sealing section and the main seepage channel. A drainage component is installed at the concentrated water outlet of the target water sealing section, and the water spray area on the well wall is intercepted so that the water behind the wall is discharged through a determined drainage path. The drainage flow rate and water pressure parameters are collected during the drainage process to generate the basic state of the drainage system. Based on the location of the main seepage channel, the guide assembly, and the well wall quality condition, the arrangement of the back wall grouting holes is determined. The back wall grouting holes located around the main seepage channel are formed into an outer water interception hole group, and the back wall grouting holes located between the outer water interception hole group and the guide assembly are formed into an inner filling hole group, thus generating the arrangement result of the back wall grouting hole group. Keep the drainage assembly in the water-guiding state, inject cement-water glass dual-liquid slurry into the well wall through the peripheral water-cutting hole group, and correlate the peripheral grouting pressure with the water flow rate at the same time according to the time correspondence to generate the peripheral pressure-guiding response. When the water flow rate continues to decrease relative to the basic state of the drainage foundation and the peripheral grouting pressure continues to increase, it is determined that the peripheral water-cutting state has been reached. After the outer water interception state is reached, double-liquid grouting is carried out towards the main seepage channel through the inner filling hole group. The inner grouting pressure is correlated with the water flow rate at the same time to generate an inner pressure-flow response. When the water flow rate drops to the final sealing flow rate range determined according to the water sealing target and the inner grouting pressure tends to stabilize, the inner filling state is determined to be reached. After the inner filling state is reached, the drainage path of the guide assembly is closed, the guide assembly is connected to the dual-liquid grouting path, and cement-water glass dual-liquid grout is injected into the remaining seepage channel corresponding to the original water guiding position through the guide assembly, so that the outer water interception area, the inner filling area and the final sealing area corresponding to the original water guiding position are connected to each other to form a continuous wall post-sealing water body; After the water-sealing body behind the continuous wall has solidified, the target water-sealing section is inspected by grouting and the leakage status of the well wall is re-measured. The water-sealing construction results are generated based on the inspection grouting results and the re-measured leakage status.
2. The method for vertical shaft guide and cut-off combined with wall-mounted dual-liquid grouting and water sealing according to claim 1, characterized in that, The method involves collecting data on leakage locations, leakage patterns, water flow rates, water pressure parameters, and well wall quality at different depths and circumferential positions on the well wall. Analysis of the spatial continuity and water flow rate correlations between leakage locations is conducted to determine the target sealing zone and the dominant seepage channel, including: Establish a well wall deployment position reference according to the depth direction of the vertical well and the circumferential position of the well wall. Map the concentrated water outlet position, the fissure water outlet position and the water spraying area of the well wall to the well wall deployment position reference to obtain the distribution of well wall leakage positions. The water flow rate, water pressure parameters and well wall quality status corresponding to each well wall leakage location are configured to the corresponding well wall unfolding position to form a well wall leakage status distribution. The distribution of well wall leakage status is correlated regionally based on the degree of spatial connectivity between adjacent well wall leakage locations, and the leakage extension direction is determined based on the continuous change of water flow rate with location within the correlated region. The target water sealing section is determined based on the leakage extension direction, water flow distribution, and water pressure distribution, and the leakage area that connects the centralized water outlet and is continuously distributed along the leakage extension direction is determined as the dominant seepage channel.
3. The method for vertical shaft guide and cut-off combined with wall-mounted dual-liquid grouting and water sealing according to claim 2, characterized in that, The process involves installing a drainage component at the concentrated outlet location of the target water-sealing section and intercepting the water spray area on the well wall, allowing the water behind the wall to be discharged through a determined drainage path. The drainage flow rate and water pressure parameters are collected during the drainage process to generate the basic state of the drainage system, including: A water guiding channel communicating with the seepage space behind the wall is set at the centralized water outlet position so that the centralized seepage water is discharged to the water collection position through the water guiding channel. An interception channel is set along the water spraying area of the well wall to guide the water spraying on the well wall surface to the water collection position, so that the concentrated water and the water spraying on the well wall are discharged along the corresponding drainage paths respectively. While keeping the water guiding channel connected, the water guiding flow rate and corresponding water pressure parameters are collected, and the water guiding flow rate and water pressure parameters are correlated according to a unified time reference. Based on the corresponding water flow rate and water pressure parameters, a guide foundation state characterizing the water release state of the main body before grouting is generated.
