A TBM grouting construction method to prevent cutterhead consolidation and segment misalignment
By adopting rapid-setting, early-strength grout and grout-stopping ring technology in TBM tunnel construction, the problems of segment misalignment and grout cross-flow were solved, achieving full-area tunnel compaction and stable equipment operation, thus improving construction quality and efficiency.
Patent Information
- Application Number
- CN202611304108.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-26
- Publication Date
- 2026-11-10
AI Technical Summary
In existing TBM tunnel construction, the grouting behind the tunnel segments is delayed, leading to problems such as segment misalignment and water leakage. The grout can easily flow forward to the cutterhead, causing equipment failure. Incomplete grouting leads to equipment failure and long-term damage. There is a lack of a systematic grouting process with time-sequential and zone-isolated grouting.
Low-level fixed-point grouting is carried out using fast-setting and early-strength grout to form an early support structure; a grout-stopping ring is constructed by layered grouting from bottom to top to form a closed grouting zone and block the grout flow channel; pea gravel is blown in and cement mortar is backfilled in the closed grouting zone, and the grout-stopping ring is used to seal and isolate, so as to achieve stable pressure and dense grouting.
It effectively prevents segment misalignment and cutterhead consolidation, achieves full tunnel compaction, improves construction quality and efficiency, reduces project costs and carbon footprint, and avoids equipment failure and long-term damage.
Smart Images

Figure CN123064495A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of grouting technology behind the tunnel wall in TBM tunnel construction, specifically to a TBM grouting construction method to prevent cutterhead consolidation and segment misalignment. Background Technology
[0002] In hard rock TBM tunnel construction, the excavation gap between the segment wall and the surrounding rock is usually filled using the traditional backfilling grouting process of "pebble filling followed by cement mortar backfilling". This process is a one-time continuous grouting mode, and has the following main technical defects in actual construction.
[0003] Firstly, after TBM excavation, the grouting and filling of the gaps behind the tunnel segments is delayed, leaving the formed segments without effective support and constraint under the combined effects of surrounding rock stress and the equipment's own weight. Poor gravel filling and untimely grouting can easily lead to severe segment misalignment, damage, and leakage. Due to factors such as construction technology and geological conditions, uneven and non-compact gravel filling frequently occurs, further causing segment misalignment, cracking, and water leakage. Segment misalignment is affected by multiple factors, including assembly operations, segment location selection, and the initial setting time of the grout behind the tunnel wall, and has long been a key concern in TBM construction. Secondly, traditional integral grouting processes lack zonal sealing and isolation structures, making it difficult to effectively control the grout diffusion path under grouting pressure. The grout easily flows forward to the TBM cutterhead and shield area and solidifies. Because the grouting site is close to the TBM cutterhead, the grout can easily enter the cutterhead, increasing the difficulty of restarting the TBM later. This defect can range from causing abnormal wear of the cutting tools to serious equipment malfunctions such as cutterhead seizure and shield jamming, severely restricting the continuity and efficiency of tunneling construction. Thirdly, traditional grouting methods are limited by poor grouting pressure stability and obstructed venting channels, easily leading to quality defects such as incomplete filling, grout bleeding and shrinkage, and residual voids and cracks behind the tunnel wall. Problems such as segment misalignment and water leakage caused by improper grouting frequently occur in projects, inducing long-term defects such as tunnel water leakage, structural settlement, and lining cracking, resulting in high rework rates and persistently high overall construction costs.
[0004] Existing improved grouting technologies mainly focus on conventional methods such as grout ratio optimization, grouting pressure fine-tuning, and secondary grouting. They do not fundamentally solve the main problems of grout forward movement, early segment instability, and insufficient grout density over a large area. They lack a systematic grouting process with time-sequential, zoned isolation, and logical sealing, and cannot simultaneously achieve multiple construction goals such as early segment stability, cutterhead anti-consolidation, and full-area dense filling behind the wall. Summary of the Invention
[0005] Therefore, the present invention provides a TBM grouting construction method to prevent cutterhead consolidation and segment misalignment, solving the problems of segment settlement misalignment, grout forward consolidation of the cutterhead, and incomplete backfilling in the existing TBM backfilling process.
[0006] To achieve the above objectives, the present invention provides the following technical solution: a TBM grouting construction method for preventing cutterhead consolidation and segment misalignment, comprising: After S1 and TBM excavate 3 to 4 rings of segments, low-level fixed-point grouting is carried out using quick-setting and early-strength grout through the grouting holes at the bottom and sides of the formed segments to form an early support structure. S2. After continuous tunneling to a cumulative total of 10-15 rings of tunnel segments, select a stable tunnel segment ring and use a bottom-up layered grouting method to seal the entire ring of tunnel segment wall with grout, solidify to form an independent grout-stopping ring, and construct two parallel grout-stopping rings at a set interval to form a closed grouting section with both ends sealed. S3. Within the closed grouting zone, the pea gravel backfilling and cement mortar backfilling and compaction operations are completed sequentially; the grout stop ring blocks the forward flow channel of the grout through its sealing and isolation function, and the closed grouting zone is stabilized and compacted during grouting. S4. Follow the TBM tunneling progress and repeat the S1 to S3 processes.
