A method for winter construction of cement-stabilized soil base course

By using modified cement-stabilized soil mixture and multi-layer sealing and insulation structure, combined with an intelligent temperature control system, the problem of frost damage to cement-stabilized soil base course during winter construction in frigid regions has been solved, achieving improved strength and overall protection, while reducing construction costs and the risk of defects.

CN123109022APending Publication Date: 2026-11-17CHINA MCC 2 GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611500914.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-24
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing cement-stabilized soil base courses suffer from problems such as freeze-thaw cracking, loose edges, strength reduction, roadbed frost heave, and erosion by snowmelt water during open-air winter construction in frigid northern regions, lacking comprehensive protective measures.

Method used

The system uses a dense-grained graded cement-stabilized soil mixture, combined with a multi-layered sealed insulation structure and an intelligent temperature control and monitoring system. This includes laying a moisture-retaining and waterproof layer, a buffer and crack-resistant layer, a main insulation layer, and a windproof and seepage-proof surface layer from bottom to top. It is also equipped with an electric heating cable for emergency heating, timely drainage of meltwater, and temperature monitoring to ensure the strength and integrity of the base layer.

Benefits of technology

It effectively improves the strength of the base layer, reduces the probability of freeze-thaw cracks, ensures the integrity of the base layer, reduces material costs, simplifies the demolition process, ensures the construction standards of the surface layer in the following year, and reduces the investment in repairing defects in the later stage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109022A_ABST
    Figure CN123109022A_ABST
Patent Text Reader

Abstract

This invention belongs to the field of municipal construction and mainly relates to a method for winter construction of cement-stabilized soil base courses, including the following steps: S1. Mixing cement-stabilized soil mixture according to the specified proportions for frost resistance; S2. Layered spreading and compaction of cement, followed by 7 consecutive days of reinforcement and curing; S3. Frost-resistant sealing of the base course sides and anti-seepage treatment of the roadbed surface; S4. Multi-layer sealing and integrated laying of the winter insulation system, from bottom to top, laying a moisture-retaining and waterproof layer, a buffer and crack-resistant layer, a main insulation layer, and a windproof and seepage-proof surface layer; S5. Establishing a full-process intelligent temperature monitoring and emergency heating system along the longitudinal direction of the road, conducting daily inspections, and promptly repairing and sealing; establishing a complete set of integrated construction technology for recycling and reuse, systematically solving many engineering problems such as roadbed deformation in cold regions. This application features complete process steps, convenient operation, and excellent protective effect. It also possesses significant advantages such as reusable materials, low overall construction cost, and minimal subsequent road maintenance, making it highly valuable for engineering application.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of municipal construction, and in particular to a method for winter construction of cement-stabilized soil base courses. Background Technology

[0002] In the frigid northern regions, municipal roads often face the following situation: cement-stabilized soil base courses are laid and compacted in autumn and winter, but due to time constraints and temperature limitations, asphalt surface courses cannot be laid in the same year. The base courses must overwinter outdoors until the following spring before the surface course is laid. Current winter protection methods simply involve covering the base courses with insulating blankets, which have the following drawbacks: 1. Cement-stabilized soil still contains free water in the later stages of molding. During the day-night freeze-thaw cycle in winter, the water freezes and expands, causing micro-cracks. In spring, the road surface has dense reflective cracks. 2. Poor insulation and sealing of the top and sides of the base layer allow cold wind and rain to seep in, causing the edges of the base layer to frost, peel, and loosen, resulting in a significant decrease in overall integrity; 3. Relying solely on external insulation without modifying the mixture for frost resistance results in insufficient hydration at low temperatures, leading to a 20%–40% strength loss after wintering; 4. The lack of tiered temperature control monitoring and drainage measures leads to water seeping into the bottom of the base layer after snow melts, causing frost heave and deformation of the base layer. 5. Traditional insulation materials have low reusability, high winter protection costs, and cumbersome procedures for cleaning the insulation layer in the spring.

