Pipe jacking construction grouting control method, device, equipment and storage medium
By introducing elastic polymer particles into pipe jacking construction and adjusting the particle size distribution and dosage according to the geological characteristics, a lubricating and sealing layer is formed, which solves the problems of leakage and insufficient drag reduction of traditional thixotropic mud under complex geological conditions, and improves the stability and efficiency of the construction process.
Patent Information
- Application Number
- CN202611145197.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-30
- Publication Date
- 2026-11-10
Smart Images

Figure CN123064483A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of pipe jacking construction technology, and in particular to a method, device, equipment and storage medium for controlling grouting during pipe jacking construction. Background Technology
[0002] Pipe jacking is a trenchless underground pipeline construction technology widely used in urban underground pipe networks, water supply and drainage projects, integrated pipe corridors, and long-distance water and gas transmission projects. During pipe jacking, as the jacking distance increases, the frictional resistance between the outer wall of the pipe section and the surrounding soil gradually accumulates, leading to a continuous increase in jacking resistance, which can sometimes exceed the rated capacity of the jacking equipment. Therefore, it is usually necessary to inject thixotropic mud between the outer wall of the pipe section and the soil, changing the direct contact friction between the pipe and the soil to a mud-lubricated state, thereby reducing the pipe wall frictional resistance and improving the jacking efficiency.
[0003] The thixotropic drilling mud used in existing pipe jacking construction typically consists of bentonite, sodium carboxymethyl cellulose, and soda ash as its main components. Through its viscosity, lubricity, and thixotropic properties, the mud forms a mud sheath around the pipe section to reduce drag and stabilize the formation. However, in long-distance pipe jacking construction, especially under complex geological conditions such as weathered rock layers, sand layers, gravel layers, and fractured strata, the complex pore structure of the formation, irregular over-excavation gaps, and significant groundwater seepage cause traditional thixotropic drilling mud to easily diffuse and run off along the pores or fractures of the formation. This leads to a reduction in the thickness of the mud sheath around the pipe section or even its failure, causing the outer wall of the pipe section to re-contact the formation, resulting in a rapid increase in jacking resistance.
[0004] To address the aforementioned issues, existing technologies typically employ methods such as increasing mud viscosity, increasing grouting volume, or increasing replenishment frequency. However, increasing mud viscosity leads to a decrease in mud flowability and increases the conveying pressure of the grouting equipment; while increasing the grouting volume can temporarily compensate for mud loss, it cannot actively seal leakage channels in the formation and results in material waste; furthermore, existing thixotropic muds are usually applied with a fixed mix ratio, failing to fully consider the differences in geological formations in different construction sections, making it difficult to adapt to different geological conditions such as weathered rock layers, sand layers, and low-permeability soil layers.
[0005] Furthermore, existing drag-reducing grouting technologies primarily rely on the fluid lubrication of grout, which has a relatively limited function. Once the grout enters formation pores or fractures, it lacks active sealing and self-repair capabilities, failing to effectively maintain a long-term stable grout sleeve structure. Especially during long-distance pipe jacking construction, the cumulative effect of grout leakage becomes more pronounced as the jacking distance increases, easily leading to problems such as difficulty in restarting jacking after a shutdown and abnormally high jacking force.
[0006] In summary, the problems existing in the current technology urgently need to be solved. Summary of the Invention
[0007] This invention provides a grouting control method, device, equipment, and storage medium for pipe jacking construction, which addresses the deficiencies in the prior art and improves the mud sleeve retention capacity and drag reduction effect in long-distance pipe jacking construction.
[0008] This invention provides a method for controlling grouting during pipe jacking construction, comprising: Obtain the geological characteristic parameters of the area to be constructed; The particle size distribution parameters and dosage parameters of the elastic polymer particles are determined based on the formation characteristic parameters. A thixotropic slurry composition of elastic polymer particles was prepared according to the particle size distribution parameters and dosage parameters. The elastic polymer particle-reinforced thixotropic mud composition is injected into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section to form a lubricating sealing layer; The elastic polymer particle thixotropic mud composition includes a thixotropic mud base liquid and elastic polymer particles dispersed in the thixotropic mud base liquid.
[0009] According to the grouting control method for pipe jacking construction provided by the present invention, the step of determining the particle size distribution parameters and dosage parameters of the elastic polymer particles based on the formation characteristic parameters specifically includes: Based on the aforementioned formation characteristic parameters, obtain the formation porosity characteristic parameters and / or fracture characteristic parameters of the target construction section; Based on the formation pore characteristic parameters and / or fracture characteristic parameters, establish the particle size matching relationship between the elastic polymer particles and the target formation; The proportion of different particle size grades in the elastic polymer particles is determined based on the particle size matching relationship, and the amount of elastic polymer particles to be added is determined based on the permeability characteristics of the target construction section.
[0010] According to the grouting control method for pipe jacking construction provided by the present invention, the step of establishing the particle size matching relationship between the elastic polymer particles and the target formation based on the formation pore characteristic parameters and / or fracture characteristic parameters specifically includes: Based on the pore size parameters and / or crack size parameters of the target construction section, determine the bridging particle size range corresponding to the coarse particles in the elastic polymer particles; Based on the particle size range of the coarse particles, the particle size ranges corresponding to the medium and fine particles are determined according to the stepwise filling relationship. The coarse-grained particles are used to form bridging structures at the entrances of formation pores or fractures, the medium-grained particles are used to fill the internal gaps of the bridging structures, and the fine-grained particles are used to block micropore channels.