[0007] As a preferred scheme for TBM grouting construction method to prevent cutterhead consolidation and segment misalignment, in S1, the quick-setting and early-strength grout is a quaternary compound grout, which includes fine particles of TBM excavation waste, cement, quick-setting agent, and early-strength agent. The mass ratio of each component is as follows: fine particles of TBM excavation waste 45% to 55%, cement 30% to 35%, quick-setting agent 3% to 5%, early-strength agent 2% to 4%, and the balance is mixing water. The initial setting time of the quaternary compound slurry is 30-60 seconds, the final setting time is ≤10 minutes, and the early compressive strength at 30 minutes is ≥1.5 MPa. The construction parameters are: grouting pressure 0.2-0.4 MPa, grouting rate 15-20 L / min, and pressure stabilization time 3-5 min.
[0008] As a preferred TBM grouting construction method for preventing cutterhead consolidation and segment misalignment, in S1, the low-position fixed-point grouting only grouts the low-position areas of the bottom arch and the waist on both sides of the segment, and does not perform top grouting.
[0009] As a preferred TBM grouting construction method for preventing cutterhead consolidation and segment misalignment, in S2, the grout-stopping ring is constructed in the segment area 10 to 15 rings behind the shield tail.
[0010] As a preferred method for TBM grouting construction to prevent cutterhead consolidation and segment misalignment, the grout-stopping ring adopts a ternary composite grout-stopping material, which includes fine particles of TBM excavation waste, cement, and a quick-setting agent. The mass ratio of each component is as follows: 50%–60% of the fine particles of TBM excavation waste, 32%–38% of the cement, 4%–6% of the quick-setting agent, and the remainder is mixing water. The ternary composite grout-stopping material has no shrinkage and exhibits micro-expansion characteristics after curing.
[0011] As a preferred scheme for TBM grouting construction method to prevent cutterhead consolidation and segment misalignment, in S2, the bottom-up layered grouting method specifically means: grouting is performed symmetrically on the bottom arch area and the two sides of the waist in sequence, and the top closed area is grouted in layers, with the two sides of the waist being grouted symmetrically and synchronously. The construction parameters are as follows: layered grouting pressure 0.5-0.7MPa, grouting rate 20-25L / min, single-layer pressure stabilization time 5-8min, and double-sided grouting pressure difference ≤±0.05MPa.
[0012] As a preferred scheme for TBM grouting construction method to prevent cutterhead consolidation and segment misalignment, in S3, the closed grouting zone pressure-stabilized compaction grouting adopts the top opening and top-down saturated grouting method, first blowing in TBM coarse pea gravel to form a rigid support skeleton, and then injecting filling grout. The filling grout uses a binary composite filling material, which includes fine particles of TBM excavation waste and cement. The mass ratio of each component is: 60% to 70% of the fine particles of TBM excavation waste and 30% to 40% of the cement, with no additives. The construction parameters are as follows: TBM coarse-grained pebbles blasting air pressure 0.3-0.5MPa, saturated grouting pressure 0.8-1.2MPa, grouting rate 25-30L / min, and pressure stabilization time 10-15min.
[0013] As a preferred method for TBM grouting construction to prevent cutterhead consolidation and segment misalignment, in S3, when the grout outlet at the bottom of the closed grouting section continuously overflows grout without air bubbles and the grout concentration is consistent with the grouting inlet, it is determined that the grouting is saturated and dense, and the grouting is terminated.
[0014] As a preferred TBM grouting construction method to prevent cutterhead consolidation and segment misalignment, the longitudinal spacing between two adjacent grout-stopping rings is 8 to 12 segments.
[0015] The present invention has the following advantages: First, the present invention implements pure bottom low-position rapid setting grouting behind the shield tail. The initial setting time of the rapid setting early strength grout is controlled at 30-60s, and the early compressive strength at 30min is ≥1.5MPa. Rigid support can be established in a very short time after exiting the shield tail, quickly supporting the self-weight of the newly formed segments and subsequent loads, and controlling the initial segment subsidence and local misalignment deformation within the allowable range of the specifications.
[0016] Secondly, this invention features a finely constructed ternary homogeneous grout-stopping ring, which has stable solidification volume, high density, and a sealing performance of ≥98%, forming a longitudinal flow-blocking dam. During subsequent high-pressure backfilling, the grout-stopping ring can prevent the grout from leaking and flowing forward towards the shield tail and cutterhead, thus eliminating the cutterhead consolidation and jamming faults caused by the forward flow of grout.
[0017] Third, this invention implements top opening and top-down saturated grouting within the bounded grout-stopping zone at both ends. By utilizing the dual effects of grout's own weight sinking and pressure stabilization and squeezing, air is expelled step by step, eliminating the "crescent-shaped" void defect at the top caused by gas retention. The filling density behind the wall can reach more than 99%, effectively avoiding long-term problems such as tunnel water leakage and structural settlement.