[0003] Existing winter construction plans are mostly designed for low-temperature paving, and there is no complete set of processes specifically for open-air overwintering after the mixture is formed. They only provide single-layer insulation, which cannot simultaneously solve the five core overwintering problems of mixture frost resistance, sealing and insulation, snow melting and drainage, roadbed frost heave prevention, and temperature control throughout the process. Summary of the Invention

[0004] To address the aforementioned issues, this application proposes a winter construction method for cement-stabilized soil base courses. This method overcomes the shortcomings of existing open-air winter protection measures for cement-stabilized soil base courses, such as limited protection, freeze-thaw cracking, loose edges, strength reduction, roadbed frost heave, and snowmelt water erosion. It provides a comprehensive winter construction method for cement-stabilized soil base courses that integrates mixture modification, pre-curing, multi-layer sealing and insulation, lateral sealing, drainage, intelligent temperature control and monitoring, and layered removal in spring. This method significantly reduces winter frost damage and ensures that the mechanical properties of the base course meet the standards for the next year's surface layer construction.

[0005] This invention proposes a method for winter construction of cement-stabilized soil base courses, comprising the following steps: S1. Cement-stabilized soil mixture for frost resistance should be mixed according to the specified proportions. S2. Cement is laid in layers and compacted, and then reinforced and cured for 7 consecutive days. S3. Anti-freezing sealing of the base layer side and seepage prevention treatment of the subgrade surface; S4. The winter insulation system is laid in a multi-layer sealed integrated manner, with a moisture-proof and waterproof layer, a buffer and crack-resistant layer, a main insulation layer and a windproof and seepage-proof surface layer laid from bottom to top. S5. Establish a full-process intelligent temperature monitoring and emergency heating system along the road longitudinally, conduct daily inspections, and promptly repair and seal any issues.

[0006] Furthermore, the mixture adopts a dense-skeletal graded cement-stabilized soil, which, by weight, consists of 58%–65% coarse aggregate, 22%–28% fine aggregate, 4.8%–6.2% P·O42.5 early-strength cement, 5%–7% fly ash active admixture, 1.2%–1.8% composite antifreeze early-strength agent, and an optimum moisture content reduced by 0.8–1.2 percentage points. The composite antifreeze and early strength agent is composed of calcium nitrate, silica fume and air-entraining agent, so that the diameter of the air-entraining bubbles reaches 20-100μm. The aggregate is preheated to 8-15℃, the mixing water temperature is 15-25℃, the discharge temperature of the mixture is ≥12℃, and the total mixing time is ≥90s.

[0007] Furthermore, step S2, layered paving and cement compaction, includes paving each layer of cement with a thickness of 16-20cm, starting a vibratory roller to compact the road surface using a combination of static and vibratory compaction to achieve a compaction degree of ≥98%; and spraying a low-temperature moisturizing and curing agent within a preset time after compaction.

[0008] Furthermore, during the 7-day continuous pre-curing, a polyethylene waterproof membrane was first laid on the top surface of the base layer, followed by a thick rock wool insulation blanket, and sandbags were used to press it down around the perimeter; a temperature sensing probe was pre-embedded, and the core temperature of the base layer was maintained above 5°C; after 7 days, the unconfined compressive strength was tested and found to be above 85% of the design strength.

[0009] Furthermore, vehicles are prohibited from passing through during the maintenance period. The surface should be sealed with cement grout and fine sand, and micro-cracks caused by surface shrinkage should be repaired promptly.

[0010] Furthermore, step S3, which involves anti-freezing sealing of the base course sides and seepage prevention treatment of the roadbed surface, includes: Waterproof and antifreeze polymer mortar was applied to the exposed vertical sidewalls on both sides of the base layer, and thermal insulation shoulders were piled up on the outside. Longitudinal blind drains were excavated on the top surface of the roadbed and the shoulder, and permeable pipes and geotextile filter layers were laid.