4. The method for vertical shaft guide and cut-off combined with wall-mounted dual-liquid grouting and water sealing according to claim 3, characterized in that, The process of determining the arrangement of backfill grouting holes based on the location of the main seepage channel, the guide assembly, and the wellbore quality condition, and generating the arrangement result of the backfill grouting hole group, includes: The grouting coverage area is determined based on the extension range of the main seepage channel in the wellbore deployment location reference. Multiple wall-mounted grouting holes are arranged along the periphery of the grouting coverage area, so that the multiple wall-mounted grouting holes form an enclosing relationship along the circumferential periphery and depth direction of the main seepage channel, thus obtaining a peripheral water interception hole group; Multiple wall-mounted grouting holes facing the main seepage channel are arranged between the outer water interception hole group and the guide assembly to obtain an inner filling hole group; The spatial relationship between the outer intercepting hole group and the inner filling hole group is adjusted according to the well wall quality condition, so that the slurry diffusion area corresponding to the outer intercepting hole group is located outside the slurry diffusion area corresponding to the inner filling hole group, and the slurry diffusion direction corresponding to the inner filling hole group is oriented towards the concentrated water outlet position corresponding to the guide and discharge assembly.
5. The method for vertical shaft guide and cut-off combined with wall-mounted dual-liquid grouting and water sealing according to claim 4, characterized in that, Maintaining the guide assembly in a water-guiding state, and injecting cement-water glass dual-liquid slurry into the well wall through the peripheral water-cutting hole group to generate a peripheral pressure-guiding response and determine that the peripheral water-cutting state has been reached, includes: Maintain the connection between the drainage assembly and the water collection location so that the water behind the wall in the main seepage channel is continuously discharged during the external double-liquid grouting process; Double-liquid grouting is carried out sequentially according to the spatial arrangement of the peripheral intercepting holes along the periphery of the main seepage channel, and the peripheral grouting pressure and the water flow rate corresponding to the guide assembly at each grouting position are recorded simultaneously. The peripheral grouting pressure and the concurrent water flow rate are correlated according to a continuous observation time window to determine the changing trend of the peripheral grouting pressure and the attenuation trend of the water flow rate relative to the state of the guide foundation, thereby generating a peripheral pressure-flow response. When the peripheral grouting pressure continues to increase and the water flow rate continues to decrease within the continuous observation time window, it is determined that the peripheral grout diffusion area has formed a peripheral constraint on the dominant seepage channel, generating a peripheral water interception state.
6. The method for vertical shaft guide and cut-off combined with wall-mounted dual-liquid grouting and water sealing according to claim 5, characterized in that, The process of performing two-liquid grouting through the inner filling hole group toward the main seepage channel to generate an inner pressure-conduction response and determine that the inner filling state has been reached includes: While maintaining the peripheral grout diffusion area as a constraint on the main seepage channel, double-liquid grouting is carried out sequentially from the periphery to the corresponding concentrated water outlet position of the guide and discharge assembly according to the direction of the inner filling hole group. The inner grouting pressure corresponding to the inner filling hole group and the water flow rate corresponding to the guide and discharge assembly are recorded simultaneously, and the inner pressure-flow response is generated according to the continuous observation time window. The degree of change of the inner grouting pressure between adjacent consecutive observation time windows and the degree of residual water flow relative to the outer water interception state are determined based on the inner pressure-flow response. When the variation of the inner grouting pressure tends to converge between continuous observation time windows, and the water flow rate decreases to the final sealing flow rate range determined according to the allowable leakage state of the target sealing section, the inner filling state is generated.
7. The method for vertical shaft guide and cut-off combined with wall-mounted dual-liquid grouting and water sealing according to claim 6, characterized in that, After reaching the inner filling state, the drainage path of the guide assembly is closed, the guide assembly is connected to the dual-liquid grouting path, and cement-water glass dual-liquid grout is injected into the remaining seepage channel corresponding to the original water guiding position through the guide assembly, including: The final seal transition state when the water flow rate enters the final seal flow range is determined based on the internal pressure-flow response. In response to the final sealing transition state, the drainage path between the guide assembly and the water collection location is closed, and the guide assembly is connected to the dual-liquid grouting path, so that the guide assembly is converted from a water discharge channel behind the wall to a dual-liquid grout input channel; After conversion, the guide and discharge assembly performs dual-liquid grouting into the remaining seepage channel corresponding to the original centralized water outlet position, so that the dual-liquid grout diffuses from the original water guiding position to the inner filling area; Based on the changes in grouting pressure during the final sealing process, the remaining seepage channels corresponding to the original concentrated water outlet position are determined to be blocked, so that the final sealing area is connected with the inner filling area and the outer intercepting area to form a continuous wall back sealing body.