[0018] Fourth, the stabilizing grout, grout-stopping material and filling grout used in the entire process of this invention are all based on fine particles of waste slag screened on-site by TBM as the main base raw materials. The composition ratio is adjusted according to the differences in working conditions, which fundamentally gets rid of the dependence on purchased sand and gravel aggregates in traditional grouting, greatly reduces the overall construction cost and waste slag transportation and disposal costs, and reduces the carbon footprint of the project throughout its entire life cycle.
[0019] Fifth, this invention adopts a sequential design of "stabilizing the shape first, then sealing, and finally compacting". Each step has a clear function and progresses step by step. The stabilizing grouting provides a stable foundation for the subsequent grout-stopping ring construction, and the grout-stopping ring provides a longitudinal sealing boundary for the compacting grouting. The three steps work together to form a complete logic, which overcomes the technical defects of the traditional process where each link is disconnected and interferes with each other, and significantly improves the construction quality and reliability of TBM wall grouting. Attached Figure Description
[0020] To more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings in the following description are merely exemplary, and those skilled in the art can derive other embodiments based on the provided drawings without creative effort.
[0021] The structures, proportions, sizes, etc. illustrated in this specification are only for the purpose of assisting those skilled in the art in understanding and reading the content disclosed herein, and are not intended to limit the conditions under which the present invention can be implemented. Therefore, they have no substantial technical significance. Any modifications to the structure, changes in the proportions, or adjustments to the size, without affecting the effects and objectives that the present invention can produce, should still fall within the scope of the technical content disclosed in the present invention.
[0022] Figure 1 This is a schematic diagram of the TBM grouting construction method for preventing cutterhead consolidation and segment misalignment provided in Embodiment 1 of the present invention.
[0023] Figure 2 This is a technical roadmap for a TBM grouting construction method to prevent cutterhead consolidation and segment misalignment, as provided in Embodiment 1 of the present invention. Detailed Implementation
[0024] The following specific embodiments illustrate the implementation of the present invention. Those skilled in the art can easily understand other advantages and effects of the present invention from the content disclosed in this specification. Obviously, the described embodiments are only some, not all, of the embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention. Example 1
[0025] See Figure 1 and Figure 2 This invention provides a TBM grouting construction method to prevent cutterhead consolidation and segment misalignment, comprising: After S1 and TBM excavate 3 to 4 rings of segments, low-level fixed-point grouting is carried out using quick-setting and early-strength grout through the grouting holes at the bottom and sides of the formed segments to form an early support structure. S2. After continuous tunneling to a cumulative total of 10-15 rings of tunnel segments, select a stable tunnel segment ring and use a bottom-up layered grouting method to seal the entire ring of tunnel segment wall with grout, solidify to form an independent grout-stopping ring, and construct two parallel grout-stopping rings at a set interval to form a closed grouting section with both ends sealed. S3. Within the closed grouting zone, the pea gravel backfilling and cement mortar backfilling and compaction operations are completed sequentially; the grout stop ring blocks the forward flow channel of the grout through its sealing and isolation function, and the closed grouting zone is stabilized and compacted during grouting. S4. Follow the TBM tunneling progress and repeat the S1 to S3 processes.
[0026] Specifically, after the newly formed tunnel segments emerge from the shield tail, the stress from their own weight and the stress from the overlying surrounding rock are mainly concentrated at the bottom and waist arch of the segments. The bottom is the most sensitive area for segment settlement and misalignment. This invention adopts the principle of bottom-priority grouting, using a fast-setting, early-strength grout to quickly solidify and form behind the shield tail, providing early rigid support and constraint for the newly formed tunnel segments emerging from the shield tail, and preferentially counteracting the tendency of the segments to suspend and settle. At the same time, grouting is only carried out at the bottom and waist low positions, without top grouting, which can reserve space for slight convergence deformation of the top surrounding rock, avoiding the surrounding rock compression and segment floating defects caused by early full-section grouting, and realizing the safe forming logic of "stabilizing the bottom first, then sealing the top". Stabilizing grouting is carried out every 3 to 4 rings of tunneling, and the grouting frequency is matched with the tunneling rhythm to ensure that the newly formed tunnel segments obtain effective support in a very short time. The function of the grout-stop ring is to longitudinally seal and enclose the compartment. It is essential to ensure that the ring body is free of air holes, layered gaps, and uniform stress. This invention adopts a bottom-up layered grouting method, utilizing the grout's own weight to naturally fill and expel air upwards, which avoids the problems of bottom air accumulation and void filling caused by top-down grouting. Symmetrical synchronous grouting on both sides of the waist can balance the lateral thrust generated by grouting pressure on one side, preventing the grout-stop ring from forming skewed and uneven stress on the segments, ensuring that the entire grout-stop structure is dense, sealed, and continuous. The grout-stop ring is constructed by selecting 10 to 15 rings of stable segments behind the shield tail. The surrounding rock stress in this area is basically stable, there is no risk of dynamic deformation of the segments, and the distance from the front cutterhead working area is sufficient to isolate the grouting working area from the tunneling working area. Two parallel grout-stop rings form a sealing structure at both ends, providing a longitudinal rigid boundary for subsequent zoned dense grouting, ensuring that there is no grout leakage or cross-flow between grouting sections. The closed grouting section has formed a sealed structure at both ends. Relying on the sealing and limiting effect of the grout-stopping rings at both ends, the grouting pressure can be stably increased. This invention adopts a top-opening, top-down saturated grouting method, utilizing the dual effects of gravity penetration and pressure stabilization to allow the grout to slowly fill from top to bottom, gradually expelling residual air inside the pea-grain skeleton and avoiding air accumulation and voids in the bottom and waist dead corners. Compared with traditional bottom grouting, the top-sinking filling can achieve full-section saturated grouting without dead corners, solving the common problems of dense bottom, voids at top, and uneven filling in traditional grouting. At the same time, the mechanical cut-off effect of the grout-stopping rings at both ends prevents the grout from leaking and flowing towards the shield tail and cutterhead, eliminating the cutterhead consolidation and jamming faults caused by the forward flow of grout. TBM tunneling is a continuous process, and the grouting behind the tunnel wall needs to be dynamically matched with the tunneling speed. This invention uses a cyclic iterative design to divide the tunnel longitudinally into several grouting sections. Each section completes the grouting operations of each stage in sequence according to the time sequence logic of "stabilizing the shape first, then sealing, and finally compacting". The sections are connected end to end and continuously advanced, ultimately realizing a systematic logical grouting of stabilizing the shape of the tunnel segments, sealing longitudinally, and compacting the entire tunnel.