[0011] Furthermore, the moisture-retaining and waterproof layer includes: a full-coverage black PE geomembrane with an overlap width of ≥30cm, and the overlap is sealed with tape to prevent the evaporation of moisture inside the base layer and the infiltration of rain and snow from the outside; The buffer and crack-resistant layer includes: geotextile absorbent cotton, which absorbs a small amount of water seeping in from melting snow and prevents ice formation under the membrane from compressing the base layer; The main insulation layer includes: double-layer thickened flame-retardant rock wool insulation felt, with staggered joints; The windproof and seepage-proof surface layer includes: full coverage with geomembrane waterproof fabric, each section is sealed with precast concrete strips and sandbags, and double-layer insulation strips are added to seal the expansion joints and construction joints.

[0012] Furthermore, establishing a fully intelligent temperature monitoring and emergency warming system for overwintering in step S5 includes, A set of temperature sensors is installed at each interval along the longitudinal direction of the road, buried in the core of the base layer, the middle of the insulation layer, and the top surface of the roadbed, respectively, and the automatic data acquisition system records the temperature in real time; When the core temperature of the base layer is below 0℃, a recyclable electric heating tape is laid under the insulation layer to control the temperature within the range of 5-8℃.

[0013] Furthermore, promptly clear the snow from the top after snowfall, and remove the snow immediately when it reaches a certain thickness to prevent the heavy snow from damaging the insulation layer and allowing meltwater to seep in.

[0014] Furthermore, after seven consecutive days of average daily temperatures exceeding 5°C, the winter insulation system is dismantled in layers, and the strength of the base layer is tested and repaired.

[0015] The beneficial effects of this application are as follows: By using a composite antifreeze early strength agent to adjust the mix ratio and lower the optimal moisture content, combined with low-temperature mixing and temperature control measures, the base layer can achieve a pre-curing strength of more than 85% of the design strength after 7 days, and the strength loss after overwintering can be controlled within 8%, effectively solving the problem of significant winter strength reduction of traditional unmodified water-stabilized base layers. The system employs a four-layer staggered joint sealing insulation structure consisting of a geomembrane, absorbent buffer cotton, double-layer rock wool, and windproof and waterproof fabric. This is combined with expansion joint insulation sealing strips to eliminate cold bridges. The system also incorporates antifreeze mortar and gravel insulation shoulders on the side walls to comprehensively block rain and snow infiltration and low-temperature air intrusion, significantly reducing the probability of cracks caused by freeze-thaw cycles. Thirdly, longitudinal blind drains with a 2‰ slope are installed on the road shoulders to promptly drain melting snow and seepage water from overwintering, preventing water from seeping into the roadbed and causing frost heave and ensuring the overall flatness of the base layer. Temperature sensing and monitoring systems are deployed along the route. When the temperature is low, the self-regulating electric heating tape is activated for emergency warming to continuously keep the core of the base layer from freezing and prevent capillary water freezing and heave from damaging the skeleton structure from the inside. The entire set of thermal insulation and protective materials can be disassembled in layers and reused for 3 to 5 wintering cycles, which greatly reduces the cost of single wintering protective materials. The spring dismantling process is simple and effectively shortens the preparation period for resumption of work. The entire process of this invention is suitable for the winter protection construction of water-stabilized base courses of municipal roads and highways in the cold north. The base course performance can directly meet the asphalt surface paving construction standards in the following year, which significantly reduces the investment in road surface repair in the later stage. The overall economic benefits and engineering practicality are outstanding. Attached Figure Description

[0016] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0017] Figure 1 A flowchart illustrating a method for winter construction of cement-stabilized soil base courses; Figure 2 This is a schematic diagram of the cross-sectional structure of a method for overwintering cement-stabilized soil base course construction. Detailed Implementation

[0018] To make the objectives, technical solutions, and advantages of this application clearer, the following detailed description is provided in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the scope of this application. All other implementations obtained by those skilled in the art based on the embodiments of this application without inventive effort are within the scope of protection of this application. In the various drawings, the same elements are represented by the same or similar reference numerals, and for clarity, the various parts in the drawings are not drawn to scale.