[0011] According to the present invention, the grouting control method for pipe jacking construction includes at least one of elastic polyurethane microspheres, cross-linked polyacrylamide microspheres, natural rubber microspheres, and silicone rubber microspheres, and the mass ratio of the coarse particles, the medium particles, and the fine particles is (35-50): (30-40): (15-25).
[0012] According to the grouting control method for pipe jacking construction provided by the present invention, the step of preparing an elastic polymer particle thixotropic mud composition based on the particle size distribution parameters and dosage parameters specifically includes: Preparation of thixotropic mud base liquid; Elastic polymer particles of different particle sizes are mixed according to the particle size distribution parameters to obtain an elastic particle mixture; The elastic particle mixture is added to a dispersion medium for pre-dispersion treatment to obtain an elastic particle pre-dispersion liquid. The elastic particle pre-dispersion liquid is added to the thixotropic mud base liquid and stirred to uniformly disperse the elastic polymer particles in the thixotropic mud base liquid.
[0013] According to the present invention, a grouting control method for pipe jacking construction includes the step of injecting the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the pipe section and the stratum according to the corresponding construction section, specifically comprising: The construction area is divided into multiple grouting control zones along the jacking direction; For different formation types corresponding to different grouting control sections, the particle content and grouting pressure in the elastic polymer particle thixotropic mud composition are adjusted.
[0014] According to the present invention, a grouting control method for pipe jacking construction, after the step of injecting the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the pipe section and the stratum according to the corresponding construction section, further includes: By monitoring the jacking force, pipe circumferential friction, and grouting pressure during the pipe jacking construction process, the dosage parameters of the elastic polymer particles and the grouting pressure are dynamically adjusted. When the detected pipe circumferential friction exceeds the preset threshold, the amount of elastic polymer particles in the subsequent construction section is increased. When a continuous drop in grouting pressure is detected, the proportion of coarse particles is increased to enhance the bridging and sealing capacity of the leakage channels.
[0015] The present invention also provides a grouting control device for pipe jacking construction, comprising: The parameter acquisition module is used to acquire the geological characteristic parameters of the area to be constructed. The parameter determination module is used to determine the particle size distribution parameters and dosage parameters of the elastic polymer particles based on the formation characteristic parameters. The mixture preparation module is used to prepare an elastic polymer particle thixotropic slurry composition according to the particle size distribution parameters and dosage parameters. The mixture injection module is used to inject the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section, so as to form a lubricating sealing layer; The elastic polymer particle thixotropic mud composition includes a thixotropic mud base liquid and elastic polymer particles dispersed in the thixotropic mud base liquid.
[0016] The present invention also provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement the grouting control method for pipe jacking construction as described above.
[0017] The present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the grouting control method for pipe jacking construction as described above.
[0018] The present invention also provides a computer program product, including a computer program that, when executed by a processor, implements the grouting control method for pipe jacking construction as described above.
[0019] The grouting control method, apparatus, equipment, and storage medium for pipe jacking construction provided by this invention introduces elastic polymer particles into a thixotropic mud base fluid, enabling the formed grouting system to simultaneously possess lubrication, drag reduction, and leakage sealing functions. Compared to the traditional method of relying solely on mud viscosity to maintain the mud sleeve, the elastic polymer particles can enter the annular gap between the outer wall of the pipe section and the formation along with the mud, and form auxiliary support structures at formation pores or fractures, improving the integrity and stability of the mud sleeve, thereby reducing the problem of increased jacking resistance caused by mud loss during long-distance pipe jacking construction.
[0020] This invention determines the particle size distribution and dosage parameters of elastic polymer particles based on the geological characteristics of the area to be grouted, enabling the elastic polymer particles to match the pore or fracture structure of the target formation and achieving adaptive configuration for different geological conditions. Compared to existing fixed-ratio grouting methods, this invention can adjust the particle composition according to the formation's permeability, pore size, and fracture development level, improving the grouting system's adaptability to complex formations.
[0021] This invention establishes a particle size matching relationship between elastic polymer particles and the target formation, and determines the proportional relationship between particles of different size grades based on this matching relationship, enabling elastic polymer particles of different size grades to exert a synergistic effect. Specifically, larger-sized particles preferentially form bridging structures at the entrances of pores or fractures, medium-sized particles fill the gaps within the bridging structures, and smaller-sized particles further seal micro-leakage channels, thereby improving the compactness and stability of the sealing layer.
[0022] This invention mixes elastic polymer particles according to a preset particle size distribution, and adds them to the thixotropic mud base liquid after pre-dispersion treatment. This allows the elastic polymer particles to be uniformly dispersed in the mud system, avoiding particle agglomeration or sedimentation, improving the transport stability of the elastic polymer particles during the grouting process, and enabling them to reach the target area uniformly with the mud and play a sealing role.
[0023] This invention divides the construction area into multiple grouting control sections along the jacking direction, and adjusts the dosage of elastic polymer particles and grouting pressure according to the stratum type corresponding to different grouting control sections, so that the grouting parameters can match the actual stratum conditions, realizing the transformation from traditional fixed parameter grouting to segmented differentiated grouting control, and improving the accuracy and effectiveness of grouting construction.