[0027] In one possible embodiment, in S1, the quick-setting and early-strength grout is a quaternary compound grout, which includes fine particles of TBM excavation waste, cement, quick-setting agent, and early-strength agent. The mass ratio of each component is as follows: 45%–55% of the fine particles of TBM excavation waste, 30%–35% of the cement, 3%–5% of the quick-setting agent, 2%–4% of the early-strength agent, and the balance being mixing water. The initial setting time of the quaternary compound grout is 30–60 seconds, the final setting time is ≤10 minutes, and the early compressive strength at 30 minutes is ≥1.5 MPa. The construction parameters are: grouting pressure 0.2–0.4 MPa, grouting rate 15–20 L / min, and pressure stabilization time 3–5 minutes.
[0028] Specifically, this invention employs a four-component compound system consisting of waste slag fine particles, cement, accelerator, and early-strength agent. The waste slag fine particles from the TBM excavation site serve as an inert filling skeleton, reducing the amount of externally purchased materials. Cement provides basic cementitious strength; the accelerator ensures the grout initially sets within 30-60 seconds, allowing the grout hardening speed to precisely match the load application speed brought by the TBM excavation; the early-strength agent ensures that the compressive strength explosively surpasses the 1.5MPa threshold within 30 minutes, physically guaranteeing the achievement of stable structure. The low-pressure setting of 0.2-0.4MPa prevents newly formed weak segments from being deformed by eccentric pressure. Low-speed grouting and short-term pressure stabilization ensure that the accelerator grout quickly and uniformly adheres to the surrounding rock behind the wall, forming a uniform support layer.
[0029] In one possible embodiment, in S1, the low-position fixed-point grouting only grouts the bottom arch and the low-position areas on both sides of the segment, and does not perform top grouting.
[0030] Specifically, in the initial stage after the new tunnel segment emerges from the shield tail, a gap naturally exists between the top of the segment and the surrounding rock due to gravity. If grouting is injected into the top simultaneously, the grout may fall due to its own weight before solidification, failing to effectively remain in place, resulting in material waste and affecting the bottom support effect. This invention adopts a "stabilize the bottom first" strategy, grouting only the bottom and the low-lying areas on both sides. This can quickly establish a lower rigid support layer, prioritizing the restraint of segment subsidence and misalignment deformation trends. At the same time, the reserved voids at the top can serve as a release space for the initial minor convergence deformation of the surrounding rock, effectively preventing segment floating and excessive compression of the surrounding rock. After the subsequent grout stop ring is constructed, the top area will be fully and densely filled in S3 through top-down saturated grouting.
[0031] In one possible embodiment, in S2, the grout-stopping ring is constructed in the area of 10 to 15 ring segments behind the shield tail.
[0032] Specifically, after the TBM passes through, the surrounding rock stress adjusts from its original state to a secondary equilibrium state, typically stabilizing around 10 rings behind the shield tail. The tunnel segments initially face dynamic deformation risks after exiting the shield tail, but the segment structure stabilizes after several rings of self-supporting surrounding rock. Constructing a grout-stopping ring in this area prevents the ring from being damaged due to unstable surrounding rock deformation and ensures a sufficient safe distance from the front cutterhead working area, effectively isolating tunneling disturbances from grouting operations.
[0033] In one possible embodiment, the grout-stopping ring is made of a ternary composite grout-stopping material, which includes fine particles of TBM excavation waste, cement, and an accelerator. The mass ratio of each component is as follows: 50%–60% of the fine particles of TBM excavation waste, 32%–38% of the cement, 4%–6% of the accelerator, and the remainder is mixing water. The ternary composite grout-stopping material does not shrink after curing and has micro-expansion characteristics.