[0019] See Figure 1-2 As shown, this invention proposes a method for winter construction of cement-stabilized soil base courses, comprising: This invention proposes a method for winter construction of cement-stabilized soil base courses, comprising the following steps: S1. Cement-stabilized soil mixture for frost resistance should be mixed according to the specified proportions. Specifically, the mixture adopts a dense-skeletal graded cement-stabilized soil, which, by weight, consists of 58%–65% coarse aggregate, 22%–28% fine aggregate, 4.8%–6.2% P·O42.5 early-strength cement, 5%–7% fly ash active admixture, 1.2%–1.8% composite antifreeze early-strength agent, and an optimum moisture content reduced by 0.8–1.2 percentage points. The composite antifreeze and early strength agent is composed of calcium nitrate, silica fume and air-entraining agent, so that the diameter of the air-entraining bubbles reaches 20-100μm. The aggregate is preheated to 8-15℃, the mixing water temperature is 15-25℃, the discharge temperature of the mixture is ≥12℃, and the total mixing time is ≥90s.

[0020] S2. Cement is laid in layers and compacted, and then reinforced and cured for 7 consecutive days. Specifically, step S2, layered paving and cement compaction, includes paving each layer of cement with a thickness of 16-20cm, starting a vibratory roller to compact the road surface using a combination of static and vibratory compaction to achieve a compaction degree of ≥98%; and spraying a low-temperature moisturizing and curing agent within a preset time after compaction.

[0021] Specifically, during the 7-day continuous pre-curing, a polyethylene waterproof membrane was first laid on the top surface of the base layer, followed by a thick rock wool insulation blanket, and sandbags were used to press it down around the perimeter. Temperature sensing probes were pre-embedded, and the core temperature of the base layer was maintained above 5°C. After 7 days, the unconfined compressive strength was tested and found to be above 85% of the design strength.

[0022] As a preferred option, vehicles should be prohibited from passing through during the curing period, and the surface should be sealed with cement grout and fine sand, and surface shrinkage micro-cracks should be repaired in a timely manner.

[0023] S3. Anti-freezing sealing of the base layer side and seepage prevention treatment of the subgrade surface; Specifically, step S3, which involves anti-freezing sealing of the base course side and seepage prevention treatment of the roadbed surface, includes: Apply waterproof and frost-resistant polymer mortar to the exposed vertical sidewalls on both sides of the base layer, and build an insulation shoulder on the outside; preferably, apply at least two coats of waterproof and frost-resistant polymer mortar, with a total thickness of ≥8mm; the insulation shoulder is 30cm wide × 50cm high; Longitudinal blind drains are excavated on the top surface and shoulder of the roadbed, and permeable pipes and geotextile filter layers are laid. As a preferred option, the slope of the blind drains is 2‰, which directs snowmelt and rainwater to the drainage ditch outside the road, preventing water from seeping into the roadbed and causing frost heave.

[0024] S4. The winter insulation system is laid in a multi-layer sealed integrated manner, with a moisture-proof and waterproof layer, a buffer and crack-resistant layer, a main insulation layer and a windproof and seepage-proof surface layer laid from bottom to top, and each layer is tightly sealed without gaps. Specifically, the moisture-proof layer includes: a full-coverage black PE geomembrane with an overlap width of ≥30cm and the overlap sealed with tape to prevent the evaporation of moisture inside the base layer and the infiltration of rain and snow from the outside; The buffer and crack-resistant layer includes: geotextile absorbent cotton, which absorbs small amounts of water seeping from melting snow and prevents ice formation under the membrane from compressing the base layer; preferably, the geotextile absorbent cotton in the buffer and crack-resistant layer is 3cm thick. The main insulation layer includes: double-layer thickened flame-retardant rock wool insulation felt, with staggered joints. The preferred flame-retardant rock wool insulation felt has a thickness of ≥10cm. The windproof and seepage-proof surface layer includes: full coverage with geomembrane waterproof cloth, with each section preferably spaced 2m apart, and sealed with precast concrete strips and sandbags. Double-layer insulation strips are added to the expansion joints and construction joints to prevent cold bridging.