[0024] This invention further monitors the jacking force, pipe friction resistance, and grouting pressure during pipe jacking construction to dynamically adjust the elastic polymer particle dosage and grouting pressure. When an abnormal increase in pipe friction resistance or a continuous decrease in grouting pressure is detected, the particle dosage can be adjusted in a timely manner or the proportion of coarse particles can be increased to enhance the sealing ability of leakage channels, achieve dynamic optimization control of the grouting process, and improve the stability and reliability of long-distance pipe jacking construction.
[0025] In summary, this invention combines formation feature identification, elastic polymer particle gradation design, preparation of thixotropic mud composition of elastic polymer particles, and segmented grouting control to achieve adaptive matching between grouting materials and the construction environment. This improves the retention capacity and drag reduction effect of mud sleeves under complex formation conditions and effectively solves the problems of easy leakage, insufficient drag reduction continuity, and difficulty in adapting to complex formation changes in traditional thixotropic mud during long-distance pipe jacking construction. Attached Figure Description
[0026] To more clearly illustrate the technical solutions in this invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of this invention. For those skilled in the art, other drawings can be obtained from these drawings without creative effort.
[0027] Figure 1 This is a flowchart illustrating the grouting control method for pipe jacking construction provided by the present invention; Figure 2 This is a schematic diagram of the grouting control device for pipe jacking construction provided by the present invention; Figure 3 This is a schematic diagram of the structure of the electronic device provided by the present invention. Detailed Implementation
[0028] To make the objectives, technical solutions, and advantages of this invention clearer, the technical solutions of this invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this invention. All other embodiments obtained by those skilled in the art based on the embodiments of this invention without creative effort are within the scope of protection of this invention.
[0029] To address the problems in existing technologies, this invention proposes a grouting control method for pipe jacking construction to improve the mud sleeve retention capacity and drag reduction effect during long-distance pipe jacking construction. The grouting control method for pipe jacking construction is described below, as follows: Figure 1 As shown, including but not limited to the following steps: Step 110: Obtain the geological feature parameters of the area to be constructed.
[0030] In step 110, before the pipe jacking construction, geological information of the construction area is collected to obtain geological characteristic parameters that characterize the geological conditions of the construction area.
[0031] The geological characteristic parameters are used to reflect the structural characteristics, permeability, and related information affecting the grouting effect of the strata surrounding the pipe section during pipe jacking construction. Specifically, these geological characteristic parameters can be obtained through geological survey data, field testing data, and experimental analysis data.
[0032] For example, information on the corresponding stratum type, stratum distribution, and basic parameters of the soil or rock mass can be obtained through geological survey reports of the construction area; information on the internal structural characteristics of the stratum can be obtained through on-site sampling and testing; and parameter information that reflects the seepage characteristics of the stratum can be obtained through permeability tests, pore analysis tests, or fracture detection methods.
[0033] After obtaining the geological feature parameters, geological condition analysis is performed on the construction area based on the geological feature parameters to determine the geological adaptability information corresponding to different construction sections, providing a data basis for subsequent configuration of elastic polymer particle parameters.
[0034] Step 120: Determine the particle size distribution parameters and dosage parameters of the elastic polymer particles based on the formation characteristic parameters.
[0035] In step 120, the composition parameters of the elastic polymer particles are determined based on the geological characteristic parameters of the area to be constructed obtained in step 110, so that the elastic polymer particles can adapt to the geological environment of the corresponding construction section.
[0036] Specifically, based on the formation characteristic parameters, the formation permeability, structural stability, and mud loss risk of different construction sections are analyzed, and the particle size distribution parameters and dosage parameters of the elastic polymer particles are determined based on the analysis results.
[0037] The particle size distribution parameter is used to characterize the composition ratio of particles of different sizes in the elastic polymer particles, and the dosage parameter is used to characterize the addition ratio of elastic polymer particles in the thixotropic mud base liquid.
[0038] When determining the above parameters, the configuration ratio of elastic polymer particles can be adjusted according to the geological characteristics of the construction section, so that the elastic polymer particles can enter the annular gap between the outer wall of the jacking pipe section and the stratum along with the thixotropic mud during the subsequent grouting process, and play a filling role in the pore or fracture area of the stratum, thereby improving the stability of the grouting structure.
[0039] By configuring the elastic polymer particle parameters according to the geological characteristics, the grouting material can be adapted to different construction environments, avoiding the unstable grouting effect caused by using a fixed ratio.
[0040] Step 130: Prepare an elastic polymer particle thixotropic mud composition according to the particle size distribution parameters and dosage parameters.
[0041] In step 130, based on the particle size distribution parameters and dosage parameters of the elastic polymer particles determined in step 120, the elastic polymer particles are combined with the thixotropic mud base liquid to prepare an elastic polymer particle thixotropic mud composition for grouting in pipe jacking construction.
[0042] Specifically, the first step is to prepare a thixotropic mud base liquid that meets the requirements of pipe jacking construction. The thixotropic mud base liquid can be a mud system containing bentonite, thickening components and conditioning components. By mixing and stirring the components, a base slurry with a certain viscosity and thixotropic properties is formed.