[0034] Specifically, the grout-stopping ring needs to possess high strength, high sealing performance, and rapid curing properties. Simultaneously, the material should be of the same origin as the stable grouting material to simplify on-site material preparation. Compared to the quaternary system of stable grouting, the grout-stopping material eliminates the early-strength component and increases the amount of waste residue. It uses cement and a quick-setting agent to ensure rapid curing within 25-30 seconds to achieve initial strength, meeting the requirements of continuous operation. More importantly, this material exhibits micro-expansion characteristics (no shrinkage) after curing, actively squeezing and filling the minute cracks between the surrounding rock and the outer wall of the tunnel lining segments, achieving a sealing performance of ≥98%, forming a high-density longitudinal flow barrier, effectively blocking the longitudinal flow channels of grout during subsequent high-pressure grouting in the section.
[0035] In one possible embodiment, in S2, the bottom-up layered grouting method specifically involves: sequentially grouting the bottom arch area, symmetrically grouting the two sides of the waist, and layered grouting the top closed area, with the two sides of the waist being grouted symmetrically and synchronously; the construction parameters are: layered grouting pressure 0.5-0.7MPa, grouting rate 20-25L / min, single-layer pressure stabilization time 5-8min, and double-sided grouting pressure difference ≤±0.05MPa.
[0036] Specifically, the bottom-up grouting sequence fully utilizes the physical property that the density of grout is greater than that of air. After the grout is injected from the bottom, the liquid level gradually rises, driving the air in the gaps behind the wall upwards to be discharged through the top vent, fundamentally preventing air accumulation at the bottom and the formation of voids. The principle of symmetrical synchronous grouting on both sides of the waist is based on pressure balance: the grouting pressure is as high as 0.5-0.7 MPa. If grouting is carried out on one side of the waist first, the lateral thrust will cause the segments and the uncured grouting material to be biased to the opposite side, resulting in skewed grouting ring formation, uneven stress on the segments, or even cracking. Simultaneous grouting on both sides and controlling the pressure difference within ±0.05 MPa can achieve real-time self-balancing of the horizontal thrust, ensuring uniform stress and precise alignment of the entire grouting ring structure. Stabilizing the pressure of each layer for 5-8 minutes ensures that each layer of grout has initially set to a certain strength before grouting the next layer, avoiding cross-grouting and mutual interference.
[0037] In one possible embodiment, in S3, the closed grouting section's pressure-stabilizing and compacting grouting adopts a top-opening, top-down saturated grouting method. First, TBM coarse-grained pebbles are blown in to form a rigid support skeleton, and then filling grout is injected. The filling grout uses a binary composite filling material, which includes fine particles of TBM excavation waste and cement. The mass ratio of each component is: 60%–70% of the fine particles of TBM excavation waste and 30%–40% of the cement, without any admixtures. The construction parameters are: TBM coarse-grained pebbles blown in with an air pressure of 0.3–0.5 MPa, saturated grouting pressure of 0.8–1.2 MPa, grouting rate of 25–30 L / min, and pressure stabilization time of 10–15 min.
[0038] Specifically, firstly, coarse-grained pebbles from the TBM are uniformly blown into the gaps behind the wall using high-pressure air at 0.3–0.5 MPa. The accumulation of coarse-grained pebbles forms a rigid skeleton structure, resisting the stress of the surrounding rock on the one hand, and providing pore channels and supporting boundaries for subsequent grout filling on the other. On this basis, a binary filling grout consisting of waste residue, fine particles, and cement is injected. The grout permeates and flows through the gaps in the pebble skeleton, with the fine-grained waste residue and cement working together to fill the tiny pores, ultimately forming a dense body interwoven with coarse aggregate and fine grout. This binary compound system has the simplest ratio among the three types of materials, with a waste residue content as high as 60%–70%, no additives, and excellent fluidity (initial fluidity 220–235 mm), allowing it to autonomously permeate and fill every tiny pore in the skeleton. The grouting pressure is increased to 0.8–1.2 MPa, relying on the sealing and limiting effect of the grout stop rings at both ends to achieve stable pressure and saturated filling. The pressure stabilization time is 10–15 minutes to ensure full grout penetration and complete air venting, ultimately increasing the density of the stone body to over 99%.
[0039] In one possible embodiment, in S3, when the grout outlet at the bottom of the closed grouting section continuously overflows grout without air bubbles and the grout concentration is consistent with the grouting concentration, it is determined that the grouting is saturated and compacted, and the grouting is terminated.
[0040] Specifically, after the grout is injected from the top, it slowly permeates and fills the gaps from top to bottom under gravity. The air in the gaps behind the wall is gradually squeezed downwards by the grout and eventually converges at the bottom of the section. When grout begins to overflow from the bottom outlet, it indicates that the grout front has reached the farthest end of the section; continuous overflow without air bubbles indicates that the air along the way has been expelled and there are no residual air pockets; the overflow grout concentration is consistent with the grout injection concentration, indicating that there has been no significant bleeding or segregation of the grout during the flow process, and the filling medium is uniform and dense. Only when all three conditions are met can it be determined that the entire area is saturated and dense. At this point, grouting is terminated to ensure that there are no voids, no delamination, and no shrinkage defects in the gaps behind the wall.