[0025] After all insulation layers are laid, extend each layer of insulation material down to the toe of the slope along the roadbed slope. Compact the material in a top-down sequence, then secure it with soil nails and anchor plates to prevent the insulation layers from being blown off by the wind. Finally, check the sealing and connection of each part around the entire roadbed, and seal any gaps or warped edges. This completes the construction of the winter insulation system. After the temperature rises and stabilizes in the following spring, remove the insulation protection system layer by layer. After cleaning up construction waste, the subsequent pavement structure layer construction can begin.

[0026] S5. Establish a winter-end intelligent temperature monitoring and emergency heating system along the longitudinal direction of the road, conduct daily inspections, and promptly repair and seal the system. Specifically, establishing a full-process intelligent temperature monitoring and emergency warming system for overwintering in step S5 includes, A set of temperature sensors is installed at each interval along the longitudinal direction of the road, buried in the core of the base layer, the middle of the insulation layer, and the top surface of the roadbed, respectively, and the automatic data acquisition system records the temperature in real time; When the core temperature of the base layer is below 0℃, a recyclable electric heating tape is laid under the insulation layer to control the temperature within the range of 5-8℃.

[0027] The electric heating cables are laid longitudinally along the road and linked to a temperature monitoring system for automatic temperature control. When the monitored data rises above a set threshold, the heating system automatically shuts down to avoid unnecessary energy waste. During winter, designated personnel review the monitoring data daily and conduct on-site inspections of the insulation system. If damage, displacement, or sealing failure is found in the insulation layer, it is immediately repaired and compacted with the same specification of insulation material, and the seal is re-applied to prevent the base layer from freezing and affecting construction quality. When the protective system is dismantled at the end of winter construction, the electric heating cables can be collected and reused in similar projects, reducing overall construction costs.

[0028] As a preferred method, daily inspections include promptly clearing snow from the top after snowfall, and immediately removing snow when the snow reaches a certain thickness of more than 10cm to prevent the heavy snow from damaging the insulation layer and allowing meltwater to seep in.

[0029] Specifically, after seven consecutive days when the average daily temperature exceeds 5°C, the winter insulation system will be dismantled in layers, and the strength of the base layer will be tested and repaired.

[0030] After removing the windproof and waterproof cloth, the rock wool insulation felt is recycled. The recycled material can be reused for 3 to 5 winter cycles. The absorbent cotton and the impermeable membrane are removed. After the removal is completed, the base surface is dried for 2 to 3 days. The base strength, flatness and cracks are tested. Minor cracks are pre-treated with emulsified asphalt slurry sealant. After the standard is met, the asphalt surface layer is laid.

[0031] Example 1: A 20cm cement-stabilized crushed stone base course was constructed in early December, with the lowest temperature that year being -22℃. The asphalt surface course was then constructed in March of the following year, using the method of this invention. 1. Mixture ratio: 62% coarse aggregate, 25% fine aggregate, 5.5% cement, 6% fly ash, 1.5% composite antifreeze and early strength agent, optimum moisture content 4.6%; mixing and discharge temperature 14℃; 2. Curing should begin immediately after compaction. Maintain core temperature at 6-12℃ for 7 days of pre-curing. The strength should reach 4.3MPa after 7 days (86% of the design value of 5MPa). 3. Apply antifreeze mortar to the side walls, install crushed stone insulation shoulders on both sides, and lay DN100 permeable drainage pipe blind drains longitudinally on the shoulders; 4. A four-layer thermal insulation and sealing system provides full coverage, with temperature sensors embedded every 50m; electric heating is activated during periods of extreme low temperatures in winter, with the lowest core temperature of the base layer at 2.2℃, and no icing throughout the entire process; 5. In April of the following year, as temperatures rose, the insulation material was removed in layers. The base layer was tested and found to have no through cracks, with surface micro-cracks less than 0.1 mm wide and a strength of 4.72 MPa, resulting in a loss of only 5.6%. An AC-20 asphalt base layer was then laid directly, and after one year of operation, there were no reflective cracks or subsidence defects.