[0043] Subsequently, the elastic polymer particles are configured according to the particle size distribution parameters determined in step 120, and the elastic polymer particles are added to the thixotropic mud base liquid according to the dosage parameters.
[0044] During the addition process, the elastic polymer particles are uniformly dispersed in the thixotropic mud base liquid through stirring and mixing, avoiding significant agglomeration or sedimentation of the elastic polymer particles, thereby forming an elastic polymer particle thixotropic mud composition containing the thixotropic mud base liquid and the elastic polymer particles.
[0045] The elastic polymer particles have a certain elastic deformation capacity, which can be transported with the thixotropic mud base liquid during the grouting process, and can undergo adaptive deformation when subjected to formation constraints or pressure changes, thereby improving the adaptability of the grouting material to complex formation environments.
[0046] Step 140: Inject the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section to form a lubricating sealing layer; The elastic polymer particle thixotropic mud composition includes a thixotropic mud base liquid and elastic polymer particles dispersed in the thixotropic mud base liquid.
[0047] In step 140, the elastic polymer particle thixotropic mud composition prepared in step 130 is transported to the pipe jacking construction grouting system, and the composition is injected into the annular gap formed between the outer wall of the pipe section and the surrounding strata according to the construction requirements of the corresponding construction section.
[0048] Specifically, during the pipe jacking process, the elastic polymer particle thixotropic mud composition is transported to the target grouting location through grouting channels set on the pipe section or external grouting equipment, so that it diffuses between the outer wall of the pipe section and the stratum and gradually covers the outer periphery of the pipe section.
[0049] The injected thixotropic mud composition of elastic polymer particles forms a lubricating and sealing layer within the annular gap. The thixotropic mud base fluid reduces friction between the outer wall of the pipe section and the formation while maintaining the flow and transport performance of the grouting system. The elastic polymer particles enhance the structural stability of the grouting layer and fill local voids in the annular gap, thereby improving the integrity of the lubricating and sealing layer.
[0050] Through the above methods, a composite grouting layer with lubricating and sealing functions is formed during pipe jacking construction, reducing the resistance during pipe section jacking and improving the stability of the grouting resistance reduction effect during long-distance pipe jacking construction.
[0051] As a further optional embodiment, the step of determining the particle size distribution parameters and dosing parameters of the elastic polymer particles based on the formation characteristic parameters specifically includes: Based on the aforementioned formation characteristic parameters, obtain the formation porosity characteristic parameters and / or fracture characteristic parameters of the target construction section; Based on the formation pore characteristic parameters and / or fracture characteristic parameters, establish the particle size matching relationship between the elastic polymer particles and the target formation; The proportion of different particle size grades in the elastic polymer particles is determined based on the particle size matching relationship, and the amount of elastic polymer particles to be added is determined based on the permeability characteristics of the target construction section.
[0052] In this embodiment, by combining the geological structure characteristics and permeability of the area to be constructed, the particle size composition and addition ratio of the elastic polymer particles are designed in a targeted manner, so that the prepared elastic polymer particle thixotropic mud composition can be adapted to the grouting requirements under different geological conditions.
[0053] Specifically, firstly, based on the aforementioned formation characteristic parameters, the formation porosity characteristic parameters and / or fracture characteristic parameters of the target construction section are obtained. The formation porosity characteristic parameters characterize the internal pore structure of the soil and may include parameters such as average pore size, pore distribution range, porosity, and permeability coefficient. The fracture characteristic parameters characterize the development of fractures within the rock mass and may include parameters such as fracture width, fracture spacing, and fracture connectivity.
[0054] In practice, pore structure and fracture structure information corresponding to the target construction section can be obtained based on geological survey data, on-site sampling and testing results, or stratum detection equipment. For example, for porous strata such as sand or gravel layers, the average pore size of the strata can be obtained through stratum permeability tests, particle size distribution analysis, or porosity testing; for fractured strata such as weathered rock layers or fractured rock layers, fracture width and distribution characteristics can be obtained through core analysis, borehole imaging detection, and other methods.
[0055] Furthermore, based on the obtained formation pore characteristic parameters and / or fracture characteristic parameters, a particle size matching relationship between the elastic polymer particles and the target formation is established.
[0056] Specifically, based on the pore size or fracture width of the formation in the target construction section, the migration state of elastic polymer particles during mud seepage and the sealing requirements are analyzed to determine the appropriate particle size range for the current formation conditions. When the target construction section has large pores or fractures, elastic polymer particles with larger particle sizes are required to enter the pore or fracture inlet area and create a blocking effect; when the target construction section has small pore channels, elastic polymer particles with smaller particle sizes are required to improve the filling capacity of small seepage channels.
[0057] By establishing a matching relationship between the particle size of elastic polymer particles and the pore size and fracture size of the formation, the elastic polymer particles can be adaptively configured according to the spatial structure of the formation, avoiding the problems of particles that are too small to effectively prevent mud loss or particles that are too large to enter the target sealing area.
[0058] Furthermore, the proportional relationship between particles of different particle size grades in the elastic polymer particles is determined according to the particle size matching relationship, and the amount of elastic polymer particles to be added is determined according to the permeability characteristics of the target construction section.