[0041] In one possible embodiment, the longitudinal spacing between two adjacent grout-stopping rings is 8 to 12 ring segments.
[0042] Specifically, the spacing between grout-stop rings, i.e., the longitudinal length of a single grouting interval, requires a balance between construction efficiency and grouting quality. An interval that is too short (<8 rings) will lead to excessively high frequency of grout-stop ring construction, increasing construction procedures and material consumption, and reducing overall tunneling efficiency. An interval that is too long (>12 rings) will result in significant pressure attenuation along the flow path of the grout over long distances, making it difficult to maintain effective pressure stability at the end, and easily leading to incomplete filling at the far end of the interval. This invention controls the interval length to 8–12 rings. Within this range, the volume of grout injected per cycle is moderate, and the pressure attenuation is controllable, ensuring both grouting pressure stabilization and filling density while also considering construction economy, achieving optimal synergy between efficiency and quality.
[0043] The invention will now be described in further detail with reference to specific application scenarios.
[0044] Application Scenario 1: This embodiment is applied to the construction of a hard rock TBM mountain tunnel with a diameter of 6.0m, and adopts the traditional pebbly gravel + cement mortar backfilling process.
[0045] S1. Pre-construction stabilization grouting: After the TBM has excavated 4 rings of tunnel segments, large-scale grouting is stopped. Grouting holes are selected at the bottom arch and sides of the tunnel segments. A quaternary compound stabilization grouting material is used, with the following proportions: 50% TBM fine-particle waste, 33% cement, 4% quick-setting agent, 3% early-strength agent, and 10% mixing water. The grout sets initially in 45 seconds, sets completely in 8 minutes, and has a strength of 1.8 MPa after 30 minutes. The grouting pressure is controlled at 0.3 MPa, the grouting rate is 18 L / min, and the pressure is stabilized for 4 minutes to quickly support the newly formed tunnel segments and effectively avoid the problems of suspended settlement and slight misalignment of the newly formed tunnel segments.
[0046] S2. Construction of the grout-stop ring: Continue tunneling to the position of the 12th segment. Select this stable segment ring and adopt a bottom-up, left-right symmetrical layered grouting process. Use a ternary compound grout-stop material with a ratio of 55% TBM fine particle waste, 35% cement, 5% quick-setting agent, and 5% mixing water. Control the layered grouting pressure at 0.6MPa, the grouting rate at 22L / min, and the single-layer pressure stabilization at 6min. Keep the grouting pressure consistent on both sides. Layered curing forms a complete closed grout-stop ring. Construct a second grout-stop ring every 10 segments to form a closed grouting zone.
[0047] S3. Interval Compact Grouting: Within the grouting interval sealed by two grout-stopping rings, coarse-grained gravel excavated by the TBM is first filled with 0.4MPa pneumatic pressure to form a rigid support skeleton. Then, a binary compound filling grout is injected, with a ratio of 65% TBM fine-grained waste and 35% cement. The saturated grouting pressure is controlled at 1.0MPa, the grouting rate at 28L / min, and the pressure is stabilized for 12min. The grout gradually fills the gaps between the gravel and the fine cavities in the surrounding rock from top to bottom. Because the grout-stopping rings at both ends are sealed, there is no channel for the grout to flow forward, avoiding grout consolidation failures in the cutterhead and shield. At the same time, stable and pressure-stabilized grouting can be achieved, increasing the backfill density to 99.2%, with no voids, bleeding, or shrinkage defects.
[0048] S4. Cyclic Construction: Construction is carried out in cycles following the tunneling progress. There are no obvious misalignments or floating phenomena of the tunnel segments throughout the entire process. The tunnel alignment accuracy meets the standards, and there are no cutterhead consolidation or jamming faults. Construction efficiency and project quality are greatly improved.
[0049] Application Scenario 2: This embodiment is applied to the construction of a TBM tunnel in deeply buried fractured surrounding rock. The tunnel diameter is 5.5m, the surrounding rock has poor integrity, developed fissures, and large convergence deformation. Traditional grouting is prone to segment instability, grout channeling, and voids behind the tunnel wall, making construction control difficult.
[0050] S1. Early-stage stabilization grouting: Adapting to the large deformation characteristics of fractured surrounding rock, low-level stabilization grouting is carried out immediately after the TBM excavates 3 rings of segments. Quaternary compound stabilization grouting material is selected, with the following proportions: 52% TBM fine-particle waste, 32% ordinary Portland cement, 4.5% quick-setting agent, 3.5% early-strength agent, and 8% mixing water. The grout initially sets in 38 seconds, sets for 9 minutes, and has an early compressive strength of 1.65 MPa at 30 minutes. The grouting pressure is strictly controlled at 0.35 MPa, the grouting rate is 16 L / min, and the pressure is stabilized for 5 minutes. Through low-level rapid consolidation support, the uneven settlement and initial misalignment of newly formed segments in fractured surrounding rock sections are effectively constrained, avoiding the problem of segment suspension and instability in soft strata.