[0032] Comparative example: Adjacent halves of the same road section are covered with traditional single-layer cotton blankets. The unmodified mixture that overwintered had a strength of only 3.1 MPa the following spring, a loss of 38%, with dense longitudinal and transverse cracks and loose peeling at the edges of the base layer, requiring extensive milling repair.

[0033] The beneficial effects of this application are as follows: By using a composite antifreeze early strength agent to adjust the mix ratio and lower the optimal moisture content, combined with low-temperature mixing and temperature control measures, the base layer can achieve a pre-curing strength of more than 85% of the design strength after 7 days, and the strength loss after overwintering can be controlled within 8%, effectively solving the problem of significant winter strength reduction of traditional unmodified water-stabilized base layers. The system employs a four-layer staggered joint sealing insulation structure consisting of a geomembrane, absorbent buffer cotton, double-layer rock wool, and windproof and waterproof fabric. This is combined with expansion joint insulation sealing strips to eliminate cold bridges. The system also incorporates antifreeze mortar and gravel insulation shoulders on the side walls to comprehensively block rain and snow infiltration and low-temperature air intrusion, significantly reducing the probability of cracks caused by freeze-thaw cycles. Thirdly, longitudinal blind drains with a 2‰ slope are installed on the road shoulders to promptly drain melting snow and seepage water from overwintering, preventing water from seeping into the roadbed and causing frost heave and ensuring the overall flatness of the base layer. Temperature sensing and monitoring systems are deployed along the route. When the temperature is low, the self-regulating electric heating tape is activated for emergency warming to continuously keep the core of the base layer from freezing and prevent capillary water freezing and heave from damaging the skeleton structure from the inside. The entire set of thermal insulation and protective materials can be disassembled in layers and reused for 3 to 5 wintering cycles, which greatly reduces the cost of single wintering protective materials. The spring dismantling process is simple and effectively shortens the preparation period for resumption of work. The entire process of this invention is suitable for the winter protection construction of water-stabilized base courses of municipal roads and highways in the cold north. The base course performance can directly meet the asphalt surface paving construction standards in the following year, which significantly reduces the investment in road surface repair in the later stage. The overall economic benefits and engineering practicality are outstanding.

[0034] In the accompanying drawings of this embodiment, the same or similar reference numerals correspond to the same or similar components. In the description of this application, it should be noted that if terms such as "upper," "lower," "left," and "right" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, they are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, the terms used to describe positional relationships in the accompanying drawings are only for illustrative purposes and should not be construed as limiting this patent. For those skilled in the art, the specific meaning of the above terms can be understood according to the specific circumstances.

[0035] In this document, relational terms such as "first" and "second" are used merely to distinguish one entity or operation from another, without necessarily requiring or implying any actual relationship or order between these entities or operations. Finally, it should be noted that the above embodiments are clearly illustrative of the invention and not intended to limit the implementation. Those skilled in the art will recognize that various variations and modifications can be made based on the above description. It is neither necessary nor possible to exhaustively describe all possible implementations. However, obvious variations and modifications derived therefrom remain within the scope of this invention.

Claims

1. A method for winter construction of cement-stabilized soil base courses, characterized in that, Includes the following steps: S1. Cement-stabilized soil mixture for frost resistance should be mixed according to the specified proportions. S2. Cement is laid in layers and compacted, and then reinforced and cured for 7 consecutive days. S3. Anti-freezing sealing of the base layer side and seepage prevention treatment of the subgrade surface; S4. The winter insulation system is laid in a multi-layer sealed integrated manner, with a moisture-proof and waterproof layer, a buffer and crack-resistant layer, a main insulation layer and a windproof and seepage-proof surface layer laid from bottom to top. S5. Establish a full-process intelligent temperature monitoring and emergency heating system along the road longitudinally, conduct daily inspections, and promptly repair and seal any issues.