[0059] Specifically, based on the degree of pore or crack development in the target construction section, elastic polymer particles are configured in combinations of different particle size grades, and the proportions between different particle size grades are adjusted to allow them to work synergistically during grouting. Larger particle size grades of elastic polymer particles are used to improve the sealing ability of larger pores or cracks, while smaller particle size grades are used to enhance the filling effect on internal gaps and micro-leakage channels.
[0060] Simultaneously, the amount of elastic polymer particles added is determined based on the permeability characteristics of the target construction section. When the target construction section has high permeability and a significant risk of mud loss, the amount of elastic polymer particles added is increased to enhance the grouting system's ability to seal formation pores or fractures. When the target construction section has low permeability and the primary requirement is to reduce jacking resistance, the amount of elastic polymer particles added is reduced to maintain good flow and transport performance of the grouting system.
[0061] The above method enables adaptive determination of the particle size distribution parameters and dosage parameters of elastic polymer particles according to different formation conditions. This allows the thixotropic mud composition of elastic polymer particles prepared subsequently to balance lubrication and drag reduction performance with formation sealing stability, thereby improving the reliability of grouting effect in pipe jacking construction under complex formation conditions.
[0062] As a further optional embodiment, the step of establishing the particle size matching relationship between the elastic polymer particles and the target formation based on the formation porosity characteristic parameters and / or fracture characteristic parameters specifically includes: Based on the pore size parameters and / or crack size parameters of the target construction section, determine the bridging particle size range corresponding to the coarse particles in the elastic polymer particles; Based on the particle size range of the coarse particles, the particle size ranges corresponding to the medium and fine particles are determined according to the stepwise filling relationship. The coarse-grained particles are used to form bridging structures at the entrances of formation pores or fractures, the medium-grained particles are used to fill the internal gaps of the bridging structures, and the fine-grained particles are used to block micropore channels.
[0063] In this embodiment, by acquiring the pore characteristic parameters and / or fracture characteristic parameters of the target construction section, a particle size matching relationship is established between the elastic polymer particles and the target formation structure, enabling the particle size distribution of the elastic polymer particles to adapt to the permeability channel characteristics under different formation conditions. Specifically, based on information such as formation pore size, fracture width, connectivity, and permeability parameters, the main channels that may lead to mud loss in the target construction section are analyzed, and the suitable particle size range of the elastic polymer particles is determined according to the pore characteristic parameters and / or fracture characteristic parameters.
[0064] Furthermore, based on the established particle size matching relationship, the proportional relationship between elastic polymer particles of different particle size grades is determined, so that the prepared elastic polymer particle thixotropic mud composition can form a continuous and stable particle-filled structure after injection into the formation. At the same time, the amount of elastic polymer particles added is determined according to the permeability characteristics of the target construction section, so that the elastic polymer particles maintain an appropriate distribution in the thixotropic mud base fluid and meet the lubrication, drag reduction, and plugging control requirements under different formation conditions.
[0065] By using the above method, the particle size distribution parameters and dosage parameters of the elastic polymer particles are determined specifically according to the actual formation conditions, avoiding the problem that the particles cannot effectively fill the formation channels or the grouting resistance increases due to the use of a fixed ratio, and improving the adaptability of the elastic polymer particle thixotropic mud composition to complex formation environments.
[0066] As a further optional embodiment, the elastic polymer particles include at least one of elastic polyurethane microspheres, cross-linked polyacrylamide microspheres, natural rubber microspheres, and silicone rubber microspheres, and the mass ratio of the coarse particles, the medium particles, and the fine particles is (35-50): (30-40): (15-25).
[0067] In this embodiment, the elastic polymer particles can be selected according to the geological conditions of the construction area and the grouting performance requirements, including at least one of elastic polyurethane microspheres, cross-linked polyacrylamide microspheres, natural rubber microspheres, and silicone rubber microspheres. The elastic polymer particles have a certain elastic deformation capacity, and can undergo adaptive deformation when subjected to geological constraint pressure or disturbance during pipe jacking construction, thereby improving the adhesion between the particles and the pores and fractures of the geological formation, and enhancing the stability of the grouting material in the gaps around the pipe wall.
[0068] Furthermore, based on different formation pore sizes and permeability characteristics, the elastic polymer particles are divided into coarse-grained, medium-grained, and fine-grained particles, and blended according to a preset mass ratio. The coarse-grained particles are primarily used to enter larger pores or fracture channels and form an initial bridging structure at the channel inlet to limit further seepage and diffusion of the slurry; the medium-grained particles are used to fill the gaps formed between the coarse-grained particles, improving the compactness of the particle packing structure; and the fine-grained particles are used to fill micropores, improving the continuity and integrity of the sealing layer.
[0069] Specifically, the mass ratio of the coarse-grained particles, the medium-grained particles, and the fine-grained particles can be set to (35-50):(30-40):(15-25). This gradation method allows elastic polymer particles of different particle sizes to form a multi-level filling structure in the thixotropic mud base fluid. While ensuring the slurry's flow and transport performance, it also improves the grouting material's adaptability to complex formation pore structures, thereby enhancing the formation effect of the lubrication and sealing layer between the outer wall of the pipe section and the formation during pipe jacking construction.