[0051] S2. Grouting Ring Construction: Continuing excavation to the 10th segment position, a grouting ring is constructed around a segment with stable surrounding rock stress. A bottom-up, strictly symmetrical, synchronous layered grouting process is adopted, using a ternary compound grouting material with the following proportions: 58% TBM fine-particle waste, 33% ordinary Portland cement, 5.5% quick-setting agent, and 3.5% mixing water. The layered grouting pressure is controlled at 0.65 MPa, the grouting rate at 24 L / min, and the single-layer pressure stabilization time at 7 min. The pressure difference between the two sides is controlled within ±0.05 MPa. The micro-expansion characteristics are used to achieve a tight fit between the segment and the surrounding rock, with a sealing performance of 98.5%. A second grouting ring is constructed every 8 segments to form a short-interval closed grouting cavity, which is suitable for the rapid deformation and easy leakage of fractured surrounding rock.
[0052] S3. Inter-section compaction grouting: Within the confined section, coarse-grained TBM pebbles are first pneumatically blown in at 0.45 MPa to quickly form a rigid support skeleton, resisting the compression and deformation of the fractured surrounding rock. Then, a binary compound filling grout is used, with a ratio of 68% fine-grained TBM waste and 32% ordinary Portland cement. The saturated grouting pressure is controlled at 1.1 MPa, the grouting rate at 26 L / min, and the pressure is stabilized for 14 minutes. A top-down saturated grouting mode is adopted to gradually expel air from the skeleton gaps and fill the fine cracks in the surrounding rock. Double grout-stopping rings block the grout's forward flow, preventing grout consolidation problems on the cutterhead and shield. The compaction density behind the fractured surrounding rock section wall can reach 99.0%, with no voids or water leakage risks.
[0053] S4. Cyclic Construction: Shortens the cycle step for fractured surrounding rock conditions, steadily iterates construction, and ensures controllable segment alignment throughout the process. There is no misalignment or floating of segments, no subsequent settlement defects, and no equipment jamming or malfunctions. It is suitable for TBM grouting construction in soft, fractured, and complex strata.
[0054] The specific process control indicators and physical property evolution test results are shown in Table 1: Table 1: Results of Synergistic Testing of Process Control Indicators and Physical Properties at Each Stage of Phased and Zonal Construction
[0055] As can be seen from the linkage analysis between the physical and mechanical properties and construction steps in Table 1, the reason why the construction method involved in this invention can achieve the expected beneficial effects is due to the following synergistic logic between mechanics and technology: First, the material's ultra-early strength aging matched and supported the "rapid stabilization" process in step S1. In step S1, to achieve the goal of "constraining the initial settlement of newly formed segments and inter-ring misalignment," the grout injected at the bottom must establish a rigid supporting force before the subsequent supporting trolley moves in. Tests show that the effective time (initial setting) of the action under S1 condition is strictly controlled between 38s and 45s, and within 30 minutes, its transient load-bearing stiffness (compressive strength) explosively crosses the threshold of 1.5MPa (measured at 1.65 to 1.80MPa). This proves that the "pure bottom, low-position fixed-point rapid setting grouting" action in this method is valid on the time axis, and the grout hardening speed can accurately keep up with the load pressure brought up by the TBM tunneling, physically ensuring the achievement of the stabilization action.
[0056] Secondly, the high sealing properties of the flow-blocking dam matched and supported the "longitudinal logic interception" process in step S2. When constructing the grout-stopping ring in step S2, the method required that the ring body achieve "continuous circumferential sealing without dead angles" to cut off the subsequent longitudinal grout leakage channels. Data showed that the S2 circumferential grout-stopping material solidified rapidly within 25-30 seconds, and the solidified body exhibited micro-expansion characteristics. The measured sealing stone rate at the interface with the surrounding rock and the outer wall of the tunnel lining segments reached over 98.5%. This extremely high in-situ sealing and solidification action provided an extremely robust longitudinal rigid boundary limit for the "high-pressure stabilizing saturated grouting" in step S3. From a hydrodynamic perspective, this confirmed that the method could block the construction control logic of grout leakage to the TBM cutterhead.
[0057] Third, the high fluidity and volume stability of the filling medium synergistically achieve the "full-area saturation and compaction" process in step S3. During the backfilling of the closed grouting section in step S3, the method employs a "top-down" saturation filling action. This requires the filling grout to possess long-term flow and self-compacting capabilities. Tests show that the S3 filling grout has an initial fluidity as high as 220mm-235mm, and its completion time (final setting) is delayed to 11-12 hours. This high fluidity ensures that, driven by the synergistic effect of its own weight gradient and mechanical pressure stabilization, the grout can autonomously penetrate and fill every tiny pore in the pea-sized stone skeleton, increasing the final density of the stone body to over 99.0%. Thus, at the methodological level, the invention's objective of "full-section, no dead-angle saturated backfilling, and radical cure of crescent-shaped hollow defects" is achieved.