2. The method for winter construction of cement-stabilized soil base course according to claim 1, characterized in that, The mixture adopts a dense-skeletal graded cement-stabilized soil, and by weight, it consists of 58%–65% coarse aggregate, 22%–28% fine aggregate, 4.8%–6.2% P·O42.5 early-strength cement, 5%–7% fly ash active admixture, 1.2%–1.8% composite antifreeze early-strength agent, and the optimum moisture content is reduced by 0.8–1.2 percentage points. The composite antifreeze and early strength agent is composed of calcium nitrate, silica fume and air-entraining agent, so that the diameter of the air-entraining bubbles reaches 20-100μm. The aggregate is preheated to 8-15℃, the mixing water temperature is 15-25℃, the discharge temperature of the mixture is ≥12℃, and the total mixing time is ≥90s.

3. The method for winter construction of cement-stabilized soil base course according to claim 1, characterized in that, Step S2, layered paving and cement compaction, includes paving each layer of cement with a thickness of 16-20cm, starting a vibratory roller to compact the road surface using a combination of static and vibratory compaction to achieve a compaction degree of ≥98%; and spraying a low-temperature moisturizing and curing agent within a preset time after compaction.

4. The method for winter construction of cement-stabilized soil base course according to claim 1, characterized in that, During the 7-day continuous pre-curing process, a polyethylene waterproof membrane was first laid on the top surface of the base layer, followed by a thick rock wool insulation blanket, and sandbags were used to press it down around the perimeter. Temperature sensing probes were pre-embedded, and the core temperature of the base layer was maintained above 5°C. After 7 days, the unconfined compressive strength was tested and found to be above 85% of the design strength.

5. The method for winter construction of cement-stabilized soil base course according to claim 4, characterized in that, Vehicles are prohibited from passing through during the maintenance period. The surface should be sealed with cement grout and fine sand, and micro-cracks caused by shrinkage should be repaired promptly.

6. The method for winter construction of cement-stabilized soil base course according to claim 1, characterized in that, Step S3, which involves anti-freezing sealing of the base course side and seepage prevention treatment of the roadbed surface, includes: Waterproof and antifreeze polymer mortar was applied to the exposed vertical sidewalls on both sides of the base layer, and thermal insulation shoulders were piled up on the outside. Longitudinal blind drains were excavated on the top surface of the roadbed and the shoulder, and permeable pipes and geotextile filter layers were laid.

7. The method for winter construction of cement-stabilized soil base course according to claim 1, characterized in that, The moisture-proof layer includes: a full-coverage black PE geomembrane with an overlap width of ≥30cm, and the overlap is sealed with tape to prevent the evaporation of moisture inside the base layer and the infiltration of rain and snow from the outside; The buffer and crack-resistant layer includes: geotextile absorbent cotton, which absorbs a small amount of water seeping in from melting snow and prevents ice formation under the membrane from compressing the base layer; The main insulation layer includes: double-layer thickened flame-retardant rock wool insulation felt, with staggered joints; The windproof and seepage-proof surface layer includes: full coverage with geomembrane waterproof fabric, each section is sealed with precast concrete strips and sandbags, and double-layer insulation strips are added to seal the expansion joints and construction joints.

8. The method for winter construction of cement-stabilized soil base course according to claim 7, characterized in that, Step S5, establishing a full-process intelligent temperature monitoring and emergency heating system for overwintering, includes: A set of temperature sensors is installed at each interval along the longitudinal direction of the road, buried in the core of the base layer, the middle of the insulation layer, and the top surface of the roadbed, respectively, and the automatic data acquisition system records the temperature in real time; When the core temperature of the base layer is below 0℃, a recyclable electric heating tape is laid under the insulation layer to control the temperature within the range of 5-8℃.

9. The method for winter construction of cement-stabilized soil base course according to claim 8, characterized in that, After snowfall, promptly clear the snow from the top. When the snow reaches a certain thickness, remove it immediately to prevent the heavy snow from damaging the insulation layer and allowing meltwater to seep in.

10. The method for winter construction of cement-stabilized soil base course according to claim 1, characterized in that, After seven consecutive days when the average daily temperature exceeds 5°C, the winter insulation system is dismantled in layers, and the strength of the base layer is tested and repaired.