[0070] As a further optional embodiment, the step of preparing the elastic polymer particle thixotropic mud composition according to the particle size distribution parameters and dosage parameters specifically includes: Preparation of thixotropic mud base liquid; Elastic polymer particles of different particle sizes are mixed according to the particle size distribution parameters to obtain an elastic particle mixture; The elastic particle mixture is added to a dispersion medium for pre-dispersion treatment to obtain an elastic particle pre-dispersion liquid. The elastic particle pre-dispersion liquid is added to the thixotropic mud base liquid and stirred to uniformly disperse the elastic polymer particles in the thixotropic mud base liquid.
[0071] In this embodiment, by premixing and predispersing the elastic polymer particles, elastic polymer particles of different particle sizes can be distributed in the thixotropic mud base liquid with high uniformity, thereby avoiding the agglomeration, sedimentation or local enrichment of elastic particles during grouting, and improving the stability and construction adaptability of the formed grouting composition.
[0072] Specifically, a thixotropic mud base is first prepared according to construction requirements. This thixotropic mud base provides basic bonding, suspension, and lubrication properties, ensuring that the subsequently added elastic polymer particles remain stably dispersed. Then, elastic polymer particles of different particle sizes are mixed according to predetermined particle size distribution parameters, forming an elastic particle mixture in a target proportion.
[0073] Further, the elastic particle mixture is added to a dispersion medium for pre-dispersion treatment. Through stirring, shearing, or other dispersion methods, the surface of the elastic polymer particles is fully wetted, and the mutual aggregation between particles is reduced, resulting in an elastic particle pre-dispersion liquid with good flowability and dispersion stability. Finally, the elastic particle pre-dispersion liquid is added to the thixotropic mud base liquid and continuously stirred to allow the elastic polymer particles to be uniformly embedded within the thixotropic mud base liquid, forming an elastic polymer particle thixotropic mud composition.
[0074] Through the above preparation process, the dispersion uniformity of elastic polymer particles in thixotropic mud base liquid can be improved, enabling the composition to maintain stable rheological properties during the grouting process of pipe jacking construction. Furthermore, by utilizing the deformation recovery ability of elastic polymer particles and the lubrication properties of thixotropic mud, the filling effect of annular gaps and the continuity of the lubrication sealing layer can be improved.
[0075] As a further optional embodiment, the step of injecting the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section specifically includes: The construction area is divided into multiple grouting control zones along the jacking direction; For different formation types corresponding to different grouting control sections, the particle content and grouting pressure in the elastic polymer particle thixotropic mud composition are adjusted.
[0076] In this embodiment, by dividing the construction area into multiple grouting control sections along the jacking direction, zoned grouting control of the pipe jacking construction process under different geological conditions is achieved. Specifically, based on geological survey data of the construction area, geological changes, and construction feedback information during the jacking process, the jacking path can be divided into multiple corresponding grouting control sections, and the corresponding geological type and construction characteristics can be determined for each grouting control section.
[0077] Furthermore, the particle content and grouting pressure in the thixotropic mud composition of elastic polymer particles are adaptively adjusted according to the formation type corresponding to different grouting control sections. For example, for formations with high permeability and well-developed pore structure, the content of elastic polymer particles can be increased to enhance the filling and sealing ability of the grouting material after entering the formation pores and reduce grout loss; for formations with low permeability or small pores, the content of elastic polymer particles can be appropriately reduced and the grouting pressure adjusted to ensure that the grout can be uniformly diffused to the annular gap between the outer wall of the pipe section and the formation.
[0078] By using the above methods, a lubricating sealing layer that matches the corresponding geological conditions is formed in different construction sections. This reduces the frictional resistance between the outer wall of the pipe section and the surrounding soil, while improving the stability and anti-seepage sealing ability of the grouting layer, thus meeting the needs of long-distance pipe jacking construction under complex geological conditions.
[0079] As a further optional embodiment, after the step of injecting the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section, the method further includes: By monitoring the jacking force, pipe circumferential friction, and grouting pressure during the pipe jacking construction process, the dosage parameters of the elastic polymer particles and the grouting pressure are dynamically adjusted. When the detected pipe circumferential friction exceeds the preset threshold, the amount of elastic polymer particles in the subsequent construction section is increased. When a continuous drop in grouting pressure is detected, the proportion of coarse particles is increased to enhance the bridging and sealing capacity of the leakage channels.
[0080] In this embodiment, by real-time monitoring of key construction parameters during pipe jacking construction and dynamic adjustment of the dosage parameters of elastic polymer particles and grouting pressure based on the monitoring results, adaptive matching between the grouting control process and the actual construction state is achieved.
[0081] Specifically, during the pipe jacking process, monitoring devices installed on the pipe jacking equipment, grouting system, and surrounding area can acquire construction parameters such as jacking force, pipe friction resistance, and grouting pressure in real time. The jacking force reflects the pushing load required for the pipe jacking equipment to overcome soil resistance and the friction resistance of the outer wall of the pipe section. The pipe friction resistance characterizes the change in contact resistance between the pipe section and the surrounding strata. The grouting pressure reflects the diffusion state and sealing effect of the elastic polymer particle thixotropic mud composition within the annular gap between the outer wall of the pipe section and the strata.