[0058] Although the present invention has been described in detail above with general descriptions and specific embodiments, modifications or improvements can be made to it, which will be obvious to those skilled in the art. Therefore, all such modifications or improvements made without departing from the spirit of the present invention fall within the scope of protection claimed by the present invention.
Claims
1. A TBM grouting construction method for preventing cutterhead consolidation and segment misalignment, characterized in that, include: After S1 and TBM excavate 3 to 4 rings of segments, low-level fixed-point grouting is carried out using quick-setting and early-strength grout through the grouting holes at the bottom and sides of the formed segments to form an early support structure. S2. After continuous tunneling to a cumulative total of 10-15 rings of tunnel segments, select a stable tunnel segment ring and use a bottom-up layered grouting method to seal the entire ring of tunnel segment wall with grout, solidify to form an independent grout-stopping ring, and construct two parallel grout-stopping rings at a set interval to form a closed grouting section with both ends sealed. S3. Within the closed grouting zone, the pea gravel backfilling and cement mortar backfilling and compaction operations are completed sequentially; the grout stop ring blocks the forward flow channel of the grout through its sealing and isolation function, and the closed grouting zone is stabilized and compacted during grouting. S4. Follow the TBM tunneling progress and repeat the S1 to S3 processes.
2. The TBM grouting construction method for preventing cutterhead consolidation and segment misalignment according to claim 1, characterized in that, In S1, the quick-setting and early-strength grout is a quaternary compound grout, which includes fine particles of TBM excavation waste, cement, quick-setting agent, and early-strength agent. The mass ratio of each component is as follows: fine particles of TBM excavation waste 45% to 55%, cement 30% to 35%, quick-setting agent 3% to 5%, early-strength agent 2% to 4%, and the balance is mixing water. The initial setting time of the quaternary compound slurry is 30-60 seconds, the final setting time is ≤10 minutes, and the early compressive strength at 30 minutes is ≥1.5 MPa. The construction parameters are: grouting pressure 0.2-0.4 MPa, grouting rate 15-20 L / min, and pressure stabilization time 3-5 min.
3. The TBM grouting construction method for preventing cutterhead consolidation and segment misalignment according to claim 1, characterized in that, In S1, the low-position fixed-point grouting only applies to the bottom arch and the low-position areas on both sides of the segment, and does not apply to the top grouting.
4. The TBM grouting construction method for preventing cutterhead consolidation and segment misalignment according to claim 1, characterized in that, In S2, the grout-stopping ring is constructed in the area of 10 to 15 ring segments behind the shield tail.
5. The TBM grouting construction method for preventing cutterhead consolidation and segment misalignment according to claim 4, characterized in that, The grout-stopping ring uses a ternary composite grout-stopping material, which includes fine particles of TBM excavation waste, cement, and an accelerator. The mass ratio of each component is as follows: 50%–60% of the fine particles of TBM excavation waste, 32%–38% of the cement, 4%–6% of the accelerator, and the remainder is mixing water. The ternary composite grout-stopping material does not shrink after curing and has micro-expansion characteristics.
6. The TBM grouting construction method for preventing cutterhead consolidation and segment misalignment according to claim 1, characterized in that, In S2, the bottom-to-top layered grouting method specifically means: grouting is performed symmetrically on the bottom arch area and the two sides of the waist in sequence, and the top closed area is grouted in layers, with the two sides of the waist being grouted symmetrically and synchronously. The construction parameters are as follows: layered grouting pressure 0.5-0.7MPa, grouting rate 20-25L / min, single-layer pressure stabilization time 5-8min, and double-sided grouting pressure difference ≤±0.05MPa.
7. The TBM grouting construction method for preventing cutterhead consolidation and segment misalignment according to claim 1, characterized in that, In S3, the closed grouting section is pressure-stabilized and compacted by top opening and top-down saturated grouting. First, TBM coarse pebbles are blown in to form a rigid support skeleton, and then filling grout is injected.
8. The TBM grouting construction method for preventing cutterhead consolidation and segment misalignment according to claim 7, characterized in that, The filling grout uses a binary composite filling material, which includes fine particles of TBM excavation waste and cement. The mass ratio of each component is: 60% to 70% of the fine particles of TBM excavation waste and 30% to 40% of the cement, with no additives. The construction parameters are as follows: TBM coarse-grained pebbles blasting air pressure 0.3-0.5MPa, saturated grouting pressure 0.8-1.2MPa, grouting rate 25-30L / min, and pressure stabilization time 10-15min.
9. A TBM grouting construction method for preventing cutterhead consolidation and segment misalignment according to claim 7, characterized in that, In S3, when the grout outlet at the bottom of the closed grouting section continuously overflows grout without air bubbles and the grout concentration is consistent with the grouting concentration, it is determined that the grouting is saturated and compacted, and the grouting is terminated.
10. The TBM grouting construction method for preventing cutterhead consolidation and segment misalignment according to claim 1, characterized in that, The longitudinal spacing between two adjacent grout-stopping rings is 8 to 12 ring segments.