8. The method for vertical shaft guide and cut-off combined with wall-mounted dual-liquid grouting and water sealing according to claim 7, characterized in that, The process of inspecting and grouting the target water-sealing section and re-measuring the well wall leakage status, and generating water-sealing construction results based on the inspection and grouting results and the re-measuring leakage status, includes: After the continuous wall back seal water body reaches the solidification state, the outer water interception area, the inner filling area and the final sealing area are inspected along the target water sealing section; The locations with remaining injectable space are determined based on the backflow status of each inspection location, the amount of grout that can be injected, and the grouting pressure. For inspection locations with remaining injectable space, supplementary double-liquid grouting is carried out, and after the supplementary double-liquid grouting is completed, the concentrated water outflow status, well wall water spray status, and well barrel leakage status of the target water sealing section are re-measured; The water leakage status of the re-measured well wall is compared with the allowable water leakage status corresponding to the target water sealing section to generate the water sealing construction result.
9. A method for sealing water by combined vertical shaft guide and cut-off with post-wall dual-liquid grouting, as described in claim 8, is characterized in that... The cement-water glass dual-liquid grout and the grouting parameters for each grouting stage are determined based on the water pressure parameters, the wellbore quality condition, and the water flow rate, including: The reference grouting pressure for each grouting stage is determined based on the water pressure parameters of the target water sealing section, and the reference grouting pressure is limited based on the well wall quality condition to obtain the allowable grouting pressure range for the corresponding grouting stage. The concentration of cement slurry and the mixing ratio of cement slurry and water glass in the peripheral water interception stage are determined based on the peripheral pressure-flow response, so that the slurry diffusion process corresponds to the process of the peripheral water interception hole group forming peripheral constraints. The cement slurry concentration and the mixing ratio of cement slurry and water glass in the inner filling stage are determined based on the inner pressure-conduction response, so that the slurry diffusion process corresponds to the filling process of the remaining space of the main seepage channel. The grouting pressure change during the final sealing process at the original centralized water outlet location and the inner filling state are used to determine the dual-liquid grout injection state during the final sealing stage, and grouting is stopped after the final sealing area and the inner filling area reach a connected and sealed state.
10. A vertical shaft guide and interception combined with a wall-mounted dual-liquid grouting and water sealing system, characterized in that, The system includes; The leakage parameter acquisition component is used to collect leakage location, leakage type, water flow rate, water pressure parameters and well wall quality status at different depths and circumferential positions of the vertical well wall; The controller is used to analyze the spatial continuity between the leakage locations and the correlation between the water flow rate to determine the target sealing section and the main seepage channel. The guide and interception execution component is used to guide and discharge water at the concentrated outlet position of the target water sealing section and to intercept the water spray area on the well wall, so that the water behind the wall is discharged through a determined water guiding path; the leakage parameter acquisition component is also used to acquire the water flow rate and water pressure parameters during the guide and discharge process, and the controller generates the basic state of the guide and interception based on the water flow rate and water pressure parameters during the guide and discharge process. The controller is also used to determine the arrangement of the back wall grouting holes based on the location of the main seepage channel, the guide and cut-off execution component and the well wall quality status, form an outer water interception hole group by forming the back wall grouting holes located outside the main seepage channel, and form an inner filling hole group by forming the back wall grouting holes located between the outer water interception hole group and the guide and cut-off execution component, thereby generating the arrangement result of the back wall grouting hole group. The dual-liquid grouting assembly is used to inject cement-water glass dual-liquid grout into the well wall through the peripheral water-cutting hole group when the guide-cutting execution assembly is in a water-guiding state. The controller correlates the peripheral grouting pressure with the concurrent water-guiding flow rate according to the time correspondence to generate a peripheral pressure-guiding response. When the water-guiding flow rate continuously decreases relative to the guide-cutting foundation state and the peripheral grouting pressure continuously increases, it is determined that the peripheral water-cutting state has been reached. The dual-liquid grouting assembly is also used to perform dual-liquid grouting towards the main seepage channel through the inner filling hole group after the peripheral water-cutting state has been reached. The controller correlates the inner grouting pressure with the concurrent water-guiding flow rate to generate an inner pressure-guiding response. When the water-guiding flow rate decreases to the final sealing flow rate range determined according to the sealing target and the inner grouting pressure tends to stabilize, it is determined that the inner filling state has been reached. The channel switching component is used to close the drainage path of the intercepting execution component after the inner filling state is reached, and to connect the intercepting execution component with the dual-liquid grouting path of the dual-liquid grouting component; the dual-liquid grouting component injects cement-water glass dual-liquid grout into the remaining seepage channel corresponding to the original water guiding position through the intercepting execution component, so that the outer water interception area, the inner filling area and the final sealing area corresponding to the original water guiding position are connected to each other to form a continuous wall post-sealing water body; The dual-liquid grouting assembly is also used to perform inspection grouting on the target water sealing section after the water sealing body behind the continuous wall has solidified. The leakage parameter acquisition assembly is also used to re-measure the water leakage status of the well wall. The controller generates water sealing construction results based on the inspection grouting results and the re-measured water leakage status of the well wall.