[0082] Furthermore, by comparing and analyzing the construction parameters obtained from real-time monitoring with the preset control conditions, when the detected pipe circumferential frictional resistance exceeds the preset threshold, it indicates that the lubrication and resistance reduction effect between the outer wall of the pipe section and the stratum in the current construction section is reduced, or the stability of the grouting layer is insufficient. At this time, the amount of elastic polymer particles in the subsequent construction section is increased, so that the lubrication and sealing layer formed by injection has better filling capacity and bearing stability, thereby reducing the pipe circumferential frictional resistance.
[0083] Furthermore, when a continuous decrease in grouting pressure is detected, it indicates that the thixotropic mud composition of elastic polymer particles may be excessively diffused into formation pores or fractures during the injection process. In this case, by increasing the proportion of coarse-grained elastic polymer particles, larger-diameter particles can preferentially form bridging structures at the inlet of the seepage channel, limiting further grout loss and improving the sealing effect of the grouting layer.
[0084] Through the above dynamic adjustment method, the thixotropic mud composition of elastic polymer particles can be adaptively optimized according to the actual formation response and grouting status during the pipe jacking construction process. While ensuring effective filling of the annular gap, it can improve the lubrication and drag reduction effect and the stability of grouting and sealing, and further enhance the reliability of long-distance pipe jacking construction under complex formation conditions.
[0085] The grouting control device for pipe jacking construction provided by the present invention is described below, such as... Figure 2 As shown, the grouting control device for pipe jacking construction described below can be referred to in correspondence with the grouting control method for pipe jacking construction described above.
[0086] A grouting control device for pipe jacking construction, comprising: Parameter acquisition module 210 is used to acquire the geological characteristic parameters of the area to be constructed; The parameter determination module 220 is used to determine the particle size distribution parameters and dosage parameters of the elastic polymer particles based on the formation characteristic parameters. The mixture preparation module 230 is used to prepare an elastic polymer particle thixotropic mud composition according to the particle size distribution parameters and dosage parameters. The mixture injection module 240 is used to inject the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section, so as to form a lubricating sealing layer. The elastic polymer particle thixotropic mud composition includes a thixotropic mud base liquid and elastic polymer particles dispersed in the thixotropic mud base liquid.
[0087] Figure 3 An example is a schematic diagram of the physical structure of an electronic device, such as... Figure 3 As shown, the electronic device may include: a processor 310, a communication interface 320, a memory 330, and a communication bus 340, wherein the processor 310, the communication interface 320, and the memory 330 communicate with each other via the communication bus 340. The processor 310 can call logical instructions in the memory 330 to execute a grouting control method for pipe jacking construction, which includes: Obtain the geological characteristic parameters of the area to be constructed; The particle size distribution parameters and dosage parameters of the elastic polymer particles are determined based on the formation characteristic parameters. A thixotropic slurry composition of elastic polymer particles was prepared according to the particle size distribution parameters and dosage parameters. The elastic polymer particle-reinforced thixotropic mud composition is injected into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section to form a lubricating sealing layer; The elastic polymer particle thixotropic mud composition includes a thixotropic mud base liquid and elastic polymer particles dispersed in the thixotropic mud base liquid.
[0088] Furthermore, the logical instructions in the aforementioned memory 330 can be implemented as software functional units and, when sold or used as independent products, can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, essentially, or the part that contributes to the prior art, or a part of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute all or part of the steps of the methods described in the various embodiments of the present invention. The aforementioned storage medium includes various media capable of storing program code, such as USB flash drives, portable hard drives, read-only memory (ROM), random access memory (RAM), magnetic disks, or optical disks.
[0089] On the other hand, the present invention also provides a computer program product, the computer program product comprising a computer program that can be stored on a non-transitory computer-readable storage medium, wherein when the computer program is executed by a processor, the computer is able to execute the grouting control method for pipe jacking construction provided by the above methods, the method comprising: Obtain the geological characteristic parameters of the area to be constructed; The particle size distribution parameters and dosage parameters of the elastic polymer particles are determined based on the formation characteristic parameters. A thixotropic slurry composition of elastic polymer particles was prepared according to the particle size distribution parameters and dosage parameters. The elastic polymer particle-reinforced thixotropic mud composition is injected into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section to form a lubricating sealing layer; The elastic polymer particle thixotropic mud composition includes a thixotropic mud base liquid and elastic polymer particles dispersed in the thixotropic mud base liquid.
[0090] In another aspect, the present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, is implemented to perform the grouting control method for pipe jacking construction provided by the methods described above, the method comprising: Obtain the geological characteristic parameters of the area to be constructed; The particle size distribution parameters and dosage parameters of the elastic polymer particles are determined based on the formation characteristic parameters. A thixotropic slurry composition of elastic polymer particles was prepared according to the particle size distribution parameters and dosage parameters. The elastic polymer particle-reinforced thixotropic mud composition is injected into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section to form a lubricating sealing layer; The elastic polymer particle thixotropic mud composition includes a thixotropic mud base liquid and elastic polymer particles dispersed in the thixotropic mud base liquid.
[0091] The device embodiments described above are merely illustrative. The units described as separate components may or may not be physically separate. The components shown as units may or may not be physical units; that is, they may be located in one place or distributed across multiple network units. Some or all of the modules can be selected to achieve the purpose of this embodiment according to actual needs. Those skilled in the art can understand and implement this without any creative effort.
[0092] Through the above description of the embodiments, those skilled in the art can clearly understand that each embodiment can be implemented by means of software plus necessary general-purpose hardware platforms, and of course, it can also be implemented by hardware. Based on this understanding, the above technical solutions, in essence or the part that contributes to the prior art, can be embodied in the form of a software product. This computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, magnetic disk, optical disk, etc., and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute the methods described in the various embodiments or some parts of the embodiments.
[0093] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, and not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features; and these modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for controlling grouting during pipe jacking construction, characterized in that, include: Obtain the geological characteristic parameters of the area to be constructed; The particle size distribution parameters and dosage parameters of the elastic polymer particles are determined based on the formation characteristic parameters. A thixotropic slurry composition of elastic polymer particles was prepared according to the particle size distribution parameters and dosage parameters. The elastic polymer particle-reinforced thixotropic mud composition is injected into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section to form a lubricating sealing layer; The elastic polymer particle thixotropic mud composition includes a thixotropic mud base liquid and elastic polymer particles dispersed in the thixotropic mud base liquid.
2. The grouting control method for pipe jacking construction according to claim 1, characterized in that, The step of determining the particle size distribution parameters and dosage parameters of the elastic polymer particles based on the formation characteristic parameters specifically includes: Based on the aforementioned formation characteristic parameters, obtain the formation porosity characteristic parameters and / or fracture characteristic parameters of the target construction section; Based on the formation pore characteristic parameters and / or fracture characteristic parameters, establish the particle size matching relationship between the elastic polymer particles and the target formation; The proportion of different particle size grades in the elastic polymer particles is determined based on the particle size matching relationship, and the amount of elastic polymer particles to be added is determined based on the permeability characteristics of the target construction section.
3. The grouting control method for pipe jacking construction according to claim 1, characterized in that, The step of establishing the particle size matching relationship between the elastic polymer particles and the target formation based on the formation porosity characteristic parameters and / or fracture characteristic parameters specifically includes: Based on the pore size parameters and / or crack size parameters of the target construction section, determine the bridging particle size range corresponding to the coarse particles in the elastic polymer particles; Based on the particle size range of the coarse particles, the particle size ranges corresponding to the medium and fine particles are determined according to the stepwise filling relationship. The coarse-grained particles are used to form bridging structures at the entrances of formation pores or fractures, the medium-grained particles are used to fill the internal gaps of the bridging structures, and the fine-grained particles are used to block micropore channels.
4. The grouting control method for pipe jacking construction according to claim 1, characterized in that, The elastic polymer particles include at least one of elastic polyurethane microspheres, cross-linked polyacrylamide microspheres, natural rubber microspheres, and silicone rubber microspheres, and the mass ratio of the coarse particles, the medium particles, and the fine particles is (35-50): (30-40): (15-25).
5. The grouting control method for pipe jacking construction according to claim 1, characterized in that, The step of preparing the elastic polymer particle thixotropic mud composition according to the particle size distribution parameters and dosage parameters specifically includes: Preparation of thixotropic mud base liquid; Elastic polymer particles of different particle sizes are mixed according to the particle size distribution parameters to obtain an elastic particle mixture; The elastic particle mixture is added to a dispersion medium for pre-dispersion treatment to obtain an elastic particle pre-dispersion liquid. The elastic particle pre-dispersion liquid is added to the thixotropic mud base liquid and stirred to uniformly disperse the elastic polymer particles in the thixotropic mud base liquid.
6. The grouting control method for pipe jacking construction according to claim 1, characterized in that, The step of injecting the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section specifically includes: The construction area is divided into multiple grouting control zones along the jacking direction; For different formation types corresponding to different grouting control sections, the particle content and grouting pressure in the elastic polymer particle thixotropic mud composition are adjusted.
7. The grouting control method for pipe jacking construction according to claim 1, characterized in that, After the step of injecting the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section, the method further includes: By monitoring the jacking force, pipe circumferential friction, and grouting pressure during the pipe jacking construction process, the dosage parameters of the elastic polymer particles and the grouting pressure are dynamically adjusted. When the detected pipe circumferential friction exceeds the preset threshold, the amount of elastic polymer particles in the subsequent construction section is increased. When a continuous drop in grouting pressure is detected, the proportion of coarse particles is increased to enhance the bridging and sealing capacity of the leakage channels.
8. A grouting control device for pipe jacking construction, characterized in that, include: The parameter acquisition module is used to acquire the geological characteristic parameters of the area to be constructed. The parameter determination module is used to determine the particle size distribution parameters and dosage parameters of the elastic polymer particles based on the formation characteristic parameters. The mixture preparation module is used to prepare an elastic polymer particle thixotropic slurry composition according to the particle size distribution parameters and dosage parameters. The mixture injection module is used to inject the elastic polymer particle-reinforced thixotropic mud composition into the annular gap between the outer wall of the jacking pipe section and the formation according to the corresponding construction section, so as to form a lubricating sealing layer; The elastic polymer particle thixotropic mud composition includes a thixotropic mud base liquid and elastic polymer particles dispersed in the thixotropic mud base liquid.
9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that, When the processor executes the computer program, it implements the grouting control method for pipe jacking construction as described in any one of claims 1 to 7.
10. A non-transitory computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by the processor, it implements the grouting control method for pipe jacking construction as described in any one of claims 1 to 7.